ERCOT
Electric Reliability Council of Texas, Inc. (ERCOT) RTO / ISOInterconnection of new data centers is paused statewide while ERCOT audits its entire large-load queue under Gov. Abbott's August 3, 2026 directive. The audit report is due to the PUCT by December 10, 2026, and ERCOT has told regulators the Batch Zero study will miss its April 9, 2027 deadline with no replacement date set. Texas law already lets ERCOT remotely disconnect non-critical loads of 75 MW or more during firm load shed.
| Measure | Status | What it does | Source |
|---|---|---|---|
| Texas Senate Bill 6 — large-load interconnection, curtailment, and remote-disconnect standardsSB 6, 89th Texas Legislature (2025) |
Effective · Jun 20, 2025
effective; PUCT implementation rulemakings ongoing through 2026
|
Applies to non-critical loads of 75 MW or greater in ERCOT. Requires remote-disconnect capability as a condition of interconnection for loads interconnecting after December 31, 2025, and authorizes utilities/ERCOT to disconnect eligible large loads during firm load shed events; creates a competitively procured voluntary curtailment/reliability service with a minimum 24-hour notice period. Also sets a $100,000 minimum interconnection study fee, mandatory disclosure of duplicative interconnection requests in Texas,… | |
| Batch Zero large-load interconnection framework (PGRR145 + NPRR1325)ERCOT Planning Guide Revision Request 145; Nodal Protocol Revision… |
Effective · Jun 18, 2026
approved/effective; classification and study timelines now partially suspended by the August 2026 audit pause
|
Groups qualified large loads of 75 MW+ into a single batch study to allocate available grid capacity year-by-year (2028–2032) via Load Commissioning Plans, set financial commitments ($50,000/MW financial security), and produce an actionable transmission plan. Key milestones: developer submissions due July 10, 2026; TSP/DSP packages due July 24, 2026; ERCOT classification notices (Base Load / Studied Load) by August 7, 2026; study results April 9, 2027; interconnection agreements executed by June 8, 2027. ERCOT… | |
| PUCT proposed rule 16 TAC §25.194 — large load interconnection standards (SB 6 implementation)PUCT Project No. 58481 |
Filed · Mar 12, 2026
proposed / pending adoption (adoption expected later in 2026)
|
Would establish interconnection standards for new or expanded loads of 75 MW+ in ERCOT: minimum study fees of $100,000 (75–249 MW) and $300,000 (250 MW+), CPI-adjusted every five years from 2027; financial security of $50,000 per MW of requested peak demand at intermediate-agreement execution plus additional security for long-lead equipment; a non-refundable interconnection fee of $50,000 per MW of contracted peak demand after study completion; site-control and development-readiness showings before studies begin;… | |
| PUCT order in Docket 59220 — first SB 6 net-metering/co-location ruling, affirming curtailment authority over co-located data…PUCT Docket No. 59220 |
Effective · Jul 23, 2026
approved with conditions (binding on the applicants; first precedent for SB 6 co-location cases)
|
PUCT approved a net-metering arrangement for a Crusoe-developed AI data center co-located behind the ~265.5 MW Goodnight 1 wind farm (a 260 MW second facility at the campus), with conditions: the full campus load must curtail within 30 minutes during ERCOT grid emergencies, physical breaker disconnection authorized, ERCOT to give 60 minutes advance notice when practicable, and the project is barred from compensation for load reductions during grid emergencies. Establishes that emergency curtailment of co-located… | |
| Gov. Abbott directive — comprehensive verification and audit of data centers in the ERCOT queue; pause on new data center…Gubernatorial directive to PUCT Chairman Thomas Gleeson and ERCOT… |
Effective · Aug 3, 2026
effective; audit in progress, pause remains pending audit completion
|
Directs PUCT and ERCOT to verify every data center project advancing through the interconnection process — power demand and sourcing, on-site generation progress, water use and cooling, state/local financial assistance, community protections, and ownership — before any additional data center is approved to advance. States that projects failing the verification and audit process 'must be denied' grid access. Binds ERCOT and the PUCT. | |
| ERCOT Market Notice M-A080326-01 — suspension of Batch Zero classification deadlineERCOT Market Notice M-A080326-01 | Effective · Aug 3, 2026 | ERCOT announced it would not meet the August 7, 2026 deadline to notify service providers of Large Load classifications in the Batch Zero Interconnection Study, citing the Governor's directive to conduct a verification process before advancing any data center large loads. ERCOT committed to file a good cause exception request with the PUCT before the PUCT's August 20, 2026 open meeting, seeking modification of timelines in Planning Guide Sections 5 and 9. | |
| ERCOT good-cause-exception filing and PUCT approval; audit timeline set (RFIs now, reports due December 10, 2026)PUCT Control No. 59142 (Item 42) |
Effective · Aug 10, 2026
approved
|
ERCOT requested relief from the August 7 classification deadline, authority for large loads to participate in the August and November Quarterly Stability Assessments (6 projects for August, up to 17 for November), and an extension for dynamic-data deficiency notifications; the PUCT granted the exceptions on August 20. ERCOT's timeline: RFIs to developers via TSPs/DSPs from late August through September, information gathering October–November, and filing of the Batch Zero Eligibility Verification Report and… | |
| PUCT Project 58484 — evaluation of transmission cost recovery (4CP methodology) for large loadsPUCT Project No. 58484 |
Filed · Aug 1, 2025
pending rulemaking (SB 6 requires amended rules no later than December 31, 2026)
|
Evaluates whether the four-coincident-peak (4CP) wholesale transmission cost allocation method appropriately assigns costs given large-load growth. Draft recommendations under comment include moving to more coincident peaks over longer intervals, eliminating interconnection cost allowances for large loads, requiring large loads to pay a share of system upgrade costs, and minimum demand charges based on contracted peak demand for 10–15 years. | |
| SB 6 companion rulemakings: Project 58479 (co-location net metering), Project 58480 (large-load forecasting, ≥10 MW definition),…PUCT Project Nos. 58479, 58480, 58482 |
Filed · Jan 2026
pending as of the December 23, 2025 source; mid-2026 adoption status not independently confirmed (see flags)
|
58479 requires PUCT approval of net-metering arrangements between new 75 MW+ customers and stand-alone generators, allowing conditional approvals (callable capacity, behind-the-meter curtailment) — the framework applied in Docket 59220. 58480 defines a large load customer as 10 MW+ at a single site for forecasting and sets documentation/milestones for inclusion in ERCOT forecasts. 58482 creates the SB 6 voluntary demand-reduction/reliability program for large loads. |