Octopod · Information package
1 of 2 · the block
Infrastructure — one Octopod block, as drawn
One block, as drawn by CES / IntelliFlex on general-arrangement SITE-HD-BESS-1B-GA-DETAIL1 (Rev A, 1:250). Every building is clickable; the mode buttons trace how power and heat move through the block.
AS DRAWN
13.2 MWgross load
8.8 MWnet IT load
8.8 MWcooling · PUE 1.5 assumed
6 × 3 MWMV-BESS · N+1
452′-4″overall
Show
CHILLER ROOM3 chillers per bldg · N+1 · roof dry coolersIT HALL2 × 20 rack positions · 2,200 kW IT per buildingCORRIDORIT HALL2 × 20 rack positions · 2,200 kW IT per buildingCHILLER ROOM3 chillers per bldg · N+1 · roof dry coolersWAREHOUSE · loading dockCONTROL ROOM · office3 × MegaBox · 3 MW · 2,500 A bus3 × MegaBox · 3 MW · 2,500 A busSWGR ≤38 kVMV-BESS · 3 MWMV-BESS · 3 MWMV-BESS · 3 MWMV-BESS · 3 MWMV-BESS · 3 MWMV-BESS · 3 MW6 × 2,100 A OVERHEAD BUSWAYS — through the IT halls into the chiller rooms452′-4″ [137,871 mm] overall252′-8″ [77,013 mm] IT halls + chiller rooms72′-2″ [21,996]66′ [20,117] MV-BESS yardPlan is to scale (1:250 drawing geometry). North per drawing. Click any building; use the mode buttons to trace power or cooling.12345662 CHILLED-WATER LOOPS (2N) · up to 35 GPM of 25 °C water to every rackrooftop dry coolers — one per chillerrooftop dry coolers — one per chiller1234512345
Power — switchgear, transformers, MV-BESS, MegaBox, buswaysCompute — IT halls and racksCooling — chiller rooms, CRAH, loops, dry coolersFacility — corridor, warehouse, control room
Opens on the whole 452′ site. Drag to pan · pinch or use + / − to zoom · “Block” zooms to the compute block, “Whole site” brings it all back.

How the block functions, in order

Follow the power in and the heat out. Click any step and it lights up on the plan above — the buildings it touches, and the direction it moves.

Walkthrough Runs the sequence on the plan, about four seconds a step.
STEP 01

Utility arrives at the switchgear building

Rated up to 38 kV. Main incoming section, potential-transformer section and station-transformer section, with an optional auto-transfer section and backup-power incoming. From here the site splits into 6 × 3 MW feeder sections.

Show it on the plan ↑
STEP 02

Each feeder gets its own step-down transformer

Six transformers sit in the yard, one beside each MV-BESS enclosure, bringing the feeder down to the distribution voltage used by the batteries and the MegaBoxes.

Show it on the plan ↑
STEP 03

MV-BESS holds the load and cleans the power

Six medium-voltage battery systems, 3 MW each, N+1. Each carries the site for 2–4 hours at full load and, at the same time, regulates the load-side voltage through sags, swells and transients. Each delivers up to 3 MW of uninterruptible power to the IT and chiller buildings.

Show it on the plan ↑
STEP 04

MegaBox steps down to the building voltage

Six 3 MW unit substations in two rows of three under the IT hall, each with 2 × 2,100 A breakers on a 2,500 A bus (12.47 kV → 415 V per the single-line).

Show it on the plan ↑
STEP 05

Six busways carry it overhead

Six 2,100 A overhead busways from six separate sources → N+1 at every rack. They run through the IT buildings and on into the chiller buildings, so the cooling plant shares the same redundant supply.

Show it on the plan ↑
STEP 06

The racks do the work

Four IT buildings, 20 NVIDIA GPU rack positions each — 80 positions carrying 8.8 MW of IT load, which is 2,200 kW per building and an average of 110 kW a rack. Any one position can take up to 250 kW, so the power envelope — not the position count — sets the density, and the density follows the server class installed. SAVRN fills this envelope with 32 NVIDIA VR200 NVL72 racks at 250 kW, 8 MW of IT. Two IT buildings form one IT hall.

Show it on the plan ↑
STEP 07

Heat leaves the rack in water and air

Each rack position receives up to 35 GPM of 25 °C chilled water. 20 CRAH units per building (50 kW each) handle the air side; 3 HVAC units per IT building manage circulation, humidity, filtration and air changes.

Show it on the plan ↑
STEP 08

Chiller rooms reject it to the roof

Four chiller buildings, 3 water chillers each (N+1), every chiller coupled to its own rooftop dry cooler. Two chilled-water loops serve the compute buildings (2N). Condenser loops modulate fan speed for efficiency. Two chiller buildings form one chiller room.

Show it on the plan ↑
STEP 09

Operate and supply

The control room holds operator stations, central servers and networking; the warehouse has the loading dock and stays customizable. Both open onto the corridor between the halls.

Show it on the plan ↑

Redundancy, with the arithmetic

What the N+1 and 2N on the drawing mean for this block.

18 MWinstalled feeder / MV-BESS / MegaBox capacity — 6 × 3 MW
13.2 MWgross load the block draws
15 MWleft with any one 3 MW path out of service — still above 13.2 MW (N+1)
2–4 hfull-load ride-through on the MV-BESS, with voltage conditioning throughout
ElementQuantitySchemeWhat it means
Power feed6 × 3 MW feeder sectionsN+118 MW installed against 13.2 MW gross. One section out → 15 MW still covers the block.
MV-BESS6 × 3 MWN+12–4 hour backup at full load plus continuous voltage conditioning. One unit out → 15 MW.
MegaBox6 × 3 MW unit substationsN+1One per busway; 2 × 2,100 A breakers each.
Overhead busways6 × 2,100 AN+1Six separate sources into each IT building; extended into the chiller buildings.
Chillers3 per chiller building (12 total)N+1Each chiller has its own rooftop dry cooler.
Chilled-water loops2 loops2NEither loop can carry the compute buildings.
HVAC3 units per IT buildingCirculation, humidity, air changes, filtration, supplemental heat/cool.

Building schedule

Footprints are scaled from the 1:250 geometry; the dimensioned figures on the plan (452′-4″, 252′-8″, 72′-2″, 66′) are as drawn.

BuildingQtyFootprintContents / rating
IT buildings4≈60′ × 36′ per hall (two buildings)20 rack positions · 2,200 kW IT (110 kW average, up to 250 kW at a position) · 20 CRAH × 50 kW · 3 HVAC · 6 busways
Chiller buildings4≈60′ × 36′ per room (two buildings)3 chillers (N+1) · pumps · rooftop dry coolers · 2 loops
Corridor1≈12′ × 60′Links halls, warehouse and control room
Warehouse1≈60′ × 12′Loading dock · customizable
Control room1≈60′ × 12′Office · restroom · operator stations, servers, networking
MegaBox6two rows of three under the IT hall3 MW unit substation · 2 × 2,100 A breakers · 2,500 A bus
MV-BESS6≈60′ × 12′ enclosures, three rows of two3 MW · 2–4 h full-load backup · power conditioning
Step-down transformers6beside each MV-BESSone per feeder
Switchgear building1≈60′ × 12′up to 38 kV · 6 × 3 MW feeders · incoming / PT / station sections

The drawing

Full sheet, rendered as a blue-line. Drag to pan, use the buttons or pinch to zoom.

SITE-HD-BESS-1B-GA-DETAIL1 general arrangement, blue-line
Open the original PDF →Open the blue-line full size →Scale 1:250 · sheet ANSI D
DrawingSITE-HD-BESS-1B-GA-DETAIL1
TitleOctopod — High density site for MV-BESS — General arrangement — 1 block — Detail 1
RevisionA — Issued for review, 26-02-12
Scale1:250
Drawn / designed / checked / engineerJLS, 26-02-12
OwnerCES Corporation · IntelliFlex Innovative Data Solutions
SheetANSI D, 1 of 1 · AutoCAD 2025

Drawing notes, as written

Transcribed word for word from the notes column of the sheet. Click a note and it lights up on the plan — the buildings that note is describing.

Site power

Gross load 13.2 MW. Net IT load 8.8 MW. Cooling 8.8 MW (assumed PUE of 1.5, to be verified). MV-BESS 6 × 3 MW (N+1).

Show it on the plan ↑

IT buildings (4×)

These buildings consist of 20 × 30-inch or 25 × 24-inch server racks. 20 CRAH units each provide 50 kW of air cooling. The overhead busways provide up to 2,100 A from 6 separate sources to achieve N+1 electrical power distribution. The busways extend through the IT buildings to the chiller buildings to provide redundant power sources to the cooling equipment. 3 HVAC units provide air circulation, humidity control, air changes, air filtration and additional heating and cooling. 2 IT buildings form 1 IT hall.

Show it on the plan ↑

Chiller buildings (4×)

These buildings consist of 3 water chillers. Each chiller system is coupled to separate dry coolers on the roof. 2 cooling-water loops distribute chilled water to the compute buildings to achieve 2N redundancy. Each server rack in the compute buildings receives up to 35 GPM of 25 °C chilled water. The condenser-water loops are automated to modulate cooling-fan speeds to achieve better efficiency. Wall-mount HVAC units provide air circulation, humidity control, air changes, air filtration and additional heating and cooling. 2 chiller buildings form 1 chiller room.

Show it on the plan ↑

Control room building

This building can be customized to client specifications. Operator stations, central servers and networking, and washrooms can be located in this building.

Show it on the plan ↑

Switchgear building

The switchgear buildings consist of 6 × 3 MW feeder sections as well as a main incoming section, a potential-transformer section, a station-transformer section and optionally an auto-transfer section and backup-power incoming section.

Show it on the plan ↑

MV-BESS (6×)

The medium-voltage battery energy storage system (MV-BESS) is designed to provide uninterrupted 2-hour backup power under full-load conditions. Concurrently, it performs active power conditioning, dynamically regulating the load-side voltage to maintain it within strict nominal limits irrespective of grid voltage sags, swells, transients, or other disturbances. Each unit provides up to 3 MW of uninterruptible power to the IT and chiller buildings.

Show it on the plan ↑
Source: CES Corporation / IntelliFlex drawing SITE-HD-BESS-1B-GA-DETAIL1 Rev A. MegaBox voltages from the companion single-line SITE-HD-UPS-1B-SLD.