SAVRN Research · Living watchlist

Nationwide Data Center Delay Watchlist

A continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, local restrictions, litigation, federal and utility dockets, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Every entry links to its documented public source.

Updated 2026-08-24 Version 3.0.0 Coverage from 2024-01-01 Compiled by SAVRN Research
Scale model of a data center campus on a white plan: completed halls, cooling plant, and electrical substation rendered in copper, with queued future phases drawn as blueprint outline and a construction crane standing still
A data center campus rendered as a plan: completed structures shown built, queued phases shown as outline. The watchlist records which projects have moved and which are on hold.
Tracked projects
224
delayed, cancelled, or under review
Local restrictions
658
county, city, township measures
Utility actions
227
PUC dockets and statements
Active lawsuits
39
filed or in progress
Stalled since Jan 2024
$170B+
across 20 states (Carbon Direct)
Q1 2026 delayed / cancelled
$130B
75 projects (Fortune)
ERCOT capacity at risk
49.8 GW
$8B–$15B revenue (BNEF)
Transformer lead time
128 wks
large power, average

National interconnection queue

Every ISO plus vertically integrated utilities with a public row-level queue, as of 2026-08-24. The full row-level queue is refreshed weekly. ERCOT Batch Zero row-level classifications are not yet published per Market Notice M-A080326-01.

32,326
Total queue rows
4,432 GW
Total capacity requested
46
Rows flagged data center
92
Large-load / DC studies
By status
Withdrawn15,314
IA signed8,099
Active4,126
Unknown2,003
Other1,982
Study698
Suspended104
By source, ISO and utility
PJM9,263
Alliant Energy6,968
MISO3,817
CAISO2,281
Dominion Energy VA2,178
NYISO2,148
ERCOT2,003
ISO-NE1,751
SPP1,028
Ameren Illinois146
AEP Indiana Michigan91
Consumers Energy88
Evergy Kansas88
AEP PSO80
AEP Ohio72
We Energies58
PacifiCorp56
AEP SWEPCO47
Evergy Missouri40
El Paso Electric39
AEP APCo34
MidAmerican Energy32
Ameren Missouri18

Tracked projects

Named data center projects with a documented delay, cancellation, withdrawal, or active review. Status reflects the most recent public signal.

ProjectLocationMWStatusCauseNotesSources
Diode Ventures Cedar Creek Lake
Diode Ventures
Cedar Creek Lake
TX · ERCOT
withdrawn
state moratorium
Pre-moratorium withdrawal, cited by Governor's office as example
Project Matador (Amarillo)
Fermi America (FRMI)
Amarillo / Potter County
TX · ERCOT
11,000 delayed
transformer supply
11 GW at build-out; 600 MW gas turbines procured; 1 GW target by end of 2026. Not affected by moratorium (BTM). Continuing construction.
GW Ranch (Fort Stockton)
Pacifico Energy
Fort Stockton
TX · ERCOT
5,000 delayed 5 GW off-grid gas + 1.8 GW battery. Bypasses ERCOT entirely. Not affected by moratorium.
Amazon 7.65 GW Gas Plant / Self-Contained Island
Amazon Web Services / partner (AMZN)
TX
TX · ERCOT
5,000 delayed 35 turbines, 5 GW campus delivery, operates as self-contained energy island off ERCOT. Announced days AFTER moratorium, no delay impact.
Stargate / Abilene (Phase 1)
Crusoe (MSFT,ORCL)
Abilene
TX · ERCOT
1,200 delayed 900 MW BTM gas microgrid + grid blend at 1.2 GW. Continuing. Additional 4.5 GW gas capacity secured by Crusoe.
Good Data Center Campus (Armstrong County)
Google (via developer) (GOOGL)
Armstrong County
TX · ERCOT
delayed Private natural gas turbines under state air permit. Not affected by moratorium.
Voltagrid Shackelford County
Voltagrid (ORCL)
Shackelford County
TX · ERCOT
700 delayed
gas pipeline delay
210 industrial gas gensets. 700 MW. Off-grid. Delayed to 2029 per SemiAnalysis due to gas pipeline permitting.
Oracle/OpenAI Texas Expansion (Original Plan)
Oracle (ORCL)
TX
TX · ERCOT
withdrawn
corporate realignmentfinancing
Oracle/OpenAI abandoned Texas expansion March 6, 2026 over financing negotiations. Pre-moratorium. Microsoft later stepped in.
CleanSpark Texas Operations (all)
CleanSpark (CLSK)
TX
TX · ERCOT
pending review
ERCOT moratorium
10-Q risk factor disclosure: 'evaluating scope and enforceability of August 3, 2026 letter'. Only known public SEC disclosure explicitly referencing the moratorium.
Lighthouse (Port Washington)
Vantage Data Centers / Oracle / OpenAI (ORCL)
Port Washington
WI · MISO
litigation active
environmental reviewlitigationcommunity opposition
$15B project. Sierra Club/Midwest Environmental Advocates lawsuit filed July 10, 2026 in Ozaukee County. Also April 2026 ballot referendum limited DC construction.
Spring Valley Technology Park
Active Infrastructure
Loudoun County / near Beaverdam Reservoir
VA · PJM
780 cancelled
zoning denialcommunity oppositionwater dispute
325-acre, 3.54M sq ft. Planning Commission voted unanimously to recommend denial. 500+ residents attended hearing.
Dulles Cloud South
Prince William County
VA · PJM
cancelled
zoning denialcommunity opposition
Nearly 2,000-acre campus. Board of County Supervisors voted unanimously to deny rezoning.
Mountain Road Technology Park
Tract
Hanover County
VA · PJM
cancelled
zoning denialwater disputecommunity opposition
Board of Supervisors voted 4-3 to deny rezoning. Water concerns (up to 90% of local supply).
Prince William 2,100-acre Campus (37 buildings)
Prince William County
VA · PJM
cancelled
zoning denialcommunity opposition
37 buildings, gigawatt-scale; killed on public-notice technicality (notices not run 6 days apart)
Project Blue (Amazon-linked)
Beale Infrastructure (AMZN)
Tucson
AZ · WECC
cancelled
zoning denialwater disputecommunity opposition
City Council voted 7-0 to end negotiations and halt annexation.
New Carlisle $13B Data Center
St. Joseph County / New Carlisle
IN · MISO
cancelled
community oppositionzoning denial
St. Joseph County Council rejected after 10-hour meeting.
Hobart Amazon Data Center
Amazon (AMZN)
Hobart
IN · MISO
litigation active
litigationcommunity opposition
Lawsuit filed to block fill permit alleging state law violations
Project Tango
Palm Beach County / Arden
FL · SERC
cancelled
community oppositionwater disputezoning denial
Palm Beach commissioners voted 5-1 to deny after 12+ hour meeting.
Pine Island Data Center Development
Pine Island
MN · MISO
litigation active
environmental reviewlitigation
TRO issued blocking construction pending MCEA challenge. Construction was to begin July 2026.
T5 @ Chicago IV
T5 Data Centers
Lake County / Grayslake
IL · PJM
litigation active
litigationcommunity oppositionzoning denial
Lawsuit filed July 31, 2026 alleging inconsistent with Comprehensive Plan. Initial status hearing Oct 30.
Markley Group Lowell Expansion
Markley Group
Lowell
MA · ISO-NE
litigation active
litigationenvironmental review
MA Superior Court blocked installation of 4 new diesel generators pending resident lawsuit.
Hexa Builders Monroe Township
Hexa Builders LLC
Monroe Township / Gloucester County
NJ · PJM
litigation active
zoning deniallitigation
Hexa filed $300M lawsuit against township for zoning ordinances banning DCs.
DC BLOX Nashville (Grassmere Park)
DC BLOX
Nashville / Grassmere
TN · SERC
litigation active
local moratoriumlitigation
Filed federal lawsuit Aug 11 challenging Nashville moratorium. Claims vested rights.
Imperial Valley $10B AI Data Center
Imperial Valley Computer Manufacturing LLC
Imperial
CA · CAISO
litigation active
litigationpermit denial
$10B project. Civil rights lawsuit filed against City of Imperial in fed court.
Natelli Investments Wake County 250MW
Natelli Investments
Wake County
NC · PJM
250 withdrawn
community oppositionzoning denial
Withdrew annexation and rezoning applications early 2026.
Hays County / San Marcos DC
Hays County / San Marcos
TX · ERCOT
cancelled
zoning denialwater disputecommunity opposition
San Marcos City Council voted 5-2 against zoning in February 2026.
Eagan Capital Expansion
Eagan Capital
Eagan
MN · MISO
litigation active
local moratoriumlitigation
Filed lawsuit June 15 against Eagan for moratorium exceeding city authority.
DataBank Orangetown Phase 2
DataBank
Orangetown / Orangeburg
NY · NYISO
delayed
environmental reviewcommunity opposition
Orangetown Planning Board voted unanimously to require EIS, delaying project indefinitely.
Boulder City BLM Site
Boulder City
NV · WECC
under appeal
water disputecommunity opposition
Boulder City Council voted unanimously to appeal BLM approval.
University of Michigan / Los Alamos Data Center
Ypsilanti
MI · MISO
delayed
water disputelocal moratorium
Ypsilanti Community Utilities Authority passed yearlong halt on water/sewer for DCs (April 2026)
Prince William Digital Gateway (PW Digital Gateway)
QTS Data Centers (Blackstone); Compass Datacenters (BX)
Gainesville, Prince William County
VA · PJM
1,700 cancelled
litigationzoning denialcommunity opposition
One of the world's largest planned data center clusters (34 buildings, 22M SF) next to Manassas National Battlefield Park was voided by courts over inadequate public notice for…
Dulles Cloud South (Dulles South data center project)
Gainesville, Prince William County
VA · PJM
cancelled
zoning denialcommunity opposition
Nearly 2,000-acre, 43M-SF proposal to rezone farmland/residential land to industrial for data centers was rejected 8-0 by the Prince William Board of Supervisors, following on…
Bristow Campus data center project
Stack Infrastructure
Bristow/Nokesville area, Prince William County
VA · PJM
delayed
community opposition
Board of Supervisors hearing on this Nokesville Road/Broad Run Creek campus was deferred amid community opposition; a supervisor said backers "know they don't have the votes."
PW Digital Gateway landowner tax litigation
QTS Data Centers (BX)
Gainesville, Prince William County
VA · PJM
litigation active
litigation
Landowners under contract to sell parcels to QTS for the Digital Gateway sued Prince William County over sharply increased tax assessments tied to the (litigation-blocked)…
Loudoun County data center application pause
Loudoun County
VA · PJM
pending review
local moratoriumcommunity opposition
Board of Supervisors voted to begin process of pausing all new data center applications, site plans and substations countywide (250 existing data centers, 53.3M SF) until new…
Hiddenwood Lane / Hiddenwood Assemblage rezoning (Aldie)
JK Technology Holdings / Aldie homeowner group
Aldie, Loudoun County
VA · PJM
withdrawn
community oppositionzoning denial
Group of Aldie homeowners on Hiddenwood Lane seeking industrial rezoning (756,000 SF data center potential) to sell out of an area surrounded by data centers indefinitely…
Innovation Gateway
Sterling, Loudoun County
VA · PJM
pending review
zoning denial
700,000 SF data center plus affordable-housing rezoning near the Innovation Station Metrorail stop; Planning Commission recommended denial (5-2) as incompatible with the Urban…
Oaklawn data center rezoning (Leesburg)
Oaklawn, LLC
Leesburg, Loudoun County
VA · PJM
cancelled
zoning denial
Leesburg Town Council denied 5-1-1 a rezoning to add up to 450,000 SF of data centers linked to affordable-housing units, citing inconsistency with the Zoning Ordinance and…
Mountain Road Technology Park (Tract)
Tract
Route 33/Mountain Road, Hanover County
VA · PJM
900 cancelled
zoning denialcommunity opposition
Hanover Board of Supervisors rejected the conditional-use permit and A1-to-M1 rezoning for a 900MW/430-acre campus on May 27, 2026, after the Planning Commission had earlier…
Chesterfield Tract data center park (Branders Road)
Tract
161 Branders Road, Chesterfield County
VA · PJM
withdrawn
zoning denialcommunity opposition
Tract withdrew its zoning request for a 744-acre rural campus after the Planning Commission unanimously recommended against it, citing inadequate infrastructure and sole access…
Chesterfield data center project (unnamed) paused amid county lawsuits
Chesterfield County
VA · PJM
litigation active
litigation
Local reporting confirms an active Chesterfield County data center project paused amid county-level lawsuits, following the Zoning Appeals Board's denial of an appeal on a…
Gigaland Data Center Campus
GigaLand LLC
Remington, Fauquier County
VA · PJM
800 withdrawn
zoning denialcommunity opposition
Fauquier Planning Commission voted to recommend denial of the original 800MW/2.2M-SF rezoning; the developer officially withdrew the application in July 2026 and plans a…
Remington Digital Campus
Remington, Fauquier County
VA · PJM
pending review
zoning denialcommunity opposition
Fauquier Planning Commission recommended denial of a separate campus near Remington Technology Park adjoining the Meadows of Remington neighborhood; a related private turbine…
Amazon Data Services Warrenton data center
Amazon Data Services (AMZN)
Warrenton, Fauquier County
VA · PJM
litigation active
litigationcommunity opposition
Citizens for Fauquier County and 10 residents sued in Fauquier Circuit Court to overturn the Town Council's special-use-permit approval for a 220,000 SF Amazon facility, alleging…
Bel Pre Tech Park (Brandy Station data center campus)
Culpeper Acquisitions LLC
Brandy Station, Culpeper County
VA · PJM
pending review
zoning denialcommunity opposition
County planners denied the 4.6M-SF, nine-building rezoning application near the historic Brandy Station battlefield; applicant requested Board of Supervisors consideration be…
Brandy Station data center proposal (David Martin parcel)
Brandy Station, Culpeper County
VA · PJM
withdrawn
zoning denialcommunity opposition
An 88-acre Brandy Station rezoning was withdrawn after an initial denial from the Culpeper County planning commission amid Brandy Station resident opposition.
Red Ace Data Center Campus
Culpeper County
VA · PJM
delayed
zoning denial
Application tabled by Culpeper County officials, per Data Center Dynamics reporting; no further detail on eventual outcome.
Stafford County stricter data center rules (GWV Data Center reclassification context)
Stafford County
VA · PJM
delayed
zoning denialcommunity opposition
Following a marathon public hearing, Stafford County adopted stricter data-center zoning rules that developers and residents split over, raising the bar for future rezoning…
Spotsylvania County data center special-use permit standards / statewide moratorium resolution
Spotsylvania County
VA · PJM
pending review
zoning denialcommunity oppositionstate moratorium
Spotsylvania supervisors split on requiring special-use permits for data centers (March 2025) and by August 2026 the Board backed a call for a statewide moratorium on data…
1500 Gateway Data Center Project
Penzance Development / 1500 Gateway Venture, LLC
City of Fredericksburg
VA · PJM
under appeal
zoning denialcommunity opposition
Fredericksburg Planning Commission unanimously rejected (7-0) the 2.1M-SF rezoning and Special Use Permit in December 2025, its second denial after an initial February 2025…
Emerald Lakes Estates data center (Great Bridge)
Doug Fuller / Emerald Lakes Estates
Great Bridge, City of Chesapeake
VA · PJM
cancelled
zoning denialcommunity opposition
Would have been Hampton Roads' first major data center; Chesapeake City Council unanimously denied the agricultural-to-light-industrial rezoning for a 350,000 SF facility on…
Chesapeake 8-month data center application pause
City of Chesapeake
VA · PJM
pending review
local moratoriumcommunity opposition
Chesapeake City Council voted to approve an 8-month hold on all new data center application decisions amid growing calls for a statewide Virginia moratorium.
Chesapeake data center zoning text amendment (Green Sea area)
City of Chesapeake
VA · PJM
delayed
zoning denialcommunity opposition
Chesapeake Planning Commission recommended against a data-center zoning text amendment in May 2025; a related zoning text amendment was indefinitely continued by the Planning…
Mt. Airy Planned Innovation, Research and Technology data center campus
VALCO (applicant); Thompson Family Office (landowner)
Ruther Glen/Jericho Road, Caroline County
VA · PJM
withdrawn
zoning denialcommunity opposition
Caroline County Board of Supervisors denied 5-1 a comprehensive-plan amendment for a 900-acre campus near the North Anna River; VALCO then withdrew its rezoning request. The…
Google Botetourt County data center campus
Google (GOOGL)
Botetourt County
VA · PJM
litigation active
litigationwater dispute
Western Virginia Water Authority stated it will not supply the 10-million-gallons/day Google sought; a FOIA lawsuit forced disclosure of secret water-use contracts (judge ordered…
Campbell County data center rezoning (MESH Capital site)
MESH Capital LLC
Concord District, Campbell County
VA · PJM
cancelled
zoning denialcommunity opposition
Campbell County Board of Supervisors voted 5-2 to reject removing 2000-era protective conditions from a 57-acre site marketed for up to three data centers, after dozens of…
Surry County data center moratorium
Surry County
VA · PJM
pending review
local moratorium
Surry County enacted an initial 60-day pause on data center approvals in June 2026, then extended it to a full two-year moratorium on July 21, 2026, while directing staff to…
Powhatan County data center zoning proposal (Route 60/Page Road)
Newport Equities / JMS Investments
Powhatan County
VA · PJM
delayed
community opposition
A community petition ("Preserve Powhatan") urged the Planning Commission to block a 120-acre data-center zoning proposal near the Chesterfield County line; the Board of…
Amazon Louisa County data center (third project, cancelled)
Amazon (AMZN)
Louisa County
VA · PJM
cancelled
community opposition
Amazon pulled a proposed third Louisa County data center project in July 2025 after strong community resistance, even as it continued building two other campuses in the county.
Amazon Louisa County data center campus (Northeast Creek overlay, active construction)
Amazon (AMZN)
Louisa County
VA · PJM
litigation active
litigation
Homeowner Austin Newsom sued Amazon for private nuisance over brown water, dust and construction noise at Amazon's second Louisa County campus; a federal judge allowed the…
Amazon Birchwood power plant data center campus
Amazon (AMZN)
Sealston, King George County
VA · PJM
litigation active
litigationzoning denial
Board of Supervisors moved in April 2024 to re-rezone the old Birchwood power plant site back to agricultural, threatening Amazon's planned 19-building, 7.25M SF campus; Amazon…
New Kent County data center-friendly technology overlay district
New Kent County
VA · PJM
cancelled
community opposition
Faced with widespread public disapproval at town-hall meetings, New Kent County supervisors spiked the plan to create a data-center-friendly overlay zone in July 2026,…
Plaza 500 data center campus / Edsall Data Center Substation 2232
Starwood Capital Group (Starwood Digital Ventures)
Lincolnia, Fairfax County
VA · PJM
pending review
community opposition
Alexandria City Council formally asked Fairfax County to deny the Edsall Road substation feeding this 226,469 SF Starwood data center near the Bren Mar neighborhood; Rep. Don…
Manassas National Battlefield adjacent data center litigation (American Battlefield Trust)
QTS / Compass Datacenters (BX)
Manassas/Gainesville, Prince William County
VA · PJM
cancelled
litigationenvironmental review
American Battlefield Trust sued to stop data center construction abutting Manassas National Battlefield Park; after a judge initially dismissed part of the suit (Nov 2024), the…
Brightseat Tech Park (former Landover Mall site)
Brightseat Associates LLC (Lerner Enterprises / The Tower Cos.)
Landover, Prince George's County
MD · PJM
820 pending review
local moratoriumcommunity opposition
Despite securing final approvals for 4.1M SF of data centers in Oct 2024, County Executive Aisha Braveboy ordered a temporary halt to all data center permitting on Sept 15, 2025…
Prince George's County Qualified Data Centers moratorium (Brandywine area)
Brandywine, Prince George's County
MD · PJM
pending review
local moratoriumcommunity opposition
Prince George's County Council initially voted against advancing data centers (Nov 2024) and enacted a countywide moratorium on "Qualified Data Centers" extended to expire June…
Quantum Frederick
Frederick County
MD · PJM
litigation active
litigationlocal moratoriumcommunity opposition
Maryland Supreme Court blocked a citizen-driven referendum bid seeking to overturn a county ordinance that expanded the ~1,600-acre Quantum Frederick campus by 1,000 acres to…
Charles County Zoning Text Amendment 25-187 (data center zoning enablement)
Charles County
MD · PJM
withdrawn
zoning denialcommunity opposition
Charles County Planning Commission twice recommended denial of ZTA 25-187, which would have permitted data centers in industrial zones, after hearings featuring "no data centers"…
Penzance Bedington data center campus
Penzance Management
Bedington, Berkeley County
WV · PJM
delayed
community opposition
Gov. Patrick Morrisey announced the $4B, 500+ acre Penzance data center near the Potomac River on Feb 26, 2026; more than 300 residents packed a March 20 county commission town…
Jefferson County (WV) data center moratorium
Jefferson County
WV · PJM
pending review
local moratoriumcommunity opposition
Jefferson County Board of Commissioners issued a 10-month moratorium (May 19, 2026) on new data center applications/rezonings, excepting sites already zoned via Planned…
Microsoft New Albany / Heath / Hebron Licking County data center campuses
Microsoft (MSFT)
New Albany, Heath, Hebron, Licking County
OH · PJM
delayed
community opposition
Microsoft paused all three Licking County data center sites (New Albany, Heath, Hebron; $1B combined, 700+ acres) in April 2025 while "evaluating sites in line with our…
Amazon Data Services Sunbury data center campus
Amazon (AMZN)
Sunbury, Delaware County
OH · PJM
pending review
local moratoriumcommunity opposition
Sunbury has an active data center development moratorium (through Jan 31); residents are gathering signatures for a city charter amendment capping data center peak load at 25MW…
Aligned Data Centers Pataskala facility
Aligned Data Centers
Pataskala, Licking County
OH · PJM
200 delayed
community opposition
Pataskala residents are collecting signatures for a municipal charter amendment capping data center peak load at 25MW, aimed squarely at blocking this proposed 200MW/89-acre…
Pennhurst data center (East Vincent Township)
Pennhurst Holdings LLC
East Vincent Township, Chester County
PA · PJM
under appeal
zoning denialcommunity oppositionlitigation
East Vincent Township officials unanimously rejected a 1.9M-SF data center on the historic Pennhurst State School site; the developer plans to appeal to the Chester County Court…
East Whiteland data center (Chesco)
East Whiteland Township, Chester County
PA · PJM
litigation active
litigationcommunity opposition
A controversial 1.6M-SF data center in East Whiteland faced community legal challenges over its approval; the project survived a court denial of the challengers' appeals in June…
North Coventry boutique data center (Envision Land Use)
Envision Land Use
North Coventry Township, Chester County
PA · PJM
cancelled
community oppositionzoning denial
North Coventry Township supervisors preemptively voted 3-2 to reject a proposed 120,000 SF data center near a PECO substation before a formal application was even filed,…
Chester County temporary data center moratorium
Chester County
PA · PJM
pending review
local moratorium
Chester County approved a temporary countywide moratorium on new data center project approvals to allow time for zoning study and regulation drafting.
King of Prussia data center campus (Brian O'Neill applications)
Brian O'Neill
Upper Merion Township, Montgomery County
PA · PJM
litigation active
litigationcommunity opposition
Developer Brian O'Neill sued Upper Merion Township; a Montgomery County judge issued an injunction (Aug 13, 2026) preventing the township from taking further action on his King…
Keystone Trade Center AI data center campus (Amazon/NorthPoint)
NorthPoint Development
Falls Township, Bucks County
PA · PJM
delayed
community opposition
Despite construction proceeding on the former U.S. Steel site (part of a $20B statewide Amazon investment), Falls Township residents organized a nearly 4,000-signature petition…
Northampton County proposed data center farm conversions
Northampton County
PA · PJM
delayed
community opposition
Northampton County residents packed public meetings voicing fierce opposition ("I don't want you") to proposed data centers taking over farmland; a local coordinated "No Data…
Homer City Energy Campus
Homer City Redevelopment / Homer City Generation
Homer City, Indiana County
PA · PJM
4,400 pending review
environmental review
Pennsylvania DEP fast-tracked and approved an air-quality permit (157 days vs. the projected 285) for this 4.4GW gas-fired data center campus at a former coal plant despite 500+…
New Hill Digital Campus
Natelli Holdings (Natelli Investments LLC)
New Hill/Apex, Wake County
NC · SERC
300 withdrawn
community oppositionzoning denial
Developer withdrew annexation and rezoning applications for a 300MW campus near the Shearon Harris Nuclear Plant after a 2,000+ signature petition and intense resident backlash…
Triangle Innovation Park West (TIP West)
Eco TIP West LLC (Kirk Bradley / Lee-Moore Capital)
Moncure, Chatham County
NC · SERC
750 litigation active
litigationlocal moratorium
Chatham County's 12-month moratorium on new data center/crypto-mine permits (adopted Feb 11, 2026) halted processing of TIP West's site plan; Eco TIP West sued the county in…
Chatham County data center and crypto-mine moratorium
Chatham County
NC · SERC
pending review
local moratorium
Chatham County commissioners unanimously approved a 12-month moratorium on new data center and cryptocurrency-mine permits (through February 2027) to draft new zoning rules and…
Gates County data center moratorium
Gates County
NC · SERC
pending review
local moratorium
Gates County's board of commissioners unanimously approved a one-year pause on new data center approvals amid growing statewide North Carolina opposition to hyperscale projects.
Person County Microsoft data center
Microsoft (MSFT)
Person County
NC · SERC
delayed
community opposition
Person County residents publicly demanded answers from Microsoft over a planned local data center; Microsoft hosted a community meeting in June 2026 amid rising central-NC…
Hexa Builders Monroe Township data center (Black Horse Pike redevelopment)
Hexa Builders LLC
Williamstown, Monroe Township, Gloucester County
NJ · PJM
litigation active
zoning deniallocal moratoriumlitigationcommunity opposition
After winning preliminary approval for two warehouses in January 2026, Hexa amended its application to swap in a 1M-SF data center; Monroe Township passed ordinances in April…
Former Newton Airport site data center proposal
Andover Township, Sussex County
NJ · PJM
litigation active
local moratoriumlitigation
A developer sued Andover Township in state Superior Court (filed July 10, 2026) to overturn its data-center ban, alleging officials enacted the prohibition preemptively before…
James City County data center special-use review policy
James City County
VA · PJM
pending review
zoning denial
James City County supervisors moved to require special-use permit review for all data centers rather than by-right development, directing staff to draft a formal policy…
Frederick County (VA) countywide data center ban consideration
Frederick County
VA · PJM
pending review
local moratoriumcommunity opposition
Frederick County supervisors moved to consider a countywide ban on new data centers, following sustained opposition from Winchester-area residents citing six proposed projects;…
DC Blox Indianapolis (Warren Township)
DC Blox
Warren Township, Indianapolis (Marion County)
IN · MISO
approved but citywide moratorium pending
community oppositionproposed moratorium
One of three Indianapolis data centers drawing the most community opposition (energy, water, noise). Approved in July 2026 and would be exempt from the moratorium the City-County…
Metrobloks Martindale-Brightwood
Metrobloks
Martindale-Brightwood, Indianapolis (Marion County)
IN · MISO
approved but citywide moratorium pending
community oppositionproposed moratorium
Approved in May 2026 despite opposition; cited as one of three Indianapolis projects driving the citywide moratorium push.
Sabey Data Center (Decatur Township)
Sabey Data Centers
Decatur Township, Indianapolis (Marion County)
IN · MISO
approved but citywide moratorium pending
community oppositionproposed moratorium
Metropolitan Development Commission approved the $4B Sabey project in March 2026; one of the three flashpoint projects behind Indianapolis's moratorium debate.
Google Franklin Township Campus (withdrawn)
Google (GOOGL)
Franklin Township, Indianapolis (Marion County)
IN · MISO
withdrawn
community oppositionrezoning denial or withdrawal
Google withdrew a proposal to rezone hundreds of acres in Franklin Township for a data center campus after contested opposition to the rezoning.
New Carlisle $13B Data Center (St. Joseph County)
Amazon (reported) (AMZN)
New Carlisle, St. Joseph County
IN · MISO
rezoning denied
rezoning denialcommunity opposition
St. Joseph County Council voted 7-2 after a 10-hour, marathon meeting to deny rezoning ~1,000 acres of farmland off Chicago Trail. Opposition cited environmental impact,…
Hobart Amazon Data Center Campus
Amazon (AMZN)
Hobart (Lake County), Ross Township
IN · MISO
active litigation
litigationpermit challenge
Hobart Plan Commission approved a fill permit Nov 6, 2025 for a 725-acre Economic Redevelopment Area near wetlands by Deep River. Residents sued alleging permit issued without…
Microsoft Granger Data Center
Microsoft (MSFT)
Granger, St. Joseph County
IN · MISO
approved amid opposition
community opposition
Approved Microsoft project in St. Joseph County drew continued resident protests at an open house over energy, water, and jobs concerns even after approval, part of broader…
301 Digital Crossroads / CoreWeave (Hammond)
CoreWeave / Decennial Group (CRWV)
Hammond
IN · MISO
development agreement expired
missed milestonesfinancing delay
City of Hammond announced the expiration of the $7B Development Agreement at 301 Digital Crossroads after required milestones were not met by the June 30, 2026 deadline; two…
Clinton County Data Center / Precast Plant / Hydroponic Farm
Unnamed developer
Clinton County
IN · MISO
rezoning denied
rezoning denialunresolved commitments
Clinton County Board of Commissioners voted 3-0 to deny rezoning ~714.55 acres from A-1 agricultural to I-1 light industrial for a mixed data center, precast plant, and…
Boone County Unincorporated Data Center Moratorium
Boone County (unincorporated)
IN · MISO
moratorium in force
county moratorium
Boone County Board of Commissioners unanimously approved a one-year moratorium (effective June 16, 2026 to June 15, 2027) on new data center development in unincorporated Boone…
Madison County Data Center Moratorium (extended)
Madison County
IN · MISO
moratorium extended
county moratorium
Madison County commissioners unanimously extended a data-center moratorium to a full year to draft zoning rules, potentially including a permanent ban. Majority of residents at…
Meta New Albany Data Center (Socrates South / AEP substation dispute)
Meta (META)
New Albany, Licking County
OH · PJM
250 regulatory approval pending
regulatory reviewpower allocation dispute
Meta sought to draw 120-250MW from an idle AEP Ohio substation originally built for Intel's delayed chip fab (Intel now slated 2030-31, delayed from original date). AEP Ohio and…
Microsoft Licking County Data Center (construction paused)
Microsoft (MSFT)
Licking County
OH · PJM
construction paused
corporate reassessmentopenai relationship changetariff costs
Microsoft halted early-stage construction on a $1B Ohio site (three parcels; two reserved for farmland), citing reassessment of cloud/AI infrastructure needs, evolving…
Amazon Data Services Sunbury Campus
Amazon (AMZN)
Sunbury, Delaware County
OH · PJM
proposed amid local moratorium and ballot fight
local moratoriumballot initiative threat
Sunbury has a data-center development moratorium in place until Jan 31 (2027); residents fear council could approve the $2B Amazon facility once it expires and are collecting…
Conserve Ohio Statewide Data Center Ban Ballot Initiative
Statewide (Ohio)
OH · PJM
signature gathering
ballot initiative threatstatewide moratorium push
Ohio Ballot Board approved a proposed constitutional amendment to prohibit large data center construction; Conserve Ohio needed 413,487 signatures from 44+ counties by July 1,…
Lighthouse Campus (Port Washington), Oracle/Vantage/OpenAI
Oracle / Vantage Data Centers (ORCL)
Port Washington, Ozaukee County
WI · MISO
1,000 active litigation
litigationenvironmental review challengeregulatory collateral dispute
Nearly 1GW Stargate-partnership campus. Wisconsin PSC's April 2026 order required hyperscale operators (incl. Oracle) to post financial security before power service; estimated…
Microsoft Mount Pleasant AI Campus (Foxconn site)
Microsoft (MSFT)
Mount Pleasant, Racine County
WI · MISO
construction partially paused
corporate reassessmentdesign changes
Built on former Foxconn site; total footprint ~1,121 acres across three parcels (215, 115, 791 acres); Microsoft now owns ~1,900 acres in Mount Pleasant. Microsoft paused…
Microsoft Kenosha Data Center (proposed)
Microsoft (MSFT)
Kenosha, Kenosha County
WI · MISO
under council consideration
community opposition
Residents packed multiple public forums urging Kenosha Common Council to slow consideration, citing water extraction, 24/7 noise, air quality tied to a linked 1,186 MW…
QTS DeForest / Vienna Annexation ($12B, cancelled)
QTS Data Centers (BAM)
DeForest / Town of Vienna, Dane County
WI · MISO
cancelled
withdrawalvillage infeasibility finding
QTS's $12B proposal required annexing 1,600 acres from the Town of Vienna into DeForest. On Jan 27, 2026 village staff determined the project 'not feasible in DeForest' after ~7…
Pine Island Data Center (Google)
Ryan Companies (developer) (GOOGL)
Pine Island, Goodhue County
MN · MISO
2,700 construction halted by court
litigationenvironmental review inadequate
Could require up to 2,700MW. MCEA sued in October 2025 alleging environmental review only covered a generic 'technology center'/'light industrial' use, not disclosing Google as…
Eagan Capital Expansion (Data Center Moratorium Suit)
Eagan Capital
Eagan, Dakota County
MN · MISO
active litigation
litigationcity moratorium
Eagan's development-pause ordinance (20MW+ new / 9MW+ expansion) is challenged by Eagan Capital, arguing the moratorium exceeds the city's authority; lawsuit filed to void the…
Farmington Technology Park (Tract)
Tract
Farmington, Dakota County
MN · MISO
708 active litigation
litigationenvironmental review challenge
Denver-based Tract's 340-acre, up-to-12-building, 2.5M-sq-ft campus (~$5B at full buildout) on former golf-course/school land. Residents sued on technical and later environmental…
Meta Rosemount Data Center (UMore Park)
Jimnist LLC (Meta subsidiary) (META)
Rosemount, Dakota County
MN · MISO
final decision paused
environmental review pending
Planning Commission approved the site plan, but the City Council paused final action until after Dec 20 pending completion of a required 5-year Alternative Urban Areawide Review…
Minneapolis Citywide Data Center Development Pause
Minneapolis, Hennepin County
MN · MISO
moratorium in force
city moratorium
Minneapolis City Council approved a five-month pause on new data center development (excludes downtown centers under 350,000 sq ft) to study environmental, energy, and…
Elk River Proposed Data Center
Elk River, Sherburne County
MN · MISO
planning commission recommended denial
planning commission denial recommendation
Elk River's planning commission recommended against a proposed data center despite advocates citing an estimated $800,000 in additional city revenue.
Inver Grove Heights Proposed Data Center
Inver Grove Heights, Dakota County
MN · MISO
final vote delayed
council vote delaycommunity opposition
City council delayed a final vote after a packed, contentious meeting erupted in boos over the delay.
University of Michigan / Los Alamos High-Performance Computing Facility
University of Michigan / Los Alamos National Laboratory
Ypsilanti Township, Washtenaw County
MI · MISO
100 opposed planned
community oppositioncity council resolution against
144.5-acre site on Textile Road near Ford Lake Dam; $1.2B taxpayer-supported project planned to start construction 2027, operational by 2031. Ypsilanti City Council unanimously…
Saline Township 'The Barn', OpenAI/Oracle Stargate Campus
Related Digital (ORCL)
Saline Township, Washtenaw County
MI · MISO
1,400 rezoning denied then litigation settled
rezoning deniallitigation
Part of OpenAI/Oracle's Stargate initiative; ~1,400MW from DTE Energy; 575 acres of farmland proposed for rezoning within a ~1,000-acre campus (two-thirds to remain open space).…
Alterra Development Marshall Data Center (Brooks Industrial Park)
Alterra Development
Marshall, Calhoun County
MI · MISO
1,000 moratorium delay
city moratoriumcommunity opposition
Alterra purchased 270 acres in Brooks Industrial Park near wetlands/a lake; original concept (gas plant + data center, ~1,000MW/1GW) later dropped the gas plant, cutting energy…
Microsoft / Franklin Partners Covenant Business Park (Lowell-area township)
Microsoft / Franklin Partners (MSFT)
Township adjacent to Lowell (Kent County)
MI · MISO
rezoning paused
community oppositionplanning commission postponement
Estimated $500M-$1B investment over 3-5 years. Site needs rezoning from industrial PUD to light industrial. A December 2025 planning commission public hearing was…
West Michigan Hyperscale Proposals (Solon, Lowell, Gaines Townships)
Solon, Lowell, and Gaines Townships (Kent County)
MI · MISO
opposed proposed
community oppositiontransparency concerns
Residents protested outside The Right Place's Developer Day (June 9-11, 2026) over multiple hyperscale proposals across three townships; criticism centered on private…
Gotion Green Township Battery/Data Plant (abandoned)
Gotion
Green Township, near Big Rapids
MI · MISO
abandoned
litigationcommunity oppositionchina ties backlash
Gotion abandoned its planned Green Township facility after legal challenges, environmental issues, and backlash over the company's China ties; Michigan had committed a $715M…
T5 @ Chicago IV (Grayslake)
T5 Data Centers
Grayslake, Lake County
IL · PJM
1,550 active litigation
litigationwetlands permit suspended
Up to 472 acres within the $750M, 641-acre Cornerstone mixed-use development; ~1.55GW electrical demand from ComEd. Village Board approved between Sept 2024-May 2025. On July 31,…
Project Vector / Endeavour Energy DeKalb Data Center
Endeavour Energy
DeKalb
IL · PJM
opposed pending council vote
community opposition
Also referred to as the 'Edged data center'; ~560 acres along Route 23; Planning and Zoning Commission backed the project after a crowded hearing, but a Change.org petition drew…
South Elgin Data Center (Whiterose Partners / Kenyon Brothers)
Whiterose Partners / Kenyon Brothers Co.
South Elgin, Kane County
IL · PJM
48 opposed effectively stalled
community oppositionpetition campaign
20-acre, 200,000-sq-ft, 48MW proposal at Kenyon Road/Route 25 requiring annexation, rezoning, and special-use permit. A petition gathered 4,800 signatures within 48 hours; a July…
Aurora Data Center and Warehouse Moratorium
Aurora, Kane/DuPage Counties
IL · PJM
moratorium in force
city moratorium
Aurora City Council enacted a 180-day moratorium (Sept 25, 2025) on new data center and warehouse development to research standards and draft zoning rules; applications can be…
Project Cardinal (Yorkville)
Yorkville, Kendall County
IL · PJM
active litigation
litigationpublic notice violation alleged
1,037-acre planned campus, approved earlier in 2026. Residents (Preserve Our Yorkville & Community LLC) sued in April alleging the city failed to give required public notice,…
Project Steel (Yorkville, Eldamain Corridor)
Yorkville, Kendall County
IL · PJM
active litigation
litigationpublic notice violation alleged
Second Yorkville lawsuit, filed by residents including Teska Family Farm, along the Eldamain Corridor; land was annexed/rezoned from residential to manufacturing; suit alleges…
Meyer Project / Yorkville Nexus V LLC Rezoning (withdrawn)
Green Door Capital
Yorkville, Kendall County
IL · PJM
withdrawn
rezoning denialno secured tenantcouncil opposition
~130-acre rezoning request (91 acres west, 37 acres east) south of Project Steel; Planning and Zoning Commission rejected in January 2026; City Council vote postponed in March;…
DC Blox Nashville Zoo-Area Data Center
DC Blox
Nashville, Davidson County
TN · SERC
active litigation
litigationcity moratoriumeminent domain threat
DC Blox filed a federal lawsuit against Metro Nashville after the city stopped processing permits under its temporary data-center moratorium (in effect through December 2026),…
Hillwood Industrial/Data Center Development (Wilson County)
Hillwood
Wilson County
TN · SERC
rezoning rejected moratorium recommended
rezoning denialcounty moratorium recommended
Texas-based Hillwood's proposed 1,380-acre, 10.35M-sq-ft industrial development (no data-center tenant named) near I-40 was rejected by Wilson County commissioners roughly 18…
xAI Colossus 1 & 2 (Memphis)
xAI / SpaceX
Memphis, Shelby County
TN · SERC
active litigation
litigationenvironmental review orderunpermitted power plant
NAACP sued xAI on April 14, 2026 alleging air pollution from unpermitted gas turbines powering Colossus 1/2 in a majority-Black Memphis community; DOJ intervened on xAI's side…
Serverfarm Clarksville ($6.6B)
Serverfarm
Clarksville, Montgomery County
TN · SERC
under construction amid scrutiny
community oppositiontransparency concerns
$6.6B project beside Johnson Regional Medical Center advancing (cranes visible, hillside cleared as of January 2026) despite growing community scrutiny over communication, water…
Douglas County I-20 Data Center Permit Denial (11-building/3-warehouse application)
Douglas County (near I-20 / Carroll County line)
GA · SERC
permit denied
permit denialcommunity oppositioncounty moratorium
Douglas County commissioners voted 4-1 to deny a proposed data center permit near the Carroll County line/I-20 after a packed, contentious commission meeting. Separately, a…
Project Sail (Coweta County)
Prologis / Atlas Development (PLD)
Coweta County (Sargent community, near Newnan)
GA · SERC
900 approved active litigation
county moratoriumlitigationcommunity opposition
Nine-building, 4.34M-sq-ft, ~900MW campus on 829 acres of protected rural conservation land near Georgia Power's Plant Yates. First surfaced Dec 31, 2024; Coweta commissioners…
Project Pegasus (Coweta County)
American Real Estate Partners (backed)
Coweta County
GA · SERC
delayed amid moratorium
county moratoriumcommunity opposition
Second Coweta County data-center proposal (Virginia-based American Real Estate Partners-backed developers) caught in the same 2025 county moratorium and zoning rewrite that…
Newton County Data Center Application Moratorium
Newton County (incl. Covington, Social Circle, Porterdale)
GA · SERC
moratorium in force
county moratorium
Newton County Board of Commissioners unanimously enacted a 30-day moratorium on new data-center applications to update ordinances amid a rapid influx of requests (does not affect…
QTS Atlanta Data Center Expansion (Howell Station, tax break withdrawn)
QTS Data Centers (BAM)
Atlanta, Fulton County (Howell Station)
GA · SERC
tax incentive withdrawn
public outcrytax break withdrawal
Development Authority of Fulton County had considered a $45M tax break for a QTS expansion near the Howell Station neighborhood; the request was withdrawn amid public outcry even…
Project Tango (Palm Beach County)
Palm Beach County (near Arden / Loxahatchee)
FL · FRCC
denied without prejudice
permit denialcommunity opposition
Palm Beach County commissioners denied the hyperscale AI data center 'without prejudice' after nearly 12 hours of debate, meaning the developer may revise and resubmit; site…
XF Group Sarasota County Hyperscale Data Center Freeze
XF Group
Sarasota County (Cattlemen Road)
FL · FRCC
moratorium in force
county moratorium
Sarasota County commissioners voted July 8, 2026 to halt acceptance, review, and approval of hyperscale data centers (50MW+) until at least July 2027 along Cattlemen Road;…
MIA-1 Data Center (Iron Mountain, Westview)
Iron Mountain (IRM)
Westview, unincorporated Miami-Dade County
FL · FRCC
16 under construction amid opposition
community oppositiontransparency concerns
16MW, 150,000-sq-ft, $150M facility on a 3.4-acre industrial site in a predominantly Black community. Approved by-right under existing industrial zoning classified as a…
Alachua Phoenix Commercial Park (rumored data center)
Alachua, Alachua County
FL · FRCC
rumored no application filed
community oppositionmeeting postponed
104-acre Phoenix Commercial Park site east of San Felasco Tech City was listed as a 'high megawatt data center development site' and later relisted as an 'industrial…
Meade County 138-Acre Data Center Rezoning (denied)
Meade County (near Brandenburg)
KY · SERC
rezoning denied
rezoning denialcommunity opposition
138-acre site along Joe Prather Highway; Planning and Zoning Commission voted unanimously against rezoning from agricultural to light industrial and the Fiscal Court agreed with…
Lexington-Fayette Former Lexmark Property Data Center Moratorium
Lexington-Fayette Urban County
KY · SERC
moratorium in force
city moratoriumcommunity opposition
Lexington-Fayette Urban County Government unanimously passed a moratorium on new data center development at a proposed site on the former Lexmark property, effective through…
Burgin / Mercer County Proposed Data Center (draft ordinance pending)
Burgin, Mercer County
KY · SERC
under review no zoning process
community oppositionno local zoning framework
Residents allege developers targeted Burgin because it lacked a formal planning/zoning process; the Mercer County Joint Planning and Zoning Commission was set to discuss a draft…
Meta Hyperion & Evest Data Centers (Richland Parish)
Meta / Entergy (META)
Richland Parish
LA · SERC
5,000 regulatory disclosure dispute
regulatory transparency disputeratepayer cost concerns
Combined Hyperion and Evest campuses represent Meta's >5GW power request, described as the largest in Louisiana history; Entergy proposing 10 new gas plants (3 approved 2025, 7…
xAI Southaven Data Center & Gas Turbine Plant (noise/class action)
xAI / SpaceX (MZX Tech LLC)
Southaven, DeSoto County
MS · SERC
active litigation
litigationunpermitted power plantnoise nuisance
One of three xAI data centers in the Memphis metro built with 57 temporary gas turbines and a permit for 41 additional permanent turbines. Three Southaven residents filed a…
Downtown Kansas City High-Rise Data Center (Quality Hill / Western Newspaper Union Building)
Revitalization Unlimited
Kansas City, Jackson County
MO · SPP
permit denied
permit denialhistoric preservation conflictcommunity opposition
Miami-based developer Revitalization Unlimited proposed a 384-foot, 20-story data center atop the historic Western Newspaper Union building in Quality Hill; Kansas City Plan…
St. Charles County Data Center Moratorium
St. Charles County
MO · SPP
moratorium in force
county moratoriumcommunity opposition
St. Charles County Council unanimously approved a six-month moratorium on new data centers after overwhelming public opposition; County Executive Steve Ehlmann said more research…
Google Stillwater Data Center Campus (up to 6 buildings)
Google (GOOGL)
Stillwater, Payne County
OK · SPP
under construction amid water concerns
community oppositionwater capacity constraints
Google building up to six data centers; first two buildings expected to use ~2.7M gallons/day, rising to 8.1M gallons/day if all six are built (against ~7M gallons/day current…
Project Anthem (East Tulsa)
East Tulsa, Tulsa County
OK · SPP
phase vote delayed
city moratorium partial exemptionplanning commission delay
Tulsa City Council voted unanimously (Mar 25, 2026) for a nine-month citywide data-center construction moratorium; Project Anthem's first and second phases were exempted, but the…
Sand Springs Meta-Backed Data Center
Meta (reported) (META)
Sand Springs, Tulsa County
OK · SPP
opposed proposed
community oppositiontransparency concerns
Tribal advocates and residents protested secrecy around a Meta-backed Sand Springs data center proposal; hundreds attended public meetings opposing the project.
Project Pilot / Beale Infrastructure De Soto Campus
Beale Infrastructure (Mount Sunflower Properties LLC)
De Soto, Johnson County
KS · SPP
approved expanded amid opposition
community oppositionnoise regulation review
Kansas' first hyperscale data center; ~300-acre site near the Panasonic EV battery plant on the former Flint Commerce Center/Ad Astra Park site. De Soto City Council approved the…
Apple Waukee Data Center (extension)
Apple (AAPL)
Waukee, Dallas County
IA · MISO
delayed extension requested
multi year construction delaydesign changes
$1.3B facility (400,000 sq ft) originally due to complete by August 2022; Apple requested a five-year extension to August 2027, citing need for more design/build time. Only…
Linn County Unincorporated Area Data Center Moratorium
Linn County (unincorporated, near Cedar Rapids)
IA · MISO
moratorium in force
county moratorium
Linn County Board of Supervisors approved an 18-month moratorium (2-1 vote, through Jan 1, 2028) for unincorporated county areas to update its data-center ordinance, conduct a…
MidAmerican Energy Salix Data Center Exploration
MidAmerican Energy (BRK.A)
Salix, Woodbury County
IA · MISO
early stage amid county moratoriums
county moratorium neighboring
MidAmerican Energy annexed nearly 1,000 acres of farmland into Salix to explore data center development, even as neighboring Plymouth, Sioux, and Woodbury counties adopted…
NorthMark Strategies / Valara Holdings Computing Center (former Kohler plant)
NorthMark Strategies (Valara Holdings)
Spartanburg County
SC · SERC
450 permitting challenged
regulatory reviewenvironmental petition
$2.8B conversion of a former Kohler kitchen/bath plant (also a longtime bitcoin-mining site) into a computing center. State regulators initially approved ~50MW; company sought to…
Stream Data Centers Marion County (abandoned)
Stream Data Centers
Marion County
SC · SERC
400 abandoned
utility interconnection timingwithdrawal
Dallas-based Stream Data Centers dropped a planned 400MW, 400-acre, ~600,000-sq-ft campus in an industrial park near Marion, SC, citing 'utility timing constraints', MPD Electric…
Greenwood County Data Center Moratorium
Greenwood County
SC · SERC
moratorium in force
county moratorium
Greenwood County Council advanced a one-year moratorium on data centers in a 4-3 vote.
Nebius Data Center (Oxmoor Valley, Birmingham)
Nebius (NBIS)
Birmingham, Jefferson County (Oxmoor Valley)
AL · SERC
active litigation
litigationzoning approval challenge
Under construction off Lakeshore Parkway. Jefferson County Circuit Judge ruled July 11, 2026 that Oxmoor Valley residents' lawsuit against the city's approval process can…
Bessemer Proposed Data Center (Little Blue Creek)
Bessemer, Jefferson County
AL · SERC
zoning request paused active litigation
litigationcouncil agenda removalenvironmental concerns
Proposed site near ecologically sensitive Little Blue Creek and Five Mile Creek (habitat for the endangered watercress darter). Bessemer City Council removed the zoning item from…
Jones Eagle / Jones Digital DeWitt Crypto Data Center
Jones Eagle LLC / Jones Digital
DeWitt, Arkansas County
AR · SPP
active litigation temporary block
litigationstate law ownership ban
Owner Qimin 'Jimmy' Chen (naturalized US citizen born in China) challenged Arkansas Act 636 (2023) and Act 174 (2024), which bar data-center/crypto-mining property ownership by…
AVAIO Data Center Project (Pulaski County)
AVAIO
Pulaski County
AR · SPP
moratorium exemption rejected
quorum court rejectioncounty moratorium dispute
Pulaski County Quorum Court rejected a proposed data-center moratorium that would have carved out an exemption specifically for the AVAIO project; separately, Little Rock's own…
Grant County Data Center FOIA Dispute
Grant County
AR · SPP
active litigation records dispute
litigationpublic records dispute
Public-records (FOIA) litigation over a proposed Grant County data center; part of a broader pattern of Arkansas Democrat-Gazette records lawsuits seeking data-center contract…
Imperial Data Center (Imperial Valley Computer Manufacturing / IVCM)
Imperial Valley Computer Manufacturing, LLC (developer Sebastian Rucci)
Imperial County (near city of Imperial)
CA · CAISO
delayed
local moratoriumwater disputecommunity opposition
Would be largest data center in California at ~1M sq ft; promoted as producing 2,500 construction jobs and $28.7M/yr tax revenue; county supervisors first approved parcel merger…
GI Partners Santa Clara Data Center (2805 Bowers Avenue)
GI Partners
Santa Clara
CA · CAISO
delayed
litigationpermit denial
Four-story data center; site cost $79M. Delayed ~5 months versus planned construction timeline before City Council approval on Aug 29, 2024.
Coachella Valley Technology Campus
Stronghold Power Systems
Coachella (Riverside County)
CA · CAISO
cancelled
local moratoriumcommunity opposition
Six data centers proposed across 450 acres of agricultural land; was to anchor a new city-run utility agency; council unanimously voted to terminate the Stronghold agreement…
Eight Form El Segundo Data Center (750 N. Nash Street)
Eight Form
El Segundo (Los Angeles County)
CA · CAISO
withdrawn
community opposition
Proposed replacing a 15-year-old Hyatt Place hotel with 160-foot, five-story data center plus dedicated electrical substation.
Monterey Park Data Center (HMC StratCap)
HMC StratCap
Monterey Park (Los Angeles County)
CA · CAISO
cancelled
community opposition
247,000 sq ft facility that would have used ~3x electricity of entire 60,000-person city; would have sat under 500 feet from nearest home; ban can only be overturned by another…
Behring AI Campus / Data Center (415 20th St.)
Behring Companies
Oakland
CA · CAISO
20 delayed
community opposition
~20,000 sq ft of an 83,000 sq ft, 4-story building; part of a larger complex with a proposed 39-story apartment tower above 19th St BART station.
San Jose Data Center Pipeline (multiple Equinix and other projects)
Multiple (incl. Equinix) (EQIX)
San Jose
CA · CAISO
pending review
state moratoriumlocal moratoriumcommunity opposition
Environmental groups Green Foothills flagged 'grandfathering' risk since developers may rush applications ahead of new standards; active CEQA EIR review process for Equinix…
High-Speed Rail Corridor Data Center Deals (Merced/Madera)
California High-Speed Rail Authority (co-development partners TBD)
Merced / Madera / Kern County
CA · CAISO
pending review
water dispute
CEO Ian Choudri says hyperscalers in talks for Central Valley sites including Kern County; Madera mayor Cecilia Gallegos said city would reject data centers over water use.
Project Blue (Tucson)
Beale Infrastructure (originally Amazon Web Services-linked; AWS later withdrew) (AMZN)
Pima County / Tucson
AZ · WECC
litigation active
community opposition
Biggest development ever proposed in Pima County/southern Arizona; developer is San Francisco-based Beale Infrastructure; despite Tucson rejection and Amazon's exit, project is…
Chandler AI Data Center (Sinema-lobbied project)
Unnamed New York developer
Chandler
AZ · WECC
cancelled
zoning denial
Chandler already hosts 10 data centers and adopted 2022 rules limiting where they can be built; vote drew national progressive praise as a rare rejection of major tech-industry…
NTT Mesa Data Center
NTT (9432.T)
Mesa
AZ · WECC
delayed
water disputecommunity opposition
NTT spent $300M on land in southeast Mesa (Pecos/Crismon roads) in March 2025; requesting minor modifications to city allowances.
Casa Grande 480-Acre Data Center Campus (Willis/Barnes parcels)
Undisclosed (landowners Dale Willis and Vernon Barnes; law firm representation)
Casa Grande (Pinal County)
AZ · WECC
under appeal
zoning denialtax incentive change
No end user/tenant publicly identified; waiver includes 800 net acre-foot water cap, on-site power requirement, noise limits, decommissioning rules, $5M community contribution.
Tract Goodyear/Buckeye Data Center
Tract
Goodyear and Buckeye (Maricopa County)
AZ · WECC
withdrawn
zoning denialcommunity opposition
Company announced a replacement project near Buckeye airport in August 2024 with similar characteristics after securing mayoral support.
Boulder City BLM Data Center (Townsite Solar 2 / Eldorado Valley)
Townsite Solar 2 (subsidiary of Texas-based hedge fund)
Boulder City
NV · WECC
litigation active
litigationenvironmental review
City stood to receive an estimated $2.3M/yr in lease/tax revenue but instead disclosed BLM rent of only $1,207.67 in 2023; former BLM policy chief called the process…
Tract Northern Nevada Land Portfolio (Storey County/Reno area)
Tract
Storey County / Washoe County
NV · WECC
litigation active
litigation
Tract has purchased more than 12,000 acres across northern Nevada; company says it never sought subsidized costs and committed nearly $1B toward NV Energy infrastructure. Related…
Reno Data Center Pipeline (city-wide moratorium)
Multiple developers
Reno
NV · WECC
halted
local moratorium
Initial 30-day moratorium adopted per city rules, then extended after a 9-hour public meeting with 5+ hours of comment; some council members want to study a permanent ban.
Boardman Transmission Line / Amazon Data Center Support Infrastructure
Amazon Web Services (AMZN)
Boardman (Morrow County)
OR · WECC
litigation active
litigation
Decision on Boardman data center delayed in 2023 by new testimony; transmission line dispute continued into 2026 with regulatory challenges.
Hillsboro Data Center Pipeline (city moratorium)
Multiple developers
Hillsboro (Washington County)
OR · WECC
halted
local moratoriumwater disputetax incentive change
Hillsboro is one of Oregon's largest tech hubs (Intel/Silicon Forest); existing facilities may continue operating.
Cascade Locks Data Center (Roundhouse Digital Infrastructure)
Roundhouse Digital Infrastructure
Cascade Locks (Hood River County)
OR · WECC
cancelled
community opposition
Cited as an early precedent case for electoral backlash against data center approvals nationally.
Umatilla County Eastern Oregon Data Center Moratorium Petition
Multiple (Amazon and others) (AMZN)
Umatilla County / Morrow County
OR · WECC
pending review
state moratoriumlocal moratoriumcommunity opposition
Part of broader statewide push including a legislature-considered one-year moratorium on data center tax breaks that Gov. Kotek has expressed support for.
Seattle Data Center Pipeline (citywide moratorium)
Multiple developers
Seattle
WA · WECC
halted
community opposition
Notable given Seattle is home to Amazon and Microsoft; part of a wider wave of Washington state municipal moratoria.
Spokane Data Center Pipeline (citywide moratorium)
Multiple (incl. Avista large-load customer) (AVA)
Spokane
WA · WECC
halted
local moratorium
Data Center Coalition warned the moratorium sends a bad signal to a $1B+ minimum investment industry and could push Spokane out of site-selection conversations.
Federal Way Data Center Moratorium
Undisclosed
Federal Way
WA · WECC
halted
local moratorium
Part of broader Puget Sound-region wave of municipal pauses.
Grant County PUD Data Center Load Growth Cap
Multiple (Microsoft and others in Quincy/Moses Lake corridor) (MSFT)
Grant County (Quincy/Moses Lake)
WA · WECC
delayed
community opposition
Quincy is historically Microsoft's flagship 'data centers gone right' market; new caps signal a shift even in the most data-center-friendly Washington jurisdiction.
Broomfield Data Center Pipeline (18-month moratorium)
Multiple developers
Broomfield
CO · WECC
10 halted
local moratorium
Threshold set at 10 MW; part of a wave of Front Range municipalities enacting pauses in 2026.
Project Taurus (Colorado Springs)
Raeden
Colorado Springs (El Paso County)
CO · WECC
under appeal
litigationcommunity opposition
Located along Garden of the Gods Road on a former microchip manufacturing site west of Centennial Boulevard; developer Jason Green (Raeden) touts water-efficient closed-loop…
Douglas County / Parker Flexential Data Center
Flexential
Douglas County (Parker)
CO · WECC
litigation active
tax incentive change
Tax rebate value approximate ($19M); denial and rebate approval reflect a split regulatory record in the same county within months.
Aurora Data Center Pipeline (moratorium debate)
Multiple (incl. Microsoft Aurora AI Campus) (MSFT)
Aurora
CO · WECC
delayed
local moratorium
Councilwoman Amy Wiles championed a pause; council ultimately opted for regulation over outright ban, but process caused delay for pipeline projects including the Microsoft…
Lex Developments Pocatello Data Center ($2.6B)
Lex Developments
Pocatello (Bannock County)
ID · WECC
under appeal
litigation
Proposed at a former polysilicon plant site; Idaho Conservation League highlighted unprecedented cumulative energy use concerns, comparing water use to an 18-hole golf course or…
Meta Kuna Data Center Expansion Pause
Meta (META)
Kuna (Ada County)
ID · WECC
delayed
corporate realignment
Original $800M facility reached 'peak construction' before expansion was paused; 2023 Idaho law nearly stripped Kuna's urban renewal incentive tied to the project.
Stratos Project (Box Elder County)
Undisclosed developer (backed by Kevin O'Leary)
Box Elder County
UT · WECC
7,000 litigation active
local moratoriumzoning denialcommunity opposition
Roughly 20,000-acre hyperscale campus near the Great Salt Lake requiring an estimated 7 GW of power - more than double Utah's current statewide energy use; celebrity investor…
West Jordan Facebook Data Center (historical, cancelled)
Facebook (Meta) (META)
West Jordan
UT · WECC
cancelled
tax incentive change
Historical precedent case frequently cited in current Utah data center debates; included for completeness though outside the post-Jan 2024 window as background context.
Project Jupiter (Santa Teresa / Doña Ana County)
Yucca Growth Infrastructure (developer); Oracle and OpenAI (end users) (ORCL)
Santa Teresa (Doña Ana County)
NM · WECC
litigation active
litigationzoning denialcommunity oppositionfinancing
Bonds ($165B) issued for Oracle/OpenAI development before Planning & Zoning Commission had voted on zoning, per plaintiff allegations; judge dismissed pro se resident's second…
Project Zenith (Roswell)
Undisclosed
Roswell (Chaves County)
NM · WECC
pending review
community opposition
County framework would only apply to projects seeking public incentives; privately financed projects exempted.
Meta Los Lunas Expansion (Phase 3)
Meta (META)
Los Lunas (Valencia County)
NM · WECC
pending review
water disputecommunity opposition
Original Meta investment estimated at $3.3B in Los Lunas; expansion phase raised renewed local water-use scrutiny.
New York Statewide Hyperscale Data Center Moratorium (Executive Order 62)
Multiple developers statewide
Statewide
NY · NYISO
halted
state moratoriumlocal moratorium
First state to enact such a moratorium; affects pending projects including STAMP (Genesee County), Tonawanda, and Niagara Falls proposals; legislature had separately passed its…
STAMP Data Center (Stream U.S. Data Centers / Genesee County)
Stream U.S. Data Centers (via Genesee County Economic Development Center)
Town of Alabama, Genesee County (STAMP industrial park)
NY · NYISO
250 litigation active
litigationstate moratoriumlocal moratoriumzoning denial
2.2M sq ft facility; $1.46B in requested state/local sales tax breaks ($716M state + $716M local); Hochul had previously called it a 'local decision' she wouldn't override (March…
Wildflower Yaphank Data Center
Wildflower
Yaphank, Town of Brookhaven (Suffolk County)
NY · NYISO
halted
local moratorium
Long Island Power Authority said it does not anticipate service issues, with infrastructure costs borne by the developer; Suffolk County Water Authority says no water application…
Lysander Data Center Moratorium
Undisclosed
Lysander (Onondaga County, Syracuse area)
NY · NYISO
halted
local moratorium
Part of the broader Syracuse-area wave of caution following major Micron/semiconductor-adjacent development pressure in the region.
Islip Data Center Moratorium Consideration
Undisclosed
Islip (Suffolk County)
NY · NYISO
pending review
local moratorium
Reflects a cascading pattern of Long Island towns adopting pauses in mid-2026.
Markley Group Lowell Data Center Generator Expansion
Markley Group
Lowell
MA · ISO-NE
litigation active
litigationcommunity opposition
This is a litigation update on the previously tracked Markley Group Lowell Expansion entry - court-ordered construction pause specifically targeting diesel backup generator…
Westfield Data Center ($4B)
Undisclosed developer
Westfield
MA · ISO-NE
delayed
community opposition
Case highlights retroactive political risk even for previously-approved projects as statewide sentiment on data centers shifts.
Atlas Capital Group Bloomfield Data Center
Atlas Capital Group
Bloomfield (Hartford County)
CT · ISO-NE
pending review
zoning denial
Proposed 900,000 sq ft data center plus 127,000 sq ft substation (over 1M sq ft total) at 132 Griffin Road North; among the first major hyperscale-scale proposals in Connecticut.
New Haven Data Center Moratorium Proposal
Multiple (regulatory, no single named project)
New Haven
CT · ISO-NE
pending review
local moratorium
Precautionary, policy-level pause rather than a response to one specific project; part of statewide CT data center policy debate.
Nottingham Business Park Data Center
Nottingham Business Park LLC (developer Thomas Moulton)
Nottingham
NH · ISO-NE
withdrawn
community opposition
One of the largest small-town grassroots petition campaigns against a single data center project nationally.
Verrus Data Center (Mill Creek Corporate Center)
Verrus
Salem (Marion County)
OR · WECC
pending review
local moratoriumzoning denialcommunity opposition
Same statewide wave as Hillsboro's 120-day moratorium, enacted the same week; large crowds filled the Salem Public Library auditorium for the hearing.
Smithfield Data Center (Hanton City Investments)
Hanton City Investments LLC
Smithfield
RI · ISO-NE
litigation active
zoning denial
A test case for whether an in-process application filed shortly before a newly passed local ban can be grandfathered in.
Bates Mill Data Center (Lewiston)
Undisclosed developer
Lewiston
ME · ISO-NE
cancelled
state moratoriumlocal moratorium
Proposed inside a historic mill building; project's secrecy (unnamed backers) fueled resident suspicion and contributed to rejection.
Diode Ventures Cedar Creek Lake Data Center
Diode Ventures
Henderson County (Cedar Creek Lake / Cedar Creek Reservoir)
TX · ERCOT
withdrawn
water disputecommunity opposition
Update/confirmation of previously tracked entry - confirms formal withdrawal date and cause; Cedar Creek Lake is a major regional drinking-water and recreation reservoir, which…
Blueprint Data Centers Taylor Facility
Blueprint Data Centers
Taylor (Williamson County)
TX · ERCOT
litigation active
litigationcommunity opposition
135,000 sq ft facility; case highlights title/deed-restriction risk as an emerging litigation vector for Texas data center siting distinct from zoning or environmental claims.
Meta Temple Data Center
Meta (META)
Temple (Bell County)
TX · ERCOT
delayed
corporate realignment
Part of the same Meta redesign wave that paused the Kuna, Idaho facility.
Project Patriot / Knox Ranch (Granbury)
Bilateral Energy
Granbury (Hood County)
TX · ERCOT
litigation active
litigationcommunity opposition
One of several Hood County data center disputes (see also Comanche Circle/Sailfish and Project Red/Yellow entries) reflecting a concentration of Central Texas litigation around…
Comanche Circle / Sailfish Investors Data Center
Sailfish Investors (developer Ryan Hughes)
Hood County
TX · ERCOT
delayed
community opposition
Included here as a delay/opposition case even though ultimately approved, given the scale of community pushback documented in local coverage; distinct 2,100-acre parcel from the…
Project Red and Project Yellow (Hood County)
National CRE Holdings and Greenland Capital
Hood County
TX · ERCOT
under appeal
litigation
Two related data center proposals in Hood County, adding to the county's concentration of contested projects alongside Comanche Circle and Project Patriot/Knox Ranch.
Wichita Falls Data Center Rezoning (Data Nova X)
Data Nova X (originally proposed under different developer branding)
Wichita Falls
TX · ERCOT
cancelled
zoning denialcommunity opposition
Rezoning rejection halted the project as proposed; local coverage noted skepticism over the developer's rebranding partway through the approval process.
RCM Hill LLC Data Center (Hill County)
RCM Hill LLC
Hill County
TX · ERCOT
litigation active
litigationlocal moratorium
Notable as a case where litigation pressure from the developer side successfully forced a county to reverse its own moratorium.
Highlander SM One LLC Data Center (San Marcos)
Highlander SM One LLC
San Marcos (Hays County)
TX · ERCOT
cancelled
zoning denialcommunity opposition
Distinct developer/parcel from the already-tracked Hays County/San Marcos data center entry; this project was rejected outright twice rather than approved.
Skybox Datacenters San Angelo Project
Skybox Datacenters
San Angelo (Tom Green County)
TX · ERCOT
delayed
community opposition
City-owned land angle distinguishes this from typical private-parcel disputes; raised transparency and public-benefit questions locally.
Red Oak Data Center Rezoning (Compass Datacenters)
Compass Datacenters
Red Oak (Ellis County)
TX · ERCOT
delayed
zoning denialcommunity opposition
Included as a documented opposition/delay case with a notable community-benefit concession, even though the rezoning was ultimately approved.
Texas Statewide Data Center Interconnection Audit (ERCOT Batch Zero)
Multiple (up to ~300 projects statewide, including Sherman/Grayson County pipeline)
Statewide (ERCOT footprint, incl. Sherman/Grayson County)
TX · ERCOT
halted
interconnection queue
Sherman/Grayson County is a major semiconductor and data-infrastructure growth corridor (Texas Instruments, GlobiTech) directly affected by the pause; this is a statewide…
No matches.

Jurisdictional actions

State, local, and federal moratoriums, executive orders, audits, and legislation affecting data center approval or interconnection.

JurisdictionActionDateStatusSources
TX
state · Governor Greg Abbott / PUCT / ERCOT
Comprehensive verification and audit of all data centers in ERCOT interconnection process
Timing: ERCOT told the PUCT at its August 20, 2026 open meeting that it aims to file the comprehensive verification and audit report by December 10, 2026, one week before the December PUCT open meeting. ERCOT stated the verification will take several months but less than nine, and that the Batch Zero transmission planning study will NOT be complete by its original April 9, 2027 target.
2026-08-03 audit in progress
NY
state · Governor Kathy Hochul (Executive Order 62) / DEC
Statewide pause on discretionary DEC permits for data centers ≥50 MW until Generic Environmental Impact Statement completes
Timing: ~1 year (until GEIS complete)
2026-07-14 audit paused
Indianapolis / Marion County
local · City-County Council
Pause on all new data center construction city-wide through Dec 31, 2027
Timing: Through Dec 31, 2027
2026-08-10 audit paused
Nashville / Metro Davidson
local · Metro Nashville Council
Moratorium on certain data center permits and appeals until at least December 1, 2026
Being challenged in federal court by DC BLOX
2026-07-21 litigation active
Loudoun County
local · Board of Supervisors
Board voted 6-1 to direct staff to prepare moratorium options for Sept 15 meeting; Dillon's Rule constrains authority
Home to Data Center Alley, 250+ existing DCs. Virginia state law may not permit local moratorium.
2026-07-23 pending review
Seattle
local
One-year moratorium on new data centers 2026-06-09 audit paused
Spokane
local
One-year moratorium on new data centers 2026-06-23 audit paused
Broomfield
local
18-month pause on data centers 2026-07-07 audit paused
Prince George's County
local
Two-year pause on hyperscale data centers 2026-07-07 audit paused
Eagan
local
Moratorium on new data centers >20MW / expansions >9MW until Feb 17, 2027
Being challenged in court by Eagan Capital (filed June 15, 2026)
2026-02-17 litigation active
AZ
state · Arizona Legislature (budget)
Three-year moratorium on data center sales tax exemption
Timing: Through June 30, 2029
2026-07-01 audit paused
VA
state · General Assembly (Bill)
HB 1515, Moratorium on new DCs (1 MW+) until interconnection requests fulfilled or July 2028
Continued/still in committee
2026-01-XX pending review
Denmark (Energinet)
national
3-month grid connection pause 2026-05-04 audit paused
Ireland (EirGrid)
national
Freeze ended Dec 2025; new connections must bring own on-site power 2025-12-XX delayed
federal · FERC
Show-cause orders to six RTOs (PJM, MISO, SPP, CAISO, ISO-NE, NYISO), 60 days to justify or reform large-load tariffs across 5 reform areas 2026-06-18 pending review
Texas (statewide)
state · Gov. Greg Abbott / ERCOT / PUCT
Governor Abbott directed a comprehensive audit of up to 300 pending large-load data center interconnection projects, pausing new approvals until ERCOT and PUCT complete energy and water usage review
BNEF estimates the audit could delay 49.8 GW of data center load and cost projects up to $15 billion; Texas also enacted SB 6 (2025) creating large-load curtailment and cost-allocation…
Timing: Pending audit completion
2026-08-03 audit paused
New York (statewide)
state · Gov. Kathy Hochul / Executive Order No. 62
Executive Order 62 establishes the nation's first statewide temporary moratorium on new large (50MW+) hyperscale data center permitting while NYSDEC develops a Generic Environmental Impact Statement and siting framework
Follows earlier legislative effort (S.9144/A.10141, 20MW threshold, 3-year pause) that stalled in committee; NYSDEC permitting for large data centers is paused under the EO.
Timing: Until GEIS/permitting framework complete
2026-07-14 pending review
Arizona (statewide)
state · Gov. Katie Hobbs / Arizona Legislature
Arizona froze new data center sales-tax exemption applications for three years amid a state budget fight over cost of tax incentives
Sparked a rush of incentive applications before the freeze deadline; existing exemptions unaffected.
Timing: 3 years
2026-06-13 pending review
Virginia (statewide)
state · Virginia General Assembly / Del. Shin (HB 1515)
HB 1515 would prohibit localities from granting final approval for new data centers until pending AI data center interconnection requests are fulfilled or July 1, 2028; continued to 2027 session in House Rules Committee
Virginia is a Dillon's Rule state; localities cannot impose moratoria on their own, so this would be the first statewide legislative pause. More than 60 data center bills considered in the…
Timing: Through July 1, 2028 (if enacted)
2026-02-06 pending review
Maine (statewide)
state · Maine Legislature / Gov. Janet Mills
LD 307 would have imposed an 18-month moratorium on data centers over 20MW pending a coordination council review; passed legislature but vetoed by Gov. Mills on April 24, 2026; override vote failed 20-11 in Senate (short of two-thirds)
Mills signed executive order creating 15-member Maine Data Center Advisory Council to deliver recommendations by early 2027. Local moratoria (Scarborough, Brunswick, Warren, Hot…
Timing: 18 months (vetoed, not enacted)
2026-04-24 litigation active
Georgia (statewide)
state · Georgia General Assembly / Public Service Commission
HB 1059 proposed statewide ban on new data center permits until impact study completes; died in committee. Separately, Georgia PSC unanimously approved a rule requiring new Georgia Power customers above 100MW (chiefly data centers) to pay their own site-specific and upstream…
Multiple GA counties/cities enacted their own moratoria (Cherokee County, Chamblee, Garden City, Newton County, DeKalb County, Athens-Clarke County, Camden County, Rockdale County).
Timing: N/A (PSC rate rule enacted; legislative ban died)
2026-01-26 pending review
Ohio (statewide)
state · Ohio ballot petitioners / Ohio General Assembly
Proposed constitutional amendment to ban data centers over 25MW; petitioners gathered ~70,000 of 413,488 signatures required by July 1, 2026 deadline and failed to qualify for ballot; separately Substitute HB 646 (dedicated rate class, halved sales-tax exemption, closed-loop…
At least 20+ Ohio municipalities/townships enacted their own moratoria independently (see Franklin, Delaware, Licking County entries).
Timing: Ballot effort failed; backers plan retry in 2027
2026-04-03 litigation active
Michigan (statewide)
state · Michigan Legislature
Statewide moratorium bills (HB 5594-5596, SB 1018-1020) reintroduced for a 1-year/365-day pause on data center construction alongside a Senate Democratic regulatory package; none enacted
Gov. Whitmer has called a moratorium 'an automatic non-starter.'
Timing: 365 days (if enacted)
2026-06-24 pending review
Pennsylvania (statewide)
state · Gov. Josh Shapiro
Gov. Shapiro announced a major shift sharply limiting data center development and expanding the review process for new projects, taking a hard line against 'predatory' developers, after PA House/Senate bills (model ordinance, 18-month local moratorium authorization, Sen. Muth's…
PA Senate had separately advanced a bill allowing localities to enact up to 18-month data center moratoria.
Timing: TBD (new review process)
2026-08-17 pending review
Vermont (statewide)
state · Vermont Legislature (S.205)
S.205 would impose a moratorium on data centers above 10MW until July 1, 2030, the longest pause window of any 2026 state bill
In committee as of mid-2026; Vermont has minimal existing data center capacity, so bill is largely preventive.
Timing: Until July 1, 2030
2026-01-01 pending review
Oklahoma (statewide)
state · Oklahoma Legislature (Sen. Standridge Sacchieri, SB 1488)
SB 1488 would pause new data center construction statewide until November 1, 2029 while a study commission examines rural, ratepayer, and water impacts
In committee as of mid-2026.
Timing: Until Nov. 1, 2029
2026-01-22 pending review
South Dakota (statewide)
state · Gov. Larry Rhoden / SD Legislature
SB 135 ('Data Center Bill of Rights for Citizens') and HB 1038 signed into law, not a moratorium, but requires 10MW+ facilities to pay for their own grid upgrades, disclose water/energy projections, and preserves local home-rule authority over siting/moratoria
First enacted state-level data center restriction in the country (though framed as disclosure/cost-allocation rather than an outright pause).
Timing: Permanent (enacted law)
2026-03-24 pending review
Florida (statewide)
state · Florida Legislature / Governor
SB 484 (Chapter 2026-65) signed into law effective July 1, 2026: affirms local land-use authority over large-load data centers, sets minimum utility tariff/service requirements, restricts certain water-use permits, and orders a state study of large-scale data centers
Enables the wave of Florida county moratoria (Sarasota, Palm Beach).
Timing: Permanent (enacted)
2026-07-01 pending review
Texas (statewide)
state · Texas Legislature / Gov. Abbott (SB 6)
SB 6 signed into law setting planning, interconnection, and cost-allocation rules for large electric loads including data centers, allowing ERCOT to curtail large loads during grid emergencies
Predecessor/complement to the Aug. 2026 audit/pause; establishes legal basis for curtailment during the audit.
Timing: Permanent (enacted)
2025-06-01 pending review
Loudoun County
county · Loudoun County Board of Supervisors
Phase 1 zoning rewrite eliminated by-right AI data center development countywide; every new data center now requires a Special Exception (SPEX) permit with public hearings. Board separately voted 6-1 (July 22, 2026) to direct staff to study a full pause on processing all data…
County attorney says formal moratoria are not legal in VA except narrow circumstances; grandfathering for applications filed before Feb 12, 2025 more than 500ft from residential areas.…
Timing: Phase 2 standards expected ~March 2027
2025-03-18 pending review
Prince William County
county · Prince William County Board of Supervisors
Board initiated zoning text amendment (DPA2026-00006) on March 3, 2026 to eliminate by-right AI data center approval within the Data Center Opportunity Zone Overlay District (DCOZOD) and require a Special Use Permit (SUP) for all data centers; also closed the overlay to future…
Follows controversial PW Digital Gateway rezoning approved without a water-use study; Board also unanimously denied rezoning for the ~2,000-acre Dulles Cloud South campus and abandoned…
Timing: Pending final adoption
2026-03-03 pending review
Hanover County
county · Hanover County Board of Supervisors
Board voted 4-3 to deny rezoning and conditional-use permit for Tract's 430-acre Mountain Road Technology Park data center campus, citing water use, noise, and speculative nature of the project
Hanover Planning Commission had earlier voted to deny the HHHunt-affiliated rezoning on Jan 15, 2026; Board also launched a broader public review of data center policy.
Timing: N/A (project rejected)
2026-05-28 litigation active
Fairfax County
county · Fairfax County Board of Supervisors
Adopted Zoning Ordinance Amendment ZO 112.1-2024-9 imposing 200ft residential setback for buildings (300ft for equipment), a 1-mile Metrorail-station buffer requiring special exception, mandatory pre/post-construction noise studies, and building design standards for AI data…
Projects with site plans submitted before July 16, 2024 grandfathered (e.g., Plaza 500 in Bren Mar). 4.4M sq ft of data centers under construction in Fairfax as of early 2024.
Timing: Permanent (enacted ordinance)
2024-09-11 pending review
Prince George's County
county · Prince George's County Council (Chair Oriadha)
County Council approved a 2-year moratorium on new hyperscale data center development following a countywide task force review; extended the pause in early July
Timing: 2 years
2026-07-08 pending review
Sarasota County
county · Sarasota County Commission
County blocked hyperscale data center applications for at least one year, with commissioners stating 'no, not now, never' regarding large AI data centers
Sarasota County cities subsequently united in opposition to the fast-growing AI data center industry.
Timing: At least 1 year
2026-07-09 pending review
Palm Beach County
county · Palm Beach County Board of County Commissioners
County halted new AI/large-scale data center applications under a moratorium directive, while carving out an exception allowing the pending 'Project Tango' application to proceed to a decision
Zoning board separately recommended a formal one-year pause on new large-scale data centers.
Timing: ~1 year (pending ULDC revisions)
2026-07-07 pending review
Chesterfield County
county · Chesterfield County Board of Supervisors
Board indicated it will not approve any more data centers in the county, effectively pausing new approvals amid growing local opposition
One county data center project reportedly halted amid legal dispute.
Timing: Indefinite
2026-06-01 pending review
Warrenton (Fauquier County)
city · Warrenton Town Council
Town Council took up data center regulation in 2025 amid opposition to an Amazon data center and transmission line proposal near Warrenton
Timing: Ongoing review
2025-01-01 pending review
Manassas / Prince William County
county · Virginia Court of Appeals
Court of Appeals ruling blocked construction of 37 data centers proposed adjacent to Manassas National Battlefield Park, halting the Digital Gateway-linked project
Prince William supervisors subsequently abandoned defense of the related Digital Gateway rezoning.
Timing: Pending further appeal
2026-04-07 litigation active
Fauquier County
county · Fauquier County Board of Supervisors
County approved a policy curbing new data centers; officials also caused Amazon to 'indefinitely postpone' its proposed AWS data center in the county
Timing: Ongoing
2025-06-01 pending review
Culpeper County
county · Culpeper County Board of Supervisors
County put new 'guardrails' on data centers even while approving the Red Ace Data Center campus (69.19 acres rezoned rural to light industrial); Piedmont Environmental Council urged a full ban in the draft zoning code
Timing: Ongoing
2025-01-01 pending review
Berkeley County
county · Berkeley County Council / residents
Local residents organized opposition to a proposed $4 billion data center in Berkeley County; county officials (site of WV's first 'high impact' data center) sought clarity on tax-split rules amid growth concerns
No formal moratorium yet identified, but active organized opposition and legislative scrutiny.
Timing: Ongoing
2026-03-23 pending review
Front Royal / Warren County
city · Front Royal Town Council / Warren County
Front Royal adopted a moratorium in June 2026 and declared no data centers are permitted in the town's industrial areas, effectively ruling out data centers town-wide
Timing: Indefinite
2026-06-01 pending review
Chesapeake
city · Chesapeake City Council
City Council approved an 8-month pause on data center applications, paired with a Comprehensive Plan amendment process
Council had earlier rejected an AI data center rezoning in June 2025 over environmental/disruption concerns.
Timing: 8 months
2026-07-22 pending review
Montgomery County
county · Montgomery County Executive / Council
County Executive paused new data center permit applications for 6 months by executive order in June 2026; County Council advancing a bill to extend the pause to 18 months and cap facility size
Timing: 6 months (proposed extension to 18 months)
2026-06-01 pending review
Frederick County
county · Frederick County Council
Frederick County adopted a data center application pause similar to Montgomery County's
Timing: Not specified
2026-06-01 pending review
Baltimore (city)
city · Baltimore City Council
City Council passed a one-year moratorium on new data center development pending a zoning study
Timing: 1 year
2026-05-12 pending review
Baltimore County
county · Baltimore County Council
Baltimore County adopted a data center application pause similar to Montgomery and Frederick counties
Timing: Not specified
2026-06-01 pending review
Washington County
county · Washington County Board of Commissioners
Western Maryland county approved a yearlong data center moratorium
Timing: 1 year
2026-07-01 pending review
Calvert County
county · Calvert County Board of Commissioners
County board passed a 6-month moratorium on new data centers
Timing: 6 months
2026-08-01 pending review
Indianapolis
city · Indianapolis City-County Council
Council approved a data center moratorium pausing approval of new data centers through the end of 2027, overriding Mayor Hogsett's earlier veto/endorsement position; awaits Metropolitan Development Commission sign-off
Development committee had advanced it 10-3 before full council vote.
Timing: Through end of 2027
2026-08-10 pending review
Boone County
county · Boone County Commissioners
Commissioners approved a moratorium on new data center development
Timing: Not specified
2026-06-15 pending review
Hobart
city · Hobart residents / Circuit Court
Residents/opponents filed suit challenging an Amazon data center project in Hobart, Indiana
See lawsuits.json for docket detail.
Timing: N/A (litigation)
2025-01-01 litigation active
Nashville (Metro Davidson County)
city · Metro Council (BL2026-1448)
Metro Council passed data center zoning and permit regulations that ban some data centers, pause the rest, and add new regulations, after a record-setting council meeting
Related to DC BLOX v. Nashville litigation (see lawsuits.json).
Timing: Not specified (permanent zoning changes plus pause)
2026-07-21 pending review
Wilson County
county · Wilson County Commission
County commission approved a six-month moratorium on data centers to study impacts on water and power
Timing: 6 months
2026-07-14 pending review
McMinnville
city · McMinnville City Council
City adopted a new pause on data center applications
Timing: Not specified
2026-01-01 pending review
Federal Way
city · Federal Way City Council
City passed a one-year data center moratorium
Timing: 1 year
2026-01-01 pending review
Broomfield
city · Broomfield City Council
City Council passed an 18-month temporary ban on new or expanded data centers of 10MW or more
Timing: 18 months
2026-07-08 pending review
Denver
city · Denver City Council
City Council unanimously passed a one-year moratorium on new data center construction
Proposal first introduced March 31, 2026.
Timing: 1 year
2026-05-18 pending review
Aurora
city · Aurora City Council
City Council rejected a proposed six-month data center moratorium and instead approved new siting rules and water regulations
Aurora had earlier paused data center/warehouse development approvals temporarily in Sept. 2025.
Timing: N/A (moratorium rejected; regulations adopted instead)
2026-08-11 pending review
Boulder County
county · Boulder County Commissioners
Commissioners declared a moratorium on new data center (and detention center) development while updating land-use code (docket DC-26-0003)
Timing: Pending land-use code update
2026-08-10 pending review
Lochbuie
city · Lochbuie Board of Trustees
Town enacted a five-year data center moratorium, the longest local pause identified in Colorado
Timing: 5 years
2026-01-01 pending review
Douglas County
county · Douglas County Commissioners
Commissioners kept data centers and crypto mines on hold pending new regulations, without adopting a formal moratorium
Timing: Pending regulation development
2026-04-25 pending review
Minneapolis
city · Minneapolis City Council
City Council gave final approval to a data center development pause
Timing: Not specified
2026-06-25 pending review
Inver Grove Heights
city · Inver Grove Heights City Council
City adopted a new pause on data center development
Timing: Not specified
2026-01-01 pending review
Ypsilanti Township / Ypsilanti Community Utilities Authority
utility · Ypsilanti Community Utilities Authority (YCUA)
YCUA board approved a 12-month moratorium on supplying water/sewer service to new data centers (Resolution No. 2026-08)
Ypsilanti City Council separately voted in support of the YCUA moratorium.
Timing: 12 months
2026-04-16 pending review
Flint
city · Flint City Council
City adopted a new pause on data center development
Timing: Not specified
2026-01-01 pending review
Chandler
city · Chandler City Council (Ordinance No. 5033)
City Council adopted Ordinance No. 5033 establishing zoning restrictions on data centers after years of resident complaints about noise and resource use
Predates the 2024-2026 wave but remains in force and is frequently cited as a model.
Timing: Permanent (enacted ordinance)
2022-01-01 pending review
Casa Grande
city · Casa Grande City Council
City Council approved data center waivers/exceptions to local rules amid state-level tax incentive pause, drawing debate over possible damages liability
Timing: Not specified
2026-08-03 pending review
Tucson
city · Tucson City Council
City Council voted 7-0 to end negotiations and halt annexation for Project Blue, a 290-acre Amazon-linked data center campus (developer Beale Infrastructure), citing water supply and ratepayer concerns
Developer subsequently pursued the site in unincorporated Pima County instead.
Timing: N/A (project halted)
2026-01-01 pending review
Ravenna
city · Ravenna City Council
City Council unanimously adopted a one-year moratorium on new data centers, heading off a proposed facility on State Route 14
Part of a wave of Northeast Ohio moratoria.
Timing: 1 year
2026-01-01 pending review
Lordstown (village)
city · Lordstown Village Council (Ordinance 1-2026)
Village Council passed an emergency 180-day moratorium on new data center permits after first enacting and then repealing an outright ban amid a developer's Ohio Supreme Court challenge; council later moved to extend the moratorium
Underlying dispute reached the Ohio Supreme Court.
Timing: 180 days (extended)
2026-01-01 litigation active
Franklin County (Prairie Township / Washington Township)
county · Prairie Township Trustees / Washington Township Trustees
Prairie Township enacted a 6-month moratorium on data center zoning applications; Washington Township separately paused new data centers to assess fire safety and emergency readiness
Franklin County also convened a dedicated Data Center Moratorium Work Group.
Timing: 6 months (Prairie Twp.)
2026-04-01 pending review
Sunbury (Delaware County)
county · Sunbury City Council
City Council passed a moratorium on data centers effective until 2027; residents separately petitioned to place a charter amendment banning data centers on the November 2026 ballot
Neighboring Pataskala pursuing a similar fall ballot measure.
Timing: Through 2027
2026-04-16 pending review
St. Albans Township (Licking County)
county · St. Albans Township / Licking County Planning Commission
Township officials sought to ban data center complexes; Licking County Planning Commission approved St. Albans Township's plan to ban data centers
Microsoft separately paused its own $1bn data center plans in Licking County.
Timing: Not specified
2026-01-01 pending review
Sugar Grove (Kane County)
county · Sugar Grove Village Board / Kane County officials
Officials considering a moratorium on data centers in unincorporated Kane County; Sugar Grove weighing a data center crackdown
Aurora, IL city council separately approved new data center regulations.
Timing: Under consideration
2026-04-06 pending review
Lake County (unincorporated)
county · Lake County Board
County Board voted to temporarily ban new data centers in unincorporated Lake County; a subsequent proposed 8-month moratorium cleared its first procedural step in August 2026
Linked to Grayslake/T5 litigation (see lawsuits.json).
Timing: 8 months (subsequent proposal)
2026-06-20 pending review
McHenry County
county · McHenry County Board
County considering data center regulatory requirements amid regional Chicagoland backlash against new projects
Timing: Under consideration
2026-06-01 pending review
Chatham County
county · Chatham County Board of Commissioners
County enacted a 12-month moratorium on data centers and cryptocurrency mining
A developer sued Chatham County over the moratorium (see lawsuits.json).
Timing: 12 months
2026-02-18 litigation active
Apex (Wake County)
city · Apex Town Council
Town Council approved a yearlong pause on data center projects amid opposition to the proposed New Hill Digital Campus
Developer subsequently withdrew the New Hill Digital Campus application.
Timing: 1 year
2026-03-11 pending review
Wendell (Wake County)
city · Wendell Board of Commissioners
Town adopted a temporary moratorium on data centers while it rewrites zoning rules
Timing: Pending zoning rewrite
2026-03-01 pending review
Boone
city · Boone Town Council
Town approved a data center development moratorium
Timing: Not specified
2026-03-23 pending review
Woodfin (Buncombe County)
city · Woodfin Town Council
Council asked staff to draft a temporary moratorium on data centers as the Land Development Ordinance (LDO) is updated
Timing: Pending LDO update
2026-01-01 pending review
Hot Springs (Madison County)
city · Hot Springs Town Council
Town imposed a data center moratorium as small towns weigh costs of development
Timing: Not specified
2026-07-23 pending review
Stokes County
county · Stokes County Planning Board
Planning Board backed a pause on data center development
Timing: Not specified
2026-07-10 pending review
Cherokee County
county · Cherokee County Commission
County approved a data center moratorium
Timing: Not specified
2026-07-22 pending review
Chamblee
city · Chamblee City Council
City Council approved a pause on data center applications
Timing: Not specified
2026-07-22 pending review
DeKalb County
county · DeKalb County Commission
Commission extended its data center moratorium by six months amid public health concerns; extended again through June 23, 2026 and later through September
Commission also voted against an amendment that would have created permanent data center regulations, opting to continue the pause instead.
Timing: Multiple extensions (through Sept. 2026)
2025-12-16 pending review
Rockdale County
county · Rockdale County Commission
County re-extended its data center moratorium multiple times, most recently through September 8, 2026
Timing: Through Sept. 8, 2026 (re-extended)
2026-01-01 pending review
Garden City
city · Garden City Council
City put the brakes on data centers with a new local restriction
Timing: Not specified
2026-06-16 pending review
Athens-Clarke County
county · Athens-Clarke County Commission
County extended its temporary moratorium on new data centers through June 5, 2026
Timing: Through June 5, 2026 (extended)
2026-01-01 pending review
Camden County
county · Camden County Commission
County adopted a 9-month data center moratorium
Kingsland city manager recommended a parallel measure.
Timing: 9 months
2026-05-05 pending review
Monterey Park
city · Monterey Park City Council
City Council overwhelmingly voted to permanently ban new data centers, the first California city to do so
Timing: Permanent
2026-06-03 pending review
Patterson
city · Patterson City Council
City adopted a 45-day moratorium chilling talks of data center construction
Timing: 45 days
2026-01-01 pending review
Mendocino County
county · Mendocino County Board of Supervisors
Supervisors moved toward a data center moratorium
Timing: Under consideration
2026-07-01 pending review
City of Imperial
city · City of Imperial Council / local leaders
Local leaders challenged a million-square-foot hyperscale data center project in Imperial, California amid moratorium conflict; underlying dispute proceeded to federal litigation (IVCM v. City of Imperial, see lawsuits.json)
Timing: N/A (litigation)
2026-01-01 litigation active
Coachella
city · Coachella City Council
City Council unanimously approved a 45-day moratorium on new data center applications and voted to terminate the utility agreement behind the proposed Coachella Valley Technology Campus; moratorium later extended into 2027 while the city drafts a permanent ban
Timing: Extended into 2027
2026-01-01 pending review
Tulare County
county · Tulare County Board of Supervisors
County stalled data center developments with a moratorium that could be extended
Timing: Could be extended
2026-01-01 pending review
Linn County
county · Linn County Board of Supervisors
Board of Supervisors voted 2-1 to impose an 18-month moratorium on new applications to rezone land into the county's large-scale data center district, months after adopting a data center zoning ordinance (1,000-ft residential setbacks, mandatory water study/agreement, noise and…
Timing: 18 months
2026-01-01 pending review
Birmingham
city · Birmingham City Council
City Council enacted zoning rules for hyperscale data centers (500-ft setback from residential districts, closed-loop cooling capping water use, certified-mail notice to nearby owners), called Alabama's strictest data center ordinance
Leeds, Homewood, Cullman, and Fort Payne also adopted new pauses.
Timing: Permanent (enacted)
2026-01-01 pending review
Leeds
city · Leeds City Council
City adopted a new pause on data center development, part of a wave of four Alabama cities acting in 2026
See also Homewood, Cullman, Fort Payne.
Timing: Not specified
2026-01-01 pending review
New Jersey (statewide)
state · New Jersey Legislature / Governor
Data Center Fair Share Act signed into law, requiring 50MW+ facilities to commit to paying at least 85% of projected power costs for a decade
Timing: 10-year commitment period (permanent law)
2026-07-07 pending review
Monroe Township
city · Monroe Township Council
Township took regulatory action affecting data center development, subject of Hexa Builders litigation (see lawsuits.json)
Timing: N/A (litigation)
2025-01-01 litigation active
East Windsor Township
city · East Windsor Township Committee (Ordinance No. 2026-06)
Township adopted Ordinance No. 2026-06 establishing a data center moratorium
Timing: Not specified
2026-01-01 pending review
Neptune Township
city · Neptune Township Committee
Township banned data centers (and ICE detention facilities) via local ordinance
Timing: Permanent (enacted)
2026-07-13 pending review
Andover
city · Andover Township Committee
Sussex County town officially banned data centers after public pushback
Timing: Permanent (enacted)
2026-05-29 pending review
Oklahoma City
city · Oklahoma City Council
City Council approved a moratorium on new data centers, effective immediately and expiring Dec. 31, 2026, covering all new applications
Timing: Through Dec. 31, 2026
2026-04-21 pending review
Jackson County / Springfield
county · Jackson County Legislature / Springfield City Council
Jackson County and Springfield, Missouri both adopted new pauses on data center development
Timing: Not specified
2026-01-01 pending review
Manitowoc County
county · Manitowoc County Board
County Board voted unanimously to impose an 18-month data center moratorium
Timing: 18 months
2026-04-29 pending review
Dodge County
county · Dodge County Board
County adopted a new pause on data center development
Timing: Not specified
2026-01-01 pending review
Champaign County
county · Champaign County Board
County Board approved a 1-year data center moratorium
Timing: 1 year
2026-04-24 pending review
Valparaiso
city · Valparaiso City Council
Council voted 6-1 for a data center moratorium
Timing: Not specified
2026-07-15 pending review
Fort Worth
city · Fort Worth City Council
City Council unanimously voted to take first steps toward a data center moratorium
Timing: Under development
2026-08-12 pending review
Hill County
county · Hill County Commissioners Court
Hill County adopted a one-year moratorium on data center development, then rescinded it roughly three weeks later (June 5, 2026) amid a $100 million developer lawsuit, replacing it with a checklist of requirements for applicants
Developer filed a $100M suit challenging the moratorium.
Timing: Rescinded
2026-06-05 litigation active
Nottingham
city · Nottingham Town Meeting
Town approved a 12-month moratorium on data center development via town meeting vote
Timing: 12 months
2026-07-03 pending review
Gray
city · Gray Town Council
Gray joined a growing list of Maine towns adopting data center moratoriums, following Scarborough, Brunswick, and Warren after the statewide LD 307 override failed
Timing: Not specified
2026-08-06 pending review
Reading
city · Reading City Council
City adopted a 180-day pause on data centers
Timing: 180 days
2026-07-01 pending review
York County
county · York County Planning Commission
Planning Commission recommended data center moratorium/regulation
Timing: Not specified
2026-01-01 pending review
Pulaski County
county · Pulaski County Quorum Court
Data center moratorium measure remained unresolved after an earlier vote-count failure
Timing: Unresolved
2026-01-01 pending review
Reno
city · Reno City Council
City extended its existing data center moratorium into 2027
Timing: Through 2027
2026-01-01 pending review
Memphis
city · Memphis City Council
Memphis data center moratorium proposal begins City Hall process
Separately, DOJ moved to intervene and dismiss the NAACP's Clean Air Act suit over gas turbines powering xAI's Memphis Colossus 2 site on national-security grounds (see lawsuits.json).
Timing: Under process
2026-08-01 pending review
Waterloo
city · Waterloo City Council
City considering a three-month data center moratorium
Timing: 3 months (proposed)
2026-01-01 pending review
Denmark (national)
national · Danish national grid operator / government
Denmark paused new data center grid connections amid mounting power grid strain, with total connection requests reaching roughly 60GW
Denmark built one of Europe's cleanest grids; AI data center demand is straining that capacity.
Timing: Not specified
2026-05-04 pending review
Ireland (national)
national · Commission for Regulation of Utilities (CRU) / EirGrid
Ireland ended its multi-year moratorium on new power connections to data centers, publishing a final policy on data centre grid connections via CRU; EirGrid had previously pulled the plug on roughly 30 Irish data center projects during the pause
Data centers reportedly account for roughly 21% of Ireland's electricity consumption.
Timing: Ended (moratorium lifted)
2025-12-12 pending review
Amsterdam
city · Amsterdam Municipality
Amsterdam halted new data center construction citywide via a municipal moratorium, later easing restrictions gradually with Haarlemmermeer before formally resuming construction after roughly a year's pause
Dutch Data Center Association criticized the rules as 'symbol politics.'
Timing: ~1 year (lifted with restrictions)
2025-04-18 pending review
Germany (national)
national · German Bundestag / Energy Efficiency Act
Germany's Energy Efficiency Act mandates heat-reuse requirements as a data center siting gate and imposes broader energy efficiency restrictions on new data centers, described as the first regulated data center market in Europe
Timing: Permanent (enacted law)
2026-01-01 pending review
Singapore (national)
national · Infocomm Media Development Authority (IMDA) / Economic Development Board
Singapore lifted its longstanding data center moratorium via a pilot phase accepting new applications, subject to strict environmental sustainability standards and conditions
Precedent frequently cited as the model for 'lifting with conditions' after a construction pause.
Timing: Moratorium lifted; new conditional framework in place
2022-01-01 pending review
No matches.

Local restrictions

County, city, township, and borough measures: moratoriums, zoning denials, permit pauses, and ordinances affecting data centers. Newest first.

JurisdictionStateActionDateStatusSources
Santa Clara
city · Planning Commission
CA Uphold denial of GI Partners data center on appeal
Santa Clara Planning Commission denied a 72MW data center permit at 2805 Bowers Ave (3-2 in favor; failed the required 4-vote majority, so the permit was denied). Chair noted the city has…
2024-03-06 in force
Adair County
county · Board of Supervisors/County Commission
IA Impose 1200-foot data center setbacks in Adair County
Applied Digital proposed a 200MW, $1.5B data center with two 300,000 sq ft buildings adjacent to a NextEra substation connected to wind farms in Guthrie and Audubon counties. Supervisors…
2024-04-24 in force
Town of Chesterton
city · City Council
IN Community pressure forces Provident Realty Advisors to withdraw in Town of Chesterton
Provident Realty Advisors proposed a $1.3B data center on the 200-acre former Brassie Golf Course site along Pearson Road. The plan called for eight buildings at 150,000 sq ft each with…
2024-06-01 expired
DeKalb County
county · Board of Supervisors/County Commission
TN Impose 5000-foot data center setbacks in DeKalb County
DeKalb County, Tennessee, Commission, considered data center regulations proposed by County Mayor Matt Adcock after receiving an inquiry about a nuclear-powered data center. The proposed…
2024-06-01 expired
Clinton County
county · Board of Supervisors/County Commission
IA Pause wind energy projects in Clinton County pending regulations
Clinton County enacted a moratorium on wind project applications on June 10, 2024, extended multiple times through September 2025, prompted by NextEra Energy and Sky Pilot Wind/Ranger…
2025-12-08 in force
City of Atlanta
city · City Council
GA Ban data centers near MARTA stops and Beltline in Atlanta
Atlanta City Council enacted data center zoning restrictions in phases. In September 2024, data centers were prohibited within 2,640 feet of high-capacity transit stops and banned within…
2024-09-01 in force
Fairfax County
county · Board of Supervisors/County Commission
VA Impose 200-foot data center setbacks in Fairfax County
Fairfax County Board of Supervisors adopted a Data Centers Zoning Ordinance Amendment on September 10, 2024, requiring a special exception for almost all data centers. The amendment…
2024-09-10 in force
Morton County
county · Board of Supervisors/County Commission
ND Impose indefinite data centers moratorium in Morton County
Morton County adopted a moratorium on data centers and cryptocurrency mining facilities in September 2024. The moratorium prevents permitting of these facilities until the county…
2024-09-01 in force
Jackson County
county · Board of Supervisors/County Commission
IA Pause data centers in Jackson County pending regulations
Jackson County enacted a data mining facility moratorium in September 2024 (Resolution #1066), which was lifted in November 2024 after supervisors and county staff studied the issue. The…
2024-09-17 expired
City of Thorndale
city · City Council
TX Pass resolution opposing Data Factory Austin bitcoin mine
Data Factory Austin proceeded with bitcoin mining near Thorndale despite city opposition. The city passed a resolution voicing concerns about the 15 MW facility, and residents launched a…
2024-10-01 expired
City of Peculiar
city · Planning Commission
MO Restrict Diode Ventures 500-acre data center in City of Peculiar
Peculiar originally added a 'data center' definition to its light industrial zoning, enabling Diode Ventures' proposed $1.5B Harper Road Technology Park, a 500-acre campus with multiple…
2024-10-01 expired
Jones County
county · Board of Supervisors/County Commission
IA Pause data centers and crypto mining in Jones County pending regulations
Jones County enacted a moratorium on data center development circa October 2024. The moratorium was replaced by a permanent Cryptocurrency and Data Center Ordinance restricting such…
2025-05-13 expired
Osceola County
county · Board of Supervisors/County Commission
FL Block US Development rezoning of 434 acres of farmland
US Development filed to rezone 434 acres from agricultural to industrial near Yeehaw Junction for a nine-building, 7+ million sq ft data center campus, with each three-story building…
2024-10-01 in force
Gilmer County
county · Planning Commission
GA Ban commercial crypto mining in Gilmer County
Gilmer County residents successfully blocked a proposed cryptocurrency server farm on Eller Road in Ellijay. Cyndie Roberson, cofounder of Gilmer County Citizens Against Crypto Mining,…
2024-11-01 in force
Pima County
county · Board of Supervisors/County Commission
AZ Require conditional use permits in Pima County
The Pima County Board of Supervisors approved Project Blue's CUP zoning amendment and the sale of 290 acres for nearly $21M to Beale Infrastructure on Christmas Eve 2025, despite…
2025-12-16 in force
Oliver County
county · Board of Supervisors/County Commission
ND Halt data centers and crypto mining in Oliver County after Applied Digital proposal
Over 200 people packed the Betty Hagel Memorial Civic Center in Center, ND as Oliver County leaders debated a proposed moratorium on data centers and cryptocurrency mining. The Oliver…
2024-12-12 expired
Fort Worth
city · City Council
TX Restrict Black Mountain Power 530-acre data center in Fort Worth
Black Mountain Power LLC has obtained rezoning approval for over 450 acres in southeast Fort Worth for a $10B data center. The City Council approved zoning changes in multiple phases: 141…
2025-01-01 pending
Milam County
county · Board of Supervisors/County Commission
TX Ban data centers in designated zones in Milam County
Milam County (TX) has become a flashpoint for data center buildout as SB Energy (SoftBank) and partners advance the Stargate / Milam County campus near Sharp (Rockdale / Thorndale area), a…
2026-01-09 in force
Reno
city · City Council
NV Deny Webb Data Center's 82,000 sq ft facility in Reno on appeal
Sierra Club Toiyabe Chapter appealed the Planning Commission's approval of Webb Data Center's 82,000 sq ft facility, arguing the city established zoning guidelines without public input and…
2025-01-22 in force
Hitchcock County
county · Board of Supervisors/County Commission
NE Impose 1-year data centers and crypto mining moratorium in Hitchcock County
Hitchcock County passed a one-year moratorium on data center and cryptocurrency mining development via resolution in February 2025, responding to crypto companies seeking cheap power and…
2025-02-01 expired
Reno
city · City Council
NV Propose data centers moratorium in Reno (rejected)
Reno Planning Commission voted 4-2 in February 2025 to recommend a temporary moratorium on new data center permits, citing concerns about energy use, water consumption, and the city's lack…
2025-02-05 in force
Ada County
county · Board of Supervisors/County Commission
ID Adopt data center zoning standards in Ada County
Ada County proactively developed data center zoning standards following Meta's data center in nearby Kuna and Diode Ventures' 620-acre Gemstone Technology Park (approved 3-2 by Kuna City…
2025-11-01 in force
Clayton County
county · Board of Supervisors/County Commission
IA Pause data centers and crypto mining in Clayton County pending regulations
Clayton County Board of Supervisors approved a temporary moratorium on rezoning requests and conditional use permits for digital asset mining/data centers in February 2025. The moratorium…
2025-02-25 in force
Kootenai County
county · Board of Supervisors/County Commission
ID Convert Kootenai County moratorium into permanent ban
Kootenai County lifted its 182-day moratorium on data center building permits after adopting permanent regulations that ban data centers from being located over the Spokane Valley-Rathdrum…
2025-03-02 expired
Nassau County
county · Board of Supervisors/County Commission
NY Propose battery energy storage systems moratorium in Nassau County
Nassau County towns imposed moratoriums on battery energy storage systems (BESS). Jupiter Power (owned by BlackRock) cancelled its contract for the proposed 275 MW Oyster Shore Energy…
2025-04-01 in force
Town of Burns Harbor
city · Planning Commission
IN Block Provident Realty Advisors rezoning of 102 acres in Town of Burns Harbor
Provident Realty Advisors, after being rejected in Chesterton, proposed a seven-building, 102-acre data center campus at the corner of S. Babcock and Haglund Roads on the Worthington Steel…
2025-05-05 expired
Reno
city · City Council
NV Oppose StoneGate data center in Reno
StoneGate proposed converting 1,767 acres in Reno's Cold Springs area approved for ~5,000 homes into industrial/data center use, reducing housing to ~1,350 units. The Planning Commission…
2025-05-21 in force
Henrico County
county · Board of Supervisors/County Commission
VA Create data center overlay zone in Henrico County
The Henrico County Board of Supervisors adopted the Data Center Comprehensive Plan Amendment on June 10, 2025, incorporated into the Vision 2026 Comprehensive Plan. As of January 2025, all…
2025-06-01 in force
Little Rock
city · City Council
AR Block AVAIO Digital Partners rezoning of 760 acres in Little Rock
AVAIO Digital's 'Project Leo', a $6B, 760-acre hyperscale data center campus near Little Rock, has broken ground with a fully approved Site Plan. The first phase (150 MW) is expected to be…
2025-06-01 in force
Cherokee County
county · Board of Supervisors/County Commission
SC Restrict Cielo Digital Infrastructure 86-acre data center in Cherokee County
Cielo Digital Infrastructure's $2.1B data center was approved by Cherokee County Council. The development at Ford Road in Gaffney will include four 400,000 sq ft facilities with an…
2025-06-01 in force
Clark Township
township · Township Board
MI Impose 1-year data centers moratorium in Clark Township
Clark Township enacted a 1-year moratorium on data center development in June 2025, making it one of the earliest communities in Michigan to take preemptive action, months before the…
2025-06-01 in force
Commercial Point / Scioto Township
township · Township Board
OH Deny K-NOVA 450MW data center permit in Commercial Point / (moratorium on data center development).
K-NOVA LLC's proposal for the Rickenbacker Exchange development in Commercial Point stalled when a related ordinance 'died due to a lack of motion' in the Village Council. K-NOVA's…
2026-03-01 in force
City of La Grange
city · City Council
KY Impose 150-day data centers moratorium in City of La Grange (Western Hospitality Partners)
La Grange passed a 150-day moratorium on data centers and private utilities on June 2, 2025, later extended by another 150 days. Response to "Project Lincoln," a proposed $6 billion…
2025-06-02 expired
Millard County
county · Board of Supervisors/County Commission
UT Block Creekstone Energy rezoning of 1100 acres of farmland
Millard County Commission unanimously approved Creekstone Energy's rezoning of ~1,200 acres from agricultural to heavy industrial on June 3, 2025, despite public opposition at the hearing.…
2025-06-03 in force
City of Johnson City
city · City Council
TN Impose 1-year data centers and crypto mining moratorium in City of Johnson City (BrightRidge)
BrightRidge electric utility announced in May 2025 a moratorium on data center project proposals in its service area, including a south Johnson City Bitcoin mining/data center site,…
2026-05-22 in force
Clarke County
county · Board of Supervisors/County Commission
IA Impose indefinite data centers and solar moratorium in Clarke County
Clarke County Board of Supervisors approved a temporary moratorium on data center construction in unincorporated areas in June 2025, prompted by Applied Digital's interest in a 200 MW,…
2025-06-23 in force
Town of Warrenton
city · City Council
VA Ban data centers in designated zones in Town of Warrenton
Warrenton Town Council voted unanimously (5-0) on July 8, 2025 to amend the zoning ordinance, striking all references to data centers from Articles 3, 9 and 12, effectively banning new…
2025-07-08 in force
Perry Township
township · Village Board
OH Require use permit for Province Group data center in Perry Township
Province Group formally withdrew its zoning application for a data center campus in Perry Township/Perry Village as of July 2025. The developer had signed an agreement to purchase 163…
2025-07-01 expired
Oldham County
county · Board of Supervisors/County Commission
KY Impose 150-day data centers moratorium in Oldham County (Western Hospitality Partners)
Western Hospitality Partners proposed 'Project Lincoln: OC Data Center,' a $6B, 600MW facility initially planned for 267 acres at 3557 North Highway 53. Due to fierce opposition from 'We…
2025-07-02 expired
Gilroy
city · City Council
CA Ban data centers in designated zones in Gilroy
Amazon Web Services received approval on July 3, 2025 for a 218,000 sq ft, 49 MW data center requiring 25 emergency generators on a 56-acre site in Gilroy, California. Two Change.org…
2026-06-15 in force
Mesa
city · City Council
AZ Require use permit for CyrusOne data center in Mesa
Mesa City Council adopted new zoning rules on July 8, 2025, restricting data centers to General Industrial and Heavy Industrial zones (roughly 4.1% of city land) and requiring special use…
2025-07-08 in force
St. Charles
city · City Council
MO Convert St. Charles moratorium into permanent citywide ban
After CRG withdrew its data center proposal from St. Charles, the Festus City Council unanimously annexed 240 acres for data center development. At least two residents filed lawsuits; Wake…
2026-05-19 in force
Augusta Charter Township
township · Township Board
MI Force public referendum on Thor Equities data center in Augusta Charter
Thor Equities proposed a $1 billion data center on 810 acres (building on about 20%) near Milan. Despite the Planning Commission recommending denial, the Board of Trustees unanimously…
2025-08-01 in force
Wake County
county · City Council
NC Impose 12-month data centers and crypto mining moratorium in Wake County (Natelli Investments)
Natelli Investments LLC withdrew its annexation and rezoning applications for the New Hill Digital Campus on March 5, 2026, a 190-acre, 250-300 MW data center on Shearon Harris Road near…
2025-08-01 expired
Bessemer
city · City Council
AL Oppose Logistics Land Investment data center in Bessemer
Bessemer City Council voted 5-2 on November 18, 2025 to approve the Project Marvel data center on ~700 acres. The decision followed extensive community opposition. [Update 2026-07-14]: The…
2026-07-13 in force
Yerington
county · Board of Supervisors/County Commission
NV Oppose Copia Power Devco data center in Yerington
Copia Power Devco LLC (backed by Carlyle) received 4-1 approval from Lyon County commissioners for a Master Plan Amendment to build the Monarch Data Center - 4.6 million sq ft across 14…
2025-12-04 in force
Lebanon
county · Board of Supervisors/County Commission
IN Rally against Meta data center in Lebanon
Meta officially broke ground on its $10B+, 1500-acre data center campus at the LEAP Innovation and Research District in Lebanon, Indiana on February 11, 2026. The campus will feature 13…
2025-08-01 in force
North Tonawanda
city · City Council
NY Impose two-year moratorium on crypto mining and data centers in North Tonawanda
North Tonawanda Common Council unanimously approved a two-year moratorium on all new crypto mining and data center developments in July 2024, expiring July 2026. The ban covers new…
2026-06-16 in force
Clayton County
county · Board of Supervisors/County Commission
GA Halt data centers in Clayton County after TA Realty proposal
Clayton County Board of Commissioners approved a moratorium on new data center applications through December 31, 2025, citing resident concerns about rapid data center growth. On December…
2025-09-01 in force
Troup County
county · Board of Supervisors/County Commission
GA Impose 90-day data centers moratorium in Troup County (Fertile Ground Investments)
Troup County enacted a 90-day moratorium on data center applications on September 16, 2025, after Fertile Ground Investments proposed a 600 MW data center on 437 acres near Hogansville.…
2025-09-01 in force
City of LaGrange
city · City Council
GA Impose 180-day data centers moratorium in City of LaGrange (Thor Equities / Form8tion)
LaGrange City Council passed a 180-day moratorium on new data center applications in September 2025 amid community backlash. The moratorium expired in March 2026. On March 27, 2026, the…
2025-09-23 expired
Pike County
county · Board of Supervisors/County Commission
GA Halt data centers in Pike County after Amazon/AWS proposal
Pike County enacted a 6-month data center moratorium in September 2025 as part of a wave of Georgia county ordinances (alongside Lamar, Troup, and Clayton counties), prompted by Amazon/AWS…
2025-09-01 in force
Lamar County
county · Board of Supervisors/County Commission
GA Halt data centers in Lamar County after Amazon/AWS proposal
Lamar County enacted a 6-month moratorium on data center development in September 2025 after AWS purchased 985 acres for $270 million, the largest real estate transaction in county…
2025-09-01 in force
Hampden Township
township · Township Board
PA Deny Undisclosed data center permit in Hampden Township
Hampden Township Commissioners unanimously rejected a proposed zoning ordinance amendment that would have designated office-park zones for data centers. Some 300 residents signed a…
2025-09-01 expired
St. Louis
city · City Council
MO Propose data centers moratorium after Contour proposal
On April 21, 2026, the St. Louis Board of Public Service unanimously approved the permit for a 120 MW data center adjacent to the historic Armory in Midtown St. Louis, weeks after Mayor…
2026-04-21 in force
Griffin
county · City Council
GA Impose 180-day data centers moratorium in Griffin
Griffin City Council unanimously passed a 180-day moratorium on data centers and other technological facilities, prompted in part by interest from Hillwood and other developers. The…
2026-01-13 in force
Jerome Township
township · Township Board
OH Impose 9-month data centers moratorium in Jerome Township (Amazon/AWS)
Jerome Township trustees unanimously approved a 9-month moratorium after residents complained of persistent noise from existing Amazon/AWS data centers. Up to four new projects were…
2025-09-03 expired
Louisville
city · City Council
KY Propose data centers moratorium after Poe Companies proposal
One 525MW data center project in southwest Louisville has been cleared to proceed, built by Poe Companies and PowerHouse Data Centers (starting at 100MW, expanding to 400MW). District 17…
2025-09-11 expired
Blakely
city · City Council
PA Block Kriger / Alpesh 'Al' Patel data center through opposition in Blakely
Developers proposed a data center campus offering up to 1.5GW of capacity on 209 acres in Blakely Borough, requiring power equivalent to the entire output of the nearby Lackawanna Energy…
2025-09-12 expired
College Station
city · City Council
TX Deny Priority Power 600MW data center permit in College Station
College Station residents mounted strong opposition to Priority Power's proposed 600MW datacenter on 200 acres of Midtown Drive. More than 75 individuals registered to speak in person and…
2025-09-12 expired
Town of Tarboro
city · City Council
NC Reject 300MW Energy Storage Solutions data center permit in Tarboro by 7-1 vote
The Tarboro Town Council rejected a Special Use Permit for Energy Storage Solutions' proposed 300MW, eight-phase data center on a 52-acre site near Anaconda and McNair roads by a 7-1 vote.…
2025-09-15 expired
Social Circle
city · City Council
GA Impose 90-day data centers moratorium in Social Circle (Multiple)
Social Circle approved a 90-day moratorium on new data center applications after being overwhelmed with seven applications. Despite the moratorium, the council approved a controversial…
2025-09-18 in force
Menomonie
city · City Council
WI Oppose Balloonist data center in Menomonie
Menomonie signed an NDA with Balloonist LLC in February 2024, over a year before announcing the $1.6B data center proposal in July 2025. Over the following six months, residents…
2025-09-24 expired
White County
county · Board of Supervisors/County Commission
IN Halt data centers in White County after Undisclosed proposal
White County's Board of Commissioners passed a moratorium on data center development on October 20, 2025, after residents packed public meetings in opposition. The moratorium was prompted…
2025-10-01 in force
Village of Yorkville
city · Village Board
WI Reject Microsoft-linked backup data center proposal in Village of Yorkville
A developer proposed a backup data center at Kuiper Farm (2400 55th Drive) in the Village of Yorkville, about five miles from Microsoft's AI data center under construction in Mount…
2025-12-08 expired
Jones County
county · Board of Supervisors/County Commission
GA Impose 90-day data centers moratorium in Jones County (EagleRock Partners)
EagleRock Partners withdrew its rezoning application for the 600+ acre Crooked Creek Technology Park after organized opposition under the 'No Data Centers in Jones County' campaign.…
2025-10-22 in force
Columbia
city · City Council
MO Block Undisclosed rezoning of 63 acres of farmland
A landowner sought to rezone 63 acres of farmland near U.S. 63 for a potential data center. The Planning & Zoning Commission voted 5-2 to recommend the change, but the City Council…
2025-11-19 expired
Preble County
county · Planning Commission
OH Deny Patrick Scanlon (developer) rezoning of 300 acres of farmland
Preble County Planning Commission unanimously (11-0) denied rezoning of 300 acres of farmland for a data center. The developer withdrew his application in October after residents organized…
2025-10-01 expired
Mason County
county · Planning Commission
KY Oppose 2,000-acre data center ordinance adoption in Mason County via We Are Mason County coalition
Mason County, Kentucky, planning commission approved a zoning ordinance paving the way for a 2,080-acre data center campus north of AA Highway, west of Maysville, by an undisclosed Fortune…
2026-03-27 in force
Platte County
county · Board of Supervisors/County Commission
MO Study data center impacts on water resources in MO
Project Kestrel, a $100B multi-phase data center campus by Shenandoah Computing LLC (linked to Google), proposes six hyperscale data centers totaling 1.8 million sq ft on 379 acres at the…
2025-10-01 in force
Lordstown
city · City Council
OH Impose 180-day data centers moratorium in Lordstown (Bristolville 25 Developer)
Lordstown, OH data center opposition. OpenAI is involved in a SEPARATE nearby Stargate project, not this one. Hyperscaler and MW figures previously attached were incorrect conflations.
2025-10-01 in force
Conshohocken / Plymouth Township
township · Township Board
PA Petition to block Brian O'Neill (developer) data center in Conshohocken /
A developer attempted to convert the Cleveland Cliffs steel plant on 66 acres of Plymouth Township's riverfront corridor into a data center for undisclosed Big Tech tenants. Over 1,000…
2025-10-01 expired
Lackawanna County
county · Board of Supervisors/County Commission
PA Propose data centers moratorium after 1778 Rich Pike proposal
Lackawanna County Commissioner Bill Gaughan asked Governor Shapiro and the PA General Assembly for a three-year statewide moratorium on new large-scale data center approvals. The county…
2025-10-01 in force
East Vincent Township
township · Planning Commission
PA Deny Penn Hurst Holdings DE data center on 125 acres in East Vincent
East Vincent's planning commission recommended rejection of a proposed 1.9 million sq ft data center at the former Pennhurst State School and Hospital for the second time. Commission cited…
2025-10-01 expired
Gordon County
county · Board of Supervisors/County Commission
GA Pause data centers in Gordon County pending regulations
Gordon County enacted a preemptive data center moratorium, despite no active data center proposals. County officials studied ordinances in Jackson, Spalding, and Wayne counties to develop…
2026-02-04 in force
Albemarle County
county · Board of Supervisors/County Commission
VA Create data center overlay zone in Albemarle County
Albemarle County proposed a zoning overlay for data centers that would designate five areas as appropriate. The Piedmont Environmental Council raised concerns. The county paused the…
2025-10-01 pending
Muscogee
county · Tribal Government
OK Deny Undisclosed data center on 5500 acres in Muscogee
Jordan Harmon and Mackenzie Roberts (both Muscogee Nation citizens) organized town halls after plans emerged to build a massive AI data center on 5,500 acres of Muscogee Nation land (the…
2025-10-01 expired
Dundee Township
township · Township Board
MI Impose 90-day data centers moratorium in Dundee Township (Cloverleaf Infrastructure)
Dundee Township enacted a 90-day moratorium on data center development in October 2025 in response to Cloverleaf Infrastructure's proposal. The moratorium was extended six months in…
2025-10-02 in force
City of Bristol
city · City Council
TN Impose 2-year data centers moratorium in City of Bristol
The City of Bristol unanimously approved a 2-year moratorium on data processing centers in September-October 2025, passing on both readings. The moratorium will remain in effect through…
2025-10-07 in force
Village of Caledonia
city · Village Board
WI Petition to block Microsoft data center in Village of Caledonia
Microsoft cancelled its 244-acre, 900 MW Caledonia data center (Project Nova) after a 2,000-signature petition and strong community opposition forced a rethinking of the plan. Microsoft…
2025-10-09 expired
Meade County
county · Board of Supervisors/County Commission
KY Deny Thomas A. Hobbs Living Trust rezoning of 138 acres of farmland
Thomas A. Hobbs Living Trust requested rezoning of a 138-acre site along Joe Prather Highway (25025 Joe Prather Hwy, Ekron) from Agricultural/Residential to Light Industrial for data…
2025-10-14 expired
Manchester Township
township · Township Board
MI Impose 2-year data centers moratorium in Manchester Township
Manchester Township enacted a 2-year data center moratorium beginning October 14, 2025, one of the longest moratorium durations among Michigan communities. By Feb 2026, at least 27…
2025-10-14 in force
Logan County
county · Board of Supervisors/County Commission
CO Impose 180-day battery energy storage systems moratorium in Logan County
Logan County Commissioners unanimously approved a 180-day moratorium on solar, wind, data center, and battery energy storage development in October 2025 after Granite Renewables (New…
2025-10-21 in force
Douglas County
county · Board of Supervisors/County Commission
GA Impose 90-day data centers moratorium in Douglas County (DC BLOX)
Douglas County imposed a 90-day data center moratorium in a 4-1 vote in March 2025, later extended in August 2025 to study ratepayer impacts. DC BLOX closed $1.15B in green loan financing…
2025-10-22 in force
Stafford County
county · Board of Supervisors/County Commission
VA Impose 750-foot data center setbacks in Stafford County
Stafford County adopted Virginia's strictest data center regulations in a 4-2-1 vote on October 22, 2025, including a 750-foot setback from residences (up from 100 ft), 200-foot vegetative…
2025-10-22 in force
Putnam County
county · Board of Supervisors/County Commission
IN Halt data centers and solar in Putnam County after Undisclosed proposal
Putnam County passed a one-year moratorium on wind, solar, data centers, and small modular nuclear reactor projects in November 2025. As of March 2026, commissioners are reviewing…
2025-11-01 in force
Campbell County
county · Board of Supervisors/County Commission
VA Deny Mesh Capital data center on 57 acres in Campbell County
Mesh Capital LLC sought to remove a protective proffer from a 57-acre property on Cabin Field Road. Supervisors voted 5-2 to deny the request in October 2025. However, since data centers…
2025-11-01 in force
Lufkin
city · City Council
TX Deny Amp Z 175MW data center permit in Lufkin
Denver-based Amp Z proposed Project Lufkin, a multi-gigawatt data center on 1,000+ acres at the former Southland Paper Mill site near the Neches River in Angelina County, TX. Total…
2025-11-01 in force
Rockford
city · City Council
IL Petition to block Monarch Energy data center in Rockford
Monarch Energy's proposed $12B, 800 MW data center on 1,100+ acres near Chicago-Rockford International Airport is advancing. Monarch Rock Air LLC was formed April 2025. On February 17,…
2025-11-01 in force
York County
county · Board of Supervisors/County Commission
SC Petition to block QTS Data Centers data center in York County
QTS is building a nine-building $1 billion campus near Lake Wylie, threatening the 95-acre Penland Christmas Tree Farm next door. Residents are concerned about noise, blinding security…
2026-07-13 in force
South Strabane Township
township · Planning Commission
PA Ban data centers in designated zones in South Strabane
South Strabane Township began drafting data center regulations after CNX Resources' 1,400-acre tract (with 400 buildable acres) was marketed by JLL for data center development. 'No Data…
2025-11-01 in force
Cumberland County
county · Board of Supervisors/County Commission
NC Petition to block Energy Storage Solutions data center in Cumberland County
Energy Storage Solutions (ESS) is planning a 'NetZero' data center off Dunn Road in Fayetteville (Cumberland County, NC), built in 8 phases with $6.4B investment as part of ESS's $19.2B…
2025-11-01 in force
Lyon County
county · Planning Commission
NV Block Tract rezoning of 1060 acres in Lyon County
Tract acquired 1,060 acres near Silver Springs in Lyon County to develop a datacenter park with up to 1.6GW capacity. The Lyon County Planning Commission unanimously approved the rezoning…
2025-11-01 in force
Jonesborough
borough · City Council
TN Impose 2-year crypto mining moratorium in Jonesborough 2025-11-03 in force
Norton
city · City Council
OH Propose data centers moratorium after Quantum HPC proposal
Norton City Council introduced a 180-day moratorium on data center zoning certificates after rejecting Quantum HPC's proposed 485,000 sq ft data center ('Project Triton') at the former PPG…
2025-11-03 in force
Wiscasset
city · City Council
ME Oppose Undisclosed (under NDA) data center in Wiscasset
Wiscasset Selectboard voted in November 2025 to pause conversations about a $5B data center on town-owned land along the Back River after resident Richard Davis launched 'Protect…
2025-11-04 in force
Johnson County
county · Board of Supervisors/County Commission
IA Impose one-year moratorium on data center rezoning and permits in unincorporated Johnson County
Johnson County Board of Supervisors unanimously approved a one-year moratorium on data center rezoning and permits in unincorporated areas on Nov. 8, 2025. The moratorium runs through…
2025-11-08 in force
Tama County
county · Board of Supervisors/County Commission
IA Pause data centers in Tama County pending regulations
Tama County Board of Supervisors approved moratoriums on both data mining/centers and battery storage on November 10, 2025. Applies to all proposed facilities regardless of size,…
2025-11-10 in force
Barberton
city · City Council
OH Impose indefinite data centers moratorium after Quantum HPC proposal
Barberton City Council approved an indefinite moratorium on data centers in November 2025. In neighboring Norton, Quantum HPC's Project Triton proposal for the old PPG mine on Limestone…
2025-11-10 in force
Mitchell County
county · Board of Supervisors/County Commission
IA Pause data centers and solar in Mitchell County pending regulations
Mitchell County approved moratoriums on utility-scale solar (Resolution #1326-25, Nov 12, 2025, unanimous) and data centers until Dec 31, 2026 (Resolution #1336-25, Nov 25, 2025, 4-1…
2025-11-25 in force
Pittsfield Township
township · Township Board
MI Impose 180-day data centers moratorium in Pittsfield Township
Pittsfield Township enacted a 180-day data center moratorium in November 2025, one of at least 27 Michigan communities to do so. Township representative Morgan Foreman is co-sponsoring the…
2025-11-18 in force
Sullivan County
county · Board of Supervisors/County Commission
TN Impose 4-month crypto mining moratorium in Sullivan County
Sullivan County Commissioner Jessica Means introduced a 4-month moratorium resolution on data mining and crypto mining centers on November 20, 2025. The commission deferred the vote at…
2025-11-20 pending
Howell Township
township · Township Board
MI Halt data centers in Howell Township after Meta proposal
Township enacted a unanimous six-month moratorium on Nov. 20, 2025 after ~2 hours of public comment. Trustee Bob Wilson confirmed Meta was behind the project, estimating a $9B investment…
2025-11-20 expired
Marshall County
county · Board of Supervisors/County Commission
IN Halt data centers in Marshall County after Undisclosed proposal
On April 20, 2026, Marshall County Commissioners voted to enact a permanent ban on data centers across the county, replacing the prior one-year moratorium. The action is reported as the…
2026-04-20 in force
Wilmington
city · City Council
OH Require use permit for Amazon/AWS data center in Wilmington
Amazon/AWS proposed a $4B datacenter on 471 acres in Wilmington with a 30-year, 100% property tax abatement (effective 70% abatement). On April 23, 2026, Wilmington residents Jessica Sharp…
2025-11-26 in force
Monroe County
county · Board of Supervisors/County Commission
GA Impose moratorium on data centers in Monroe County after rejecting $5.8B Bolingbroke campus
Monroe County passed a data center moratorium on unincorporated land after commissioners unanimously rejected the 900-acre, $5.8 billion Bolingbroke Technology Campus. Nearly 900 residents…
2025-12-01 in force
Athens-Clarke County
county · Board of Supervisors/County Commission
GA Propose data centers moratorium after FAE Clark (end-user unknown) proposal
Athens-Clarke County Commission originally imposed an emergency moratorium on data centers in December 2025, extended it to June 5, 2026, and used the time to develop permanent…
2026-04-09 in force
Town of Carlton
township · Township Board
WI Force Cloverleaf Infrastructure to scrap data center plans in Carlton after public opposition
Cloverleaf Infrastructure scrapped plans in Carlton (Kewaunee County) after local residents objected to the idea. Town Chairman David Hardtke told Cloverleaf 'if this is such a good thing…
2025-12-01 expired
Big Rapids Township
township · Township Board
MI Ban data centers in Big Rapids Township's airport industrial park
Big Rapids Township passed an ordinance banning data centers in its 120-acre airport industrial park, part of a wave of at least 27 Michigan communities enacting moratoria or zoning…
2025-12-01 in force
Edgecombe County
county · Board of Supervisors/County Commission
NC Oppose Energy Storage Solutions data center over water in Edgecombe County
Energy Storage Solutions (ESS) plans a $19.2B, 900 MW, 300-acre data center and energy storage campus at the Kingsboro Business Park, Tarboro, NC, part of ESS's ~$38B North Carolina…
2026-07-14 expired
Sioux Falls
city · City Council
SD Force public referendum on Gemini Capital data center in Sioux Falls
Gemini Capital proposed a $1.9B, 500 MW hyperscale data center on 164 acres in eastern Sioux Falls. The City Council voted 7-0 on Jan. 6, 2026 to rezone the farmland for light industrial…
2025-12-01 in force
Lawrence County
county · Board of Supervisors/County Commission
OH Halt data centers in Lawrence County after Strata Expanse proposal
Houston-based Strata Expanse hosted a ribbon cutting for an AI data center in the Haverhill area at 1476 County Road 1A. A petition gathered 5,570 signatures voicing concerns about the…
2025-12-01 in force
Moorestown
city · City Council
NJ Deny New Urban data center on 25 acres in Moorestown
Moorestown Township Council opted out of data center development on a 25-acre vacant site (former Pulverizer Services / New Albany Business Park Redevelopment Area) along New Albany Road.…
2025-10-31 expired
Monroe Township
township · City Council
NJ Remove data centers from Hexa Builders Redevelopment Plan permitted uses in Monroe Township
Monroe Township (Gloucester County) introduced Ordinance O:20-2026 on April 8, 2026 to ban data centers from the Hexa Redevelopment Plan on Black Horse Pike. Final adoption vote scheduled…
2026-04-08 pending
Breckinridge County
county · Board of Supervisors/County Commission
KY Pause data centers and solar in Breckinridge County pending regulations
Breckinridge County Fiscal Court passed an AI Data Center Moratorium ordinance in November 2025. Meanwhile, TeraWulf is advancing a $3-4B large-scale data center campus in nearby…
2025-11-17 in force
Tyrone Township
township · Township Board
MI Impose 6-month data centers moratorium in Tyrone Township
Tyrone Township (Livingston County) enacted a 6-month moratorium on data center development on December 2, 2025. The township is located near Howell Township, where a major $1 billion Meta…
2025-12-02 in force
Starke County
county · Planning Commission
IN Halt data centers in Starke County after ABEI Energy proposal
Starke County Planning Commission unanimously advanced a one-year moratorium on hyperscale data centers exceeding 5,000 sq ft in December 2025, making it the fourth Indiana county to act.…
2025-12-04 in force
Green Charter Township
township · Township Board
MI Halt data centers in Green Charter after Undisclosed proposal
Green Charter Township adopted a one-year moratorium on data center development on Dec. 9, 2025, citing concerns about water consumption, energy usage, and noise. The township was among…
2025-12-09 in force
St. Joseph County
county · Board of Supervisors/County Commission
IN Deny Amazon/AWS rezoning of 1200 acres of farmland
On December 10, 2025 the St. Joseph County Council voted 7-2 to deny a $12B data center from an undisclosed developer. Amazon has separate already-approved projects in the region (an…
2025-12-10 expired
City of Chandler
city · City Council
AZ Deny Active Infrastructure 150MW data center permit in City of Chandler
City Council voted 7-0 on December 12, 2025 to reject Active Infrastructure's $2.5B, 150 MW AI data center proposal on 40 acres near Queen Creek and Dobson roads. The city received over…
2025-12-12 expired
Coweta County
county · Board of Supervisors/County Commission
GA Oppose 900MW Prologis data center on 832 acres in Coweta County
Coweta County's moratorium on data center applications expired December 17, 2025, and the Board adopted a data center ordinance on December 16. On April 10-11, 2026, Coweta County…
2026-06-16 in force
DeKalb County
county · Board of Supervisors/County Commission
GA Impose 100-day data centers moratorium in DeKalb County (PCC-DeKalb)
DeKalb County, Georgia Commission extended its data center moratorium until June 23, 2026 at the December 16, 2025 meeting due to community concerns about public health and environmental…
2026-06-09 in force
Lewiston
city · City Council
ME Deny MillCompute 24MW data center permit in Lewiston
Lewiston City Council voted 7-0 on December 16, 2025 to reject a $300M AI data center proposed by MillCompute LLC and building owner Bill Johnson's Twin Cities LLC for the historic Bates…
2025-12-16 expired
Gates County
county · Board of Supervisors/County Commission
NC Halt data centers and crypto mining in Gates County after Undisclosed proposal
Gates County passed a 12-month moratorium on data centers and cryptocurrency mining facilities after receiving two inquiries from PACE, a firm that prepares ordinances and land use…
2025-12-17 in force
Waterville Township
township · Township Board
OH Impose 12-month data centers moratorium in Waterville Township (Undisclosed)
Waterville Township trustees unanimously approved a 12-month moratorium on Dec. 17, 2025, citing concerns about electrical grid strain, water supply, and quality of life. The city of…
2025-12-17 in force
Lowell Township
township · Township Board
MI Ban data centers in designated zones in Lowell Township
Franklin Lowell LLC applied to rezone 235 acres at Covenant Business Park near Grand Rapids for a data center. A public hearing was abandoned when the venue couldn't hold the opposition…
2025-12-18 in force
South Bloomfield
city · Village Board
OH Impose 180-day data centers moratorium in South Bloomfield
South Bloomfield Village Council adopted a 180-day moratorium on data center construction and a new zoning code that does not list data centers as a permitted use, effectively preemptively…
2025-12-19 in force
Vineland
city · City Council
NJ Cap data center water consumption in NJ
~100 people gathered to protest a 350 MW hyperscale AI data center under construction in Vineland, which will have roughly Empire State Building-sized footprint and nearly double the…
2025-12-23 in force
Oshtemo Township
township · Township Board
MI Halt battery energy storage systems in Oshtemo Township after Undisclosed proposal
Oshtemo Charter Township (Kalamazoo County) is formally considering a data center moratorium as of early 2026, joining Portage and at least 27 other Michigan communities with active…
2026-01-01 in force
Luther
city · City Council
OK Propose data centers moratorium after Beltline Energy proposal
Beltline Energy is eyeing a 400-acre parcel near an OG&E power plant for a data center, with discussions ongoing since mid-2025. As of early 2026, no formal application has been filed,…
2026-06-17 in force
Conewago Township
township · Township Board
PA Block Elysian Partners rezoning of farmland in Conewago Township
Residents of Conewago Township in York County, Pennsylvania object to plans by Elysian Partners to rezone agricultural and residential land for AI data centers. The petition argues the use…
2026-01-01 in force
City of Taylor
city · City Council
MI Impose 1-year data centers moratorium in City of Taylor
Taylor enacted a 1-year data center moratorium in January 2026. Separately, Sens. Rosemary Bayer (D-West Bloomfield), Erika Geiss (D-Taylor), and Sue Shink (D-Northfield Twp.) introduced…
2026-01-01 in force
Dorr Township
township · Township Board
MI Halt data centers in Dorr Township after Microsoft proposal
Dorr Township (Allegan County) enacted a moratorium on data center development while the planning commission develops an ordinance to regulate the facilities, expected to take about six…
2026-01-01 in force
Caledonia Township
township · Township Board
MI Impose 6-month data centers moratorium in Caledonia Township
Caledonia Township (Kent County) implemented a 6-month moratorium on data center and data mining operations effective January 1, 2026, running through June. The moratorium follows…
2026-01-01 in force
Shippingport
city · City Council
PA Contest Aligned Data Centers approval at former nuclear plant site
Aligned Data Centers (acquired by BlackRock/GIP for $40B) received conditional use approval from Shippingport Borough Council in January 2026 for 'Project Phoenix,' a $10B data center…
2026-01-28 in force
Wood County
county · Board of Supervisors/County Commission
OH Halt data centers in Wood County after Meta proposal
Meta revealed plans for an $800M, 715,000 sq ft data center on 280 acres in Middleton Township. 7 of Wood County's 19 townships have adopted temporary moratoriums, with 8 more discussing…
2026-01-06 in force
Northville
city · City Council
MI Impose 12-month data centers moratorium in Northville
The Northville City Council unanimously approved a 12-month preemptive moratorium on data centers on January 6, 2026, halting any data center applications. Unlike other communities,…
2026-01-06 in force
Henry County
county · Board of Supervisors/County Commission
GA Ban data centers in designated zones in Henry County
Henry County began drafting strict data center regulations following interest from developers including Hampton Technology Park. Proposed rules include 200-foot buffers, 1,000-foot…
2026-01-06 in force
Springfield Township
township · Township Board
MI Impose 180-day data centers moratorium in Springfield Township
Springfield Township (Oakland County) Board of Trustees approved a 180-day moratorium on data center plans on January 7, 2026, three days after planners with consulting firm Giffels…
2026-01-07 in force
Ironton
city · City Council
OH Halt data centers in Ironton after Strata Expanse proposal
Strata Expanse (Houston), RAVEL, and Supermicro held a ribbon-cutting in December 2025 for an AI Center of Excellence and data center at 1476 County Road 1A in Lawrence County's Haverhill…
2026-01-09 in force
Saline Township
township · City Council
MI Halt data centers in City of Saline after Related Digital proposal
The Michigan Public Service Commission voted 3-0 in December 2025 to conditionally approve DTE Energy's 19-year, 1.4 GW power supply agreement for the Stargate data center campus in Saline…
2026-01-12 in force
Stokes County
county · Board of Supervisors/County Commission
NC Ban data centers in designated zones in Stokes County
Stokes County Board of Commissioners approved (3-2 vote) in January 2026 the rezoning of approximately 1,845 acres of residential-agricultural land along the Dan River for heavy industrial…
2026-01-12 expired
Roswell
city · City Council
GA Impose 90-day data centers moratorium in Roswell
Roswell City Council approved a 90-day emergency moratorium on new data centers (through April 12) as one of its first acts under a new mayor and three new council members. The Community…
2026-01-12 in force
Village of Greenleaf
city · Village Board
WI Legal challenge to Cloverleaf Infrastructure data center in Village of Greenleaf
Houston-based Cloverleaf Infrastructure offered $120,000 per acre for approximately 600 acres to build the first AI data center in northeast Wisconsin, directly across from Ledgestone…
2026-01-13 expired
City of Madison
city · City Council
WI Halt data centers in City of Madison after QTS Data Centers proposal
City of Madison, WI adopted a data center moratorium on January 13, 2026. This was a policy-driven, preventative action, not tied specifically to the QTS/DeForest proposal. QTS figures…
2026-01-13 in force
Birmingham
city · City Council
AL Impose 180-day data centers moratorium in Birmingham (Nebius)
Birmingham City Council unanimously approved a 270-day moratorium on applications for new or expanding hyperscale data centers on March 3, 2026. Facilities under 20 megawatts are exempt.…
2026-03-03 in force
Harvey County
county · Board of Supervisors/County Commission
KS Pause data centers and crypto mining in Harvey County pending regulations
Harvey County Commission unanimously approved a moratorium on data center construction in unincorporated areas through the end of 2028 (roughly three years). Commissioner Don Schroeder…
2026-01-13 in force
City of Saginaw
city · City Council
MI Impose 6-month data centers moratorium in City of Saginaw
Saginaw City Council unanimously approved a resolution enacting a 6-month blanket prohibition on data centers on January 13, 2026. Councilwoman Carly Rose Hammond proposed the motion,…
2026-01-13 in force
Armada Township
township · Township Board
MI Impose 180-day data centers moratorium in Armada Township
Armada Township enacted a 180-day moratorium on data center development starting January 14, 2026. The moratorium gives the township time to review zoning, infrastructure capacity, and…
2026-01-14 in force
Sedgwick County
county · Board of Supervisors/County Commission
KS Impose 3-year data centers moratorium in Sedgwick County (Monarch Energy)
Sedgwick County Commissioners unanimously voted on March 4, 2026 to extend the moratorium on data center permit applications to June 11, 2026. Two companies, Monarch Energy (San Diego) and…
2026-01-15 in force
Villa Ridge
county · Board of Supervisors/County Commission
MO Ban data centers in designated zones in Villa Ridge
Change.org petition with 6,140+ signatures voicing concerns about a proposed data center on Robertsville Road in Villa Ridge, near Shaw Nature Reserve. The land (613 acres total) is owned…
2026-01-15 pending
Yukon
city · Planning Commission
OK Block Gamma Resources rezoning of 295 acres in Yukon
Yukon (OK) faces opposition to a Gamma Resources data center proposal near I-40. As of early 2026, the project is currently STALLED, zoning hearings have been deferred TWICE due to local…
2026-01-15 in force
Kansas City
city · City Council
MO Restrict Multiple 700MW data center in Kansas City
Kansas City, Missouri, Council unanimously approved zoning changes reclassifying data centers as industrial facilities, limiting them to specific zoning districts, revoking by-right status…
2026-01-16 in force
Coweta
city · City Council
OK Deny Beale Infrastructure rezoning of 295 acres in Coweta
In Coweta, Oklahoma, Beale Infrastructure's $800M Project Atlas proposed 295 acres for an Amazon/AWS data center with 400MW capacity. The Planning Commission voted 4-1 to deny rezoning on…
2026-01-19 expired
Village of Godfrey
city · Village Board
IL Impose 180-day data centers moratorium in Village of Godfrey
Village of Godfrey, Illinois, unanimously approved a 180-day moratorium on data center construction applications on January 20, 2026, after Cloverleaf Infrastructure proposed a 500MW data…
2026-01-20 in force
Monterey Park
city · City Council
CA Impose 45-day data centers moratorium in Monterey Park (HMC Capital (StratCap))
Monterey Park, California, City Council unanimously adopted a 45-day moratorium on data center development on January 21, 2026, prompted by a proposed 250,000 sq ft data center at Saturn…
2026-01-21 in force
Naperville
city · City Council
IL Deny Karis Critical 36MW data center permit in Naperville
Naperville, Illinois, City Council voted 6-1 to deny Karis Critical's proposal for a 145,000 sq ft data center on the former Nokia/Lucent campus (36 MW, $250M, 40 acres). A Change.org…
2026-01-21 expired
City of Pontiac
city · City Council
MI Halt data centers in City of Pontiac after Concord Infrastructure proposal
In City of Pontiac, Michigan, Pontiac City Council unanimously passed a six-month moratorium on the consideration of data centers 'pending further study and enactment of city regulation,'…
2026-01-21 in force
Grand Blanc Township
township · Township Board
MI Impose 1-year data centers moratorium in Grand Blanc Township
Grand Blanc Township Board of Trustees passed a one-year moratorium on data center development on January 21, 2026, rejecting all applications until the period expires unless shortened or…
2026-01-21 in force
Sylvan Township
township · Township Board
MI Impose 6-month data centers moratorium in Sylvan Township
Sylvan Township (near Chelsea, Washtenaw County) enacted a 6-month moratorium on data centers on January 22, 2026. Supervisor Amanda Nimke stated: 'We clearly can't stop them, but we can…
2026-01-22 in force
El Paso
city · City Council
TX Terminate city contracts with Meta and halt $10B data center expansion in El Paso
Meta expanded its El Paso data center investment from $1.5B to $10B (1GW capacity, 1,000 acres). Construction began November 2025 with completion targeted February 2029. El Paso Electric…
2026-06-18 expired
Village of Romeo
city · Village Board
MI Pause data centers in Village of Romeo pending regulations
The Village of Romeo enacted a data center moratorium on January 26, 2026, joining the wave of Macomb County communities (including nearby Armada Township, Lenox Township, and Sterling…
2026-01-26 in force
Pekin
city · City Council
IL Ban data centers from using Mahomet Aquifer groundwater via SB 4004
In Illinois, Hundreds of residents packed a city council meeting to challenge a data center proposed on the Lutticken Farm along the Mahomet Aquifer, Which serves nearly 1 million people…
2026-03-09 expired
Larimer County
county · Board of Supervisors/County Commission
CO Impose 30-day data centers moratorium in Larimer County
Larimer County extended its temporary moratorium on data center facilities to August 25, 2026, following a public hearing on February 9, 2026. The pause allows staff time to develop…
2026-01-27 in force
New Orleans
city · City Council
LA Halt data centers and crypto mining in New Orleans after MS Solar Grid Data proposal
The New Orleans City Council voted unanimously 6-0 on January 28, 2026 to impose a one-year moratorium on construction of data centers, server farms, and cryptocurrency mining facilities,…
2026-01-28 in force
Fayetteville
city · Planning Commission
GA Block Corvus Investment Group rezoning of 240 acres in Fayetteville
Fayetteville's Planning & Zoning Commission denied Corvus Investment Group's request to rezone 240+ acres along Highway 85 North and Highway 314 to Business Park, a classification that…
2026-01-27 in force
Carroll County
county · Board of Supervisors/County Commission
GA Block Atlas Development rezoning of 350 acres in Carroll County
Atlas Development filed a Development of Regional Impact for 'Project Bus,' a 12-building data center campus on approximately 350 acres in Temple (northern Carroll County, Georgia,). The…
2026-01-28 expired
Barrington Hills
city · City Council
IL Force Brennan Investment Group to withdraw $2B data center proposal in Barrington Hills
Brennan Investment Group withdrew its $2 billion data center proposal for land south of Penny Road and west of Pond Gate Drive in Barrington Hills, Illinois, a suburb northwest of Chicago…
2026-01-29 expired
Sangamon County
county · Board of Supervisors/County Commission
IL Propose data centers moratorium in Sangamon County (rejected)
Sangamon County Board voted 17-10 on April 7, 2026 to approve CyrusOne's $500M data center on 280 acres of farmland near Waverly, ~14 miles southwest of Springfield, despite hundreds of…
2026-02-01 in force
Carroll County
county · Board of Supervisors/County Commission
MD Pause data centers in Carroll County pending regulations
Carroll County Board of Commissioners voted to draft a deferral ordinance placing a temporary moratorium on data center projects, despite no developers having applied. The preemptive…
2026-02-01 in force
Champaign County
county · Board of Supervisors/County Commission
OH Petition to block Thor Equities data center in Champaign County
Thor Equities proposed a $1 billion, 500MW data center (Urbana Technology Hub) on 48+ acres in Champaign County, Ohio, near Urbana. On March 3, 2026, the Urbana City Council voted 6-1 to…
2026-03-03 in force
Vienna Township
township · Township Board
OH Pause data centers in Vienna Township pending regulations
Vienna Township in northeast Ohio is using a pause on data centers to develop lasting zoning changes rather than a temporary moratorium. Trustee Phil Pegg requested zoning to place a limit…
2026-02-01 in force
Pecos County
county · Board of Supervisors/County Commission
TX Rally against Pacifico Energy data center in Pecos County
Pacifico Energy's GW Ranch project in Pecos County, Texas, ~17 miles north of Fort Stockton, received TCEQ approval in early 2026 as the 'largest permitted data center campus' in the U.S.…
2026-02-01 in force
Solon Township
township · Township Board
MI Impose 6-month data centers moratorium in Solon Township
Solon Township, Michigan, (Kent County) Board unanimously approved a 6-month moratorium on new data center proposals in early February 2026, extended from an initial 90-day proposal after…
2026-02-01 in force
Dickerson
county · Board of Supervisors/County Commission
MD Halt data centers in Dickerson after Atmosphere Data Centers proposal
California-based Atmosphere Data Centers plans a $2 billion, 300MW data center complex on 170 acres at the site of a decommissioned coal-fired power plant in Dickerson, Maryland,.…
2026-02-01 in force
Citrus County
county · Planning Commission
FL Block Deltona Corp rezoning of 813 acres in Citrus County
In Citrus County, Florida, Deltona Corp proposed an 813-acre AI data center near CR 491 and Tram Road in Lecanto. The Planning & Development Commission voted 4-3 to postpone any decision.…
2026-05-26 in force
Saugatuck Township
township · Township Board
MI Pause data centers in Saugatuck Township pending regulations
Saugatuck Township in Allegan County placed a moratorium on data center development in February 2026, part of a wave of at least 27 Michigan communities enacting temporary pauses. The…
2026-02-01 in force
Montgomery County
county · Board of Supervisors/County Commission
MD Require use permit for Atmosphere Data Centers data center in Montgomery County
Montgomery County, Maryland, enacted a moratorium on new data center development through the end of 2026, prompted by Atmosphere Data Centers' proposed 300MW complex on 170 acres in…
2026-02-02 in force
Baltimore County
county · Board of Supervisors/County Commission
MD Halt data centers in Baltimore County after Security Land and Development proposal
Baltimore County, Maryland, Council unanimously passed a moratorium temporarily freezing data center development through January 1, 2027, blocking permits until the Planning Board studies…
2026-02-02 in force
Maumee
city · City Council
OH Impose 12-month data centers moratorium in Maumee (Meta)
Maumee City Council approved a 12-month moratorium on Feb. 2, 2026, joining the wave of northwest Ohio communities responding to Meta's $800M data center in nearby Middleton Township.…
2026-02-02 in force
Ashville
county · Village Board
OH Deny EdgeConneX 1800MW data center permit in Ashville
The Ashville, Ohio, Village Council voted 4-2 to deny EdgeConneX's annexation request for a 490-acre parcel needed for a $10 billion, 680-acre, 1.8GW data center campus about 17 miles…
2026-02-02 in force
Lenox Township
township · Township Board
MI Impose 4-month data centers moratorium in Lenox Township
Lenox Township Board of Trustees adopted a 4-month moratorium on new data center development effective February 2, 2026, with the option for one additional 4-month extension. The…
2026-02-02 in force
Hancock County
county · Board of Supervisors/County Commission
KY Shield residential ratepayers from data center costs in KY
In Hancock County, Kentucky, Change.org petition with 1,052 signatures voicing concerns about TeraWulf's data center at the former Century Aluminum smelter site in Hawesville. TeraWulf…
2026-02-02 in force
City of Mason
city · City Council
MI Force public referendum on data center in City of Mason
In City of Mason, Michigan, residents submitted a referendum petition with 700+ signatures against Ordinance 266 (M-3 Technology Innovation zoning district). On March 16, 2026, Mason City…
2026-02-03 in force
Village of DeForest
city · Village Board
WI Deny QTS Data Centers 1600MW data center permit in Village of DeForest
In the Village of DeForest, Wisconsin, QTS Data Centers proposed a $12B project involving five data center buildings on nearly 1,600 acres of farmland in the Town of Vienna. The 'No Data…
2026-02-03 expired
Sterling Heights
city · City Council
MI Propose data centers moratorium in Sterling Heights
The Sterling Heights City Council unanimously voted to impose a one-year moratorium on any new data centers proposed in the city. Officials noted that the city's zoning restrictions,…
2026-02-03 in force
Lodi Township
township · Township Board
MI Impose 180-day data centers moratorium in Lodi Township
Lodi Township (Washtenaw County) enacted a 180-day moratorium on data center development on February 3, 2026, joining a sweeping wave of at least 27 Michigan communities now pausing data…
2026-02-03 in force
Covington Township
township · Township Board
PA Halt 1778 Rich Pike / Quantm Group's 35-building, 1.5GW data center on 1,000 acres in Covington Township
1778 Rich Pike LLC / Quantm Group plans 'Project Gouldsboro,' a $14.25 billion, 35-building, 1.5GW data center campus across Clifton and Covington townships on nearly 1,000 acres. Clifton…
2026-02-03 in force
New Castle County
county · Board of Supervisors/County Commission
DE Uphold denial of Starwood Digital Ventures data center on appeal
In New Castle County, Delaware, Starwood Digital Ventures proposed 'Project Washington,' a $10 billion, 1.2GW datacenter on 580 acres near Delaware City. The facility would consume as much…
2026-02-04 in force
Mt. Orab
city · City Council
OH Impose 180-day data centers moratorium in Mt. Orab (DB STU)
In Mt. Orab, Ohio, Village Councilman Eric Lang introduced two ordinances for a 180-day data center moratorium amid community outcry over a mysterious 1,000-acre 'mega site' project…
2026-02-04 in force
Muhlenberg Township
township · Township Board
OH Impose 12-month data centers moratorium in Muhlenberg Township (Pacifico Energy)
Muhlenberg Township, Ohio, (Pickaway County, near Circleville) passed a 12-month moratorium on new data centers after a petition gathered 700+ signatures (proposed by Pacifico Energy) (120…
2026-02-06 in force
Montour County
county · Board of Supervisors/County Commission
PA Deny Talen Energy / Amazon rezoning of 800 acres of farmland
Montour County, Pennsylvania, commissioners unanimously denied Talen Energy's request to rezone 800+ acres from agricultural to industrial to allow a co-located data center near the…
2026-02-10 expired
Hood County
county · Board of Supervisors/County Commission
TX Propose data centers and crypto mining moratorium in Hood County (rejected)
Hood County (40 miles SW of Fort Worth) has received at least five data center applications (proposed by Sailfish Development). Commissioners voted down a proposed moratorium 3-2, twice,…
2026-02-10 expired
City of Oregon
city · City Council
OH Deny Capacity 500MW data center permit in City of Oregon
In City of Oregon, Ohio, Oregon City Council initially voted 3-2 with one abstention against granting Capacity LLC a six-month extension for a proposed $2 billion, 500MW data center on 170…
2026-02-10 in force
Hayes Township
township · Township Board
MI Impose 180-day data centers moratorium in Hayes Township
Hayes Township, Michigan, (Charlevoix County) Board of Trustees unanimously enacted a 180-day moratorium on data centers on February 10, 2026, despite no current data center proposals.…
2026-02-10 in force
City of South Lyon
city · City Council
MI Impose 12-month data centers moratorium in City of South Lyon
In City of South Lyon, Michigan, South Lyon City Council adopted a 12-month moratorium on new data center applications on February 10, 2026, extending it beyond the original proposal of…
2026-02-10 in force
Erie Township
township · Township Board
MI Pause data centers in Erie Township pending regulations
Erie Township (Monroe County) enacted a limited moratorium on data center development on February 10, 2026, joining nearby Dundee Township which has had a moratorium since October 2025 in…
2026-02-10 in force
Bernalillo County
county · Board of Supervisors/County Commission
NM Adopt data center zoning standards in Bernalillo County
Bernalillo County guardrails resolution (proposed by Commissioner Eric Olivas) passed 4-1 (Benson dissent) on February 11, 2026. Project Jupiter (Oracle / $50B / ~1,400 acres) is a…
2026-02-11 in force
Town of Canton
city · City Council
NC Impose 12-month data centers and crypto mining moratorium in Town of Canton (Unknown)
In Town of Canton, North Carolina, Canton Board of Aldermen approved a 12-month moratorium on data center construction, cryptocurrency mining, and server farms after about 50 residents…
2026-02-11 in force
Blanchester
city · City Council
OH Impose moratorium in Blanchester after surrounding AWS and data center proposals
Blanchester Village Council unanimously approved a moratorium on Feb. 12, 2026, after AWS proposed a $3B data center in nearby Wilmington (which was tabled) and other projects emerged in…
2026-02-12 in force
Walla Walla County
county · Board of Supervisors/County Commission
WA Oppose Port of Walla Walla's $36M land sale to AWS for $4.8B data center campus
In Walla Walla County, Washington, Port of Walla Walla unanimously approved $36M sale of 553 acres at Wallula Gap Business Park to AWS for a $4.8B, 16-building, 3.4M sq ft data center…
2026-02-12 in force
York Township
township · Township Board
MI Impose 6-month data centers moratorium in York Township (Sansone Group)
York Township, Michigan, (Washtenaw County) enacted a 6-month moratorium on data center development on February 12, 2026, after representatives for developer Sansone Group discussed a…
2026-02-12 in force
Chatham County
county · Board of Supervisors/County Commission
NC Impose 12-month data centers and crypto mining moratorium in Chatham County
Chatham County, North Carolina, approved a 12-month moratorium on the development of new data centers and cryptocurrency mining facilities on February 13, 2026, after Natelli Investments…
2026-02-13 in force
Dickson City
city · City Council
PA Restrict data centers to industrial zones in Dickson City
Dickson City, Pennsylvania, Borough Council adopted regulations that define, regulate and restrict data centers as special exceptions in the town's light manufacturing district, limiting…
2026-02-13 in force
Hubbard Township
township · Township Board
OH Impose 12-month data centers moratorium in Hubbard Township (Bristolville 25 Developer)
Hubbard Township, Ohio, trustees voted 2-1 to approve a resolution placing a one-year moratorium on data centers entering the township in February 2026 (proposed by Bristolville 25…
2026-02-15 in force
Lowndes County
county · Board of Supervisors/County Commission
GA Block DC BLOX rezoning of 720 acres in Lowndes County
DC BLOX is the company behind the Lowndes County, Georgia, data center proposal (720 acres). DC BLOX's CEO informed the landowner (Pope Langdale) the facility could create up to 400 jobs…
2026-02-17 in force
Richfield Township
township · Township Board
OH Impose 12-month data centers moratorium in Richfield Township
Richfield Township (Lucas County) passed a 12-month data center moratorium on Feb. 17, 2026, part of a wave across northwest Ohio triggered by Meta's $800M data center in nearby Middleton…
2026-02-17 in force
Ann Arbor Township
township · Township Board
MI Impose 12-month data centers moratorium in Ann Arbor Township
Ann Arbor Township Board of Trustees passed a 12-month moratorium on data centers. No developer has approached township officials about a data center; the moratorium is a proactive measure…
2026-02-17 in force
Columbiana
county · City Council
AL Impose 300-foot data center setbacks in Columbiana
Columbiana City Council unanimously approved a new ordinance imposing zoning restrictions on future data centers, becoming the first Alabama municipality to pass such restrictions ($200M).…
2026-02-17 in force
Monclova Township
township · Township Board
OH Impose 12-month data centers moratorium in Monclova Township
Monclova Township trustees unanimously approved a 12-month moratorium on Feb. 18, 2026 after residents packed multiple meetings. Although no data center has been proposed in the township,…
2026-02-18 in force
Elmwood Township
township · Township Board
MI Impose 9-month data centers moratorium in Elmwood Township
Elmwood Township, Michigan, Board unanimously approved a 9-month moratorium on data centers (reduced from originally proposed 12 months). No known data center plans exist for the county;…
2026-02-18 in force
Middleton Township
township · Township Board
OH Demand transparency on Meta's $800M data center under construction in Middleton Township
A Meta data center spanning 715,000 sq ft under construction in Middleton Township, Ohio, was revealed in April 2025, anticipated operational in 2027 with 100 employees (350 MW, 280…
2025-04-01 in force
New Brunswick
city · City Council
NJ Deny Amzak Capital Management data center on 22 acres in New Brunswick
New Brunswick, New Jersey, City Council voted unanimously on Feb 19, 2026 to remove data centers as a permitted use from the Jersey-Sandford Redevelopment Plan, killing the Amzak…
2026-02-19 in force
Mercer County
county · Board of Supervisors/County Commission
KY Enact one-year moratorium on data center applications in Mercer County
The Mercer County Commission voted 3-2 on March 3, 2026 to enact a one-year moratorium on data center applications, halting all activity relating to data center projects in the county.…
2026-02-19 in force
Aurora
city · City Council
IL Adopt strictest-in-Illinois data center noise and setback regulations in Aurora
Aurora (IL) is debating what supporters describe as the strictest-in-Illinois data center noise and setback ordinance. The February 19, 2026 Planning & Development Committee meeting did…
2026-02-19 pending
Town of Dryden
city · City Council
NY Ban commercial crypto mining in Town of Dryden
Town of Dryden, NY adopted a preventative data center zoning restriction on February 19, 2026. The TeraWulf Cayuga project referenced in earlier coverage is in Lansing, not Dryden,…
2026-02-19 in force
Manitowoc County
county · Board of Supervisors/County Commission
WI Pause data center permits for statewide study in WI
Three northeast Wisconsin towns -- Two Creeks, Two Rivers, and Mishicot -- passed resolutions calling on Manitowoc County to place a one-year moratorium on new data center permits and…
2026-02-20 in force
North Coventry Township
township · Township Board
PA Deny Envision Land Use data center on 18 acres in North Coventry
In North Coventry Township, Pennsylvania, Township supervisors voted 3-2 to reject a 120,000 sq ft, three-story 'boutique' data center on 18 acres off Route 724 before the proposal was…
2026-02-23 in force
Denver
city · City Council
CO Halt data centers in Denver after CoreSite proposal
Denver City Council planning committee approved on March 31, 2026 a measure for a one-year moratorium on acceptance/processing of data center permit and site development applications.…
2026-02-24 in force
Lincoln County
county · Board of Supervisors/County Commission
SD Propose data centers moratorium after Gemini Data Center SD proposal
Lincoln County Commissioner Joel Arends proposed a one-year moratorium on hyperscale data centers requiring 100+ MW, calling it an opportunity to 'press pause and further research' the…
2026-02-24 expired
Sunbury
city · Planning Commission
OH Block Amazon/AWS rezoning of 330 acres in Sunbury
On April 15, 2026, Sunbury City Council unanimously passed a moratorium on data centers effective until January 31, 2027, pausing the proposed $2 billion AWS data center project at the…
2026-04-15 in force
Cobb County
county · Board of Supervisors/County Commission
GA Impose 180-day data centers moratorium in Cobb County (Grindcap (MMM Acquisitions))
Cobb County, Georgia, Board of Commissioners voted unanimously to implement a 180-day moratorium on new data center permits and rezoning applications in unincorporated areas, prompted by…
2026-02-24 in force
Franklin County
county · Board of Supervisors/County Commission
IN Halt data centers in Franklin County after ABEI Energy proposal
Franklin County, Indiana, Commissioners voted unanimously to extend the data center moratorium through February 2027, preventing new applications while the county gathers information and…
2026-02-24 in force
West Rockhill Township
township · Township Board
PA Restrict data centers to industrial zones in West Rockhill
West Rockhill Township Board of Supervisors unanimously adopted a zoning ordinance regulating data centers on April 15, 2026, limiting them to the township's Planned Industrial district by…
2026-04-15 in force
East Rockhill Township
township · Township Board
PA Restrict data centers to industrial zones in East Rockhill
East Rockhill supervisors advanced a preemptive data center ordinance (no application yet received). Restricts data centers to industrial districts at Pennridge Airport, requires 50-acre…
2026-02-24 in force
City of Portage
city · City Council
MI Pause battery energy storage systems in City of Portage pending regulations
In City of Portage, Michigan, Portage enacted a temporary moratorium on data centers and battery energy storage facilities through end of year to allow the city to review zoning rules and…
2026-02-25 in force
Pacific
city · City Council
MO Force Beltline Energy to table $16B, 16-building data center campus on 500 acres in Pacific
Atlanta-based Beltline Energy pitched a $16B, 16-building datacenter campus on 500 acres requiring annexation into Pacific (1.3GW). Hundreds of residents packed Pacific High School in…
2026-02-25 pending
Phillipsburg
city · City Council
NJ Ban data centers in all zones in Phillipsburg
Phillipsburg, NJ Town Council unanimously adopted Ordinance 2026-08 on April 14, 2026 banning data centers in all zoning districts. The final vote followed a February 24 first reading.…
2026-02-25 in force
Dearborn County
county · Board of Supervisors/County Commission
IN Pause data centers and solar in Dearborn County pending regulations
Dearborn County, Indiana, Board of Commissioners approved a one-year moratorium on rezoning proposals for commercial solar, battery storage, and data centers effective February 26. The…
2026-02-25 in force
Fort Meade
county · Board of Supervisors/County Commission
FL Block Stonebridge rezoning of 1330 acres in Fort Meade
Community members rallied outside Fort Meade, Florida, City Hall to protest a proposed $2.6 billion, 1.2-gigawatt, 4.4-million-square-foot hyperscale data center on over 1,330 acres being…
2026-02-25 in force
City of Kings Mountain
city · City Council
NC Halt data centers in City of Kings after T5 Data Centers proposal
In City of Kings Mountain, North Carolina, Kings Mountain City Council voted 5-2 to approve a six-month moratorium on new data centers while the city studies impacts on water supplies,…
2026-02-26 in force
Spring Hill
city · City Council
KS Block rezoning of 316 acres in Spring Hill
Spring Hill, Kansas, City Council voted on October 23, 2025 to move forward with rezoning 316 acres from Rural Residential to M-1 Industrial for a potential data center, though no end user…
2026-03-25 in force
East Whiteland Township
township · City Council
PA Declare data center zoning invalid and pause new applications for 180 days to draft updated regulations
East Whiteland Township (Chester County) held an April 15, 2026 hearing on the developer's expanded 887,000 sq ft data center plan as the township advances its curative amendment process…
2026-02-26 in force
Brookings
city · City Council
SD Deny Sequitor Edge data center permit in Brookings
Brookings, South Dakota, City Council voted unanimously to reject a $644K sales-tax rebate for Sequitor Edge's proposed $41 million co-location data center. The denial came alongside…
2026-02-26 expired
Hall County
county · Board of Supervisors/County Commission
GA Impose 180-day data centers moratorium in Hall County
Hall County, Georgia, Commission voted 4-0 on February 26, 2026, to approve a 180-day moratorium on data centers, planned industrial development, and detention centers, prompted by…
2026-02-26 in force
Spartanburg County
county · Board of Supervisors/County Commission
SC 4000-signature petition opposing NorthMark Strategies data center
TigerDC formally withdrew its $3 billion 'Project Spero' AI data center from Tyger River Industrial Park after Spartanburg County Council unanimously voted down two Fee-In-Lieu-Of-Tax…
2026-02-27 expired
Weld County
county · Board of Supervisors/County Commission
CO Restrict Global AI 438-acre data center in Weld County
Weld County, Colorado, commissioners PASSED Code Ordinance 2026-01 on a 4-1 vote on April 6, 2026. The ordinance prohibits data centers on agricultural land and requires site plan or…
2026-04-06 in force
Leland
city · City Council
NC Block rezoning of 1385 acres in Leland
The Town of Leland initiated a preemptive text amendment to regulate data center facilities, requiring closed-loop cooling systems, a 60% renewable energy mandate, and restricting data…
2026-02-27 pending
Linn County
county · Board of Supervisors/County Commission
IA Impose 1000-foot data center setbacks in Linn County
Linn County Board of Supervisors unanimously approved one of the most comprehensive local data center zoning ordinances in the country on Feb. 18, 2026, in response to Google's proposed $7…
2026-03-01 in force
Charles County
county · Planning Commission
MD Restrict TeraWulf 250-acre data center in Charles County
The Charles County Planning Commission voted to recommend denial of Zoning Text Amendment #25-187, which would have established zoning regulations for data centers in the county (proposed…
2026-03-02 in force
Fulton County
county · Board of Supervisors/County Commission
IN Halt data centers in Fulton County after Decennial Group proposal
Fulton County, Indiana, Commissioners approved a one-year moratorium on data center construction on March 3, 2026, after a heated public hearing where residents voiced concerns about the…
2026-03-03 in force
Lyon Township
township · Township Board
MI Impose 180-day data centers moratorium in Lyon Township (Verrus)
Lyon Township, Michigan, (Oakland County) board voted unanimously to enact a 180-day moratorium on data centers and all proposed developments 100,000+ sq ft on March 3, 2026. The…
2026-03-03 in force
Anchorage
city · City Council
AK Restrict data centers to industrial zones in Anchorage
The Anchorage Assembly adopted Ordinance AO 2026-27 on March 27, 2026, establishing a new land use and permitting framework for data centers before receiving any large-scale applications.…
2026-03-27 in force
Blanchard
city · City Council
LA Halt data centers in Blanchard after Amazon/AWS proposal
Rural communities in North Caddo Parish organized a boycott of the official community meeting for Amazon/AWS's proposed $12 billion data center campus on 810 acres in Blanchard, Louisiana,…
2026-03-03 in force
Delta County
county · Planning Commission
MI Impose 12 month data centers and crypto mining moratorium in Delta County
Delta County, Michigan, Planning Commission considered a resolution to suspend data center and cryptocurrency mining projects for 12 months while a zoning ordinance is developed.…
2026-03-03 pending
Penn Forest Township
township · Township Board
PA Ban data centers in designated zones in Penn Forest Township
Penn Forest Township, Pennsylvania, supervisors approved a comprehensive data center ordinance at a well-attended meeting at Penn's Peak (proposed by Mele Brothers Realty). The ordinance…
2026-03-03 in force
Mercer County
county · Board of Supervisors/County Commission
ND Halt data centers in Mercer County after NextEra Energy Resources proposal
Mercer County Commission voted 3-2 for a one-year moratorium after NextEra subsidiary Boulevard Associates had been quietly acquiring land options on roughly 530 acres under NDA (proposed…
2026-03-03 in force
Calvert County
county · Board of Supervisors/County Commission
MD Impose 24-month data centers moratorium in Calvert County (Amazon)
Calvert County Board of Commissioners voted 2-3 against a proposed 24-month moratorium on data center permits. Commissioner Hart had proposed the moratorium after Amazon AWS began…
2026-03-03 expired
Urbana
city · City Council
OH Impose 12-month data centers moratorium in Urbana (Thor Equities)
Urbana City Council voted 6-1 to approve a 12-month moratorium on data centers over 10,000 sq ft, halting a proposed 460,000 sq ft Thor Equities facility off Routes 55 and 68 (400 MW, 133…
2026-06-17 in force
Palo
city · City Council
IA Block Google from annexing into Palo to evade Linn County's strict data center ordinance
Google abandoned unincorporated Linn County and is pursuing annexation into the City of Palo, Iowa (pop. 1,407) to avoid the county's strict data center zoning. Palo held a town hall on…
2026-06-15 in force
Champaign County
county · Board of Supervisors/County Commission
IL Propose data centers moratorium in Champaign County
On April 23, 2026, the Champaign County Board passed a 12-month moratorium on new large-scale data centers (≥10,000 sq ft of processing area) in unincorporated areas, reversing the…
2026-04-23 in force
Pittsylvania County
county · Board of Supervisors/County Commission
VA Deny 2,200-acre, 84-building data center campus with 3,500MW gas plant in Pittsylvania County
The Pittsylvania County Board of Supervisors voted to deny a massive 2,200-acre datacenter campus proposal that would have included 84 datacenter buildings and a 3,500MW natural gas power…
2025-04-01 expired
Louisa County
county · Board of Supervisors/County Commission
VA Require use permit for Amazon data center in Louisa County
Amazon Web Services withdrew a conditional use permit application for a 7.2 million-square-foot data center campus on 1,370 acres in Louisa County's Mineral area (south of Davis…
2025-07-25 expired
Spotsylvania County
county · Board of Supervisors/County Commission
VA Require conditional use permits in Spotsylvania County
Spotsylvania County has approved data centers and is trying to implement regulations (873 acres). In December 2025, the board voted 4-3 to approve design standards requiring special-use…
2025-11-01 in force
Fauquier County
county · Board of Supervisors/County Commission
VA Deny Gigaland 600MW data center permit in Fauquier County
GigaLand withdrew its original datacenter application in Fauquier County, Virginia, after significant community opposition, but resubmitted a scaled-down proposal in early 2026, reduced by…
2026-07-16 pending
Fauquier County
county · Board of Supervisors/County Commission
VA Deny Headwaters Site Development data center on 67 acres in Fauquier County
Headwaters Site Development LLC withdrew its rezoning application for a $400M, four-building data center on 67 acres at Catlett Road and Gaskins Lane in Fauquier County on July 15, three…
2024-07-15 expired
Frederick County
county · Board of Supervisors/County Commission
VA Deny Winchester Gateway data center on 749 acres in Frederick County
In June 2025, the Frederick County Board of Supervisors voted by consensus against moving forward with applications for two large data centers: the proposed 644-acre Meadow Brook…
2025-06-25 expired
Mecklenburg County
county · Board of Supervisors/County Commission
VA Pause data centers in Mecklenburg County pending regulations
Mecklenburg County Board of Supervisors voted in March 2025 to end by-right zoning for data centers, requiring all data center applications to undergo staff-level review, a public hearing,…
2025-03-01 in force
Orange County
county · Board of Supervisors/County Commission
VA Adopt data center setback and noise-limit standards in Orange County
Orange County adopted new zoning regulations restricting data center development after community opposition. The county initially proposed a 'floating zone' approach that would allow…
2025-09-01 in force
Fluvanna County
county · Board of Supervisors/County Commission
VA Pause data centers in Fluvanna County pending regulations
Fluvanna County, Virginia, enacted a moratorium on data center development while studying zoning changes to address proposals spreading from Louisa and Albemarle counties. The Planning…
2025-11-19 in force
Sprigg Township
township · Township Board
OH Halt data centers in Sprigg Township after 68 Yards proposal
Sprigg Township, Ohio, trustees in Adams County passed a one-year voluntary moratorium on data centers on March 2, 2026, targeting a proposed facility at the former Stuart power plant site…
2026-03-02 in force
Scioto Township
township · Township Board
OH Impose 12-month moratorium on data centers in Scioto Township while overhauling zoning code
Scioto Township trustees in Pickaway County enacted a 12-month moratorium on data center applications in March 2026, joining at least 15 Ohio communities resisting AI industry expansion.…
2026-03-06 in force
Cincinnati
city · City Council
OH Create data center overlay zone in Cincinnati
Cincinnati, Ohio, City Council enacted an interim development control overlay after discovering data centers are currently interpreted as 'self storage' under existing zoning code, meaning…
2026-02-06 in force
Dexter Township
township · Township Board
MI Impose 180-day data centers moratorium in Dexter Township
Dexter Township adopted a 180-day moratorium on data center applications via Resolution #26-705, joining at least 19 Michigan communities that have paused data center development.…
2026-02-01 in force
Zeeland Township
township · Planning Commission
MI Pause data centers in Zeeland Township pending regulations
Zeeland Township's planning commission approved a one-year moratorium on data center applications in early 2026 while developing regulations for large-scale energy projects. The moratorium…
2026-01-01 in force
Lansing
city · City Council
MI Block Deep Green rezoning of 2.7 acres in Lansing
Deep Green withdrew its $120M downtown Lansing data center application on April 6, 2026, hours before the City Council was scheduled to vote on selling and rezoning the land. CEO Mark Lee…
2026-04-06 expired
Lancaster City
city · City Council
PA Require special exception permits for CoreWeave data center conversion of former R.R. Donnelly plants in Lancaster City
CoreWeave announced a $6 billion commitment to build an AI data center in Lancaster, converting former R.R. Donnelley/LSC Communications printing plants into a state-of-the-art facility…
2025-10-06 in force
Hazle Township
township · Township Board
PA Deny NorthPoint Development data center on 1280 acres in Hazle Township
Hazle Township, Pennsylvania, Board of Supervisors unanimously rejected NorthPoint Development's 1,280-acre, 15-building 'Project Hazelnut' data center campus in Luzerne County after more…
2025-11-18 expired
New Castle Township
township · Township Board
PA Restrict KRNL Data Centers data center via zoning in New Castle Township
KRNL Data Centers, a New York City-based developer, proposed a five-building campus on ~100 acres of conservation-zoned forest in New Castle Township, Schuylkill County. 'Save Frackville'…
2025-09-10 in force
Dorrance Township
township · Township Board
PA Halt data centers in Dorrance Township after Brewster Land Company proposal
Dorrance Township adopted a zoning ordinance amendment on September 22, 2025, allowing data centers only in industrial zones. Brewster Land Company LLC owns a 155-acre parcel zoned B-2…
2025-08-11 in force
Luzerne County
county · Board of Supervisors/County Commission
PA Impose 500-foot data center setbacks in Luzerne County
Luzerne County, Pennsylvania, proposed a zoning amendment covering 20 municipalities that rely on county zoning. Defines three data center tiers, Hyperscale (100,000+ sq ft, up to 200 MW),…
2026-02-02 pending
East Manchester Township
township · Township Board
PA Pause data center zoning after public opposition in East Manchester
East Manchester Township approved two ordinances: one regulating siting, design, construction, and operation of data centers; another establishing a data center overlay district near…
2025-10-14 in force
East Windsor
city · City Council
NJ Deny data center permit in East Windsor
East Windsor, New Jersey, Council voted down a redevelopment plan after a standing-room-only meeting where residents from the Twin Rivers community raised questions about a data center…
2025-11-25 expired
Lubbock
city · Planning Commission
TX Deny Texas Solar Works data center on 936 acres in Lubbock
Planning and Zoning Commission voted 4-3 to reject a 936-acre hyperscale AI data center zoning change from Low Density Single Family to General Industrial, requested by Hugo Reed and…
2026-01-08 expired
Cascade Township
township · Township Board
MI Impose 6-month data centers moratorium in Cascade Township
Cascade Township Board voted unanimously on February 26, 2026 for a 6-month moratorium on data center permits, with an option for a 6-month extension. The action was preemptive, no data…
2026-02-26 in force
Gaines Charter Township
township · Planning Commission
MI Block Microsoft rezoning of 356 acres in Gaines Charter
In Gaines Charter Township, Michigan, Microsoft seeking to rezone 316 acres (purchased from Steelcase for $45.3M) for data center. Dec 2025 hearing canceled when 250+ overflowed venue.…
2026-03-03 expired
Newton County
county · Board of Supervisors/County Commission
GA Impose 30-day data centers moratorium in Newton County
In Newton County, Georgia, Board of Commissioners unanimously enacted 30-day moratorium on data center applications. Existing ordinance limits DCs to Stanton Springs overlay, but…
2026-01-20 in force
City of Industry
city · City Council
CA Oppose City of Industry zoning amendments enabling data center conversion of Puente Hills Mall
City of Industry's Planning Commission voted in December 2025 to recommend zoning changes allowing data centers citywide (proposed by EdgeCore) (62 acres). City Manager Joshua Nelson wrote…
2025-01-15 in force
City of Oakley
city · City Council
CA Rally against data center in City of Oakley
In City of Oakley, California, Oakley City Council approved the 164-acre Bridgehead Industrial Project on March 11, 2026 in a 4-1 vote, but with an amendment excluding data centers after…
2026-03-11 expired
City of El Monte
city · City Council
CA Impose 45-day data centers moratorium in City of El Monte
In City of El Monte, California, On March 12, 2026, the City Council postponed action on data center moratorium evaluation after a verbal altercation during public comment led police to…
2026-03-19 in force
Harlingen
city · City Council
TX Restrict Eneus Energy 1785-acre data center in Harlingen
Harlingen city commissioners on April 1, 2026 called for public hearings and signaled plans to impose a 120-day moratorium on data centers to study impact on residents, resources and…
2026-02-26 in force
New Castle County
county · Board of Supervisors/County Commission
DE Adopt comprehensive data center regulations with 1,000-foot residential buffers and open-loop cooling ban in New Castle County
New Castle County Council passed 12-0 (with one absent) first-of-their-kind data center regulations after 7 months of debate. Requires 1,000-foot buffer from residential zones (reducible…
2026-03-11 in force
Town of Apex
city · City Council
NC Propose data centers moratorium in Town of Apex
The Apex Town Council voted unanimously on April 14, 2026 to adopt a one-year moratorium on data center development, following the March 5 withdrawal of Natelli Investments' New Hill…
2026-03-10 in force
Moore County
county · Board of Supervisors/County Commission
TN Pause data centers in Moore County pending regulations
The Moore County, Tennessee, Metro Council is considering a two-year moratorium on data center construction and expansion, which would take effect April 20, 2026. During the moratorium,…
2026-03-01 pending
Caddo Parish
county · Board of Supervisors/County Commission
LA Propose data centers moratorium in Caddo Parish
Following Governor Jeff Landry's announcement of Amazon's $12 billion investment in three interconnected data center campuses across Caddo, Louisiana, and Bossier parishes, Commissioner…
2026-02-02 expired
Warrenton
city · City Council
MO Approve conditional use permit for Crusoe 340-acre data center in Warrenton with conditions
The Warrenton, Missouri, Board of Aldermen voted unanimously in January 2026 to approve a conditional use permit for a Crusoe data center on a 340-acre parcel, consisting of two…
2026-01-20 in force
Troy
city · City Council
IL Halt data centers in Troy after Cloverleaf Infrastructure proposal
The Troy, Illinois, Planning Commission approved a six-month moratorium on data processing centers in March 2026, following the collapse of Cloverleaf Infrastructure's proposal for a…
2026-03-12 in force
Ashville
city · Village Board
OH Impose 180-day data centers moratorium in Ashville (EdgeConneX)
Ashville, Ohio, Village Council unanimously passed a 180-day emergency moratorium on December 20, 2025, in response to EdgeConneX's proposal on 680 acres including an on-site 200-megawatt…
2025-12-20 in force
Tulsa
city · City Council
OK Propose data centers moratorium in Tulsa
Tulsa City Council unanimously passed a NINE-month data center moratorium (through December 31, 2026) on March 26, 2026. Originally proposed by Councilor Laura Bellis as a 365-day…
2026-03-26 in force
Shreveport
city · City Council
LA Deny Franks Investment Company conditional use permit in Shreveport
Shreveport, Louisiana, Metropolitan Planning Commission denied a special use permit for a 2.8 million sq ft Franks Investment Company LLC data center at 7340 Greenwood Road (Resilient…
2025-12-03 in force
Henrico County
county · Board of Supervisors/County Commission
VA Uphold denial of Centra Logistics data center on appeal
In Virginia, Henrico County's Board of Zoning Appeals unanimously denied Centra Logistics' vested rights claim for a data center complex on nearly 200 acres along Darbytown Road in the…
2026-02-27 expired
Chesterfield County
county · Board of Supervisors/County Commission
VA Require use permit for WestDulles Properties data center in Chesterfield County
Reston-based developer WestDulles Properties filed an appeal in March 2026 of Chesterfield County staff's determination that a Conditional Use Permit (CUP) is required before its 170-acre…
2026-01-01 in force
Powhatan County
county · Board of Supervisors/County Commission
VA Block Province Group rezoning of 181 acres in Powhatan County
Powhatan County, Virginia, Board of Supervisors voted 5-0 on Oct. 29, 2025 to approve rezoning of approximately 61 additional acres to expand the planned Province Group data center campus…
2025-10-29 in force
DeKalb County
county · Board of Supervisors/County Commission
TN Ban data centers in designated zones in DeKalb County
DeKalb County, Tennessee, Commission is considering data center regulations proposed by County Mayor Matt Adcock after receiving an inquiry about locating a nuclear-powered data center in…
2026-03-01 pending
Maricopa County
county · Board of Supervisors/County Commission
AZ Block data center rezoning in Maricopa County
The Maricopa County, Arizona, Board of Supervisors unanimously approved a modernized zoning ordinance establishing specific rules for data center development, effective January 9, 2026.…
2025-12-10 in force
Millard County
county · Board of Supervisors/County Commission
UT Rezone 4,400+ acres from agricultural for Creekstone Energy solar farm powering AI data centers
Millard County, Utah, Commission approved rezoning of 4,400+ acres from agricultural to forest/range for Creekstone Energy solar farm to power AI data centers, despite resident opposition.…
2026-04-22 in force
Falls Township
township · Township Board
PA Oppose Amazon data center in Falls Township
Amazon is building a 1-million-square-foot data center on 1,800 acres at the Keystone Trade Center in Falls Township, Bucks County, fast-tracked through Governor Shapiro's PA Permit Fast…
2026-02-20 in force
Bryan
city · City Council
TX Adopt data center zoning standards in Bryan
Bryan, Texas, City Council proactively annexed 162 acres near the RELLIS campus and adopted a Planned Development zoning district allowing data centers with stricter-than-normal standards…
2025-09-16 in force
Newark
county · Board of Supervisors/County Commission
DE Block 847,000 sq ft data center replacing White Clay Corporate Center in Newark
Verdantas/Shelbourne proposed an 847,000 sq ft data center complex on a 44-acre site at the White Clay Center Industrial Park off Ogletown Road in Newark, DE. The proposal would demolish…
2026-01-30 in force
Grant County
county · Board of Supervisors/County Commission
IN Impose 24-month data centers moratorium in Grant County
Grant County Commissioners passed a 24-month moratorium on data centers on March 2, 2026. The Area Plan Commission began drafting ordinance language focusing on transparency, resource…
2026-03-02 in force
Lake County
county · Board of Supervisors/County Commission
IN Impose 55 dB noise limit on data centers in Lake County
Lake County, Indiana, Council approved stringent data center regulations: only permitted in industrial zones with special approval, 200-ft setbacks from residential/agricultural, 55dB…
2026-02-18 in force
Thomas County
county · Board of Supervisors/County Commission
GA Impose 12-month data centers moratorium in Thomas County
Thomas County, Georgia, Board of Commissioners unanimously approved a 12-month moratorium on AI data center construction in January 2026. Commission Chair Mark NeSmith said the board was…
2026-01-20 in force
Irwin County
county · Planning Commission
GA Petition to block Google data center in Irwin County
Google proposed a 1GW data center on 546 acres near Irwinville in an agricultural zone. The Irwin County, Georgia, Planning Commission voted to recommend approval on Feb 26, 2026. However,…
2026-03-02 expired
Nobles County
county · Board of Supervisors/County Commission
MN Reject data centers in agricultural preservation district and pursue environmental review in Nobles County
Nobles County (MN) Board of Commissioners voted 3-2 on April 21, 2026 to deny a zoning change that would have allowed Geronimo Power's proposed $4 billion, ~640-acre data center campus on…
2026-04-21 expired
Culpeper County
county · Board of Supervisors/County Commission
VA Require conditional use permits in Culpeper County
Culpeper County, Virginia, unanimously required conditional use permits for data centers on industrial land in September 2025, impacting 3,000+ acres across 140+ parcels that previously…
2025-09-02 in force
Reno
city · City Council
NV Deny Oppidan 5MW data center permit in Reno
Oppidan proposed a 5MW data center on a 7-acre site in the Stead area of Reno, Nevada,. The Sierra Club Toiyabe Chapter raised environmental, grid, and water concerns. Despite opposition,…
2025-03-12 in force
Lowell
city · City Council
MA Impose 360-day moratorium on Markley Group data center expansion
Lowell City Council voted 10-0 on March 10, 2026 to enact a one-year moratorium on data center development, the first such municipal moratorium in Massachusetts. Championed by community…
2026-03-11 in force
Gibraltar
city · City Council
MI Halt data centers in Gibraltar after Raeden proposal
Gibraltar, Michigan, City Council unanimously approved a year-long moratorium in March 2026, freezing a proposed 100 MW data center at the former McLouth Steel site (27800 W. Jefferson…
2026-03-09 in force
Essex
city · City Council
IL Block Constellation Energy rezoning of 600 acres in Essex
Constellation Energy purchased over 600 acres near Essex, Illinois, and is seeking rezoning and annexation. Much of the land was sold by village board members or their relatives. The Essex…
2025-11-01 in force
Kosciusko County
county · Board of Supervisors/County Commission
IN Deny Prologis rezoning of 554 acres of farmland
Kosciusko County, Indiana, Area Plan Commission unanimously denied (8-0) Prologis's rezoning request for 554 acres of farmland near Leesburg from agricultural to industrial for a…
2025-04-22 expired
Washington Township
township · Township Board
OH Impose 90-day data centers moratorium in Washington Township
Washington Township in northwestern Franklin County passed a 90-day moratorium on data centers in unincorporated parts of the township on December 8, 2025. The township also asked the city…
2025-12-08 in force
St. Albans Township
township · Township Board
OH Ban data centers in designated zones in St. Albans Township
St. Albans Township, Ohio, held a public hearing on March 10, 2026 on a proposal to become the first township in Licking County to ban data centers. The township sits on the eastern edge…
2026-03-10 in force
Two Creeks
township · Township Board
WI Impose 6 month data centers moratorium in Two Creeks
Two Creeks, along with Two Rivers and Mishicot, held a joint town board meeting and approved identical resolutions calling on Manitowoc County to adopt a one-year moratorium on data center…
2026-02-01 in force
Two Rivers
township · Township Board
WI Impose one-year moratorium on data center permits in Two Rivers, Two Creeks, and Mishicot
Two Rivers, Wisconsin, joined Two Creeks and Mishicot at a joint town board meeting on February 12, 2026 in approving identical resolutions calling for a one-year moratorium on data center…
2026-02-01 in force
Mishicot
township · Township Board
WI Impose 6-month data centers moratorium in Mishicot
Mishicot, Wisconsin, joined Two Creeks and Two Rivers at a joint town board meeting after several hundred people packed the Grey Fox Bar and Grill on January 26, 2026 for an informational…
2026-02-01 in force
Forsyth County
county · Board of Supervisors/County Commission
GA Restrict data center water usage in Forsyth County
Forsyth County, Georgia, enacted a strict data center ordinance that prohibits data center cooling systems from using the county water system, one of the most restrictive approaches among…
2025-10-01 in force
Covington
city · City Council
GA Impose 180-day data centers moratorium in Covington
The City of Covington, Georgia, council imposed a 180-day moratorium on new data center requests on January 5, 2026 (by 3Rivers Development). During the moratorium, city staff will review…
2026-01-05 in force
Newton County
county · Board of Supervisors/County Commission
GA Pause data centers in Newton County pending regulations
Newton County Board of Commissioners unanimously enacted an emergency moratorium on data center applications in February 2026, joining a wave of Georgia moratoriums. Previously, SC…
2025-11-01 in force
Ottawa
city · City Council
IL Impose 180-day data centers moratorium in Ottawa
Ottawa City Council established a 180-day moratorium on data centers across all zoning districts, the first such moratorium in the Illinois Valley. Mayor Robert Hasty cited the need for…
2026-03-03 in force
Forney
city · City Council
TX Require conditional use permits in Forney
The City of Forney, Texas, is considering new zoning rules that would formally regulate data center development within city limits. A public hearing is scheduled for March 17, 2026 on a…
2026-03-17 pending
Brazoria County
county · Board of Supervisors/County Commission
TX Deny Nightpeak Energy data center on 158 acres in Brazoria County
Brazoria County, Texas, commissioners unanimously rejected a package of tax abatements sought by Nightpeak Energy for its proposed $3.5 billion Old Ocean Data Center campus outside Sweeny,…
2026-03-13 expired
Fredericksburg
city · Planning Commission
VA Deny Penzance Development 600MW data center permit in Fredericksburg
Penzance Development / 1500 Gateway LLC proposed a 600 MW data center on 84 acres in Fredericksburg, Virginia. Residents of the Great Oaks Lane neighborhood objected to the project, citing…
2025-12-11 expired
City of Provo
city · City Council
UT Deny B+F Timpanogos Tech rezoning of 9 acres in City of Provo
The Provo City, Utah, Council voted unanimously (7-0) on March 11, 2026 to deny a zoning change for a proposed AI data center at 1507 S. 180 East in the East Bay area. Developer B+F…
2026-03-11 expired
Fayetteville
city · City Council
NC Ban data centers in all zones in Fayetteville
Fayetteville, North Carolina, City Council voted in early March 2026 to remove data centers as a permitted use from ALL zoning categories within city limits. A pending application by CHI…
2026-03-05 pending
Washington Township
township · Planning Commission
MI Block Prologis rezoning of 312 acres in Washington Township
Prologis is seeking to rezone 312 acres on 32 Mile Road for a Microsoft data center. The Planning Commission has postponed the rezoning decision four times (Jan -> Feb -> April -> June 11)…
2026-03-11 in force
Olyphant Borough
borough · City Council
PA Adopt data center zoning standards in Olyphant Borough
Olyphant Borough Council on April 14, 2026 rejected a proposed data center zoning amendment after residents argued the regulations were too lax (covering setbacks, noise, water usage,…
2026-04-14 pending
Londonderry Township
township · Township Board
PA Create data center overlay zone in Londonderry Township
Londonderry Township, Pennsylvania, tabled a zoning ordinance that would create a data center overlay district after overwhelming resident opposition at a packed public hearing. Proposed…
2026-02-11 in force
City of Scranton
city · City Council
PA Adopt data center zoning standards in City of Scranton
Scranton City, Pennsylvania, Council introducing an amendment to the 2023 zoning ordinance to regulate data centers, following advice from Lackawanna County planners that municipalities…
2026-03-17 pending
Wilmington
city · City Council
OH Block Ardent Technologies rezoning of 545 acres in Wilmington
Wilmington, Ohio, City Council voted 5-2 on Feb 20 to rezone 545 acres from rural residential to light industrial for a second data center campus by Ardent Technologies (affiliated with…
2026-02-20 in force
Minooka
city · Village Board
IL Restrict Equinix 340-acre data center in Minooka
Equinix was approved for a $2B, 368-acre, 700MW campus in Minooka, Illinois, about 50 miles southwest of Chicago, requiring 3 million gallons of water per day from a $1.54 billion Lake…
2025-10-01 in force
Logan County
county · Board of Supervisors/County Commission
IL Block Hut 8 rezoning of 200 acres in Logan County
The Logan County (IL) Board voted 9-2 in February 2026 to approve a 60-day moratorium on accepting data center applications, prompted by Hut 8 Corp's proposal for a $5B, 500 MW data center…
2025-12-01 in force
Lee County
county · Board of Supervisors/County Commission
NC Rally against Deep River Data data center in Lee County
Lee County commissioners voted 6-1 on March 16, 2026 to begin drafting a moratorium on data centers and cryptomining, following a packed public meeting. On April 20, 2026, after a roughly…
2026-03-16 in force
Blakely
county · Board of Supervisors/County Commission
GA Oppose QTS Technology Services data center over water in Blakely
QTS filed a Developments of Regional Impact application for a 12 million sq ft QTS Technology Services data center campus on the outskirts of Blakely, Georgia, the 'Peanut Capital of the…
2026-03-01 in force
New Kent County
county · Board of Supervisors/County Commission
VA Create data center overlay zone in New Kent County
Following Goochland's lead, New Kent County, Virginia, is proposing a 1,800-acre Technology Overlay District along the Route 33 corridor. Controversial fast-track process would skip…
2026-02-17 pending
Franklin County
county · Board of Supervisors/County Commission
MO Block rezoning of 800 acres in Franklin County
Franklin County, Missouri, Planning & Zoning Commission is considering county-wide data center regulations including 1,000-ft setbacks from residential areas. The commission will hold its…
2026-03-17 pending
Meade County
county · Board of Supervisors/County Commission
KY Halt data centers in Meade County after PowerHouse Industries proposal
Meade County, Kentucky, Fiscal Court adopted Ordinance 2025-07 on January 13, 2026, establishing a moratorium on data center development while the county reviews its zoning ordinance and…
2026-01-13 in force
Monterey Park
city · City Council
CA Ban data centers in all zones in Monterey Park
Monterey Park, California, City Council voted unanimously to place a permanent data center ban on the June 2, 2026 ballot (by HMC Capital / HMC StratCap). If approved by voters, it would…
2026-03-04 pending
Warren County
county · Board of Supervisors/County Commission
NJ Distribute model data center ordinance in Warren County
Warren County Commissioner James R. Kern III, a member of the county Planning Board, distributed an advisory model data center siting ordinance to mayors and governing bodies across all…
2026-01-15 in force
Logan County
county · Board of Supervisors/County Commission
CO Restrict Granite Renewables 4198-acre data center in Logan County
Logan County, Colorado, adopted new data center regulations on February 18, 2026, lifting its moratorium and allowing Granite Renewables' proposed $15B, 2GW project on 4,198 acres to…
2026-02-18 in force
Lyon County
county · Board of Supervisors/County Commission
NV Block Monarch Data Center rezoning of 505 acres in Lyon County
Copia Power's Monarch Data Center, backed by Carlyle Group, won approval for an $11B, 1,000 MW campus on 505 acres rezoned from agriculture in Mason Valley. The 14-building, 4.6M sq ft…
2025-12-07 in force
East Lansing
city · City Council
MI Impose 6-month data centers moratorium in East Lansing
East Lansing City Council enacted a 6-month moratorium on data center development in March 2026, pausing new applications while the city studies potential impacts on the community. The…
2026-03-17 in force
Detroit
city · City Council
MI Pause data centers in Detroit pending regulations
Detroit, Michigan, City Council voted 6-2 on March 18, 2026 for a resolution asking Mayor Mary Sheffield to halt all data center permits for two years while the city studies environmental…
2026-03-10 in force
Monroe County
county · Board of Supervisors/County Commission
WV Resist data center siting in Monroe County after state law preempted local authority
Monroe County residents organized opposition to potential data center development (by Undisclosed developer (state-facilitated)). The Monroe County Commission denied ongoing data center…
2026-02-01 in force
Clinton County
county · Board of Supervisors/County Commission
IN Petition to block Logistix Realty data center in Clinton County
Logistix Realty proposed a data center near Frankfort, first petitioning to rezone land within city limits (withdrawn July 2025), then filing a new request in December 2025 to rezone 715…
2025-12-01 expired
Elkhart County
county · City Council
IN Oppose Pinnacle Properties data center over water in Elkhart County
Pinnacle Properties, representing landowner Christine Truee Wilhelm, sought to rezone 247 acres of farmland on County Road 23 in Bristol, Indiana, for a data center campus of 800,000 to…
2024-09-01 in force
Cass County
county · Board of Supervisors/County Commission
MI Petition to block Hyperscale Data data center in Cass County
Hyperscale Data (parent of Alliance Cloud Services) operates a 30 MW data center in Dowagiac and plans expansion to 70 MW by 2027 and 340 MW by 2029, enough energy to power 100,000+ homes.…
2025-12-01 in force
Kalkaska County
county · Board of Supervisors/County Commission
MI Community pressure forces Rocklocker to withdraw in Kalkaska County
Rocklocker LLC (headed by Traverse City geologist Matt Rine) proposed a gigawatt-scale hyperscale data center on 1,440 acres of state-owned land near Island Lake and South River roads,…
2025-11-01 expired
Crawford County
county · Board of Supervisors/County Commission
GA Impose 6-month data centers moratorium in Crawford County
Crawford County, Georgia, Board of Commissioners passed a 6-month (180-day) moratorium on data center permits on January 6, 2026, by a unanimous 5-0 vote, on the recommendation of Planning…
2026-01-06 in force
Town of Boone
city · City Council
NC Pause data centers and crypto mining in Town of Boone pending regulations
Boone Town, North Carolina, Council voted 5-0 to approve a one-year moratorium on data center and cryptocurrency mining development on March 23, 2026, cheered by a capacity crowd at town…
2026-03-23 in force
Washington County
county · Board of Supervisors/County Commission
TN Impose moratorium on data centers and crypto mining in Washington County through June 2027
Washington County, Tennessee, Commission voted 13-2 on March 23, 2026 to enact a moratorium on data center construction, operation, and permitting, including cryptocurrency mines, through…
2026-03-23 in force
Baltimore City
city · City Council
MD Impose one-year moratorium on 10MW+ data centers as prohibited zoning use in Baltimore City
Baltimore City Council President Zeke Cohen introduced a one-year moratorium on data centers with 10MW+ electrical demand on March 23, 2026. The legislation would classify such facilities…
2026-03-23 pending
Monroe Township
township · Township Board
OH Impose 12-month moratorium on data centers and small modular nuclear reactors in Monroe Township
Monroe Township, Ohio, trustees unanimously passed a 12-month moratorium on new proposals and development of data centers and small modular nuclear reactors. Monroe Township is the second…
2026-03-09 in force
Chesterfield County
county · Board of Supervisors/County Commission
VA Require conditional use permit for WestDulles' 430-acre data center in Chesterfield County
WestDulles is appealing a determination that its proposed 430-acre data center complex near Chester requires a Conditional Use Permit under Chesterfield County's new zoning ordinance that…
2026-03-09 in force
Watauga County
county · Board of Supervisors/County Commission
NC County-wide moratorium on data centers in Watauga County pending regulations
Watauga County, North Carolina, Commissioners unanimously voted on March 24, 2026 to schedule a public hearing on April 21 for a potential county-wide data center moratorium. This follows…
2026-03-24 pending
Archbald Borough
borough · City Council
PA Deny conditional use permit for 18-building data center campus in Archbald
Council voted down Provident Realty Advisors' application to build a giant data center after months of growing outcry. About 200 residents showed up wearing yellow shirts. Archbald (pop.…
2026-03-27 expired
Apple Valley
city · Planning Commission
MN Deny data center zoning and permits that conflict with Apple Valley 2040 Comprehensive Plan
Apple Valley, Minnesota, Planning Commission recommended denial on March 18, 2026 of three key components of the Apple Valley Technology Park data center project: the Preliminary Plat,…
2026-03-18 expired
City of Fayetteville
city · Planning Commission
GA Block data center construction on Highway 85 in Fayetteville
Crow Holdings Development and CHI Acquisitions LP officially withdrew their appeal on March 18, 2026 to build a 300,000 sq ft data center on 37.4 acres on Highway 85 North near Fayette…
2026-03-18 expired
City of Liberty
city · City Council
MO Scrutinize $202M in data center tax abatements approved in Liberty without public referendum
Liberty City, Missouri, Council approved $1.4 billion in bonds and $202.7 million in tax abatements over 25 years for Metrobloks, an LA-based developer, to build three buildings totaling…
2026-03-24 in force
Pemberton Township
township · Township Board
NJ Ban data center construction and operation throughout Pemberton Township
Pemberton Township became the first municipality in New Jersey to outright ban data centers when it passed Ordinance 10-2026 on February 20, 2026, prohibiting the construction and…
2026-02-20 in force
Lawton
city · City Council
OK Restrict data center development to 2MW by-right limit with council review for larger facilities
Lawton City Council voted 5-3 on February 24, 2026 to approve a zoning ordinance amendment setting one of the most restrictive data center limits in the country: data centers with peak…
2026-02-24 in force
Habersham County
county · City Council
GA Oppose Big Red Apple data center development in Cornelia
The Big Red Apple Innovation Corridor, a proposed $300 million, 284-acre mixed-use development by Cook Communities at 1900 Level Grove Road in Cornelia, Habersham County, included a data…
2025-12-01 expired
Fort Worth
city · City Council
TX Delay and add conditions to Edged Data Centers tax abatement at Veale Ranch
Fort Worth City Council unanimously voted on March 31, 2026 to delay a decision on a 10-year, 50% tax abatement worth ~$18.2 million for Edged Data Centers' proposed $1.1 billion data…
2026-03-31 pending
Saline County
county · Board of Supervisors/County Commission
KS Three-year pause on data centers, nuclear, and hydrogen facilities in unincorporated Saline County
Saline County Board of Commissioners voted 4-0 on March 18, 2026 to enact a three-year moratorium on data centers, nuclear power generation facilities, and hydrogen-based energy plants in…
2026-03-18 in force
Plain Township
township · Township Board
OH 12-month pause on data center construction in Plain Township to study impacts
Plain Township trustees in Stark County, Ohio enacted a 12-month moratorium on data center construction on March 27, 2026, to assess potential impacts on health, safety, utilities, and…
2026-03-27 in force
Huron County
county · Board of Supervisors/County Commission
MI Expand data center moratorium from 6 months to 3 years to develop county regulations
Huron County, Michigan, Planning Commission voted unanimously on April 1, 2026 to expand its data center moratorium from six months to three years, following a public hearing where…
2026-04-01 pending
Manitowoc County
county · Board of Supervisors/County Commission
WI County-wide one-year moratorium on data center permits in Manitowoc County
Manitowoc County Planning and Parks Commission unanimously approved a 1-year moratorium on data center permits on March 31, 2026, following petitions from Three Towns (Two Creeks, Two…
2026-03-31 pending
Massillon
city · City Council
OH Develop data center zoning recommendations for Massillon before proposals arrive
Massillon, Ohio, City Council hired an outside attorney on March 31, 2026 to develop data center zoning recommendations as interest from data center developers grows across Stark County.…
2026-03-31 pending
Hanover Township
township · City Council
PA Regulate data center location, noise, water, and power demand in Hanover Township
Township passed data center ordinance regulating location, noise, water usage, power demand, and emergency management. Most likely site is Starpointe Industrial Park. Community members…
2026-03-31 in force
Montgomery Township
township · City Council
PA Declare zoning ordinance invalid to proactively adopt data center regulations before developers seek court approval
Supervisors declared township zoning ordinance 'substantively invalid' for lacking data center provisions, triggering the curative amendment process under PA Municipalities Planning Code.…
2026-03-23 in force
Jenkins Township
township · City Council
PA Create 550-acre Data Center Overlay District limited to CenterPoint industrial zone with conditional use requirement
Jenkins Township, Luzerne County, Pennsylvania, held a public hearing on March 31, 2026 for a proposed zoning amendment creating a 550-acre Data Center Overlay District limited to the…
2026-03-31 pending
Phillipsburg
city · City Council
NJ Ban data centers from all zoning districts in Phillipsburg
Phillipsburg, NJ Town Council UNANIMOUSLY adopted Ordinance 2026-08 on April 14, 2026, banning data centers in all zoning districts townwide. Residents cited concerns about a potential…
2026-03-26 in force
Yorkville
city · City Council
IL Block third data center rezoning near Caledonia residential subdivision in Yorkville
Yorkville Nexus V LLC / Green Door Capital WITHDREW the 91-acre Meyer Property data center rezoning application on April 14-15, 2026, following the city council's April 1 tabling and…
2026-04-01 expired
City of Carver
city · City Council
MN Preemptive moratorium on data center development in Carver, MN
Carver City Council unanimously approved a 1-year moratorium on data center development on April 6, 2026. This is a preemptive action, no specific data center project was pending, to allow…
2026-04-06 in force
Sault Ste. Marie Tribe of Chippewa Indians
county · Tribal Government
MI Indefinite moratorium on AI data centers on Sault Tribe lands
The Sault Tribe Board of Directors voted unanimously on April 7, 2026 to approve an indefinite moratorium on AI data center development on tribal lands, citing concerns about resource…
2026-04-07 in force
Brentwood
city · City Council
MO Classify data centers as conditional use requiring public hearings and monitoring
Brentwood, Missouri Board of Aldermen held the first reading on April 6, 2026 of a bill to classify data centers as conditional use in the light industrial district, requiring public…
2026-04-06 pending
Northfield
city · City Council
MN Strict data center environmental efficiency standards as regulatory model
Northfield, Minnesota, highlighted as a potential model for data center regulation with the strictest environmental efficiency standards in the state, covering noise, lighting, building…
2026-04-08 in force
Pike County
county · Board of Supervisors/County Commission
OH Scrutinize what could be the country's largest data center in an economically distressed region
On April 21, 2026, AEP Ohio announced plans to build approximately 50 miles of 765-kV high-voltage transmission line across Pike, Jackson, and Gallia counties in southern Ohio to power a…
2026-04-21 pending
Hutto
city · City Council
TX Oppose rezoning of 40 acres from apartments to data center
On April 17, 2026, Zydeco Development withdrew its rezoning application for a proposed 950,000-square-foot data center at the southeast corner of County Road 119 and Limmer Loop in Hutto,…
2026-04-17 expired
Cochise County
county · Board of Supervisors/County Commission
AZ Adopt data center regulations requiring special use authorization and water/noise impact plans
Cochise County Board of Supervisors voted 3-0 on April 7, 2026 to adopt new data center regulations requiring special use authorization, noise impact analyses, water use plans, proof that…
2026-04-07 in force
York County
county · Board of Supervisors/County Commission
VA Establish data center zoning standards in York County VA
York County (Virginia) Planning Commission unanimously advanced data center zoning amendments to the Board of Supervisors on April 8, 2026. The amendments increase maximum building height…
2026-04-08 pending
Swain County
county · Board of Supervisors/County Commission
NC Pass 12-month data center moratorium in Swain County
Swain County held a packed public hearing on April 1, 2026 (the most crowded meeting ever in their building) with 30+ speakers over two hours, only one opposed the moratorium. Triggered by…
2026-04-01 in force
Town of Clyde
city · City Council
NC Pass data center moratorium in Town of Clyde
The Town of Clyde, NC passed a one-year moratorium on data center development at its April 16, 2026 meeting following a public hearing. This follows neighboring Canton's similar moratorium…
2026-04-16 in force
Vance County
county · Board of Supervisors/County Commission
NC Block data center rezoning in Vance County
After a delayed April 6, 2026 vote and a unanimous April 12-13 planning board recommendation, the Vance County Board of Commissioners voted 6-1 on April 20, 2026 to approve a rezoning…
2026-04-20 in force
City of Rocky Top
city · City Council
TN Restrict data centers to industrial zones in Rocky Top
Rocky Top, TN: Ordinance 620 (data center zoning restrictions) second reading was NOT held on April 16, 2026 as previously scheduled. Mayor Templin confirmed the vote has been moved to May…
2026-04-01 pending
Bangor
city · City Council
ME Six-month moratorium on data center construction to update Land Development Code
Bangor city councilors unanimously passed a six-month moratorium on data center construction on April 13, 2026. The freeze gives the city time to adjust its Land Development Code before…
2026-04-13 in force
Lowhill Township
township · Township Board
PA Establish conditional use zoning requirements for data centers
Board of Supervisors adopted data center regulations titled 'Digital Infrastructure Facility,' permitting data centers as conditional use in the Regional Use Overlay 2 district. Includes…
2026-04-08 in force
Smithfield
city · Planning Commission
RI Ban data center development in Smithfield
Smithfield Planning Board voted on April 13, 2026 to advance a data center ban, giving a positive recommendation to the Town Council. The Town Council vote is scheduled for May 5, 2026.…
2026-04-01 pending
Ravenna
city · City Council
OH Pause data centers in Ravenna pending zoning and grid study
Ravenna, OH City Council held a special meeting on April 20, 2026 that advanced a 12-month data center moratorium. The second reading and public hearing are scheduled for May 18, 2026. The…
2026-04-10 pending
Shawnee Township
township · Township Board
OH Pause data centers, BESS, and solar in Shawnee Township for 18 months
Shawnee Township trustees (Allen County, Ohio) enacted an 18-month moratorium on April 13, 2026 covering data centers, battery energy storage systems (BESS), and utility-scale solar. The…
2026-04-13 in force
Botkins
city · City Council
OH Ban data center development in the Village of Botkins
The Village of Botkins, Ohio held the first reading of legislation to ban data center development during the week of April 13, 2026. If adopted, it would be one of the first outright bans…
2026-04-14 pending
DeKalb County
county · Planning Commission
IN Pause data centers in DeKalb County, Indiana for 6 months
The DeKalb County, Indiana Plan Commission recommended a 6-month data center moratorium on April 14, 2026, sending the measure to the County Commissioners for final action. The…
2026-04-14 pending
New Buffalo Township
township · Township Board
MI Block Project Maize data center in New Buffalo Township for 1 year
New Buffalo Township, Michigan (Berrien County) passed a 1-year data center moratorium on April 8, 2026, blocking an investment group's 'Project Maize' data center proposal and giving the…
2026-04-08 in force
Detroit
city · City Council
MI Draft data center zoning, grid, and environmental standards in Detroit
Following the Detroit City Council's March 18, 2026 resolution requesting a two-year data center permitting pause, the city convened a zoning policy working group in mid-April 2026 to…
2026-04-14 in force
Otoe County
county · Planning Commission
NE Pause data centers in Otoe County pending zoning standards
On April 16, 2026, the Otoe County Planning Commission voted to recommend a moratorium on data center construction in the county. Resident Wynne Benedict cited environmental and health…
2026-05-19 in force
North Franklin Township
township · Township Board
PA Proactive data center and crypto mining regulation ordinance
North Franklin Township (Washington County) adopted a proactive ordinance on April 14-16, 2026 regulating cryptocurrency mining and data center operations. No developer has filed a project…
2026-04-14 in force
Montour County
county · Board of Supervisors/County Commission
PA 26-page zoning amendment covering crypto, AI, and hyperscaler data centers
Montour County Commissioners approved a notice of intent on April 14, 2026 to adopt a 26-page zoning amendment covering cryptocurrency mining, AI data centers, and hyperscaler facilities.…
2026-04-14 pending
Rowan County
county · Board of Supervisors/County Commission
NC Temporary pause on new data center approvals in Rowan County
Rowan County (NC) Board of Commissioners approved a 1-year data center moratorium 4-0 on April 21, 2026, effective May 4, 2026. The Long Ferry Road project (EDC Charlotte LLC) is exempted…
2026-04-21 in force
Clay Township
township · Township Board
OH Preemptive 12-month moratorium on data center development in rural Clay Township
Clay Township (Highland County, OH) trustees adopted a 12-month data center moratorium on April 20, 2026. Board Chair Angela Howell cited concerns that rural communities are becoming hot…
2026-04-20 in force
City of Oakley
city · City Council
CA 45-day urgency moratorium (extensible up to 2 years) on new data center approvals
Oakley, CA (Contra Costa County) became the first Bay Area city to pass a data center moratorium, with City Council unanimously adopting a 45-day urgency ordinance on April 14-15, 2026.…
2026-04-15 in force
Centralia
city · City Council
MO Restrict data centers to conditional use in M-1 industrial zone in Centralia
On April 21, 2026, the Centralia Board of Aldermen unanimously passed an ordinance that defines and regulates data centers, requiring conditional use permits and permanent buildings (no…
2026-04-21 in force
Mansfield
city · City Council
OH Reject EnergiAcres data center / power plant due to lack of coordination and scope creep.
Mansfield Mayor Jodie Perry announced on April 21, 2026 that the city will 'no longer pursue' the proposed EnergiAcres data center and power plant project sited north of Mansfield in…
2026-04-21 expired
Washington Township
township · Township Board
OH Pause data center zoning approvals to study utility, noise, and infrastructure impacts.
On April 21, 2026, Washington Township trustees (Montgomery County, Dayton area) approved a 360-day moratorium on issuance and processing of zoning permits and approvals for data center…
2026-04-21 in force
Tiffin
city · City Council
OH Pause data center establishments to study zoning standards.
On April 21, 2026, Tiffin City Council voted 6-0 (and a separate 6-0 emergency declaration) to approve Resolution 2026-42 imposing a 12-month moratorium barring the establishment of, or…
2026-04-21 in force
Findlay
city · City Council
OH Temporarily ban new data center establishments to review codes.
On April 21, 2026, Findlay City Council approved a 12-month data center moratorium (Ordinance 2026-42) by a 9-1 vote, with Councilman B.J. Preston casting the lone 'nay' vote, arguing data…
2026-04-21 in force
Dayton
city · Planning Commission
OH Recommend a 180-day moratorium and ban on large data centers within city limits.
On April 14, 2026, the Dayton City Plan Board recommended adopting a 180-day moratorium on data center applications and a zoning code text amendment that would prohibit large data centers…
2026-04-14 pending
Plainfield
city · Village Board
IL Pause data center applications pending state legislation and local regulations.
On April 21, 2026, Plainfield Village Board unanimously approved a 180-day moratorium on data center and warehouse-for-computing-infrastructure proposals. The moratorium pauses…
2026-04-21 in force
Tonopah
county · Board of Supervisors/County Commission
AZ Rezone 638 acres to enable 2.25 million sq ft data center campus.
On April 15, 2026, the Maricopa County Board of Supervisors approved a request to rezone a 638-acre site at the northeast corner of 491st Avenue and Thomas Road outside Tonopah (west of…
2026-04-15 in force
Oklahoma City
city · City Council
OK Pause new data center rezoning through end of 2026.
On April 22, 2026, the Oklahoma City Council unanimously approved a moratorium on new data center developments through December 31, 2026, prohibiting rezoning requests intended for data…
2026-04-22 in force
Reno
city · City Council
NV Initiate text amendment to revise data center siting, noise, water, and environmental rules.
On Earth Day (April 22, 2026), the Reno City Council voted unanimously to initiate a text amendment to Title 18 of the Annexation and Land Development Code to revise data center…
2026-04-22 in force
Orange County
county · Board of Supervisors/County Commission
NC Pause new data centers via 12-month moratorium
On April 21, 2026, the Orange County Board of Commissioners voted unanimously 6-0 to approve a one-year moratorium on large-scale data centers covering AI training facilities,…
2026-04-21 in force
Glynn County Board of Commissioners
county · Board of Supervisors/County Commission
GA Restrict data center water use under new zoning ordinance
On April 17, 2026, the Glynn County Board of Commissioners unanimously approved new zoning ordinances that include a section permitting data centers, rejecting calls from the planning…
2026-04-16 in force
Jackson City Council
city · City Council
MS Pause data center development with 183-day moratorium
On April 21, 2026, Jackson City Council President Brian Grizzell introduced a draft ordinance establishing a 183-day moratorium on construction, expansion, permitting, or site-plan…
2026-07-14 in force
Tredyffrin Township
township · Township Board
PA Authorize draft zoning amendments to regulate data centers in Tredyffrin Township
The Tredyffrin Township Board of Supervisors voted unanimously on April 21, 2026 to authorize township staff and the solicitor to draft zoning amendments regarding data centers. No…
2026-04-21 pending
Harford County Council
county · Board of Supervisors/County Commission
MD Enact 90-day moratorium on data center development in Harford County (Bill 26-005)
Councilmember Jacob Bennett officially introduced Bill 26-005 at the Harford County Council meeting on Tuesday, April 21, 2026, proposing a 90-day moratorium on data center development.…
2026-04-21 pending
Memphis City Council
city · City Council
TN Approve land sale to xAI for Colossus Water Recycle Plant
The Memphis City Council gave final approval to sell 13 acres south of the T.E. Maxson Wastewater Treatment Plant to xAI for $820,000 to build the $80M 'Colossus Water Recycle Plant.'…
2025-03-04 in force
Memphis City Council
city · City Council
TN Direct 25% of xAI city property tax to surrounding neighborhoods
The Memphis City Council unanimously passed Mayor Paul Young's ordinance allocating 25% of xAI's city property tax revenue, estimated at $3M-$3.2M of $13M first-year revenue, up to $100M…
2025-08-01 in force
Saline Township Planning Commission
township · Planning Commission
MI Deny rezoning of 575 farmland acres for Stargate data center
After an August 5, 2025 first public hearing dominated by opposition, the Saline Township Planning Commission tabled Related Digital's 'conditional rezoning' application for 575 acres from…
2025-08-12 expired
Saline Township Board
township · Township Board
MI Deny rezoning for Stargate data center
The Saline Township Board voted 4-1 to deny the rezoning of 575 acres of agricultural land needed for the Stargate data-center campus. Treasurer Jennifer Zink stated the project conflicted…
2025-09-10 expired
Saline Township Board
township · Township Board
MI Rescind I-1 industrial designation to block citizen referendum
At an overflow special meeting, the Saline Township Board voted 5-0 to rescind its prior I-1 industrial designation and revert the data-center property back to A-1 Agricultural zoning,…
2026-01-28 in force
City of Port Washington
city · City Council
WI Annex 500 acres and create I-3 Technology Campus zoning for data center
Port Washington's city authorities unanimously approved annexing 500 acres from the Town of Port Washington and creating a new I-3 Technology Campus District zoning classification…
2025-05-01 in force
Port Washington Common Council
city · City Council
WI Approve $8B Vantage development agreement with $175M public infrastructure reimbursement
The Port Washington Common Council unanimously approved the development agreement with Vantage Data Centers for what was then announced as an $8 billion data-center campus on 672 acres on…
2025-08-19 in force
Port Washington Plan Commission
city · Planning Commission
WI Establish TID No. 5 boundaries / project plan for $458M Vantage TIF
The Port Washington Plan Commission, after hours of public comment, approved Resolution 2025-3 establishing the boundaries and project plan for Tax Incremental District No. 5, the $458…
2025-10-16 in force
Port Washington Common Council & Joint Review Board
city · City Council
WI Create $458M TID No. 5 for Vantage Lighthouse
The Port Washington Common Council formally voted to create Tax Incremental District (TID) No. 5, a $458 million TIF, for the Vantage Lighthouse data center. On November 18, 2025, the…
2025-11-04 in force
Port Washington Plan Commission
city · Planning Commission
WI End 24-hour construction at Lighthouse site
After months of resident complaints, including reports of 110-decibel noise, incessant backup beeping, and bright work lights shining 24 hours a day into nearby homes, the Port Washington…
2026-03-25 in force
Village of Mount Pleasant Village Board
city · Village Board
WI Approve $13.3B Microsoft 15-building expansion site plans
The Mount Pleasant Village Board unanimously approved two site plans for Microsoft's $13.3B expansion, adding 15 data-center buildings on two new campuses, after the Plan Commission…
2026-01-26 in force
Niles
city · City Council
OH Block Bitdeer 300 MW annexation and adopt moratorium in Niles
On Monday April 20, 2026, the City of Niles announced it would take "no further action" on a proposed annexation of three Weathersfield Township parcels submitted by Whitetail Creek LLC (a…
2026-04-20 expired
Harnett County
county · Board of Supervisors/County Commission
NC Pause data center development in Harnett County pending regulations
Harnett County Commissioners on April 21, 2026 voted to schedule a public hearing for May 4, 2026 on a proposed one-year data center moratorium and authorized modifications to the county's…
2026-04-21 pending
Cumberland County
county · Board of Supervisors/County Commission
NC Pause data center development in Cumberland County pending regulations
The Cumberland County (NC) Board of Commissioners voted 6-0 (one absent) on April 20, 2026 to schedule a public hearing on May 18 at 6:45 p.m. on a proposed data center moratorium.…
2026-06-15 in force
Bethel Township
township · Planning Commission
PA Develop data center zoning ordinance for Bethel Township
Bethel Township Planning Commission unanimously voted on April 21, 2026 to begin developing a draft data center ordinance, with Chairman Dale Snader noting "It's coming, and I suppose we…
2026-04-21 pending
Plymouth Township
township · Township Board
PA Resolve dispute over 43 zoning conditions attached to proposed AI data center at Cleveland-Cliffs site
Developer Brian O'Neill resubmitted a zoning application in May 2026 to build a 2M-sq-ft, 10-building AI data center across 66 acres of the former Cleveland-Cliffs steel mill site in…
2026-07-27 pending
Montgomery County
county · Board of Supervisors/County Commission
MD Impose a data center permit moratorium and ban hyperscale facilities countywide
Montgomery County Council member Evan Glass introduced Bill 19-26 in May 2026 as a 6-month data center permit freeze, prompted partly by a proposed 360 MW campus at a former coal plant…
2026-07-28 in force
Town of Brookhaven
township · Township Board
NY moratorium
After backlash over a rumored AI data center in Yaphank, Supervisor Dan Panico proposed an 18-month moratorium and the Brookhaven Town Board voted unanimously on May 29, 2026 to schedule a…
2026-05-29 pending
Cranford Township
township · Township Board
NJ ordinance + zoning restriction
Cranford announced it will introduce a land-use ordinance amendment on June 8, 2026 to explicitly prohibit AI data centers, reversing its August 2025 broadening of permitted uses in the…
2026-06-09 pending
City of Summit
city · City Council
NJ ordinance + zoning restriction
Summit Common Council introduced an ordinance amending prohibited land uses to ban AI data centers, with debate over a 20-MW peak-power threshold. Council Member Jamel Boyer voted against…
2026-06-16 in force
City of Allentown
city · City Council
PA zoning restriction + public comment/hearing
Allentown City Council tabled Bill 20 on June 3, 2026 after ~4 hours of testimony from a standing-room-only crowd. The bill would permit data centers in G-I and I-M districts by special…
2026-06-03 pending
Town of Scarborough
borough · City Council
ME moratorium
On June 3, 2026, the Scarborough Town Council unanimously approved a 180-day data center moratorium, retroactive to April 1, halting a ~52-acre data center proposal submitted in April and…
2026-06-03 in force
City of Westbrook
city · City Council
ME moratorium
On June 1, 2026, the Westbrook City Council unanimously approved a 180-day data center moratorium; the planning board will review the land-use ordinance and report back. It is part of a…
2026-06-01 in force
City of Fort Worth
city · City Council
TX zoning restriction + ordinance
Fort Worth city staff presented proposed citywide data center rules on June 2, 2026: ban cryptocurrency mining as a primary data center use; require a 250-ft setback from homes (300-ft for…
2026-06-02 pending
Pinal County
county · Board of Supervisors/County Commission
AZ project withdrawal/rejection + public comment/hearing
Facing ~60 opposed public comments and ~50 emails, the developer’s attorney told the Pinal County Board of Supervisors on May 28, 2026 that the owner wants the “La Osa” campus made…
2026-05-28 pending
Dane County
county · Board of Supervisors/County Commission
WI moratorium
The Dane County Board unanimously approved Sub 1 to RES-039 on June 4, 2026, an 18-month moratorium pausing zoning permit applications for hyperscale data centers (defined as 5,000+…
2026-06-04 in force
Brown County
county · Board of Supervisors/County Commission
WI moratorium
On June 2, 2026, the Brown County Planning, Development & Transportation Committee unanimously declined to advance Supervisor Christopher Welch’s proposed countywide data center…
2026-06-02 expired
Shawano County
county · Board of Supervisors/County Commission
WI moratorium
On June 3, 2026, the Shawano County Planning, Development & Zoning Committee unanimously recommended a one-year moratorium for unincorporated (county-zoned) areas after a public hearing at…
2026-06-03 pending
Jackson County
county · Board of Supervisors/County Commission
MO moratorium
On June 1, 2026 the Jackson County (Missouri) Legislature held over two competing data center moratorium proposals (Ord. 6074, a 120-day pause incl. battery storage; Ord. 6087, a year-long…
2026-06-22 in force
City of Virginia Beach
city · City Council
VA zoning restriction
On June 2, 2026, the Virginia Beach City Council voted unanimously to direct staff to draft a zoning ordinance amendment making traditional and hyperscale data centers non-permitted uses…
2026-06-02 pending
Newberry County
county · Board of Supervisors/County Commission
SC moratorium + permit_denial
On June 4, 2026, the Newberry County Council voted unanimously to deny an ordinance that would have let a developer purchase county land for a potential data center, and enacted a one-year…
2026-06-04 in force
Hernando County
county · Board of Supervisors/County Commission
FL moratorium
In early June 2026, the Hernando County Commission approved a one-year data center moratorium. No company is named. [Validation: status corrected to pending, June 2 was a first-reading…
2026-06-04 pending
Holmes County
county · Board of Supervisors/County Commission
FL moratorium + study_or_report
On June 2, 2026, the Holmes County Commission directed the county attorney to draft a permanent ban on AI data centers, with a public hearing set for June 16.
2026-06-02 pending
Iron County
county · Board of Supervisors/County Commission
UT moratorium
On May 26, 2026, the Iron County Commission adopted a 180-day pause (the maximum allowed under Utah law) on accepting or processing new or incomplete land-use applications for data…
2026-05-26 in force
Howard County
county · Board of Supervisors/County Commission
MD moratorium
The Howard County Council passed CB31-2026, a temporary moratorium pausing data center development through November 2027 to modernize the county's roughly 1993-era zoning regulations…
2026-06-02 in force
McMinnville
city · City Council
TN moratorium
On June 3, 2026, the McMinnville Board of Mayor and Aldermen unanimously approved on first reading an 18-month moratorium covering data centers, Bitcoin mining, and microchip…
2026-06-09 in force
Town of Hillsborough
borough · City Council
NC moratorium
The Town of Hillsborough enacted a 60-day moratorium on AI data centers and data mining to update its land-use ordinances, joining recent actions by Orange County, Chatham County, and the…
2026-06-01 in force
Little Rock
city · City Council
AR ordinance + zoning restriction
On June 3, 2026, Little Rock's Board of Directors unanimously approved new citywide data center regulations during an hours-long meeting that featured heavy criticism of a proposed ~$1B…
2026-06-03 in force
Reno
city · City Council
NV moratorium
On June 1, 2026, the Reno City Council voted 6-1 to extend its data center moratorium into 2027, described as the first such extension in Nevada, while the city continues work on a Title…
2026-06-01 in force
Grove City
city · City Council
OH moratorium
On June 1, 2026, Grove City passed a 12-month (1-year) moratorium on data center development, amended to create a task force to study impacts and develop regulations during the pause.
2026-06-01 in force
City of Brawley
city · City Council
CA moratorium
On May 19, 2026, the Brawley City Council voted 3-2 (Grass and Kelley dissenting) to approve Ordinance No. 2026-03, an immediate moratorium on data centers requiring more than 50 MW of…
2026-05-19 in force
City of Imperial
city · City Council
CA moratorium
On May 20, 2026, the City of Imperial council voted 4-0 to direct staff to return with a moratorium on hyperscale data centers within city limits; the item returned June 3 with the council…
2026-05-20 pending
City of Calexico
city · City Council
CA moratorium
The Calexico City Council was scheduled to consider a proposed data center moratorium at its June 3, 2026 meeting (alongside a public-safety budgeting mandate). No specific data center…
2026-06-03 pending
Imperial County
county · Board of Supervisors/County Commission
CA moratorium + zoning restriction
On June 2, 2026, after 1+ hour of public comment and 296 emailed comments, the Imperial County Board of Supervisors declined to adopt staff-drafted 'Data Center Development Guidelines' (21…
2026-06-16 in force
Town of Brunswick
city · City Council
ME moratorium
On June 1, 2026 the Brunswick, Maine Town Council unanimously approved a 180-day moratorium (through ~Dec 2026) on processing applications for new or expanded data centers with electrical…
2026-06-01 in force
Moosic Borough
borough · Village Board
PA ordinance + zoning restriction
Moosic Borough (Lackawanna County) is finalizing one of the county's most comprehensive data center ordinances, with a Borough Council public hearing targeted for its June 8, 2026 meeting.…
2026-06-08 pending
Warren Township, Somerset County
township · Township Board
NJ zoning restriction + ordinance
The Warren Township (Somerset County, NJ) Committee approved the first reading (May 18, 2026) of an ordinance, introduced by Committeeman Daniel Croson, that would prohibit data centers as…
2026-06-18 in force
Lexington-Fayette Urban County
county · City Council
KY opposition action + moratorium
On June 8, 2026 Lexington Mayor Linda Gorton announced the city will not provide public incentives to DartPoints, which closed a ~$29M private purchase of the former Lexmark property (745…
2026-06-08 in force
Fayetteville
city · City Council
AR zoning restriction + ordinance
On June 4, 2026 Fayetteville Mayor Molly Rawn (with Councilman Scott Berna) announced proposed ordinance amendments making data centers a conditional use across all zoning districts…
2026-06-16 in force
Clay County
county · Board of Supervisors/County Commission
FL moratorium + public comment/hearing
On June 9, 2026 the Clay County (FL) Commission held the first of two required public hearings on a proposed 12-month moratorium halting rezoning and permitting for data centers in…
2026-06-23 in force
Gardner
city · City Council
KS moratorium
On June 1, 2026 a proposed six-month data center moratorium FAILED at the Gardner (KS) City Council, Councilmember Kelly Johnson's motion died for lack of a second; Vice President Kacy…
2026-06-01 expired
City of Edmond
city · City Council
OK moratorium
On June 8, 2026 the Edmond (OK) City Council voted 5-0 to enact an immediate moratorium on accepting new data center applications through Dec 31, 2026, giving the city ~5 months to study…
2026-06-08 in force
Box Elder County
county · Board of Supervisors/County Commission
UT moratorium
On June 10, 2026 the Box Elder County Commission unanimously approved a 180-day moratorium on new data center development in unincorporated Box Elder County (zoned and unzoned land), to…
2026-06-17 in force
Montgomery County
county · Board of Supervisors/County Commission
MD moratorium + executive_action
On June 13, 2026 Montgomery County Executive Marc Elrich signed an executive order imposing a six-month moratorium on new data center permits, directing the Department of Permitting…
2026-06-13 in force
Borough of Red Bank
borough · City Council
NJ ordinance + zoning restriction + opposition action
On June 11, 2026 the Red Bank Borough Council unanimously voted to ban data centers (final adoption) and unanimously passed an 'AI Accountability Proclamation' calling on the State of New…
2026-06-11 in force
Old Bridge Township
township · Township Board
NJ opposition action + zoning restriction
After a heated, packed public meeting (~June 9), the Old Bridge Township (Middlesex County) Council moved to draft an ordinance that would permanently ban data centers township-wide,…
2026-06-12 pending
Anderson County
county · Board of Supervisors/County Commission
TN moratorium
On June 15, 2026 the Anderson County (TN) Commission approved a two-year moratorium on new cryptocurrency mining, data processing, and battery storage development (facilities ≥20,000 sq ft…
2026-06-15 in force
Spartanburg County
county · Board of Supervisors/County Commission
SC moratorium
On June 15, 2026 the Spartanburg County (SC) Council unanimously directed the county manager and attorney to draft a data center moratorium/ban ordinance while awaiting state legislation.…
2026-06-22 pending
Greenwood County
county · Board of Supervisors/County Commission
SC moratorium
In the June 16-17, 2026 window the Greenwood County (SC) Council took up a proposed one-year data center moratorium, saying it wants preemptive regulations though no projects are currently…
2026-07-07 in force
Edgerton
city · Planning Commission
KS permit_denial + moratorium
Two-part Edgerton (KS) action: on June 11, 2026 the Planning Commission DENIED (3-2) Dubai-based DAMAC Digital's ~$860M data center (a conversion of a ~400,000-sq-ft warehouse at Logistics…
2026-06-11 in force
Council Bluffs
city · City Council
IA moratorium
On June 15, 2026 the Council Bluffs (IA) City Council voted unanimously to DENY a proposed one-year data center moratorium, opting for a wastewater-management plan instead as the city…
2026-06-15 expired
Yankton County
county · Board of Supervisors/County Commission
SD moratorium
On June 16, 2026 the Yankton County (SD) Commission held a first reading of a resolution for a temporary moratorium of up to 12 months on data centers and Bitcoin-mining facilities…
2026-06-16 pending
Liberty Township, Butler County
township · Planning Commission
OH zoning restriction
Around June 15, 2026 the Liberty Township (Butler County, OH) Zoning Commission approved a proposed change requiring data center projects to go through the planned-unit-development (PUD)…
2026-06-15 pending
Hood County
county · Board of Supervisors/County Commission
TX zoning restriction + opposition action
Hood County (TX) commissioners approved the Comanche Circle data center (Sailfish Development; up to ~9 campuses / ~2,600 acres near Tolar, up to 5 GW) WITHOUT conditions after the…
2026-06-17 in force
Santa Fe County
county · Board of Supervisors/County Commission
NM moratorium
Santa Fe County (NM) commissioners are advancing a yearlong moratorium on data center developments, with a public hearing and vote expected in late June; Commissioner Lisa Cacari Stone…
2026-06-16 in force
City of Holyoke
city · City Council
MA ordinance + zoning restriction
Holyoke became the first Massachusetts city to enact a citywide ban on AI data centers. The City Council voted 9-4 on June 16-17 to prohibit any AI data center development over 12…
2026-06-18 in force
Sayreville Borough
borough · City Council
NJ moratorium
Sayreville Borough Council introduced an 18-month moratorium on data center construction on June 15, 2026, with five members voting yes; the freeze would block new data center facilities…
2026-06-15 pending
Bernards Township
township · Township Board
NJ ordinance + zoning restriction
Bernards Township (Basking Ridge) is advancing Ordinance No. 2599, which would remove 'data processing centers' as a permitted use in the township's E1-E5 office zones and prohibit data…
2026-06-18 in force
City of Asbury Park
city · City Council
NJ ordinance + opposition action
On June 10, 2026, the Asbury Park City Council unanimously passed a resolution banning data centers within city limits and calling on Gov. Mikie Sherrill to enact a statewide moratorium on…
2026-06-10 in force
Chester County
county · Board of Supervisors/County Commission
SC moratorium + ordinance
On June 15, 2026 the Chester County (SC) Council approved FIRST READING of a six-month pause on accepting new data center applications, to study power-grid demand, local utility capacity,…
2026-06-15 pending
Warren County
county · Board of Supervisors/County Commission
TN moratorium
Warren County (TN) scheduled a June 22, 2026 vote on a temporary data center ban/moratorium covering its entire jurisdiction, following the City of McMinnville's (in Warren County)…
2026-06-22 pending
Butler County
county · Board of Supervisors/County Commission
OH moratorium
On Tuesday June 16, 2026 the Butler County (Ohio) Commissioners voted unanimously to approve a six-month moratorium on data centers, effective immediately, covering the six townships under…
2026-06-16 in force
La Crosse County
county · Board of Supervisors/County Commission
WI moratorium
On Thursday June 18, 2026 the La Crosse County (Wisconsin) Board of Supervisors approved an 18-month moratorium on new data center decisions and development by a 26-2 vote (two members…
2026-06-18 in force
City of Springfield
county · City Council
OH moratorium
At its June 16, 2026 regular meeting, Springfield (Ohio / Clark County) Commissioner Larry Ricketts said he is working with city staff to draft an ordinance for a six-month moratorium on…
2026-06-16 in force
Winnebago County
county · Board of Supervisors/County Commission
WI moratorium
Announced June 16, 2026, Winnebago County (Wisconsin) Executive Gordon Hintz introduced a proposed 12-month data center moratorium that would initially cover four towns (Nekimi, Neenah,…
2026-06-16 pending
Broken Arrow
city · City Council
OK moratorium
The Broken Arrow City Council voted unanimously on Monday, June 15, 2026 to enact a six-month moratorium on data center proposals, effective immediately and expiring December 31, 2026,…
2026-06-15 in force
City of Henderson
city · City Council
NV moratorium
The Henderson City Council introduced Bill No. 3927 at its June 16, 2026 meeting, a 180-day moratorium on conditional-use-permit applications for new data centers, which would make…
2026-06-16 expired
Skagit County
county · Board of Supervisors/County Commission
WA moratorium
Skagit County's Board of Commissioners voted June 1, 2026 to adopt a six-month interim moratorium on accepting data center permit applications in unincorporated/rural parts of the county,…
2026-06-01 in force
Jefferson County
county · Board of Supervisors/County Commission
CO moratorium
The Jefferson County (CO) Board of Commissioners voted May 19, 2026 to impose a 10-month moratorium on new data center development, running through roughly March 2027. The moratorium…
2026-05-19 in force
Carroll County
county · Board of Supervisors/County Commission
AR moratorium + ordinance
NEW fight. On June 17 the Carroll County (AR) Quorum Court unanimously passed a 12-month emergency moratorium blocking construction and authorization of 'high-impact industrial and…
2026-06-17 in force
Versailles
city · City Council
KY moratorium
NEW fight. On June 16 the Versailles (Woodford County) City Council voted unanimously to enact a data center moratorium halting all related development through December 31, 2026, brought…
2026-06-16 in force
Franklin Park Borough
borough · Village Board
PA ordinance + zoning restriction
NEW preemptive regulation. On June 17 the Franklin Park Borough Council adopted Ordinance No. 697-2026 establishing a data center overlay district in the borough zoning map even though no…
2026-06-17 in force
Bowling Green
city · City Council
KY zoning restriction + moratorium
NEW item (no existing Bowling Green KY entry found). On June 16 the Bowling Green City Commission adopted data center zoning regulations (energy/water limits, noise controls, 1,500-ft…
2026-06-16 in force
Clark County
county · Board of Supervisors/County Commission
NV zoning restriction + opposition action
The Clark County Commission, sitting as the zoning board, voted unanimously on June 18, 2026 to approve Switch's nearly 57,000-sq-ft data center expansion on nine acres along Warm Springs…
2026-06-18 in force
Lordstown
county · Village Board
OH moratorium + infrastructure_opposition
Separately from the data center freeze, Lordstown Village Council is advancing a 180-day moratorium on permits for businesses using small mobile (modular) reactors or battery energy…
2026-06-15 pending
Village of Wrightstown
city · Village Board
WI Pause new data center development in Wrightstown pending an advisory referendum
Wrightstown Village Board unanimously adopted a one-year moratorium on data center projects, extending a prior resolution that had paused planning pending an August advisory referendum.
2026-07-07 in force
Dodge County Board of Supervisors
county · Board of Supervisors/County Commission
WI Pause new data center applications in Dodge County pending an ordinance
Dodge County Board of Supervisors voted 29-2 for an 18-month pause on data center development to allow drafting of a county ordinance. One outlet (Daily Dodge) disputes whether the vote…
2026-06-22 in force
Linn County Board of Supervisors
county · Board of Supervisors/County Commission
IA Pause new EU-3 data center rezoning applications in Linn County pending utility/technical studies
Linn County Board of Supervisors voted 2-1 (Sami Scheetz opposed) for an 18-month pause on new rezoning applications to the county's EU-3 large-scale data center district, distinct from…
2026-07-01 in force
Woodbury County Board of Supervisors
county · Board of Supervisors/County Commission
IA Pause new data center applications in unincorporated Woodbury County
Woodbury County Board of Supervisors voted 5-0 for a 12-month moratorium on data center applications in unincorporated county land, prompted by the town of Salix's April annexation of ~900…
2026-06-23 in force
Seward County Board of Commissioners
county · Board of Supervisors/County Commission
NE Pause data center permitting and construction in Seward County for one year
Seward County Board of Commissioners unanimously passed a one-year moratorium on data center permits and construction, becoming roughly the 10th-11th Nebraska county with a data center…
2026-06-25 in force
Bourbon County Commission
county · Board of Supervisors/County Commission
KS Pause utility-scale power generation, crypto mining, and data center development in Bourbon County
Bourbon County Commission approved a 365-day development moratorium (Resolution 24-26) by a 3-0 vote, with Commissioners Joe Allen and Gregg Motley abstaining, covering utility-scale power…
2026-06-15 in force
Dublin City Council
city · City Council
OH Strip data centers as a permitted use across Dublin's West Innovation District
Dublin City Council voted 5-2 to rezone 370 acres, formally stripping data centers as a permitted use across the West Innovation District near Ballantrae and creating a new ID-6 'Research…
2026-07-01 in force
Cache County Council
county · Board of Supervisors/County Commission
UT Pause data center applications in Cache County pending regulatory review
Cache County Council voted 6-0 (one member absent) for a 180-day pause on accepting or reviewing any data center applications on unincorporated land, explicitly citing the neighboring Box…
2026-06-23 in force
Frederick County Board of Supervisors
county · Board of Supervisors/County Commission
VA Block Equus Capital Partners' Virginia Technology Park data center rezoning
Frederick County Planning Commission recommended denial 10-0 (2026-06-03) of Equus Capital Partners' ~220-acre Virginia Technology Park data center campus near Clear Brook, which would…
2026-07-08 pending
Front Royal Town Council
city · City Council
VA Pause data center applications in Front Royal for 90 days
Front Royal Town Council voted 6-0 for a 90-day moratorium on data center applications. The moratorium followed a June 22, 2026 unanimous Town Council denial of a text amendment that would…
2026-07-07 in force
Douglas County Commission
county · Board of Supervisors/County Commission
GA Block a 4.4M sq ft data center campus rezoning in Douglas County
Douglas County Commission voted 4-1 to deny a ~700+ acre, 4.4M sq ft data center campus rezoning. Hyperscaler unconfirmed. The 6-building campus, partly within the Dog River Basin (the…
2026-07-07 expired
DeKalb County Board of Commissioners
county · Board of Supervisors/County Commission
GA Adopt setback and environmental-review standards for DeKalb County data centers
A 12-month, four-draft Data Center Text Amendment (500-ft setbacks, environmental review) failed at the DeKalb County Board of Commissioners after a year of development.
2026-06-23 expired
Colleton County Council
county · Board of Supervisors/County Commission
SC Pause new data center development in Colleton County pending regulatory review
Colleton County Council finalized a 6-month data center moratorium; the Southern Environmental Law Center agreed to pause its related lawsuit against the county for the moratorium's…
2026-07-07 in force
Spartanburg County Council
county · Board of Supervisors/County Commission
SC Pause new data center applications in Spartanburg County for one year
Spartanburg County Council passed the first reading of a 12-month data center moratorium unanimously; it does not affect the already-under-construction NorthMark project. [Update…
2026-07-20 pending
Knox County Commission
county · Board of Supervisors/County Commission
TN Pause data center development in Knox County for one year
Knox County Commission unanimously (10-0) approved a one-year moratorium on data centers.
2026-06-22 in force
Knoxville City Council
city · City Council
TN Pause large (>=10MW) data center development in Knoxville for one year
Knoxville City Council passed a one-year moratorium on large data centers (>=10 MW), following Knox County's own June 22 moratorium.
2026-07-07 in force
Loudon County Commission
county · Board of Supervisors/County Commission
TN Pause large (>=50MW) data center development in Loudon County for 6 months
Loudon County Commission passed a 6-month data center moratorium for facilities with >=50 MW peak demand.
2026-06-30 in force
Cullman City Council
city · City Council
AL Pause data center development in Cullman for one year and consider an outright ban
Cullman City Council unanimously passed a 1-year moratorium on data centers and directed staff to draft a potential outright prohibition.
2026-06-22 in force
Oldham County Fiscal Court
county · Board of Supervisors/County Commission
KY Block Project Lincoln via a 150-day countywide data center moratorium
Oldham County passed a 150-day moratorium (until 2026-11-28) after removing a draft carve-out that would have exempted in-progress projects, directly blocking Western Hospitality Partners'…
2026-07-01 in force
Butler County Fiscal Court
county · Board of Supervisors/County Commission
KY Pause data center development in Butler County for one year
Butler County passed a 1-year data center moratorium, the third south-central Kentucky county to do so after Edmonson and Allen counties. Exact vote date is approximate.
2026-06-30 in force
Monroe Township Council
township · City Council
NJ Remove 'data processing facilities' as a permitted zoning use in Monroe Township
Council discussed 'Ordinance 013,' which would strike references to 'data processing facilities' from local land-use/planning documents, effectively closing a zoning pathway. No developer…
2026-06-29 pending
City of Westfield
city · City Council
MA Pause new data center construction and permitting in Westfield for one year
Westfield City Council unanimously passed a 1-year moratorium on new data center construction/permitting after standing-room-only public comment; this was the second of two required votes…
2026-07-06 in force
Middleton Township
township · Township Board
OH Rezone parcels bordering the Meta data center for supporting construction logistics/parking
Trustees voted 2-1 (Moulton, Vetter for; Petrea against) to rezone 13 parcels (~32 acres) from residential/agricultural to M-1 industrial to support the adjacent Meta data center,…
2026-07-07 in force
Houghton
city · City Council
MI Enact a 1-year citywide moratorium on data center facilities in Houghton, MI
City Council unanimously enacted a one-year moratorium on permitting, approval, and installation of data center facilities citywide, to allow the planning commission to study best…
2026-07-09 in force
St. Charles County
county · Board of Supervisors/County Commission
MO Impose a 6-month countywide moratorium on data centers in St. Charles County, MO
County Council unanimously approved a 6-month moratorium on data centers larger than 100,000 sq ft or exceeding 5 MW demand, following the City of St. Charles's earlier…
2026-07-14 in force
Joplin
city · City Council
MO Adopt special-use-permit zoning requirements for future data centers in Joplin, MO
City Council voted 9-0 to table a proposed ordinance requiring special-use permits (rather than by-right industrial zoning) for data centers, sending it back to Planning & Zoning to…
2026-07-06 pending
Bell County
county · Board of Supervisors/County Commission
TX Halt Murray Industries data center construction for two years
Commissioners passed a two-year construction moratorium halting a project by Murray Industries, which had already begun clearing land. It is unclear whether the moratorium covers Meta's…
2026-07-02 in force
Goodyear
city · City Council
AZ Establish first-time zoning setback/noise standards for data centers and battery storage
Goodyear City Council passed the city's first zoning ordinance overhaul since 1999, adding first-time data center and battery energy storage system (BESS) standards. Data centers now…
2026-07-06 in force
Grand County
county · Board of Supervisors/County Commission
UT Pause new data center applications for 180 days pending permanent standards
The Grand County Commission unanimously passed a 180-day moratorium pausing acceptance of new data center applications while permanent zoning standards are developed.
2026-07-07 in force
Missoula County
county · Board of Supervisors/County Commission
MT Pause countywide data center development for one year pending regulations
Missoula County approved a one-year, countywide pause on data center development -- Montana's first county-level moratorium. Distinct from the site-specific Krambu/Bonner Mill fight…
2026-07-09 in force
Marietta City Council
city · City Council
GA Block Powers Ferry Place data center rezoning and pause new Marietta data center applications
After a Planning Commission 4-3 recommendation to approve, Marietta City Council tabled Prime Group Holdings' Powers Ferry Place rezoning -- a proposal to convert part of a 90,000 sq ft…
2026-07-08 pending
Lakeland City Commission
city · City Council
FL Establish a moratorium on new data centers and large-load electric customers in Lakeland
The City of Lakeland released a proposed ordinance creating a temporary moratorium on data centers and large-load electric customers (over 50 MW/month); a public hearing was held July 6,…
2026-07-06 pending
Burgin City Council
city · City Council
KY Enable a hyperscale data center via Burgin annexation of Mercer County farmland
Burgin City Council voted 3-2 to give first reading to an ordinance annexing farmland from Mercer County -- roughly doubling the town's size (pop. ~1,000) -- to enable a hyperscale data…
2026-07-09 pending
Little Rock Board of Directors
city · City Council
AR Pause new hyperscale data center approvals in Little Rock through year-end
A measure by City Directors Kathy Webb and Capi Peck to pause new hyperscale data center approvals through year-end was deferred to August 4, 2026 at the sponsors' request. As drafted, it…
2026-07-07 pending
New Haven Board of Alders
city · City Council
CT Pause new data center development/conversions in New Haven for 12 months pending zoning standards
Alderman Richard Furlow introduced a 12-month moratorium ordinance on new data center development and conversions, scheduled for City Plan Commission review on 2026-07-15. The ordinance…
2026-07-06 pending
Wausau
city · City Council
WI Adopt zoning ordinance restricting data centers to industrial zones with conditional use review and a residential setback
City Council approved a first-of-its-kind data center zoning ordinance for Wausau: restricts data centers to medium/heavy-industrial zones (none permitted by right), requires a conditional…
2026-07-14 in force
Oshkosh
city · City Council
WI Direct staff to draft a formal data center construction moratorium ordinance
Common Council advanced a pause on data center construction, directing staff to draft a formal moratorium ordinance. No project is currently proposed for the city, but a local petition…
2026-07-14 pending
Mankato
city · City Council
MN Impose a 1-year moratorium on data centers and high-impact utility consumers pending a study
City Council voted 7-0 to pass a one-year moratorium on data centers and other 'high-impact utility consumers,' to allow a research study on localized water, power, farming, and climate…
2026-07-13 in force
Broken Bow
city · City Council
NE Impose a 6-month moratorium on new data center construction applications
City Council unanimously approved a 6-month moratorium on new data center construction applications, giving officials time to develop formal regulations. Per Zoning Administrator Jacob…
2026-07-14 in force
Americus / Lyon County
county · Board of Supervisors/County Commission
KS Halt new data center and solar-farm permits in Lyon County pending a six-month moratorium
Americus City Council held a listening session on the proposed Flint Hills Digital Campus (developer Kanza Park Place; publicly described as a potential gigawatt-scale, roughly 1,000-acre…
2026-07-15 in force
Roane County
county · Board of Supervisors/County Commission
TN Direct the regional planning commission to draft a two-year moratorium on data centers, crypto-mining, and battery storage in Roane County
The Roane County Commission approved a resolution directing the regional planning commission to draft a two-year moratorium -- amended up from an initially proposed 180 days -- on new data…
2026-07-14 in force
Lincoln County
county · Board of Supervisors/County Commission
NE Block data centers in Lincoln County via a proposed moratorium
Lincoln County Commissioners voted 3-2 against a proposed data center moratorium, with Hewgley, Bruns, and Woodruff opposed and Weems and Wuehler in favor. A recall drive targeting the…
2026-07-13 in force
Cass County
county · Planning Commission
NE Recommend a data center moratorium to the Cass County Board
The Cass County Planning Commission voted in favor of recommending a data center moratorium (no specific duration set) to the County Board, which holds final approval authority. The vote…
2026-07-13 pending
Jersey City
city · City Council
NJ Ban data centers as a primary permitted use in Jersey City's Industrial Districts
Mayor James Solomon and the City Council introduced Ordinance 26-057 on first reading, which would ban data centers as a primary principal use in Jersey City's Industrial Districts.…
2026-07-15 pending
Mercer County Fiscal Court
county · Board of Supervisors/County Commission
KY Draft a new moratorium on data centers in unincorporated Mercer County pending a joint zoning ordinance
The Mercer County Fiscal Court voted unanimously on July 14, 2026 (motion by Magistrate Susan Barrington) to direct the County Attorney to draft a new data-center moratorium covering…
2026-07-14 pending
Lansing
city · City Council
MI Impose a 182-day moratorium on new data center development in Lansing, MI
Lansing City Council voted 7-1 (Jeremy Garza dissenting) on July 15, 2026 to enact a 182-day moratorium on new data center development, effective July 27, 2026 through January 25, 2027.…
2026-07-15 in force
Warren
county · City Council
MI Request a data center moratorium in Warren, MI after storm-related power outages
Warren City Council Secretary Mindy Moore requested that a data-center moratorium be placed on a future council agenda after a July 3, 2026 storm knocked down 60+ power lines across the…
2026-07-14 pending
Logan County
county · Board of Supervisors/County Commission
NE Impose a 12-month moratorium on data centers and other energy-intensive development in Logan County, NE
The Logan County Board of Commissioners approved a 12-month moratorium on new data center, wind, solar, and cryptocurrency-mining development on July 16, 2026, becoming the twelfth…
2026-07-16 in force
Surry County
county · Board of Supervisors/County Commission
NC Pause new data center development in Surry County for two years pending an impact study
Surry County commissioners voted unanimously on July 21, 2026 to enact a two-year moratorium on new data center development, extending a prior 60-day pause. A steering committee will be…
2026-07-21 in force
Southport
city · Planning Commission
NC Recommend a 15-month moratorium on data center development in Southport pending zoning rulemaking
The Southport Planning Board voted unanimously on July 16, 2026 to recommend the city adopt a 15-month moratorium on data center development rather than proceeding directly to a zoning…
2026-07-16 pending
Cherokee County
county · Board of Supervisors/County Commission
GA Pause new data center applications in Cherokee County pending a longer-term moratorium decision
Cherokee County's Board of Commissioners unanimously approved an initial 30-day moratorium on new data center applications on July 22, 2026; an extension to 180 days (through mid-February…
2026-07-22 in force
Dougherty County
county · Board of Supervisors/County Commission
GA Pause new data center projects in Dougherty County for 45 days
Dougherty County commissioners approved a 45-day pause on new data center projects on July 20, 2026, amid rising regional concern about aquifer and grid impacts in the Albany area.
2026-07-20 in force
Albany
city · City Council
GA Determine the length of a proposed moratorium on new data center development in Albany
At a July 21, 2026 work session, the Albany City Commission directed staff to return with three moratorium-length options (180 days, 12 months, or 18 months) on new data center…
2026-07-21 pending
Brookwood
city · City Council
AL Oppose a 1,200-acre data center rezoning near Brookwood Middle School
A roughly 1,200-acre data center rezoning request near Brookwood Middle School is headed to an August 11, 2026 vote. The mayor denied a request to pause the process for a referendum. Black…
2026-08-11 pending
Neptune Township
township · Township Board
NJ Ban data centers and ICE/DHS detention facilities townshipwide
Neptune Township's Township Committee voted 3-1 on 2026-07-13 to ban both data centers and DHS/ICE immigration detention facilities townshipwide, becoming the 25th New Jersey municipality…
2026-07-13 in force
Weatherford
county · Board of Supervisors/County Commission
TX Prevent Black Mountain from siting a second hyperscale data center campus in Parker County near Weatherford
Black Mountain, the Fort Worth-based energy consortium developing the separate $10B, 530-acre data center campus in southeast Fort Worth (see fort-worth-southeast-tx-2025-01-01), purchased…
2026-06-09 pending
Milwaukee
city · City Council
WI Pass a 1-year moratorium on new data center development in Milwaukee
Milwaukee's Zoning, Neighborhoods & Development Committee postponed a proposed 1-year data center moratorium after the City Attorney's office said it lacked the required public…
2026-07-28 pending
Town of Janesville
township · Township Board
WI Adopt a moratorium on data center development to preserve agricultural land
The Town of Janesville's Planning & Zoning Committee recommended a moratorium on data center development to preserve agricultural land, following a heavily-attended public meeting. This is…
2026-07-29 pending
City of Lawrence
county · City Council
KS Adopt a 2-year moratorium on large-scale data centers and close a zoning loophole
The Lawrence City Commission unanimously approved a 2-year moratorium on large-scale data centers, extended from an originally proposed 1-year moratorium, and initiated a text amendment to…
2026-07-14 in force
City of Emporia
county · City Council
KS Establish a digital infrastructure district via ordinance; citizen petition to prohibit data centers pending
The Emporia City Commission approved three ordinances establishing a digital infrastructure district. Commissioners declined to act on a citizen petition to prohibit data centers, which…
2026-07-23 in force
Orangeburg County
county · Board of Supervisors/County Commission
SC Pause new data center construction and development in Orangeburg County pending study
Orangeburg County Council unanimously passed first reading of a data center construction and development moratorium after learning a company was scouting a Brentwood Drive site for a…
2026-07-23 pending
Falls Township
township · Township Board
PA Rewrite data-center zoning rules via curative amendment while shielding the township from developer validity challenges
Falls Township's Board of Supervisors voted to declare portions of Chapter 209 of the zoning ordinance -- covering data-center districts, setbacks, noise, and water/power requirements, and…
2026-07-27 pending
Cherry Hill Township
township · Township Board
NJ Ban large-scale data centers townshipwide via zoning ordinance
Cherry Hill Township Council voted unanimously on 2026-07-28 to ban large-scale data centers, designating them a non-permitted land use townshipwide while still allowing small in-house…
2026-07-28 in force
Cullman
city · City Council/Board of Supervisors
AL One-year data center moratorium
One-year data center moratorium (In force).
2026-06-01 in force
Fort Payne
city · City Council/Board of Supervisors
AL Six-month data center moratorium
Six-month data center moratorium (In force).
2026-06-01 in force
Independence County
county · City Council/Board of Supervisors
AR Five-year data center moratorium
Five-year data center moratorium (In force).
2026-08-01 in force
Pulaski County
county · City Council/Board of Supervisors
AR Data center moratorium
Data center moratorium (failed) (Failed / vetoed).
2026-08-01 expired
Russellville
city · City Council/Board of Supervisors
AR Six-month data center moratorium
Six-month data center moratorium (In force).
2026-07-01 in force
Union County
county · City Council/Board of Supervisors
AR One-year data center moratorium
One-year data center moratorium (In force).
2026-06-01 in force
Calipatria
city · City Council/Board of Supervisors
CA Permanent data center ban
Permanent data center ban (in development) (Proposed).
2026-07-01 pending
Coachella
city · City Council/Board of Supervisors
CA Data center moratorium moving toward permanent ban
Data center moratorium moving toward permanent ban (In force).
2026-06-01 in force
Indio
city · City Council/Board of Supervisors
CA Urgency data center moratorium
Urgency data center moratorium (In force).
2026-06-01 in force
Boulder County
county · City Council/Board of Supervisors
CO Six-month data center moratorium
Six-month data center moratorium (In force).
2026-06-01 in force
Monument
city · Local government
CO Six-month data center pause
Six-month data center pause (In force).
2026 in force
Woodland Park
city · Local government
CO 18-month data center pause
18-month data center pause (In force).
2026-07-01 in force
Groton
city · City Council/Board of Supervisors
CT Permanent zoning cap replacing 2022 moratorium
Permanent zoning cap replacing 2022 moratorium (In force).
2023 in force
Dover
city · Local government
DE Proposed 18-month pause on data center reviews
Proposed 18-month pause on data center reviews (Proposed).
2026-08-01 pending
Nassau County
county · City Council/Board of Supervisors
FL Up to 12-month data center moratorium
Up to 12-month data center moratorium (In force).
2026 in force
Pasco County
county · City Council/Board of Supervisors
FL One-year data center moratorium
One-year data center moratorium (In force).
2026-06-01 in force
Santa Rosa County
county · City Council/Board of Supervisors
FL 12-month data center moratorium
12-month data center moratorium (in development) (Proposed).
2026-06-01 pending
Zephyrhills
city · City Council/Board of Supervisors
FL One-year data center moratorium
One-year data center moratorium (In force).
2026-06-01 in force
Marietta
city · City Council/Board of Supervisors
GA Six-month data center moratorium
Six-month data center moratorium (In force).
2026-07-01 in force
City of Bloomington
city · City Council/Board of Supervisors
IL Six-month data center moratorium
Six-month data center moratorium (In force).
2026-05-01 in force
City of Carbondale
city · City Council/Board of Supervisors
IL One-year data center moratorium
One-year data center moratorium (In force).
2026-06-01 in force
City of Effingham
city · City Council/Board of Supervisors
IL 12-month data center and crypto moratorium
12-month data center and crypto moratorium (In force).
2026 in force
City of West Chicago
city · City Council/Board of Supervisors
IL 180-day moratorium
180-day moratorium (Ordinance 26-O-0011) (In force).
2026-07-01 in force
Town of Normal
city · City Council/Board of Supervisors
IL Six-month data center moratorium
Six-month data center moratorium (In force).
2026-05-01 in force
Boone County
county · City Council/Board of Supervisors
IN One-year data center moratorium
One-year data center moratorium (Ordinance 2026-08) (In force).
2026-06-01 in force
Jeffersonville
city · City Council/Board of Supervisors
IN One-year data center moratorium
One-year data center moratorium (In force).
2026-08-01 in force
New Albany (Floyd County)
county · City Council/Board of Supervisors
IN One-year data center moratorium
One-year data center moratorium (In force).
2026-07-01 in force
City of Peosta
city · City Council/Board of Supervisors
IA Six-month data center moratorium
Six-month data center moratorium (In force).
2026-06-01 in force
Dubuque County
county · City Council/Board of Supervisors
IA 12-month data center moratorium
12-month data center moratorium (In force).
2026-05-01 in force
Madison County
county · City Council/Board of Supervisors
IA One-year data-processing-facility moratorium
One-year data-processing-facility moratorium (In force).
2026-06-01 in force
Plymouth County
county · City Council/Board of Supervisors
IA One-year revocable data center moratorium
One-year revocable data center moratorium (In force).
2026-06-01 in force
Sioux County
county · City Council/Board of Supervisors
IA One-year data center and BESS moratorium
One-year data center and BESS moratorium (In force).
2026-06-01 in force
Woodbury County
county · City Council/Board of Supervisors
IA 12-month data center moratorium
12-month data center moratorium (Resolution 14064) (In force).
2026-06-01 in force
Riley County
county · City Council/Board of Supervisors
KS Temporary data center moratorium
Temporary data center moratorium (In force).
2026-05-01 in force
Bell County
county · City Council/Board of Supervisors
KY Two-year data center moratorium
Two-year data center moratorium (In force).
2026-07-01 in force
Boyle County
county · City Council/Board of Supervisors
KY One-year data center moratorium
One-year data center moratorium (In force).
2026-06-01 in force
Bullitt County
county · City Council/Board of Supervisors
KY One-year data center moratorium
One-year data center moratorium (In force).
2026-07-01 in force
Cave City
city · City Council/Board of Supervisors
KY One-year data center moratorium
One-year data center moratorium (In force).
2026-06-01 in force
Daviess County
county · City Council/Board of Supervisors
KY 12-month data center moratorium
12-month data center moratorium (In force).
2026-05-01 in force
Edmonson County
county · City Council/Board of Supervisors
KY One-year moratorium
One-year moratorium (Ordinance EC26-18) (In force).
2026-06-01 in force
Louisville-Jefferson County Metro
county · City Council/Board of Supervisors
KY Six-month moratorium on new data centers
Six-month moratorium on new data centers (In force).
2026-08-01 in force
Nelson County
county · City Council/Board of Supervisors
KY One-year data center moratorium
One-year data center moratorium (In force).
2026-07-01 in force
Nicholasville
city · City Council/Board of Supervisors
KY Six-month data center moratorium
Six-month data center moratorium (In force).
2026-08-01 in force
Frederick County
county · Local government
MD Data center permitting pause through end of 2026
Data center permitting pause through end of 2026 (In force).
2026-07-01 in force
Washington County
county · City Council/Board of Supervisors
MD 12-month data center moratorium
12-month data center moratorium (In force).
2026-06-01 in force
Flint
city · City Council/Board of Supervisors
MI 12-month data center moratorium
12-month data center moratorium (In force).
2026-06-01 in force
Meridian Township
township · City Council/Board of Supervisors
MI Six-month data center and battery storage moratorium
Six-month data center and battery storage moratorium (In force).
2026-05-01 in force
Orion Township
township · City Council/Board of Supervisors
MI Six-month data center moratorium
Six-month data center moratorium (In force).
2026-06-01 in force
Waterford Township
township · City Council/Board of Supervisors
MI Temporary data center moratorium
Temporary data center moratorium (Ord. 2026-Z-003) (In force).
2026 in force
Minneapolis
city · City Council/Board of Supervisors
MN Six-month large data center moratorium
Six-month large data center moratorium (In force).
2026-05-01 in force
City of Jackson
city · City Council/Board of Supervisors
MS 183-day data center moratorium
183-day data center moratorium (In force).
2026-07-01 in force
City of Camdenton
city · City Council/Board of Supervisors
MO One-year data center moratorium
One-year data center moratorium (In force).
2026-05-01 in force
City of Neosho
city · City Council/Board of Supervisors
MO One-year data center moratorium
One-year data center moratorium (In force).
2026 in force
City of St. Peters
city · City Council/Board of Supervisors
MO One-year data center moratorium
One-year data center moratorium (In force).
2026-05-01 in force
Nodaway County
county · City Council/Board of Supervisors
MO Six-month data center moratorium
Six-month data center moratorium (Proposed).
2026-07-01 pending
Webster County
county · City Council/Board of Supervisors
MO Six-month moratorium
Six-month moratorium (data centers and energy facilities) (In force).
2026 in force
Cherry County
county · City Council/Board of Supervisors
NE Six-month conditional-use-permit moratorium
Six-month conditional-use-permit moratorium (In force).
2026 in force
Seward County
county · City Council/Board of Supervisors
NE One-year data center moratorium
One-year data center moratorium (In force).
2026-06-01 in force
Galloway Township
township · City Council/Board of Supervisors
NJ Proposed six-month data center moratorium
Proposed six-month data center moratorium (Proposed).
2026 pending
Sayreville
city · City Council/Board of Supervisors
NJ 18-month data center moratorium
18-month data center moratorium (In force).
2026-06-01 in force
Sierra County
county · City Council/Board of Supervisors
NM 18-month data center moratorium
18-month data center moratorium (In force).
2026 in force
Socorro County
county · City Council/Board of Supervisors
NM One-year data center moratorium
One-year data center moratorium (In force).
2026-06-01 in force
Town of East Fishkill
city · City Council/Board of Supervisors
NY Three-year data center moratorium
Three-year data center moratorium (In force).
2026-06-01 in force
Town of Lysander
city · City Council/Board of Supervisors
NY Six-month data center moratorium
Six-month data center moratorium (In force).
2026-05-01 in force
Town of Manlius
city · City Council/Board of Supervisors
NY 12-month data center and crypto moratorium
12-month data center and crypto moratorium (In force).
2026-07-01 in force
Town of Oneonta
city · City Council/Board of Supervisors
NY One-year data center and crypto moratorium
One-year data center and crypto moratorium (In force).
2026-05-01 in force
Town of Perth
city · City Council/Board of Supervisors
NY One-year data center moratorium
One-year data center moratorium (In force).
2025-06-01 in force
Town of Salina
city · City Council/Board of Supervisors
NY One-year data center moratorium
One-year data center moratorium (In force).
2026 in force
Town of Van Buren
city · City Council/Board of Supervisors
NY One-year data center moratorium
One-year data center moratorium (In force).
2026 in force
Alamance County
county · City Council/Board of Supervisors
NC Proposed large-data-center moratorium
Proposed large-data-center moratorium (Proposed).
2026-08-01 pending
Charlotte
city · City Council/Board of Supervisors
NC 150-day data center moratorium
150-day data center moratorium (In force).
2026-06-01 in force
City of Durham
city · City Council/Board of Supervisors
NC Data center moratorium
Data center moratorium (60-day, extended to 12 months) (In force).
2026-05-01 in force
City of Wilson
city · City Council/Board of Supervisors
NC One-year data center moratorium
One-year data center moratorium (In force).
2026-05-01 in force
Davie County
county · City Council/Board of Supervisors
NC One-year data center moratorium
One-year data center moratorium (In force).
2026-07-01 in force
Greensboro
city · City Council/Board of Supervisors
NC Proposed 120-day moratorium for 10 MW+ data centers
Proposed 120-day moratorium for 10 MW+ data centers (Proposed).
2026-08-01 pending
Town of Waxhaw
city · City Council/Board of Supervisors
NC 12-month data center moratorium
12-month data center moratorium (In force).
2026-08-01 in force
Yadkin County
county · City Council/Board of Supervisors
NC Proposed one-year data center moratorium
Proposed one-year data center moratorium (Proposed).
2026-08-01 pending
Barnes County
county · City Council/Board of Supervisors
ND Six-month data center moratorium
Six-month data center moratorium (In force).
2026-05-01 in force
Alliance
city · City Council/Board of Supervisors
OH 18-month data center moratorium
18-month data center moratorium (In force).
2026-07-01 in force
Cleveland
city · Local government
OH Three-month pause on standalone data centers
Three-month pause on standalone data centers (In force).
2026-07-01 in force
Conneaut
city · City Council/Board of Supervisors
OH One-year data center moratorium
One-year data center moratorium (failed) (Failed / vetoed).
2026-08-01 expired
Kent
city · City Council/Board of Supervisors
OH Temporary AI data center permit moratorium
Temporary AI data center permit moratorium (Ord. 2026-31) (In force).
2026 in force
Cherokee Nation (tribal and trust lands)
city · City Council/Board of Supervisors
OK Ban on hyperscale data centers
Ban on hyperscale data centers (In force).
2026-08-01 in force
City of Hillsboro
city · City Council/Board of Supervisors
OR 120-day data center land-use moratorium
120-day data center land-use moratorium (In force).
2026-07-01 in force
Bensalem Township
township · City Council/Board of Supervisors
PA 180-day data center curative-amendment moratorium
180-day data center curative-amendment moratorium (In force).
2026-06-01 in force
Charlestown
city · City Council/Board of Supervisors
RI Zoning ban on data centers and battery storage
Zoning ban on data centers and battery storage (In force).
2026-08-01 in force
Coffee County
county · City Council/Board of Supervisors
TN One-year data center moratorium
One-year data center moratorium (In force).
2026-06-01 in force
Knox County
county · City Council/Board of Supervisors
TN One-year data center moratorium
One-year data center moratorium (through June 30, 2027) (In force).
2026-07-01 in force
Knoxville
city · City Council/Board of Supervisors
TN One-year moratorium on large data centers
One-year moratorium on large data centers (10 MW+) (In force).
2026-07-01 in force
Hill County
county · City Council/Board of Supervisors
TX One-year data center moratorium
One-year data center moratorium (rescinded) (Failed / vetoed).
2026-06-01 expired
Cache County
county · City Council/Board of Supervisors
UT 180-day data center moratorium
180-day data center moratorium (In force).
2026-06-01 in force
Snohomish County
county · City Council/Board of Supervisors
WA Emergency six-month data center moratorium
Emergency six-month data center moratorium (In force).
2026-06-01 in force
City of Superior
city · City Council/Board of Supervisors
WI One-year data center moratorium
One-year data center moratorium (In force).
2026-06-01 in force
Village of Bellevue
city · City Council/Board of Supervisors
WI 12-month data center moratorium
12-month data center moratorium (In force).
2026-08-01 in force
Village of Cottage Grove
city · City Council/Board of Supervisors
WI 12-month data center moratorium
12-month data center moratorium (In force).
2026-07-01 in force
Village of Greenville (Outagamie County)
county · City Council/Board of Supervisors
WI One-year data center moratorium
One-year data center moratorium (10,000 sq ft+) (In force).
2026-07-01 in force
No matches.

Lawsuits

Filed or active litigation over data center projects, moratoriums, permits, and environmental review.

PartiesCourtCauseFiledStatusSources
DC BLOX
v. Metro Nashville (Metropolitan Government of Nashville and Davidson County)
DC BLOX alleges Nashville officials obstructed its proposed data center near Nashville Zoo by enacting a moratorium, pausing permit processing, and…
U.S. District Court for the Middle District of Tennessee zoning 2026-08-11 active
Sierra Club Wisconsin (represented by Midwest Environmental Advocates)
v. Wisconsin Department of Natural Resources (DNR)
Challenges DNR's decision to issue permits for Vantage Data Centers' $15B Port Washington campus without a full Environmental Impact Statement…
Ozaukee County Circuit Court, Wisconsin environmental 2026-07-10 active
Eagan Capital
v. City of Eagan, Minnesota
Challenges city's data center moratorium, alleging the city overstepped its authority by effectively regulating electricity consumption via…
Minnesota state court (venue not specified in coverage) zoning 2026-07-06 active
Preservation of Community Well-being Collective (residents of Saddlebrook Farms, Grayslake, Mundelein, Round Lake Park)
v. Village of Grayslake; T5 Data Centers; Alter Asset Management Company
Alleges the village obfuscated the nature of the 472-acre T5@Chicago development during approvals and proceeded without proper notice/public input.…
Illinois state court, Lake County (venue not explicitly confirmed in coverage) zoning 2026-08-06 active
Hexa Builders LLC; 3043 Williamstown Urban Renewal LLC
v. Mayor and Township Council of Monroe (Gloucester County, NJ); Planning Board of Monroe Township; township officials
Challenges Monroe Township's redevelopment-plan amendment and township-wide data center ban as arbitrary/capricious and violating equal protection,…
Superior Court of New Jersey, Gloucester County, Law Division
GLO-L-805-26
civil rights 2026-06-09 active
Imperial Valley Computer Manufacturing LLC (IVCM)
v. City of Imperial, CA; City Council member Katherine Burnworth; City Manager Dennis Morita; City Attorney Kathrine Turner; Planning Director Othon Mora
Civil-rights suit alleging coordinated administrative obstruction and retaliation to derail a permitted $10B AI data center; claims include failure…
U.S. District Court, Southern District of California
3:26-cv-00128
civil rights 2026-01-12 active
Imperial Valley Computer Manufacturing LLC (IVCM) / related developer
v. Imperial Irrigation District and associated water authorities
Developer sues seeking access to Colorado River water allocations for the Imperial Valley AI data center project amid broader water-rights disputes…
California / federal court (venue as reported) environmental 2026-06-15 active
Sierra Club
v. Imperial County, California
Challenges Imperial County's approval of the massive IVCM data center complex, alleging inadequate CEQA environmental review.
California state court (Imperial County venue presumed) environmental 2026-05-27 active
Lowell residents (including Alex Solange, Mary Wambui and others)
v. Markley Group; Massachusetts Department of Environmental Protection (permit referenced)
Massachusetts' first lawsuit against a data center; challenges MassDEP's permit for 8 additional diesel generators at Markley's Lowell facility,…
Massachusetts state court (Superior Court, Middlesex County presumed) environmental 2026-05-07 active
Lowell residents (class action)
v. Markley Group
Class-action nuisance/environmental suit filed against Markley Lowell data center over noise and generator pollution, separate from the MassDEP…
Massachusetts state court environmental 2026-07-19 active
Minnesota Center for Environmental Advocacy (MCEA)
v. City of Pine Island, Minnesota; Ryan Companies US, Inc.
Alleges the city's Alternative Urban Areawide Review (AUAR) for the Google-linked Project Skyway data center violated the Minnesota Environmental…
District Court of Goodhue County, Minnesota, First Judicial District
25-CV-25-2298
environmental 2025-10-16 TRO granted
Hobart, Indiana residents (incl. Soriano, Venegas/Koteles, Joseph Conn per garbled court coverage)
v. Hobart city officials; Hobart City Council; Hobart Commission; landowner/Amazon Data Services (referenced)
Sought to block a fill permit and earthmoving for a proposed 168-acre Amazon data center site, alleging local-regulation and due-process violations.…
Lake Superior Court, Indiana zoning 2025-12-10 dismissed
Coalition to Protect Prince William County / American Battlefield Trust-aligned groups
v. Prince William County Board of Supervisors (and, in a companion posture, the County itself co-litigated against the developer)
Challenged the county's rezoning approval for the ~2,100-acre Prince William Digital Gateway data center corridor near Manassas Battlefield.…
Virginia Circuit Court, Prince William County (with appeal to Court of Appeals of Virginia) zoning 2024-01-12 dismissed
Bristow-area residents
v. Prince William County / Devlin Technology Park developer
Residents sued to block the Devlin Technology Park data center project approval near Bristow, VA.
Virginia Circuit Court, Prince William County zoning 2024-01-01 active
Citizens for Fauquier County
v. Town of Warrenton, VA; Amazon Data Services
Challenges Warrenton's approval of an Amazon data center, alleging improper zoning board process. Court of Appeals of Virginia sided with the…
Virginia Circuit Court (Fauquier), with appeal to Court of Appeals of Virginia zoning 2023-12-13 active
Louisa County, VA homeowner
v. Amazon Data Services
Homeowner alleges brown well water, dust, and constant loud noise caused by nearby Amazon data center construction.
Virginia Circuit Court, Louisa County environmental 2026-07-28 active
American Battlefield Trust / Manassas Battlefield preservation coalition
v. Prince William County, VA (rezoning approvals)
Virginia Court of Appeals blocked approvals covering roughly 37 data centers near Manassas Battlefield, a decision closely tied to the broader…
Court of Appeals of Virginia zoning 2026-04-07 preliminary injunction
Chesterfield County, VA residents/opposition group
v. Chesterfield County Board of Supervisors
Lawsuit opposing a data center project (linked to Meta-area development) alleges numerous Virginia Freedom of Information Act (Sunshine Law)…
Virginia Circuit Court, Chesterfield County civil rights 2026-04-01 active
Coweta County, Georgia residents
v. Project Sail data center developer / Coweta County
Residents sue to block the Project Sail data center development in Coweta County, GA.
Georgia state court (Coweta County) zoning 2026-05-11 active
Community groups (Stokes County, NC)
v. Stokes County / data center developer
Community groups sue over a planned data center in Stokes County, North Carolina.
North Carolina state court zoning 2026-03-13 active
Joliet, IL residents/opposition group
v. City of Joliet, Illinois
Lawsuit challenges the zoning and approval process for a proposed Joliet, IL data center.
Illinois state court (Will County) zoning 2026-05-26 active
Fort Meade, FL residents
v. City of Fort Meade, Florida
Residents sue the city to block a hyperscale data center land deal, alleging governance/procedural improprieties.
Florida state court (Polk County) civil rights 2026-06-23 active
Franklin Coalition
v. Data center developers (Franklin/Simpson County, KY area)
Franklin Coalition sues data center developers challenging the local approval process.
Kentucky state court zoning 2026-04-15 active
Michigan residents (Dowagiac-area data center neighbors)
v. Data center operator (unnamed in initial coverage)
Residents sue over constant 24/7 noise emitted by a data center, citing health concerns; a related class action was filed in Dowagiac, MI.
Michigan state court environmental 2026-05-29 active
Wisconsin residents
v. Microsoft Corporation
Residents sue Microsoft over noise caused by a new data center; a related public-records suit sought disclosure of projected water use by…
Wisconsin state court environmental 2026-03-01 active
Southaven, MS-area residents (class action)
v. xAI; SpaceX
Class action alleges data center 'nuisance' (noise/pollution) from co-located xAI/SpaceX facility in Southaven, Mississippi.
Federal court (N.D. Mississippi, per Reuters coverage) environmental 2026-06-09 active
NAACP (Memphis chapter / national)
v. xAI (Colossus / Colossus 2 gas turbines, Memphis, TN)
NAACP sued over unpermitted gas turbines at xAI's Memphis Colossus data center under the Clean Air Act. The Trump administration/DOJ moved June 2026…
Federal court (W.D. Tennessee, per reporting) environmental 2025-06-01 active
Sierra Club Wisconsin Chapter; Clean Wisconsin; Port Washington residents
v. Wisconsin DNR (air permit for Vantage Data Centers)
Environmental groups formally challenge/comment against air quality permits for the Port Washington data center, separate from the broader EIS…
Wisconsin DNR administrative process / Ozaukee County Circuit Court environmental 2026-06-01 active
Environmental groups (Georgia)
v. Georgia Environmental Protection Division / Plant Bowen gas turbine operators (data center-linked power)
Environmental groups challenge the air permit for gas turbines at Plant Bowen tied to Georgia data center power buildout; separate reporting covers…
Georgia state administrative/court proceeding environmental 2026-03-02 active
Rise St. James; allied environmental groups
v. Louisiana Department of Environmental Quality; Meta (Hyperion data center-linked gas power)
Challenge to air pollution permitting tied to Meta's Hyperion data center gas-power buildout in Louisiana; judge dismissed the challenge to Meta's…
Louisiana state court / administrative appeal environmental 2026-02-01 dismissed
Earthjustice and allied groups
v. Formosa Plastics; Louisiana Department of Environmental Quality
Groups sue over Formosa Plastics' permit extensions in Louisiana's industrial corridor, part of the broader wave of air-permit litigation tied to…
Louisiana state/administrative appeal environmental 2026-01-15 active
Data center opposition group
v. Missouri city government; proposed data center developer
Opposition group sues a Missouri city and the proposed data center developer over project approval.
Missouri state court zoning 2026-04-20 active
New Jersey neighbors (unspecified township)
v. Data center operator (unnamed)
Neighbors sue over persistent humming noise emitted by a nearby New Jersey data center.
New Jersey state court environmental 2026-04-01 active
Environmental/community groups (North Carolina)
v. Amazon; Duke Energy
Amazon-Duke Energy diesel backup power plans for an NC data center face legal pushback from environmental and community advocates over permitting.
North Carolina state administrative/court proceeding environmental 2026-08-01 active
Federal Energy Regulatory Commission (Commission-initiated)
v. PJM Interconnection; MISO; SPP; CAISO; ISO-NE; NYISO (and associated transmission owners)
FERC issued Section 206 show-cause orders directing all six RTOs/ISOs to justify or reform large-load/co-location interconnection rules for data…
Federal Energy Regulatory Commission (administrative proceeding, not a court)
RM26-4-000
regulatory 2026-06-18 show cause
Data center developer
v. Chatham County, North Carolina
Developer sues Chatham County over its data center moratorium/restrictive ordinance, alleging harm to a planned project.
North Carolina state court zoning 2026-05-01 active
Data center developer
v. Hill County, Texas
Developer filed a $100M lawsuit against Hill County, Texas after the county rescinded prior data center approvals/incentives amid moratorium activity.
Texas state court contract 2026-06-01 active
Citizens for Fauquier County
v. Warrenton, VA Board of Zoning Appeals
CFFC's zoning board appeal on the Amazon data center was rejected, which the group alleged occurred illegally, leading to further litigation (see…
Virginia Circuit Court, Fauquier County zoning 2023-08-01 dismissed
Loudoun County, VA homeowners
v. Dominion Energy; Virginia State Corporation Commission (as regulator)
Homeowners challenged Dominion Energy's data-center-driven transmission line siting; reporting indicates homeowners appear to have lost before the…
Virginia State Corporation Commission / Virginia courts zoning 2026-07-01 dismissed
No matches.

Federal actions

FERC dockets, congressional bills, and executive actions affecting large-load interconnection and data center power.

AuthorityDocket / billTitleDateStatusSources
FERC RM26-4-000
Show-Cause Orders to PJM, MISO, SPP, CAISO, ISO-NE, and NYISO on Large-Load/Co-Location Interconnection Rules
FERC issued Section 206 show-cause orders directing all six RTOs/ISOs (PJM, MISO, SPP, CAISO, ISO-NE, NYISO) to justify or reform their large-load and…
2026-06-18 show cause
FERC EL24-something (Talen-PJM-Amazon Interconnection Service Agreement)
FERC Rejects Interconnection Service Agreement for Talen-Amazon Susquehanna Nuclear Data Center Co-Location
FERC rejected a proposed interconnection service agreement that would have allowed Amazon Web Services' data center to draw expanded co-located load directly…
2024-11-01 passed
FERC EL26-63 (PJM co-located load complaint)
Constellation FERC Complaint Seeking PJM Rules for Data Center Co-Located Load
Constellation Energy filed a FERC complaint asking for clear PJM tariff rules governing co-located data center load at power plants (following the…
2025-01-01 pending
FERC Related to RM26-4-000 / PJM market monitor filings
PJM Market Monitor: No More Data Centers Unless They Can Be Reliably Served
PJM's Independent Market Monitor raised reliability concerns before FERC, arguing no additional data center interconnections should proceed unless reliable…
2026-07-27 pending
FERC ER25-/EL25- PJM co-located generation tariff compliance
FERC Orders PJM to Reform Tariff for Co-Located Generation and Load
FERC directed PJM to file tariff revisions establishing clear rules for co-located generation and large-load service, building on the agency's prior 2025…
2026-01-15 passed
DOE DOE directive to FERC re large-load interconnection
DOE Directs FERC to Act on Large-Load Interconnection Rulemaking
The Department of Energy directed FERC to act on a large-load interconnection rulemaking affecting data centers, with FERC subsequently committing to June…
2026-04-01 passed
DOE 2026 DOE Section 202(c) Emergency Orders
2026 DOE Section 202(c) Emergency Grid Orders
DOE issued a series of 2026 Federal Power Act Section 202(c) emergency orders addressing grid reliability strain, several tied to regions facing rapid data…
2026-01-01 passed
DOE National Transmission Needs Study (2026 Supplement)
DOE National Transmission Needs Study: Supplemental Material (July 2026)
DOE released supplemental material to its National Transmission Needs Study identifying transmission constraints and expansion needs nationally, explicitly…
2026-07-01 pending
EPA EPA AI data center regulatory policy shift
EPA Steps Back from AI Data Center Regulation, Hands Oversight to States/Communities
EPA announced it is stepping back from direct regulation of AI data center emissions and infrastructure, deferring to states and local communities to develop…
2026-06-01 passed
CEQ Executive Order 14318
Executive Order 14318: Accelerating Federal Permitting of Data Center Infrastructure
President Trump signed EO 14318 directing federal agencies (via CEQ/NEPA processes) to accelerate permitting for data center infrastructure projects,…
2025-07-01 passed
Congress S.3585
DATA Act of 2026
Sponsored by Sen. Tom Cotton (R-AR); would amend the Federal Power Act to exempt consumer-regulated (co-op/municipal) electric utilities from federal…
2026-01-07 pending
Congress S.4806
POWER Up Act
Sponsored by Sen. Cynthia Lummis (R-WY); would modernize rules for high-power grid connections, targeting faster and clearer processes for large electricity…
2026-06-17 pending
Congress S.3682
Power for the People Act of 2026
Sponsored by Sen. Chris Van Hollen (D-MD); would promote creation of data-center-specific load queues and rate classes to mitigate the cost impact of data…
2026-01-15 pending
Congress H.R.8241
Power for the People Act of 2026 (House companion)
House companion to S.3682, promoting data-center-specific rate classes and load queues to protect residential and small-business ratepayers from…
2026-01-15 pending
Congress H.R.8033
No Harm Data Centers Act
Sponsored by Rep. Greg Landsman (D-OH); would ensure American families are protected from the impacts of data centers on the electric grid. Referred to House…
2026-03-20 pending
Congress H.R.9340
Ratepayer Protection Act
Sponsored by Rep. Gabe Evans (R-CO); would amend the Public Utility Regulatory Policies Act of 1978 to establish a federal standard requiring recovery of the…
2026-06-18 pending
Congress S.3852
GRID Act
Sponsored by Sen. Josh Hawley (R-MO); would impose requirements on data centers to ensure prioritization of residential ratepayers over large-load commercial…
2026-02-11 pending
Congress H.R.9825
Data Center Water and Energy Transparency Act of 2026
Sponsored by Rep. Lauren Underwood (D-IL); would require disclosure/transparency of data center water and energy usage. Referred to House Energy and Commerce…
2026-07-22 pending
Congress S.4214
Artificial Intelligence Data Center Moratorium Act
Sponsored by Sen. Bernie Sanders (I-VT); would impose a federal moratorium on new large AI data center construction/permitting pending further study.…
2026-03-25 pending
Congress H.R.9442
Artificial Intelligence Infrastructure-related bill (119th Congress)
A 119th Congress House bill addressing AI infrastructure siting/permitting; full text available via Congress.gov. Included in the wider 2026 wave of data…
2026-07-01 pending
Congress H.R.8488
AI Data Center Site Selection Transparency Act of 2026
House bill requiring greater transparency in AI data center site-selection decisions, including disclosure of incentive negotiations and community-impact…
2026-02-01 pending
Congress H.R.8037
Protect American AI Act of 2026
House bill framed around protecting domestic AI infrastructure development and competitiveness; text available via GovInfo. Part of the broader 119th Congress…
2026-02-01 pending
Congress S.5054
Data Center Tax Accountability and Disclosure Act of 2026
Senate bill requiring disclosure and accountability around tax incentives granted to data center developers, part of the 2026 legislative wave addressing data…
2026-07-15 pending
No matches.

Utility actions

Utility and public-utility-commission dockets, tariff filings, and statements creating data center rate classes, cost-allocation rules, and interconnection conditions.

UtilityStateDocketTypeFiledActionStatusSources
Seattle City Light
WA tariff 2026-06-12 Seattle City Light proposed a New Large Data Center Load Policy creating a new rate class for data centers requesting new or expanded electric service of 10 MVA or more. The policy would require cost-based rates, customer responsibility for infrastructure and related costs, service through a queue…
New large data centers would no longer qualify for general service rates and would pay rates reflecting the incremental cost of procuring and delivering power. Developers would be…
pending
Baltimore Gas and Electric Company (BGE)
Exelon Corporation (NYSE: EXC)
MD statement 2025-02-20 BGE submitted a favorable-with-amendments position statement supporting Maryland House Bill 900, which would require electric companies to submit PSC-approved data-center rate schedules. BGE requested amendments concerning load-ramp periods, risk-mitigation measures such as CIAC payments, letters…
Data centers would be subject to specific rate schedules, contract requirements, and financial obligations intended to protect existing utility customers if projected demand is not…
pending
Maryland electric utilities (statewide - Large Load Tariff Workgroup)
MD PC 72 Large Load Tariff Workgroup tariff 2026-03-03 House Bill 1532 proposes lowering the monthly maximum demand threshold for customers required to take service under a new large-load tariff from 100 MW to 25 MW. The proposal includes requirements such as a load ramp period, minimum service term, collateral requirement, and exit fee.
Data centers with monthly demand of 25 MW or more would be subject to the proposed large-load tariff requirements, including potential minimum service terms, collateral obligations, and…
pending
Potomac Edison
MD RM 93 tariff 2026-01-21 The Maryland Office of People’s Counsel filed comments on the Maryland Public Service Commission’s proposed Large Load Tariff Workgroup regulations under Section 4-212 of the Public Utilities Article. The comments request revisions concerning infrastructure-cost allocation, electric and…
The proposed protections would require large-load customers, including data centers, to bear infrastructure buildout costs caused by their interconnection and provide contracts and…
contested
Maryland electric utilities (statewide - HB 1532)
MD other HB 1532 proposes lowering the applicability threshold for Maryland’s large-load tariff from more than 100 MW of monthly maximum demand at a single location to 25 MW. The testimony supports requiring more large-load users, including data centers, to contribute to the costs they create.
Data centers with monthly maximum demand of 25 MW or more at a single location would fall under the proposed large-load tariff. This could require them to contribute to grid-related costs…
pending
Pennsylvania electric distribution companies (statewide model tariff)
PA M-2025-3054271 tariff 2026-04-30 The Pennsylvania Public Utility Commission voted 5-0 to adopt a modified final order establishing a model Large Load Tariff Framework for customers exceeding 50 MW individually or 100 MW in aggregate, including data centers. The framework addresses cost responsibility, financial assurances,…
Data centers would be responsible for utility upgrades required for interconnection and would need to provide deposits, collateral, or other financial assurances covering infrastructure…
approved
PPL Electric Utilities Corporation
PA R-2025-3057164 rate case The Pennsylvania Public Utility Commission voted 5-0 to modify and approve a Joint Petition for Settlement resolving PPL Electric’s base rate proceeding. The settlement includes tariff provisions for certain large-load customers, including data centers, with long-term service commitments, minimum…
Data centers and other high-demand facilities may be subject to long-term service commitments and minimum demand guarantees. The provisions are intended to align large-load customer costs…
approved
Duquesne Light Co.; FirstEnergy Pennsylvania; PECO Energy Company; PPL Electric
PA M-2025-3054271 other 2025-03-27 The Pennsylvania Public Utility Commission approved convening an en banc hearing to examine interconnection and tariff issues for large-load customers, including data centers. The proceeding is considering financial security, construction-cost contributions, contract terms, study fees and timing,…
Data center developers and other large-load customers may face future requirements concerning financial security, construction-cost contributions, minimum contract terms,…
pending
Pennsylvania electric distribution companies (statewide model tariff)
PA M-2025-3054271 other 2025-11-06 The Pennsylvania Public Utility Commission issued a Tentative Order proposing a statewide model tariff for connecting large electric customers, including hyperscale data centers, to the grid and allocating related costs. The PUC voted 3-2 to advance the review and adopted the Tentative Order.
Data-center customers would be expected to contribute toward interconnection and related system costs, provide tiered collateral, and accept minimum contract terms. The proposal is…
pending
Each electric public utility in New Jersey
NJ tariff A796 would require each New Jersey electric public utility to file an application with the Board of Public Utilities within 180 days to establish a tariff for serving large load data centers. The tariff must protect non-data-center ratepayers from costs caused by data-center demand and incentivize…
Beginning one year after the act takes effect, the tariff would apply to every qualifying large load data center in a utility’s service area. The BPU could establish rates and conditions…
pending
New Jersey electric public utilities (statewide - A2770)
NJ tariff Assembly Bill A2770 would require electric public utilities serving large load data centers to file updated tariffs with the New Jersey Board of Public Utilities, including a surcharge during periods of peak electrical-grid demand. Surcharge revenues would be deposited into a newly established…
Large load data centers with actual or projected monthly demand of at least 50 megawatts would be subject to a Board-approved peak-demand surcharge. The surcharge revenues would fund…
pending
Alliant Energy
WI 6680-TE-115 special contract 2025-04 Alliant Energy filed an application in April 2025 for approval of an Electric Service Agreement under its existing Individual Contract Rate Tariff to serve a data center in Beaver Dam. On May 7, 2026, the Public Service Commission of Wisconsin approved the agreement with modifications, including…
The Beaver Dam data center must operate under the modified Electric Service Agreement, including enhanced termination charges, reporting and financial safeguards, and contributions to…
approved
We Energies
WI 6630-TE-113 tariff 2025-03 We Energies filed an application in March 2025 seeking approval of Very Large Customer and Bespoke Resources Tariffs for large data center customers. On April 24, 2026, the Public Service Commission of Wisconsin modified and approved the tariffs, including a 15-year minimum initial term, a 100 MW…
Data centers covered by the Very Large Customer tariff must pay 100% of their costs under the approved Full-Benefits resource model. The tariff applies to customers with an energy demand…
approved
Xcel Energy
MN 25-289 tariff The Commission defined “very large customers” for Xcel Energy’s tariffs as new loads of 100 MW or greater. The class also includes new customers with loads of at least 20 MW but less than 100 MW if they are system intensive and require significant system modifications or other expenditures before…
Data center developers with loads of 100 MW or more, or with loads between 20 MW and less than 100 MW that are system intensive, would fall within this very large customer tariff class.…
approved
Evergy Metro, Inc. d/b/a Evergy Missouri Metro and Evergy Missouri West, Inc. d/b/a Evergy Missouri West
MO EO-2025-0154 tariff 2025-10-29 Evergy sought approval of new and modified tariffs for large-load customers, including customers with annual peak demand of at least 100 MW, through a proposed Large Load Power Service tariff. The Data Center Coalition requested approval of a non-unanimous stipulation and rejection of the Missouri…
The proposed stipulation would provide large-load customers with a 12-year contract term, an optional five-year load ramp, an 80% minimum billing demand, collateral requirements, exit…
contested
Ohio Power Company
OH 24-508-EL-ATA tariff 2025-07-09 The Commission approved, by a 5-0 vote, a proposed opinion and order concerning Ohio Power Company. The order addresses central Ohio’s rapid data center growth while seeking to protect ratepayers from increased system-load and potential stranded costs.
The order supports new economic development associated with data center growth, while emphasizing reliability, price stability, dependable electric service, least-cost planning, and…
approved
Union Electric Company d/b/a Ameren Missouri
Ameren Corporation (NYSE: AEE)
MO ER-2026-0291 rate case 2026-06-26 Ameren Missouri filed a general rate increase request seeking approximately $343 million in additional annual electric base-rate revenues. The filing proposes a new 14(M) Large Load Customer Service classification under the Powering Missouri Growth Plan.
New data centers would receive no electric-rate discounts and would be required to pay 100% of grid-connection infrastructure costs upfront. Ameren Missouri states that commitments from…
pending
Union Electric Company d/b/a Ameren Missouri
MO ET-2025-0184 tariff 2025-05-14 Ameren Missouri proposed a Large Load Customer Rate Plan, including modifications to its Large Primary Service tariff, four new tariff riders, and changes to the Fuel Adjustment Clause. The proposed subclass would apply to customers with expected or actual demand of at least 100 MW taking…
Data centers meeting the 100 MW demand and above-115-kV transmission-service thresholds would be eligible for the proposed subclass and revised tariff structure. The proposal includes…
contested
Consumers Energy
MI Case No. U-21859 tariff 2025-02 The Michigan Public Service Commission approved Consumers Energy’s application to amend its Rate GPD tariff by establishing terms and conditions for data centers and other similarly energy-intensive, very large electric customers.
The tariff applies to customers with a minimum service threshold of 100 MW, including aggregated loads consisting of individual sites of at least 20 MW with the same common owner. Covered…
approved
DTE Electric Co.
MI Case No. U-21990 special contract 2025-12-18 The Michigan Public Service Commission conditionally approved DTE Electric Co.’s application for special contracts to supply power to a 1,383-megawatt data center in Saline Township, Washtenaw County. The approval requires DTE to bear unrecovered costs and prioritize reducing or interrupting the…
The contracts require a minimum 19-year term, minimum billing demand equal to 80% of contracted electricity use, and a termination payment of up to 10 years of minimum billing demand if…
approved
Kentucky Power Company
KY Case No. 2022-00387 special contract 2023-08-28 The Kentucky Public Service Commission rejected a proposed special contract between Kentucky Power Company and Ebon International, LLC, a cryptocurrency project, because the contract did not properly protect customers from power costs.
Special contracts for cryptocurrency or other large-load facilities may be denied unless they adequately protect utility customers from the facilities’ power costs.
denied
New York investor-owned utilities (statewide large-load proceeding)
NY Case 26-E-0045 other 2026-05-13 The City of New York filed initial comments in the New York Public Service Commission proceeding on large-load interconnection reforms. The comments recommended financial and reporting requirements, binding load forecasts, development milestones, financial security and withdrawal penalties,…
Data centers and similar large loads may need to demonstrate project readiness through permits, financing, site control, design plans, or construction and materials contracts before…
pending
New York investor-owned utilities (Energize NY Development initiative)
NY tariff The New York State Public Service Commission instituted a proceeding to advance Governor Hochul’s Energize NY Development initiative. The proceeding will review interconnection processes, cost-allocation mechanisms, and tariff structures for integrating large loads into New York’s transmission and…
Data centers and other large energy users may face revised interconnection rules, cost-allocation structures, and tariffs, potentially requiring them to pay for grid upgrades and other…
pending
Virginia Electric & Power Co.
VA PUR-2025-00058 tariff 2025-11-25 The Virginia State Corporation Commission approved a dedicated rate class for customers with demands of 25 MW or greater in Application of Va. Elec. & Power Co., Case No. PUR-2025-00058.
Data center and other large-load customers with demands of 25 MW or greater may be placed in a dedicated rate class. The specific rates, charges, and interconnection requirements were not…
approved
Central Hudson Gas & Electric Corporation; Consolidated Edison Company of New York, Inc.; New York State Electric & Gas Corporation; Niagara Mohawk Power Corporation d/b/a National Grid; Orange & Rockland Utilities, Inc.; Rochester Gas and Electric Corporation
NY Case No. 26-E-0045 other 2026-06-15 The Joint Utilities filed reply comments addressing planning, interconnection, and cost-allocation frameworks for large electric loads. They supported standardized tariff terms, beneficiary-pays cost allocation, meaningful financial commitments, NYISO-led coordination, and forecasting that…
Data-center developers may face standardized interconnection and tariff requirements, financial commitments such as collateral or minimum bills, long-term contracts, exit fees,…
pending
Niagara Mohawk Power Corporation d/b/a National Grid
NY Case 26-E-0045 other 2026-05-13 National Grid filed comments with the New York Public Service Commission in response to the February 12, 2026 Order Instituting Proceeding and Soliciting Comments in Case 26-E-0045. The comments propose reforms for large-load interconnection and cost allocation, including upfront customer funding,…
Data center developers could benefit from more predictable interconnection planning, standardized designs, digital application tools, and potentially faster connections through…
pending
National Grid Ventures
NY Case 26-E-0045 tariff 2026-05-13 National Grid Ventures filed comments in Case 26-E-0045 regarding interconnection reforms for large loads. The comments propose stricter requirements, including demand ratchets, long-term contract commitments, collateral, dedicated rate classes, cost responsibility for sole-use upgrades,…
Data centers and similar large-load facilities could be required to provide collateral, sign long-term contracts, pay minimum bills based on contract demand, fund sole-use interconnection…
pending
Consolidated Edison Company of New York, Inc. (Con Edison) and Orange and Rockland Utilities, Inc. (O&R)
NY Case No. 26-E-0045 other 2026-05-13 Con Edison and O&R filed comments responding to the New York Public Service Commission’s request for comments on a regulatory framework for large-load customers and interconnection reforms. They proposed measures including large-load deposits, withdrawal or modification fees, minimum billing or…
Data center developers could face more detailed load-forecasting requirements, deposits, minimum billing or fixed charges, and enhanced financial-security obligations. They may also be…
pending
New York Power Authority (NYPA)
NY Case 26-E-0045 other 2026-05-13 NYPA submitted comments to the New York Public Service Commission on large-load interconnection. It recommended standardized requirements, realistic study assumptions, beneficiary-pays cost allocation, collateral and project-development commitments, enhanced modeling, cluster studies, grid…
Large data-center loads seeking interconnection could face clearer size thresholds, detailed load-characteristic reporting, operational requirements, project milestones, deposits,…
pending
Duke Energy Carolinas, LLC
NC tariff Duke Energy Carolinas offers an optional High Load Factor tariff for large customers with a minimum contract demand of 1 MW, a one-year contract term, and minimum billing demand equal to 75% of contract capacity. Its service regulations authorize performance and credit provisions for customers…
Data centers and other large high-load-factor customers may use the tariff, but it does not include financial-assurance or contribution provisions. The tariff includes an early termination…
approved
Duke Energy
NC statement 2026-07-23 Duke Energy joined the federal administration’s Ratepayer Protection Pledge. North Carolina officials are urging Duke Energy to make the pledge’s commitments legally binding before the North Carolina Utilities Commission, including separate rate structures and customer responsibility for…
Data centers and other large-load customers would be expected to pay for the generation, electricity, and power-delivery infrastructure needed to serve them, including resources they…
contested
Georgia Power
GA 55378 tariff 2025-01-23 The Georgia Public Service Commission unanimously approved a new Georgia Power rule for customers using more than 100 megawatts. The rule allows recovery of site-specific and upstream generation, transmission, and distribution costs, permits contracts of up to 15 years, establishes minimum billing…
Data centers exceeding 100 MW may be required to pay costs for electricity acquisition and infrastructure built specifically for their needs. They may also face longer contract terms,…
approved
Georgia Power
GA rate case 2025-12-19 The Georgia Public Service Commission approved an agreement between its Public Interest Advocacy Staff and Georgia Power certifying construction of 9,985 MW of new energy generation, approximately 80% of which is expected to serve data centers. Georgia Power agreed to financially backstop…
Data centers are expected to account for approximately 80% of the approved new generation. Georgia Power must absorb associated costs through 2031 if projected data-center contracts do not…
approved
Georgia Power Company
GA 55378 other 2024-11-18 Georgia Power Company filed a Large Load Economic Development Report for Q3 2024 PD in parent docket 55378.
The filing does not state a specific impact on data-center developers or operators, including impacts related to large-load tariffs, interconnection, cost allocation, or data-center…
pending
Virginia Electric and Power Company (VEPCO)
Dominion Energy
VA IRP Dominion’s 2024 Integrated Resource Plan highlighted a modeled VCEA-compliance case with no new gas and no fossil-fuel retirements by 2045. Dominion stated that the case was infeasible because of the unrealistic amount of imports and renewable construction required, creating reliability concerns.
Dominion forecast data-center peak demand reaching 9 GW within the next 10 years, contributing to a 25% increase above current total system peak. This growth creates concerns about the…
contested
Kentucky Utilities Company and Louisville Gas and Electric Company
KY Case No. 2025-00045 tariff 2025-09-17 The Companies filed a post-hearing reply brief requesting approval without modification of a stipulation supporting generation resources including the Brown 12 and Mill Creek 6 natural-gas combined-cycle units. The filing addressed a forecast including 1,750 MW of data-center load by 2031 and…
Approval would allow the Companies to advance generation resources intended to serve projected data-center and other large-load growth, subject to Commission oversight and prudence review.…
contested
Liberty Utilities
MO tariff 2025 Liberty Utilities’ large-load tariff case is currently in progress. The tariff is required under Senate Bill 4 to reflect large-load customers’ share of costs and prevent other customers from being charged unjust or unreasonable costs associated with serving them.
Data centers served by Liberty Utilities would be subject to large-load rates intended to make them pay their share of costs. The provisions are designed to protect residential and…
pending
Public Service Company of Oklahoma (PSO)
OK 124090 complaint 2026-05-22 Rep. Tom Gann appealed the Oklahoma Corporation Commission’s preapproval of approximately $1.3 billion in new PSO generation and storage capacity intended in part to serve proposed large-load customers, including data centers in eastern Oklahoma. AARP and the Oklahoma Industrial Energy Consumers…
The preapproval could allow PSO to develop generation and storage capacity for proposed eastern Oklahoma data centers. The appeal challenges whether residential customers could bear costs…
contested
Oklahoma investor-owned utilities (statewide - Data Center Customer Ratepayer Protection Act)
OK tariff The Oklahoma Corporation Commission regulates qualifying “Large Load Customers” under the Data Center Customer Ratepayer Protection Act of 2026, codified at 17 O.S. §§ 900, 906. The act applies to new data centers, cryptocurrency mining operations, and artificial-intelligence computing facilities…
Data center and other qualifying large-load developers adding 75 megawatts or more must comply with the act. Certain land purchasers must provide certified-mail notice to the Oklahoma…
pending
ERCOT transmission/distribution utilities (statewide PURA §37.0561 rulemaking)
TX Project No. 58481 other 2025-07-31 The Public Utility Commission of Texas opened a rulemaking to implement large-load interconnection standards under PURA §37.0561. The proceeding addresses interconnection processes, agreements, fees, security postings, planning-guide revisions, batch studies, and related cost and reliability issues.
The proposed standards would affect how large loads, including data centers, interconnect and obtain service in Texas, including requirements for studies, security postings, and related…
pending
El Paso Electric
TX rate case El Paso Electric is seeking Public Utility Commission of Texas approval to amend its existing Economic Development Rate for data centers. The El Paso City Council authorized intervention, including retaining legal counsel and technical experts, to evaluate whether the proposed changes comply with…
The proposed changes would establish or modify the rate structure applicable to data centers and other large-load customers. The City will advocate for protections to prevent costs…
pending
Austin Energy
TX tariff 2025-12-23 The City’s memorandum describes Austin Energy’s implementation of Texas Senate Bill 6 for data centers and other large loads. Loads exceeding 75 MW require a full interconnection study, must fund identified interconnection and transmission upgrades, and may be subject to remote curtailment…
Data centers requesting more than 75 MW must complete a full interconnection study and cannot bring their entire load online until required system upgrades are completed. Projects may also…
approved
Austin Energy
TX other 2025-10-07 At an Austin Energy Utility Oversight Committee meeting, Interim General Manager Stewart Riley presented an overview of ERCOT large-load growth and Austin Energy’s challenges in serving large customers, including data centers and industrial facilities. The discussion addressed capacity…
Data-center developers may face transmission and generation capacity constraints, with infrastructure and equipment deployment potentially taking approximately 3, 5 years while customers…
pending
Pacific Gas and Electric Company (PG&E); Southern California Edison Company (SCE); San Diego Gas & Electric Company (SDG&E); Bear Valley Electric Service, Inc.; Liberty Utilities (CalPeco Electric) LLC; PacifiCorp
CA Rulemaking 26-04-xxx other 2026-04 The California Public Utilities Commission proposed instituting a rulemaking on California Advanced Electric Rate Design. The proceeding will consider rate designs and tariffs for data centers and other large-load customers, including measures to prevent stranded costs and cost shifting and to…
Data-center developers may face new or revised tariffs, service terms, demand charges, and cost-allocation requirements. The proceeding may also establish rate signals for large-load…
pending
Southern California Edison Company (U 338-E)
CA Application 24-06-014; Application 24-12-008 tariff 2024-06-26 Southern California Edison Company filed an application for approval of a Large Power Dynamic Pricing Rate and a consolidated application for approval of Marginal Cost-Based Dynamic Pricing Rates in compliance with Decision 22-10-022 and Load Management Standards.
The filing does not specifically mention data centers or identify impacts on data-center developers or operators. It concerns dynamic pricing rates for large-power and marginal-cost-based…
pending
Arizona Public Service Company (APS); Salt River Project (SRP); Tucson Electric Power (TEP)/Unisource Electric (UNS)
AZ E-00000A-25-0069 other 2026-04-16 At an Arizona Corporation Commission workshop, APS, SRP, and TEP/UNS reported on prospective large-load and data-center demand, queue processes, and capacity constraints. Proposed policies included an extra high load factor rate, “bring your own power” requirements, and standard contracts…
Data-center developers may face utility queue screening, eligibility requirements for large-load rates, direct responsibility for new generation and infrastructure costs, and up-front…
pending
Tucson Electric Power (TEP); Salt River Project (SRP); Arizona Public Service (APS)
AZ E-00000A-25-0069 tariff 2026-04-16 The Arizona Corporation Commission hosted a Large Load Users Development Workshop addressing the integration of data centers and other large load customers into the electric grid. The workshop discussed utility-specific extra-high-load tariffs and energy service agreements, including direct…
Data centers and other large load users are expected to pay the costs they cause so existing ratepayers do not bear them. Potential protections include longer contract terms, minimum…
pending
Arizona Public Service Company (APS)
AZ rate case The APS rate case addressed proposed changes to the Extra High Load Factor tariff for large-load users, including manufacturing companies and data centers, and APS’s request to implement a Formula Rate Adjustment Mechanism (FRAM). The Administrative Law Judge is expected to issue a Recommended…
Changes to the Extra High Load Factor could alter rate treatment for data centers and other large-load users. FRAM authorization could affect how APS rates are adjusted, but the specific…
pending
Tucson Electric Power Company (TEP)
AZ E-01933A-25-0187 special contract 2025-12-03 The Arizona Corporation Commission voted 4-1 to approve a 10-year Energy Supply Agreement, also described as a Special Contract, between TEP and Humphrey’s Peak Power LLC for a planned data center campus in Pima County. The agreement includes minimum monthly billing, an 18-month gradual load…
The agreement requires minimum billing payments and termination fees and makes the developer financially responsible for infrastructure serving the data center campus. These provisions are…
approved
Tri-State G&T
WY tariff 2026-03-26 Tri-State refiled its High Impact Load Tariff with FERC on March 26, 2026, after an initial rejection in October 2025 without prejudice. The tariff establishes a process for evaluating and integrating loads greater than 45 MW, or loads expected to exceed 45 MW within four years, and includes a…
Data centers exceeding 45 MW, or expected to reach that level within four years, may use the tariff process for grid integration. The tariff includes evaluation fees and a security deposit…
pending
PPL Electric Utilities
PPL Corp.
PA M-2025-3054271 tariff 2025-05 The Pennsylvania Public Utility Commission voted 3-2 to propose a statewide model tariff that electricity providers can adopt for large-load customers, including data centers. The proposal includes cost-causation measures, infrastructure contributions, collateral requirements, minimum contract…
Data center developers would receive clearer interconnection rules and rates but may have to contribute toward infrastructure and low-income customer-support programs, provide tiered…
pending
AEP Ohio
OH tariff 2025-07 The Public Utilities Commission of Ohio approved AEP Ohio’s data center tariff. The tariff generally requires large new data centers to pay for at least 85% of reserved capacity for 12 years, provide proof of financial viability, and potentially pay an exit fee equal to 36 months of minimum charges.
A data center reserving 100 megawatts but using 65 megawatts would still be billed for at least 85 megawatts. Developers must make long-term financial commitments and bear more of the…
approved
ERCOT
TX Project No. 54445 tariff 2025-05-15 The PUCT approved ERCOT-sponsored NPRR1234, establishing interconnection, modeling, visibility, study, and Subsynchronous Oscillation requirements for Large Loads and certain other load additions. Large Loads are defined as one or more facilities at a single site with aggregate peak demand of 75…
Data center developers with large loads may face new ERCOT interconnection, modeling, study, visibility, and Subsynchronous Oscillation requirements, particularly for sites with aggregate…
approved
Sacramento Municipal Utility District (SMUD)
CA statement SMUD is developing a policy for customers with electrical loads of 50 megawatts or more. The policy would establish processes for extending service, evaluating transmission costs and grid impacts, and assigning related costs to large customers to protect existing customers from cost shifts.
Data center projects requesting 50 MW or more will undergo transmission studies before moving forward, and proposed locations will be evaluated based on available capacity and grid…
pending
Sacramento Municipal Utility District (SMUD)
CA other 2026-06-17 SMUD began a Board discussion on policies for large loads of 50 MW or higher, including pricing, commodity and renewable-energy costs, infrastructure-cost recovery, financial security, environmental costs, and risk mitigation. SMUD presented potential pathways involving Board policy, rate…
Data-center developers with loads of 50 MW or higher may be subject to future customized pricing, infrastructure-cost recovery, minimum contract terms or billing demands, exit fees,…
pending
Grant County Public Utility District
WA other 2025 Grant County Public Utility District will implement limits on the growth of electricity demand from data centers receiving power from the utility. Similar limits may apply to other large industrial customers because anticipated demand could exceed the electrical distribution and transmission…
Data centers may continue current operations and grow up to their assigned load limits; the utility is not asking customers to curtail or reduce existing load. The utility anticipates…
pending
Interstate Power and Light Company
IA tariff 2024-09-20 Interstate Power and Light Company issued Rider ICR, Individual Customer Rate, effective October 1, 2024. The tariff establishes eligibility requirements, negotiated or marginal-cost-based demand and energy pricing, curtailment obligations, excess-facilities charges, service-agreement filing…
Data-center developers with projected or expanding demand of at least 25,000 kW may qualify for an individual service agreement if they meet the tariff’s requirements. Eligible customers…
approved
Xcel Energy
WI tariff 2026-06-22 Xcel Energy filed a proposal with the Public Service Commission of Wisconsin to establish a Large Load Tariff for new customers or significant load expansions of 100 MW or greater, including potential new data centers. The proposal would require these customers to pay all costs needed to serve…
New data centers of 100 MW or greater would be required to bear the full cost of necessary service infrastructure, preventing costs from being shifted to other customers if approved as…
pending
Indiana Michigan Power (I&M)
American Electric Power (AEP)
IN tariff The Indiana Utility Regulatory Commission approved a joint settlement concerning I&M’s large load tariff, with one modification. The terms require new large load customers, including data centers, to make long-term financial commitments proportional to their size, and require IURC review before…
Data center developers and other new large load customers must make long-term financial commitments intended to ensure that service costs are recovered from them rather than existing…
approved
DTE Energy
MI special contract DTE states that it has two data-center contracts, one approved and one pending approval by the Michigan Public Service Commission. The contracts require data centers to cover new costs needed to serve them, including renewable energy and battery storage costs.
Data centers in DTE’s service territory are represented as not increasing existing customers’ rates. Developers are expected to pay for new energy resources and other costs required to…
pending
Alabama Power
AL statement Alabama Power states that data centers and other large-load customers must pay the full cost of serving their energy needs, undergo engineering and planning studies before service begins, and enter agreements that may include minimum bills and minimum-term provisions. The Alabama Public Service…
Data-center developers are responsible for dedicated facilities, delivery upgrades, and customer-specific capacity costs, which are not shifted to existing customers. Developers must…
pending
Entergy Louisiana, LLC
LA U-36959 tariff Entergy Louisiana, LLC issued the First Revised Large Load, High Load Factor Power Service Rate Schedule LLHLFPS-L, effective August 30, 2024, superseding the version effective October 17, 2019.
Data center developers seeking service under this schedule must contract for at least 70 MW of firm load, maintain at least an 80% average monthly electric load factor, and take…
approved
Entergy Louisiana, LLC
LA tariff 2025-04-04 Entergy Louisiana, LLC’s Second Revised Large Power High Load Factor Service Rate Schedule LPHLF-G became effective on April 4, 2025. It superseded the version effective August 30, 2024, and was authorized by a Staff Acceptance Letter dated April 4, 2025.
The tariff is available to customers contracting for at least 200,000 kW, subject to adequate-capacity facilities and suitable phase and voltage. Charges include a $1,665,947 monthly…
approved
Entergy Mississippi; Entergy Arkansas; Entergy Louisiana
Entergy (NYSE: ETR)
AR statement Entergy stated that agreements with data center customers are expected to deliver approximately $5 billion in savings over 20 years for customers in Arkansas, Louisiana, and Mississippi. The agreements received regulatory approval, acknowledgement, or oversight from the relevant state public…
Data center customers must pay incremental costs, existing-grid costs, and other costs required to serve their facilities, while meeting contract, credit, resource-adequacy, and…
approved
Portland General Electric (PGE)
OR UM2377 tariff 2026-06 PGE filed new rates under docket UM2377 to implement Oregon’s POWER Act. The Oregon Public Utility Commission approved a new data center rate schedule on July 7, 2026, with updated rates effective July 8, 2026.
Large-load data center customers receive a 29% rate increase under the new schedule. The framework allocates growth-related infrastructure costs to data center customers through a “growth…
approved
Nevada Power Company dba NV Energy
NV Docket Nos. 23-02010 and 23-02011 tariff 2024-09-20 NV Energy’s Schedule No. LCMPE establishes the Large Customer Market Price Energy tariff for non-Residential Service Customers with an average annual hourly load of 10 megawatts or more. The tariff requires Commission approval of Energy Supply Agreements addressing cost allocation, reliability,…
A data-center load may qualify if it is a non-Residential Service Customer with an average annual hourly load of at least 10 megawatts and meets the other eligibility requirements. The…
approved
Arizona Public Service Company (APS)
AZ Decision No. 79293; A.C.C. No. 6067 tariff 2024-03-08 Arizona Public Service Company’s Rate Schedule XHLF, General Service Extra High Load Factor, became effective under Decision No. 79293. The tariff applies to customers with monthly maximum demand of at least 5,000 kW and a qualifying 92% or higher load factor, with additional requirements for…
Large-load data-center developers may qualify for XHLF service if they meet the demand, load-factor, carbon-free activity, and other requirements and execute an Electric Supply Agreement.…
approved
Arizona Public Service (APS)
AZ E-01345A-25-0105 rate case 2025-06 APS filed a rate-case request with the Arizona Corporation Commission proposing an increase of more than 45% for extra-large energy users, including data centers. APS also proposed annual formula-rate reviews to assign data-center growth costs to those customers.
Data centers and other extra-large energy users would face proposed rates intended to cover their costs of service. Annual formula-rate reviews could result in future rate increases or…
pending
Delmarva Power & Light Company
DE Docket No. 25-0826 tariff 2025-09-03 The Delaware Public Service Commission opened a docket to establish a large-load tariff for customers with monthly maximum demand of 25 MW or greater. Commission Staff must conduct stakeholder workshops, after which DPL must file revised tariff pages before interconnecting any new qualifying…
Prospective data centers and other large-load customers in DPL’s service territory forecasting or planning for monthly maximum demand of 25 MW or greater must comply with the revised…
pending
Delmarva Power & Light
DE tariff 2025-09-03 The Delaware Division of the Public Advocate and Delaware Public Service Commission Staff petitioned the Commission to establish a large load tariff requiring facilities such as data centers to pay their share of energy infrastructure costs. The Commission opened a docket and paused…
New large load facilities, including data centers, cannot interconnect in Delmarva territory while the tariff is being developed. The tariff is intended to require such facilities to pay…
pending
Mon Power; Potomac Edison
FirstEnergy Corp. (NYSE: FE)
WV IRP 2025-10-01 Mon Power and Potomac Edison submitted an Integrated Resource Plan to the Public Service Commission of West Virginia covering how they will provide reliable, cost-effective power over the next decade. The preferred plan includes keeping the Fort Martin and Harrison power stations operational,…
The IRP identifies data centers and advanced manufacturing as drivers of growing electricity demand in West Virginia. Proposed new dispatchable generation would help meet rising demand,…
pending
Evergy Kansas Central, Inc.; Evergy Kansas South, Inc.; and Evergy Metro, Inc. d/b/a Evergy Kansas Metro
KS 25-EKME-315-TAR tariff 2025-02-11 Evergy filed an application seeking approval of a Large Load Power Service (LLPS) rate plan and associated tariffs for customers seeking to interconnect at loads over 100 MW. The Kansas Corporation Commission approved the unanimous settlement agreement and LLPS tariff provisions, including annual…
Data-center developers seeking to interconnect at loads over 100 MW may use the approved LLPS rate offering. The provisions require a minimum term of five years of an optional transitional…
approved
Evergy Kansas Metro, Inc.; Evergy Kansas South, Inc.; Evergy Kansas Central, Inc.
KS 25-EKME-315-TAR tariff 2025-02-11 The Evergy Kansas operating companies filed an application seeking approval of a Large Load Service Rate Plan and associated tariffs.
The filing proposes a large-load service rate plan that could apply to data centers, but the record does not specifically identify data centers, developers, or the plan's particular impact…
pending
Alabama Power
AL special contract A generic proceeding is being established to create a process for considering electric-service contracts between Alabama Power and large-load data center customers.
The proceeding concerns how Alabama Power may consider electric-service contracts for large-load data center customers. Specific impacts on rates, interconnection, cost allocation, or…
pending
Cleco Power LLC
Cleco Corporate Holdings LLC
LA rate case 2026-06-22 Cleco Power is seeking a $102.8 million revenue-requirement increase and a new 2027 Formula Rate Plan. It also intends to file a Data Center Application seeking approval of an electric service agreement and related credit support with Applied Digital Corporation, bridge capacity, a new…
The proposed project would add 430 MW of new electric load in Rapides Parish and is expected to begin service in mid-2027, subject to regulatory approvals. Cleco states that the load could…
pending
Pacific Gas and Electric Company (PG&E)
CA A.24-11-007 tariff 2024-11-21 PG&E filed an application with the California Public Utilities Commission to establish Electric Rule 30, a streamlined approach for energizing new transmission-level retail customers. The proposal would require large-load customers to fund initial interconnection facilities and costs, with refunds…
Data center developers seeking transmission-level service would generally need to pay interconnection costs upfront, with potential refunds tied to revenues generated by their load. The…
contested
Idaho Power Company
ID IPC-E-26-07 other Idaho Power Company filed a petition to evaluate its class cost-of-service methodology, consider alternative class cost-of-service studies, and determine cost-of-service considerations for new large-load customers.
The proceeding addresses cost-of-service considerations for new large-load customers, which may include data centers. No specific data-center tariff, rates, interconnection treatment,…
pending
Tucson Electric Power (TEP)
AZ special contract 2025-12 The Arizona Corporation Commission approved TEP’s energy supply agreement for the first phase of a potential data center development southeast of Tucson. The agreement provides up to 286 megawatts, includes a gradual ramp-up, and requires separate agreements and regulatory review for future phases.
The first phase can be served using TEP’s existing energy portfolio and solar and battery storage projects under development without affecting reliability for other customers. The data…
approved
Tucson Electric Power (TEP)
UNS Energy
AZ special contract TEP submitted an energy supply agreement for Arizona Corporation Commission review to serve the potential data center previously known as Project Blue. The agreement would use an Arizona Corporation Commission-approved large-customer tariff, minimum monthly billing for reserved capacity, and…
The data center would pay TEP’s full cost of service, remain responsible for reserved capacity even if energy use falls below contracted levels, and fund infrastructure needed for its…
pending
Tri-State Generation and Transmission Association
CO tariff 2025-08-28 Tri-State Generation and Transmission Association filed a proposed High Impact Load Tariff and Agreement with the Federal Energy Regulatory Commission. The proposal would establish a process for adding high-impact loads exceeding 45 MW, including data centers, with security payments, minimum…
Data-center developers seeking service from Tri-State members would face the proposed high-impact-load process if their projects exceed 45 MW or are forecast to do so within four years.…
pending
Chelan PUD
WA other Chelan PUD states that it evaluates requests from power-intensive industries, including data centers, under established policies, engineering requirements, and rate structures. It is not considering a data-center growth moratorium at this time.
Data centers must secure and pay for the electricity they need before Chelan PUD will serve them. Large-load customers generally pay for studies, equipment, and system upgrades required…
pending
Duquesne Light Co.
PA tariff Duquesne Light told the Pennsylvania Public Utility Commission that large-load developers should pay the costs of studies and infrastructure investments that provide no benefit to other customers. It also recommended that large-load customers generate their own power to reduce impacts on existing…
Data center developers may be required to bear study and infrastructure costs that benefit no other customers and may face pressure to provide their own generation.
pending
PSEG
NJ statement PSEG reported that large-load interconnection requests had increased 47% since Q1 to 9.4 GW, with more than 90% related to data centers, and said it expects only 10, 20% of requests to come online. A proposed New Jersey bill would require electric utilities to develop a special rate structure and…
Certain new data centers could be subject to special utility rules and a dedicated rate structure intended to prevent non-data-center customers from bearing increased costs. The 9.4 GW…
pending
Wisconsin Electric Power Co. and Wisconsin Gas LLC (We Energies)
WEC Energy Group Inc. (NYSE: WEC)
WI 5-UR-112 rate case We Energies filed a rate request with the Public Service Commission of Wisconsin that includes a Customer Protection Plan requiring data centers to pay nearly $1.9 billion in 2027 and 2028 toward the infrastructure, equipment, and energy needed to serve them. The filing states that these…
Data centers are expected to pay their allocated infrastructure, equipment, and energy costs associated with service in 2027 and 2028, protecting other We Energies customers from those…
pending
We Energies
WI tariff The Public Service Commission of Wisconsin unanimously approved a special rate plan governing how data center-scale customers in We Energies’ service territory pay for electricity and infrastructure built to serve their demand. The PSC modified the proposal by extending required agreements from 10…
Qualifying data center customers must sign 15-year agreements with We Energies and pay costs associated with serving their demand. They must fund and subscribe to portions of multiple new…
approved
We Energies (WEPCO)
WI 6630-TE-113 tariff 2026-04-24 The Public Service Commission issued a preliminary decision on We Energies’ proposed Very Large Customer rate structure, finding that the proposed tariff did not sufficiently protect households and other businesses from increased utility bills and taking action to address those deficiencies.
The decision is intended to ensure that data centers and the utilities serving them pay the full costs of the energy and infrastructure they require, rather than shifting those costs to…
pending
Madison Gas and Electric
WI tariff MGE filed an application with the Wisconsin Public Service Commission proposing a Very Large Customer rate for new electric customers with demand of 100 MW or greater. MGE also proposed a Bespoke Resources Tariff allowing very large customers to receive service from dedicated energy resources and…
Data centers with demand of 100 MW or greater could be served under the proposed Very Large Customer rate, with customers responsible for incremental energy, transmission, market,…
pending
Evergy Kansas / Evergy’s Kansas utilities
KS tariff The Kansas Corporation Commission approved a settlement establishing a large-load power service rate plan for new facilities over 75 MW. The plan provides up to five years for ramp-up, requires at least 12 years of service, sets a minimum monthly bill based on 80% of contract demand, requires…
Data centers and other facilities over 75 MW must commit to long-term service and pay for at least 80% of contracted demand even when using less. They must also fund transmission upgrades…
approved
MidAmerican Energy
Berkshire Hathaway Energy
IA other MidAmerican Energy received state approval to invest $3.9 billion in nearly 2,100 megawatts of wind and solar generation. The utility said the investment would come at no net cost to consumers, supported partly by Inflation Reduction Act tax credits and other renewable-energy incentives.
MidAmerican expects Iowa’s energy demand to double by the mid-2030s as data centers and artificial intelligence development expand. The anticipated growth will require substantial…
approved
AEP Ohio
OH tariff 2025-07-11 The Public Utilities Commission of Ohio adopted AEP Ohio’s 2024 Data Center Tariff settlement on 2025-07-09. AEP Ohio filed its compliance tariff on 2025-07-11, and the tariff became effective on 2025-07-23.
New data centers and expansions seeking service from AEP Ohio must complete a mandatory PowerClerk application. Facilities or expansions of 25,000 kW or greater must pay a load-study fee…
approved
AEP Ohio
American Electric Power (AEP)
OH tariff 2026-02-12 AEP Ohio updated the Public Utilities Commission of Ohio on the operation of its approved Data Center Tariff. The tariff requires progressively increasing financial and legal commitments, including binding contracts and collateral, to align infrastructure investments with data center loads and…
Data centers and developers must provide accurate load estimates, obtain engineering studies, provide collateral, and sign binding electric-service agreements with financial commitments.…
approved
Indiana Michigan Power
AEP
IN IURC Cause No. 46276 special contract 2025-07-30 Indiana Michigan Power filed a special joint contract with Google. The proposed contract includes Google’s transfer of long-term accredited capacity from clean energy resources to I&M and a custom demand-response offering with specified curtailment limits and use of qualifying behind-the-meter…
The proposed arrangement would allow a large data center customer to provide clean-generation capacity and demand response, helping I&M meet PJM requirements and alleviate grid congestion…
pending
American Electric Power (AEP)
OH tariff AEP reported that it had secured data center tariffs in Ohio, followed by large-load tariff solutions in Indiana, Kentucky, and West Virginia. AEP also reported active filings for similar tariffs in Michigan, Oklahoma, Texas, and Virginia, including minimum demand charges and obligations for…
Data center customers in AEP service areas may be subject to dedicated data center or large-load tariffs, minimum demand charges, and binding take-or-pay obligations covering…
pending
Duke Energy
NC statement Duke Energy announced that it will include take-or-pay provisions in agreements covering 2 GW of U.S. data centers across its service area. Customers with demand exceeding 100 MW would be required to pay for a minimum amount of electricity regardless of actual usage, subject to direct regulatory…
Data center customers with signed agreements and identified land but without finalized power contracts would face minimum payment obligations once contracts are completed. Duke is also…
pending
Duke Energy
NC tariff Duke Energy proposed a large load tariff in testimony submitted to the North Carolina Utilities Commission. The proposal would apply to customers with loads of at least 50 megawatts and require minimum bills based on 75% of maximum potential usage, with minimum contract terms of 10 or 15 years.
Data centers would face long-term minimum payment obligations regardless of actual electricity use, reducing Duke Energy’s risk from building infrastructure for demand that does not…
pending
Commonwealth Edison Company (ComEd)
Exelon Corporation
IL ICC Docket No. 22-0486; ICC Docket No. 24-0181 rate case 2024-03-13 ComEd filed a revised Multi-Year Integrated Grid Plan and an adjusted rate plan to address deficiencies identified by the Illinois Commerce Commission. On December 19, 2024, the ICC approved the compliant refiled grid plan and multi-year rate plan with modifications, allowing recovery of prudent…
ComEd identified more than 11 GW of potential data-center growth in its service territory, with demand expected to ramp over up to 10 years. The approved plans support grid-capacity and…
approved
Commonwealth Edison (ComEd)
IL tariff The Illinois Commerce Commission approved ComEd’s proposal to increase security deposits required from developers of large-load projects based on projected energy needs. Projects requesting 50, 200 megawatts will start with a $1 million deposit, increasing by $500,000 for each additional 100…
Data center and other large-load developers will face higher security deposits intended to protect ComEd from costs if projects are canceled, moved, or under-utilized. The revised tariff…
approved
Ameren Missouri
MO tariff Ameren is pursuing a Large Load Customer Tariff case before the Missouri Public Service Commission for customers requesting 100 MW or more. The proposal includes minimum 15-year service contracts, minimum energy purchases, financial assurances, termination notice requirements, exit fees, and…
Data-center developers requesting 100 MW or more would need long-term commitments and financial assurances before Ameren makes generation and transmission investments. The proposed terms…
pending
Duke Energy Carolinas, LLC (DEC); Duke Energy Progress, LLC (DEP)
Duke Energy Corporation
NC E-100, Sub 208 other 2025-10-10 Duke Energy Carolinas, LLC and Duke Energy Progress, LLC filed technical conference presentation materials addressing large electric load additions, including economic development projects, contracting protections, pricing and cost recovery, and resource-planning implications. The materials…
The utilities reported an economic development pipeline of 420 projects representing an estimated 46 GW, including third-party and end-user data center categories. Data center developers…
pending
Santee Cooper
SC tariff Santee Cooper enacted a new experimental electricity rate for large-load customers requiring 50 MW or more, including data centers. The rate is effective immediately, requires 15-year contracts, permits higher charges during periods of high demand, and requires customers to ramp up to full…
Qualifying data centers must cover the costs associated with their electricity use and accept long-term contract and usage-ramp obligations. The rate is intended to prevent costs from…
approved
Santee Cooper
SC tariff 2025-04 Santee Cooper’s board unanimously approved a special, higher electricity rate for new customers requiring 50 megawatts or more, including data centers and new manufacturing facilities. The rate is intended to ensure these energy-intensive customers cover the cost of the generation they require and…
New data centers requiring at least 50 MW will pay a higher electricity rate designed to allocate the cost of required generation to those large loads rather than regular consumers. Data…
approved
Georgia Power
Southern Company
GA statement Georgia Power stated that it signed a 3.2-gigawatt, 25-year electric-service contract with OpenAI for a site near Savannah, Georgia. Service is expected to begin in phases in 2028, with 1 gigawatt of flexible demand response.
The contract provides a long-term power arrangement for a major data-center customer. Its flexible demand-response component is intended to support system reliability during periods of…
pending
Dominion Energy
VA tariff 2025-11 The Virginia SCC approved Dominion’s GS-5 “High Load” tariff for customers with at least 25 MW of demand. The tariff requires large customers to pay a greater share of generation, transmission, and distribution investments, with service under a 14-year contract and an optional four-year ramp-up…
Data centers and other large-load customers would bear more of the costs and risks associated with projected electricity demand. During the ramp-up period, customers would pay minimum…
approved
Louisville Gas & Electric and Kentucky Utilities (LG&E/KU)
PPL Corporation
KY other LG&E/KU are seeking approval to spend nearly $3 billion on two 645-megawatt natural-gas plants and to extend the life of two coal plants, citing forecast demand from future data centers. They also proposed an extremely high load factor tariff requiring qualifying new data centers to pay for at…
New data centers expecting to use at least 100 megawatts would be required to sign the proposed EHLF tariff. A 525-megawatt data center could face at least $1.4 billion in demand charges…
contested
East Kentucky Power Cooperative (EKPC)
KY tariff 2025-10-30 The Kentucky Public Service Commission approved EKPC’s request for a special tariff establishing rates and terms for prospective data centers. The tariff applies to data centers using at least 15 megawatts, requires PSC approval of each special data-center contract, removes the cap on application…
Future data centers in EKPC’s service area must use at least 15 megawatts and satisfy the special tariff requirements. Their contracts require PSC approval before taking effect, and…
approved
Entergy Arkansas, LLC
AR 23-070-TF tariff Entergy Arkansas, LLC established or revised Rate Schedule No. 69, Large Power High Load Density Service (LPHLDS), for qualifying high-energy-use or high-load-factor customers, including cryptocurrency-mining or similar operations. The tariff requires qualifying customers to take interruptible…
The tariff does not specifically mention data centers. Large, flexible, relocatable, or otherwise qualifying high-load customers may be required to use the LPHLDS tariff, accept…
approved
Entergy Louisiana
LA tariff Entergy Louisiana uses an Additional Facilities Charge to recover infrastructure costs for large-load customers, including data centers.
Data-center customers would be charged directly for applicable additional facilities and related infrastructure costs.
pending
Southwestern Electric Power Company (SWEPCO)
AEP
LA statement SWEPCO signed the White House Ratepayer Protection Pledge, stating that new large energy users should pay for the facilities and system upgrades they require. Under Louisiana Public Service Commission oversight, agreements require incoming large customers to pay for substations, transmission…
Data-center developers and other large customers are expected to pay their electricity costs and the infrastructure required to serve them, rather than having existing SWEPCO customers…
pending
Duke Energy
FL tariff Duke Energy petitioned the Florida Public Service Commission for a new large data center rate. The PSC voted 4-1 to deny consumer advocates’ motion to dismiss the petition, allowing it to proceed to an evidentiary hearing.
The proposed large data center rate and related customer protections remain under review. The petition will proceed to an evidentiary hearing, so the rate has not been finalized.
pending
Public Service Company of Oklahoma
OK tariff 2026-07-01 PSO filed a large-load tariff with the Oklahoma Corporation Commission establishing separate terms and conditions for large-scale customers, including data centers and crypto-mining operations. The tariff requires commission approval.
The tariff is intended to ensure data centers and other large-load customers pay rates reflecting the cost of serving them, helping prevent existing customers from subsidizing related…
pending
Public Service Company of Oklahoma (PSO)
OK tariff The page describes a tariff and regulatory protections for large-load customers of 150 MW or more. These protections require customer-funded infrastructure and service costs, upfront financial guarantees, and long-term payment commitments intended to shield existing customers from financial risk.
Data-center developers with loads of 150 MW or more may be required to provide financial safeguards and remain responsible for infrastructure and service costs even if usage declines or…
approved
Oklahoma Gas & Electric (OG&E)
OK tariff 2026-06-17 OG&E proposed a large-load tariff to the Oklahoma Corporation Commission for customers planning to use 75 megawatts or more. The proposal would require such customers to pay for estimated electricity usage, fund their own grid connections, and pay monthly fees that could support credits for other…
New data centers and other large energy users would be separately classified and responsible for their estimated electricity usage and grid-connection costs, reducing the risk that…
pending
Southwestern Public Service Co.
Xcel Energy
NM other Southwestern Public Service Co. filed an application with New Mexico utility regulators seeking approval to build eight new energy resources, including natural gas plants, solar and wind farms, battery storage, and transmission upgrades. The utility said the projects are partly needed to serve…
Data-center expansion is identified as a major driver of projected electricity-demand growth and the proposed resource additions. Environmental advocates argued that data centers should…
contested
Southwestern Public Service Company (SPS)
Xcel Energy Inc.
TX special contract 2026-01 SPS entered into an Electric Service Agreement with Fermi America to provide up to 200 MW of electricity to Fermi’s Project Matador Campus. Service is scheduled to begin at 86 MW in January 2026 and gradually expand to 200 MW under the ESA and applicable tariffs.
The agreement provides a dedicated, phased electricity supply for Fermi’s Project Matador Campus through SPS’s 115-kilovolt transmission system. It may also create an opportunity for SPS…
pending
Board of Public Utilities (BPU)
KS other BPU said it is developing rate structures and cost-allocation requirements for large customers as three proposed data-center projects advance. Developers would be required to pay 100% of on-site infrastructure and substation costs, provide up to $140 million in parent-company-backed collateral,…
Data-center developers would not receive special rates or utility subsidies and would bear their on-site infrastructure and associated costs. The first project to sign an agreement would…
pending
Evergy
KS other Evergy initiated processes with the Kansas Corporation Commission and the Missouri Public Service Commission to establish pricing structures for large power users. The proposed structures are intended to recognize the benefits of adding large users to the shared grid and prevent existing customers…
Evergy said electricity demand could nearly double if all potential new customers arrive in the Kansas City area. Regulators may establish safeguards to protect customers if a large data…
pending
Evergy
MO tariff 2025-11-13 The Missouri Public Service Commission approved Evergy’s large-load rate for users requiring at least 75 megawatts at peak times. The rate is intended to allocate transmission, generation, infrastructure, and grid-related costs to new large power users.
Data centers and other large power users would pay rates higher than existing commercial and industrial customers. The safeguards are intended to prevent existing customers from bearing…
contested
Brazos Electric Power Cooperative, Inc.
TX tariff 2025-11 Brazos Electric published an Interconnection Guidebook describing requirements and procedures for entities establishing or significantly modifying connections to the ERCOT grid through its transmission system. It includes interconnection requirements for Large Load Customers with peak demand of at…
Data center loads may be subject to surveys and steady-state, short-circuit, dynamic-stability, facilities, and potentially subsynchronous-oscillation studies before initial energization.…
pending
Dominion Energy
VA tariff Dominion Energy proposed creating a new rate class for data-center customers consuming more than 25 MW with a monthly load factor above 75 percent. The proposal includes 14-year contracts, minimum demand charges for transmission, distribution, and generation infrastructure, and exit fees for…
Many of the approximately 450 data centers in Dominion’s coverage zone could potentially be classified in the new rate class. Under the proposal, affected customers could be responsible…
contested
Dominion Energy Virginia
Dominion Energy
VA IRP 2024 Dominion Energy Virginia filed its 2024 Integrated Resource Plan with the Virginia State Corporation Commission and the North Carolina Utilities Commission. The plan proposes an all-of-the-above generation and grid-investment strategy, while the Virginia SCC required least-cost and Virginia Clean…
Dominion projects substantial electricity-demand growth primarily driven by data centers, including 8 GW of contracted data-center capacity through 2032 and additional demand under study.…
contested
Appalachian Power
WV special contract Appalachian Power, Google, and West Virginia manufacturers reached a settlement concerning terms for large-load customers, including potential data centers. The settlement requires Public Service Commission approval and includes minimum site capacity, contract-term, and power-purchase commitments.
Data centers locating in West Virginia would need to contract for at least 100 MW at an individual site, commit to an initial term of at least 12 years, and purchase at least 80% of their…
pending
Appalachian Power Company
VA rate case 2026-05 Appalachian Power filed an application with the Virginia State Corporation Commission seeking to raise rates, citing potential service to 36 large-load customers requiring significant infrastructure investment. The SCC separately approved new requirements for new large-load customers, including…
Data-center developers connecting to Appalachian Power’s system may be required to sign 14-year contracts and pay minimum charges. Infrastructure costs may be assigned to large customers…
pending
Old Dominion Electric Cooperative (ODEC)
VA other ODEC prepared and submitted a 2026 large load adjustment to PJM for the DOM Zone, covering data-center load forecasts over a 20-year period. The submission included projects with, or expected imminently to have, signed Construction Commitments, Electric Service Agreements, and other listed…
Data-center projects with an Electric Service Obligation and Construction Commitment were classified as Firm and allowed to impact the Reliability Pricing Model; other projects were…
pending
Old Dominion Electric Cooperative (ODEC)
VA statement ODEC CEO John Lee discussed the generation and transmission challenges and financial risks cooperatives may face when serving high-load members, including data centers. He also addressed the economic benefits data centers can bring to local communities.
Data-center development may increase generation and transmission challenges and create financial risks for cooperatives serving high-load members. Data centers may also provide economic…
pending
PG&E
CA tariff 2025-09 PG&E’s proposed Rule 30 Tariff is pending California Public Utilities Commission approval. It would apply to new load additions greater than 10 MW interconnected at 50 kV, 230 kV, including hyperscale data centers.
The tariff would establish tailored cost-recovery mechanisms, reliability standards, and service terms for large, transmission-connected, mission-critical facilities. It is intended to…
pending
City of Santa Clara dba Silicon Valley Power (SVP)
CA statement 2021-03-22 SVP submitted a public comment letter to the CAISO Board regarding the 2021, 2022 Transmission Plan. SVP requested immediate coordination with PG&E on transmission-capacity increases and mitigation projects in the South Bay due to rapid hyper-scale data-center load growth and expected reliability…
SVP projected peak load growth from 592 MW in 2020 to 1,011 MW in 2025, primarily driven by hyper-scale data centers. SVP warned that South Bay transmission constraints could affect the…
pending
Silicon Valley Power
CA IRP Silicon Valley Power’s draft Integrated Resource Plan forecasts that annual system load will nearly double by 2035, primarily due to data-center demand. The plan proposes additions including geothermal, wind, solar, storage, hydrogen, and biogas resources, as well as a planned 50 MW, four-hour…
Data centers are SVP’s largest load, with an approximately 80% load factor, requiring clean and firm resources capable of serving demand in all hours. Existing and planned transmission…
pending
PacifiCorp
OR other 2025-02 The Oregon Public Utility Commission approved PacifiCorp’s proposal to impose penalties on large-load customers, including data centers, when actual energy use at new facilities does not align with forecast needs. The proposal includes a five percent buffer for missed forecasts.
Data center operators may face penalties and higher costs when actual load falls materially below reserved or forecast load. The rules are intended to reduce unnecessary grid investment…
approved
Portland General Electric Company
OR UM 2377 tariff The OPUC approved PGE’s New Large Load Tariff in docket UM 2377. The tariff increases data center pricing by approximately 30% while lowering costs for other customers.
Data center customers will face pricing approximately 30% higher under the approved large-customer tariff.
approved
Idaho Power Company
ID tariff 2026-01-01 Schedule 19, Large Power Service, establishes service terms and charges for customers with metered demand of at least 1,000 kW in three or more of the most recent 12 billing periods. It also permits an optional mutually agreed special contract for customers contracting for firm demand of 10,000 kW…
Data-center developers with loads of 1,000 kW or more may be subject to Schedule 19 once the demand criterion is met, or may request service based on expected initial usage. Loads…
approved
Public Service Company of Colorado (Xcel Energy)
Xcel Energy
CO tariff 2026-04-02 Xcel Energy proposed a special tariff for new large-load customers requiring at least 50 megawatts of generating capacity, including data centers. The Colorado Public Utilities Commission ordered Xcel to create the tariff and must approve it.
New data centers would need to sign interconnection and energy service agreements, demonstrate site control, pay a $120,000 deposit plus load and transmission study costs, and enter…
pending
Public Service Company of Colorado
Xcel Energy
CO IRP 2025-11 The Colorado Public Utilities Commission approved Xcel Energy’s electric resource plan in November 2025, limiting new generation in the plan to 6,000 MW, with a second pool of projects if needed. It required Xcel to use large-load negotiating principles for customers needing 50 MW or more,…
Data center developers must provide financial commitments before Xcel includes their projects in its load forecast or commits to new generation and transmission. They must sign…
approved
Black Hills Energy
WY tariff 2020-05 The Wyoming Public Service Commission approved Black Hills Energy’s Large Power Contract Service Tariff. The tariff allows qualifying Wyoming retail customers with loads over 13 MW to use customer-owned, behind-the-meter dispatchable generation during periods of high demand while Black Hills…
Data centers with loads over 13 MW can use onsite backup generation and obtain market-based and renewable energy resources at a firm price. The arrangement is intended to support…
approved
Tri-State Generation and Transmission Association
CO tariff Tri-State filed a proposal with the Federal Energy Regulatory Commission for a high-impact load tariff (HILT) covering demands of 45 megawatts or more. The tariff is intended to ensure Tri-State can provide capacity to large-load developers while ensuring other cooperative members do not subsidize…
If approved, the HILT tariff would establish a framework for connecting and serving data centers and other loads of at least 45 megawatts on Tri-State’s system. Tri-State also has a…
pending
Tri-State Generation and Transmission Association, Inc.
CO tariff 2025-09 Tri-State filed its High Impact Load Tariff (HILT) with FERC to establish an integrated process for adding large loads and allocating related generation, transmission, and distribution costs. FERC denied the filing in approximately October 2025 because provisions governing energy-sale terms…
The proposed tariff would have applied to first-ready large loads exceeding 45 MW or forecasted to exceed 45 MW within four years, with requirements including site control, binding…
denied
Avista
WA statement 2026-05 Avista stated that it signed a Memorandum of Understanding with an unnamed data center developer interested in building within its Washington service territory. Negotiations are paused while Avista considers the need for broader coordinated planning; the MOU is not a final decision or commitment…
The potential data center is not guaranteed service or approval. Avista will evaluate whether it can meet the project's energy needs, with the developer responsible for the evaluation…
pending
NorthWestern Energy
MT tariff 2026-03-31 NorthWestern Energy submitted an application to the Montana Public Service Commission requesting approval of a Large New Load Tariff. The proposed tariff would require data centers and other large new-load customers to pay the full costs of the infrastructure and electric service needed to support…
Data centers would be responsible for the infrastructure and electric service costs they create. The proposed tariff includes minimum service commitments, minimum demand and energy billing…
pending
NorthWestern Energy
MT tariff 2026 Community, conservation, and Indigenous-led organizations filed a petition with the Montana Public Service Commission seeking intervention in NorthWestern Energy’s data-center tariff proceeding. The proceeding addresses rates, terms, and conditions for electricity service to data centers,…
The petition seeks data-center tariff provisions addressing capacity and energy purchase obligations, penalties, collateral, minimum payments based on forecast demand, energy efficiency,…
contested
PJM Interconnection
MD complaint 2026-05-07 The Maryland Office of People’s Counsel filed a complaint at FERC challenging PJM’s hybrid regional transmission cost-allocation methodology. The complaint asks FERC to assign data center-driven transmission costs to the PJM zones where the data centers are located or charge those costs directly…
Data center-driven transmission costs could be assigned to the zones hosting the data centers, such as Dominion Energy’s zone in Virginia, rather than broadly spread across PJM.…
contested
Delmarva Power and Light
DE tariff 2025-12-19 Delmarva Power proposed a tariff to the Delaware Public Service Commission for large-load electric customers using more than 25 megawatts. The proposal would require grid-impact studies, detailed energy-use projections, and 10-year financial guarantees from large energy users.
The tariff would establish different rates and requirements for large users such as data centers in Delmarva’s Delaware territory. The Delaware Public Service Commission has paused major…
pending
Delmarva Power and Light Company
DE 25-0826 tariff 2025-08-28 Commission staff and the Division of the Public Advocate petitioned for Delmarva Power to create a tariff for customers with monthly maximum demand of 25 megawatts or more. Delmarva Power proposed a large-demand service class, GS-LD, and an application process for customers with projected loads of…
Large-load and data-center customers would be placed in a separate proposed service class and subject to an application process for projected loads of at least 50 megawatts. The proceeding…
contested
PECO Energy Company
PA M-2025-3054271 tariff 2026-05-12 The Pennsylvania Public Utility Commission adopted a model interconnection tariff for new Large Load Customers, including individual customers exceeding 50 MW or closely located customers with aggregate capacity of at least 100 MW. The tariff addresses interconnection studies, network-upgrade cost…
Data center developers meeting the applicable thresholds may face three-to-five-year load-ramp periods, minimum five-year initial contract terms, responsibility for “but for”…
approved
New Jersey electric public utilities (statewide data center tariff standards)
NJ tariff New Jersey lawmakers passed a bill requiring the New Jersey Board of Public Utilities to establish tariff standards for data centers of at least 50 MW. The standards would allocate attributable costs to large data centers, require demand-response and efficiency programs, prioritize data-center…
Existing and prospective data centers meeting the 50 MW threshold would face special tariffs and financial-guarantee requirements intended to protect other ratepayers from grid-connection…
pending
Monongahela Power; Potomac Edison Co.
FirstEnergy
WV other Monongahela Power and Potomac Edison Co. applied to the West Virginia Public Service Commission for permission to build the Maidsville Energy Center, including a 1,200-MW gas-fired power plant and three solar projects totaling 70 MW. Mon Power also seeks to impose a customer surcharge to fund…
The project is primarily intended to serve potential data center load. If service agreements are executed and approved, data center owners would be responsible for their proportionate…
contested
Mon Power and Potomac Edison
FirstEnergy
WV other Mon Power and Potomac Edison are seeking approval to build the 1,200-megawatt Maidsville Energy Center, three solar projects, and an associated Generation Projects Surcharge. The initial surcharge is estimated to increase residential rates by $1.18 per month, or 0.9%.
Projected load growth is substantially driven by prospective data-center demand, including an unnamed large-load customer projected to reach 1,012 MW from 2033 through the end of the…
contested
Mon Power and Potomac Edison
FirstEnergy
WV other Mon Power and Potomac Edison applied to construct a $2.48 billion, 1,200-megawatt combined-cycle natural gas plant at the Fort Martin site in Monongalia County, along with 70 megawatts of solar generation. The utilities say the project is needed to address an anticipated capacity shortfall…
Opponents argued that the project could increase customer electric bills while primarily serving speculative future data centers. No specific data-center tariff, interconnection…
contested
Mon Power; Potomac Edison
FirstEnergy
WV Case No. 26-0108-E-CN other Mon Power and Potomac Edison filed an application with the Public Service Commission of West Virginia to build a 1,200-megawatt natural-gas-fired power plant adjacent to the Fort Martin Power Station, along with three solar projects. The proposed $2.48 billion project is intended largely to meet…
The proposed plant is intended to serve anticipated data-center demand, but existing customers could face an initial surcharge before the new demand is served. Opponents argue that data…
contested
Monongahela Power and Potomac Edison
FirstEnergy
WV IRP Monongahela Power and Potomac Edison asked the West Virginia Public Service Commission for permission to build a 1.2-GW gas-fired power plant in Maidsville, West Virginia. The proposed $2.5 billion project is included in the utilities’ integrated resource plan and is intended to support growing…
If the proposal is accepted, FirstEnergy said it would seek additional generation in West Virginia to support data centers and could apply for a second, third, or fourth unit. FirstEnergy…
pending
Mon Power
WV other Mon Power is asking the West Virginia Public Service Commission to approve a $2.4 billion natural gas-fired power plant near its Fort Martin Plant, with operations planned for 2031. It is also requesting a $1.18-per-month customer surcharge to help finance the plant.
The plant is intended to serve electricity demand from data centers, and Mon Power says data-center developers would eventually pay through contracts. No data-center contracts have been…
contested
Public Service Electric and Gas (PSE&G)
Public Service Enterprise Group (PSEG)
NJ statement PSE&G said its pipeline of potential large-load customers, almost all data centers, increased 47% to 9.4 GW at the end of June from 6.4 GW three months earlier. The utility expects approximately 10% to 20% of interconnection inquiries to become actual customers and is discussing supplying data…
Data-center developers face uncertainty because PSE&G expects only a minority of current interconnection inquiries to result in customers. Developers may also be evaluated for power…
pending
Consolidated Edison’s Rockland Electric; Exelon’s Atlantic City Electric; FirstEnergy’s Jersey Central Power & Light; Public Service Enterprise Group’s Public Service Electric and Gas
Consolidated Edison; Exelon; FirstEnergy; Public Service Enterprise Group
NJ tariff New Jersey legislation signed by Gov. Mikie Sherrill requires utilities to craft tariffs for data centers larger than 50 MW. The tariffs must address potential service costs, including requiring data center owners to guarantee payment for at least 85% of requested service for at least 10 years.
Data center developers must meet minimum payment guarantees and may face requirements related to energy efficiency, new clean energy, energy storage, and colocated power supplies. They may…
approved
New Jersey electric public utilities (statewide large-load tariff legislation)
NJ other New Jersey legislation would require public electric utilities to submit proposed tariffs to the New Jersey Board of Public Utilities for energy users consuming more than 100 megawatts monthly. The tariffs would begin one year after enactment, and the bill would incentivize data centers to capture…
Data centers consuming more than 100 megawatts monthly would be subject to new tariffs intended to protect other ratepayers from data-center-driven electricity cost increases. They would…
contested
Wisconsin Electric Power Company (We Energies)
WI 6630-TE-113 tariff 2025-03 We Energies proposed linked Very Large Customer and Bespoke Resources tariffs for very large data-center loads. The Wisconsin Public Service Commission approved the tariffs on 2026-04-24 with modifications, including lowering the eligibility threshold to 100 MW, extending the minimum term to 15…
Data-center customers with loads of at least 100 MW must enroll in the Very Large Customer rate class and execute a binding Bespoke Resources agreement. Developers must fund 100% of…
approved
MidAmerican Energy Company
Berkshire Hathaway Energy Company
IA special contract MidAmerican’s Load Commitment Agreement applies to new large loads, including data centers. It requires binding load-ramp schedules and a minimum monthly charge for 10 years regardless of actual usage, with signed customers funding incremental transmission and substation investments.
Data center developers must commit to binding ramp schedules and pay minimum monthly charges for 10 years regardless of actual usage. They must also fund incremental transmission and…
approved
Indiana Michigan Power Company
IN Cause No. 46097 tariff 2025-02-19 Indiana Michigan Power received commission approval to modify its existing Industrial Power Tariff for new or expanding large-load customers, including data centers. The tariff applies to loads exceeding specified capacity thresholds and includes long-term contract, minimum demand, exit-fee, and…
Data center developers must commit to an initial contract term of at least 12 years and pay monthly demand charges for at least 80% of contracted capacity, even if actual usage is lower.…
approved
Indiana Michigan Power (I&M)
American Electric Power (AEP)
IN tariff The Indiana Utility Regulatory Commission approved, with one change, a settlement agreement amending Indiana Michigan Power’s industrial power tariff for new or expanded facilities with contract capacity of at least 70 MW, or 150 MW aggregated across a company. The tariff requires large-load…
Data centers meeting the capacity thresholds would receive a standard electric-service tariff and be responsible for grid-upgrade costs rather than passing those costs to existing…
approved
Consumers Energy
MI tariff 2026-02-19 The Michigan Public Service Commission denied Michigan Attorney General Dana Nessel’s request for a rehearing in a previous Consumers Energy case involving rate structures for data centers and other large-load customers.
The approved tariff includes protections for residential customers associated with large new loads and requires data centers to pay more, helping reduce costs for other customers.
denied
Rochester Gas and Electric Corporation
NY Case No. 25-E-0379 tariff 2026-06-01 Rochester Gas and Electric Corporation issued revisions to Service Classification No. 3 in compliance with the May 14, 2026 order in Case No. 25-E-0379. The revisions establish delivery charges effective June 1, 2026, including a $401.00 monthly customer charge and an energy delivery charge of…
Customers with measured demand of at least 100 kW during any three of the previous 12 months may take service under Service Classification No. 3. Customers using or potentially using 300…
approved
AEP Ohio
OH tariff Regulators approved a new large-load tariff for AEP Ohio. Following approval, AEP Ohio reduced its large-load forecast by more than 50%, from 30 GW to 13 GW.
The tariff appears to have reduced speculative requests in AEP Ohio’s large-load pipeline. Manufacturers in Ohio said data center demand remained inflated.
approved
New York Independent System Operator (NYISO)
NY other New York Gov. Kathy Hochul signed an executive order pausing state environmental permits for new hyperscale data centers consuming 50 megawatts or more for up to one year. The pause will remain in effect while the New York Department of Public Service completes a Generic Environmental Impact…
Projects awaiting approval from the New York State Department of Environmental Conservation as of July 14 may be impacted. Projects using only local permitting processes that do not…
approved
Duke Energy Carolinas, LLC (DEC) and Duke Energy Progress, LLC (DEP)
NC other 2025-07-24 DEC and DEP filed a response to the North Carolina Utilities Commission’s June 6, 2025 request regarding integration of large-load additions exceeding 100 MW. Duke described its large-load intake process, including transmission studies, potential agreements, customer financial and performance…
Data centers and other large-load customers must engage Duke early, undergo transmission studies, and may need to provide refundable capital payments, satisfy minimum billing requirements,…
pending
Duke Energy Carolinas
NC tariff 2026-07-15 Duke Energy proposed a large-load tariff requiring customers requesting 50 megawatts or more to pay 75% of their demand charges in advance. The utility also agreed to participate in a fast-track regulatory process to develop rates for data centers and other large energy users.
Data centers and other large electricity users could be subject to a separate rate structure and advance payment of 75% of demand charges. The threshold and final cost implications remain…
contested
Georgia Power
Southern Co.
GA other Georgia Power filed an update to its load forecast as part of its request for proposals certification proceedings. The update projected capacity needs aligned with 10 GW of requested capacity resources, including five gas combined-cycle units and 11 battery energy storage facilities.
The filing reflects capacity planning for projected large-load growth, including data centers. Southern Co. reported contracts with large-load customers representing 7 GW through 2029,…
pending
Southern Company
GA statement Southern Company stated that it uses minimum 15-year contracts for data centers, minimum bill provisions similar to take-or-pay structures, termination payments tied to incremental cost to serve, and significant collateral requirements. Multiple pieces of legislation have been proposed in the…
Data-center developers seeking service from Southern Company may face minimum 15-year contracts, minimum bill obligations, termination payments, and significant collateral requirements.…
pending
Tennessee Valley Authority
TN tariff 2026-02-18 TVA proposed changes to wholesale and resale rate schedules and related policies, including removing data centers from manufacturing-service rate schedules and credits. It also proposed options for AI and data-center loads, such as a potential new large-load class, capacity commitment charges,…
Data centers would no longer be eligible for manufacturing-service rate schedules or General/Small Manufacturing Credits under the proposal. New or expanding data centers could face…
pending
Public Service Company of Oklahoma (PSO)
OK tariff PSO proposed a separate large-load electricity tariff for customers including data centers, cryptocurrency mining operations, artificial intelligence facilities, and installations requiring more than 75 megawatts. The proposal includes self-supply, partial-supply, and full-supply options,…
Data centers would face separate service terms, including long-term commitments, base and usage charges, collateral requirements, exit fees, and restrictions on early termination.…
pending
Evergy Kansas
KS tariff The Kansas Corporation Commission approved a settlement establishing a large-load power service rate plan for new facilities over 75 MW. The plan was agreed to by Evergy’s Kansas utilities, the Data Center Coalition, Sierra Club, NRDC, Google and other groups.
Data centers and other large-load customers over 75 MW may have up to five years to ramp up, followed by a minimum 12-year service term. They must pay a minimum monthly bill based on 80%…
approved
Nebraska Public Power District
NE other 2026-04-14 NPPD supported and informed the design of LB 1261, which passed into law on April 14, 2026. The law requires data center customers to build and maintain the energy infrastructure needed to serve them, bear 100% of the financial burden for new energy generation, and sign long-term contracts with…
Data center developers must bear the full cost of new energy-generation construction and associated infrastructure and enter into long-term contracts with the local public power district.…
approved
Lincoln Electric System
NE statement The Google data center in Lincoln is reshaping Lincoln Electric System’s electric system, accounting for 11% of the utility’s retail revenue and driving hundreds of megawatts of new wind energy.
The Google data center represents a substantial electric load for Lincoln Electric System and is contributing to additional wind-energy investment. The source does not state specific…
pending
CenterPoint Energy
TX statement In a first-quarter earnings presentation, CenterPoint Energy stated that ERCOT had approved 3.2 GW of data-center load, with another 9 GW expected to be submitted for approval. The company expects 8 GW to be energized by 2029, followed by an additional 4.2 GW, and is conducting a refreshed load…
CenterPoint reports 3.5 GW of data-center capacity already under construction in its Houston-area territory and expects 8 GW of data-center load to be energized by 2029. The utility said…
pending
ERCOT transmission/distribution utilities (statewide SB6 rulemaking)
TX other 2026-03-12 The Public Utility Commission of Texas voted to publish draft rule 16 TAC §25.194 to implement Texas SB 6 interconnection standards for new loads of 75 MW or greater. The proposed rule would impose interconnection fees, financial-security requirements, study fees, disclosure obligations, and…
Data centers and other projects involving 75 MW or more would need to provide site-control and permitting information, energization and generation data, study fees, and financial security…
pending
AEP Texas
AEP / American Electric Power
TX tariff AEP Texas has a pending large-load tariff proposal addressing cost responsibility for new large loads. The utility has 36 GW of large loads that comply with Senate Bill 6 and are backed by letters of agreement.
If adopted, the tariff would shift infrastructure costs associated with new large loads, including data centers, toward the customers driving those needs rather than existing customers.…
pending
Oncor Electric Delivery
TX Docket No. 59220 other 2026-01-09 FGE Goodnight I, LLC and Crusoe Energy Systems LLC jointly applied for approval to net meter the 265.5 MW GOODNIT1 wind facility with the proposed 260 MW Crusoe Load Two data center. The PUCT approved the arrangement, requiring full data-center curtailment within 30 minutes during an ERCOT…
Crusoe Load Two must fully disconnect during an ERCOT transmission emergency without financial compensation, and emergency curtailment is not capped by the capacity of the paired…
approved
Electric Reliability Council of Texas (ERCOT)
TX other 2026-08-03 Texas Gov. Greg Abbott ordered the PUCT and ERCOT to audit all data center projects in the ERCOT interconnection queue before additional projects advance. ERCOT suspended the first scheduled deliverable of its Batch Zero large-load interconnection process and planned to seek a good-cause exception…
The action could delay 49.8 GW of new data center electricity demand, with BNEF estimating potential project revenue at risk of just over $8 billion under a 60% AI-related capacity mix or…
pending
Electric Reliability Council of Texas (ERCOT)
TX other 2026-08-03 Texas Governor Greg Abbott directed the Public Utility Commission of Texas and ERCOT to conduct a comprehensive verification and audit of all data centers advancing through ERCOT’s interconnection process before additional projects may move forward. ERCOT stated that it would not issue project…
Data centers advancing through ERCOT’s interconnection process may not move forward until they complete the verification and audit process. Batch Zero projects face postponed…
pending
ERCOT transmission/distribution utilities (statewide SB6 rulemaking)
TX Project No. 58317 other 2025-07-29 Texas Senate Bill 6 directs the Public Utility Commission of Texas to establish new interconnection standards and cost-sharing requirements for ERCOT large-load customers, including customers with expected system demand exceeding 75 MW. It also requires rules addressing co-location with existing…
Data-center developers and other large-load customers may face additional interconnection delays, study and cost-sharing requirements, site-control and financial-commitment obligations,…
pending
ERCOT transmission/distribution utilities (statewide SB6 rulemaking)
TX Project 58480; Project 58481; Project 58479; Project 58482; Project 58484 other 2025-10-17 The Public Utility Commission of Texas is developing rules and evaluating policies under Texas Senate Bill 6 concerning large-load forecasting, interconnection standards, net-metering arrangements, demand-management services, and transmission-cost allocation. The materials state that proposed…
Data centers represent nearly 69% of the 189 GW of large-load requests tracked in the ERCOT queue. The proposed requirements could affect data-center interconnection, forecast…
pending
ERCOT transmission/distribution utilities (statewide SB6 rulemaking)
TX other 2026-03-12 The Public Utility Commission of Texas voted to publish draft 16 TAC §25.194 implementing Senate Bill 6 interconnection standards for new loads of 75 MW or greater. The proposed rule would require interconnection fees, financial security, disclosures, study fees, upfront payment of direct…
Data centers seeking at least 75 MW of new or expanded interconnection capacity would face a $50,000/MW non-refundable interconnection fee, $50,000/MW financial security, study fees,…
pending
Dominion Energy
VA tariff Dominion Energy’s Virginia tariff requires data centers to provide $1.5 million per MW in collateral.
Data center developers in Virginia may face substantially higher upfront collateral requirements than under the Texas SB6 proposals.
pending
Old Dominion Electric Cooperative (ODEC)
VA other 2025-03 PJM submitted a necessary studies agreement to study the grid effects of an LSP Digital Infrastructure project at or near LS Power’s Doswell power plant. ODEC protested, citing insufficient details about construction timing and when the data center would begin taking power from the grid.
The proposed colocated campus could include up to five 60-MW, always-on data center buildings, with LS Power selling up to 300 MW under a five-year power purchase agreement. ODEC raised…
contested
Black Hills Energy (Cheyenne Light, Fuel & Power)
Black Hills Corp.
WY other Black Hills stated that the proposed 1.8-gigawatt data center project in Cheyenne continues to move forward. Its Wyoming electric utility subsidiary filed a Certificate of Public Convenience and Necessity for a supporting substation in January, executed a substation agreement with the large-load…
The data center is expected to receive service under the Wyoming utility’s Large Power Contract Service Tariff through a dedicated substation. Service is expected to begin in early 2028,…
pending
Black Hills Corporation
WY tariff Black Hills Corporation serves data center and blockchain customers in the Cheyenne, Wyoming area under approved tariffs using a market energy procurement model. Earnings from these customers are separated from retail customers for rate-making purposes, providing utility-like returns without…
Data center developers and operators in the Cheyenne area may be served under the approved tariff and market energy procurement model. Existing customers, new customers, and expansions are…
approved
Grant PUD
WA statement Grant PUD plans to impose load-growth limits on data centers and notify each data-center customer of the additional megawatts remaining before its assigned limit is reached. The limits are intended to address potential outage and voltage-instability risks as data-center loads grow rapidly.
Data-center customers will face limits on additional load growth. Grant PUD may raise the limits after substation upgrades and increased transmission capacity allow the system to safely…
pending
Basin Electric Power Cooperative
ND tariff NextEra Energy Resources and Basin Electric Power Cooperative are considering jointly developing a 1,450-MW combined-cycle gas-fired power plant in North Dakota to serve a potential data center complex. They applied to the Southwest Power Pool’s fast-track interconnection study process to evaluate…
The proposed generation and transmission arrangements are intended to serve new, high-demand energy users such as data centers. Basin Electric said its program is intended to insulate…
pending
Maryland electric utilities (statewide large-load tariff docket)
MD other The page concerns large-load customer regulations and tariffs interconnecting to the electric system serving Maryland. The provided material does not state what was proposed, filed, or decided.
The provided material does not specify requirements, tariffs, interconnection procedures, cost allocation, delays, or other impacts on data-center developers or operators.
pending
Delmarva Power
DE tariff Delmarva Power proposed a large-load tariff. Stakeholders agreed to raise the eligibility threshold from 25 MW to 50 MW and exclude existing customers, while the Joint Agencies urged more stringent requirements.
Data-center and other large-load projects meeting the proposed 50 MW threshold could be subject to the tariff, while existing customers would be excluded. Additional requirements could…
pending
Delmarva Power
DE 25-0826 tariff The Delaware Public Service Commission opened docket 25-0826 to develop an interim large-load tariff for Delmarva Power customers using 25 MW or more, following a joint petition from PSC staff and the Division of the Public Advocate. The PSC also paused interconnection of new large-load facilities…
Data centers and other large-load facilities using 25 MW or more face a pause on new interconnections in Delmarva territory until the tariff is established. The tariff is intended to…
pending
PPL, PECO, and FirstEnergy Pennsylvania electric distribution companies
PA M-2025-3054271 tariff 2026-05-13 The Pennsylvania Public Utility Commission approved a model large-load tariff framework requiring single customers above 50 MW, or aggregated loads above 100 MW, to pay for grid infrastructure and interconnection upgrades caused by their projects. The framework also addresses deposits, collateral,…
Data centers and other large-load customers would bear the grid infrastructure and interconnection costs they cause rather than shifting those costs to households and small businesses. The…
approved
AEP
OH Case No. 24-508-EL-ATA tariff 2025-09 The Public Utilities Commission of Ohio denied OMAEG’s request for reconsideration and upheld its order authorizing AEP to implement a data center tariff. The PUCO rejected arguments that AEP had not demonstrated a capacity constraint, that its self-imposed moratorium was unlawful, or that the…
AEP is authorized to implement the data center tariff. OMAEG is considering whether to appeal the decision to the Supreme Court of Ohio.
denied
Ohio Edison; The Cleveland Electric Illuminating Company; The Toledo Edison Company
OH tariff 2026-06-12 The three FirstEnergy utilities filed an application with the Public Utilities Commission of Ohio seeking approval of a new Data Center Tariff, Schedule DCT. The proposed tariff includes long-term contract requirements, collateral tied to new infrastructure costs, minimum monthly billing demand…
Data-center customers would face additional contractual and financial protections intended to ensure they bear responsibility for infrastructure costs if a project does not materialize or…
pending
Alliant Energy
IA special contract Alliant implemented a five-year base electric-rate freeze in Iowa supported by data center growth. Alliant is also working with Meta to match energy and capacity requirements with clean energy.
Data center growth is identified as supporting rate stability in Iowa. Meta’s Wisconsin project is being coordinated with clean-energy matching for its energy and capacity requirements.
pending
Wisconsin Electric Power Company (WEPCO)
WI tariff 2026-04-24 The Public Service Commission of Wisconsin approved, subject to conditions, WEPCO’s proposed Very Large Customer and Bespoke Resources tariffs. The Commission extended the contract term to 15 years and required minimum billing demand charges based on forecasted or actual demand, whichever is higher.
Data-center customers must sign 15-year Energy Service Agreements, including the ramp-up period, and may be responsible for non-recoverable preparation costs, certain generating-resource…
approved
Kentucky Power
KY tariff The Kentucky PSC approved protections for large-load customers of 150 MW or more. These protections require upfront financial guarantees and long-term payment commitments, including when usage declines, to shield existing Kentucky Power customers from financial risk.
Data center customers must provide financial guarantees and make long-term payment commitments so existing Kentucky Power customers are not responsible if a project changes, leaves, or…
approved
Dayton Power & Light (AES Ohio)
OH Case 25-0960-EL-ATA et al. rate case A settlement in a PUCO proceeding requires Dayton Power & Light to file a separate proposal governing the interaction between Standard Service Offer service and data centers. The interim stipulation adopts a data-center tariff under which a data center may take SSO service only if it certifies…
The proposed framework would remove data-center load from the utility’s regular default service and establish a data-center-specific default-service class with hourly pricing and…
pending
AES Ohio
OH rate case In AES Ohio’s pending rate case, PUCO staff recommended that AES Ohio receive a new data center tariff creating separate rate classes for data centers. Staff acknowledged that AES Ohio has not experienced the same level of data center activity as AEP Ohio but said the utility should “get ahead” of…
Data centers in AES Ohio’s territory could be placed in separate rate classes under a new tariff. The recommendation would provide special rate treatment based on a potential future…
pending
East Kentucky Power Cooperative, Inc. (EKPC)
KY Case No. 2025-00140 tariff 2025-10-30 The Kentucky Public Service Commission approved EKPC’s Data Center Power tariff. The tariff applies to loads of 15 megawatts or more, with enhanced requirements for projects exceeding 250 megawatts, including uncapped application fees, scaled collateral, and a PSC-approved special contract for…
Data center developers must pay application and study-related costs, provide financial security, and obtain a project-specific PSC-approved special contract. The tariff is intended to…
approved
Northern States Power Co., d/b/a Xcel Energy
MN E-002/M-25-289 tariff 2025-10-13 Tract Capital Management, LP submitted comments to the Minnesota Public Utilities Commission on Xcel Energy’s proposed Large General Time of Day Service and Large Peak Controlled Time of Day Service tariffs for large-load customers. Tract recommended changes concerning incremental cost testing,…
The proposed tariffs would establish terms for serving new large-load customers, including data centers. Tract stated that greater predictability and transparency are needed regarding…
pending
Northern States Power Company, doing business as Xcel Energy
MN E002/M-25-___ tariff 2025-07-16 Northern States Power Company filed a petition with the Minnesota Public Utilities Commission seeking approval of new Large General Time of Day Service and Large Peak Controlled Time of Day Service tariffs for new or existing nonresidential customers with new electric demand of at least 100 MW.…
Data centers with new demand of at least 100 MW would generally be required to use one of the proposed tariffs, execute electric service and interconnection agreements, and obtain…
pending
Northern States Power Company, d/b/a Xcel Energy
MN E-002/M-25-289; E-002/M-25-387 (HCTS) tariff 2025-07-16 Xcel Energy filed a petition seeking approval of new Large General Time of Day Service and Large Peak Controlled Time of Day Service tariffs for very large customers, proposed as subclasses of the Demand class. The proposal includes a 100 MW eligibility threshold, 15-year default contract term,…
Data centers and other customers meeting the proposed 100 MW threshold could receive service under the new tariffs and related electric service agreements. The Minnesota Office of the…
contested
New York State Electric & Gas Corporation (NYSEG)
NY PSC Case 14-M-0094, et al. statement 2025-12-08 A December 8, 2025 paper discusses the potential effects of the Cayuga Data Campus on energy prices in Lansing. It states that NYISO and NYSEG must complete reliability studies, with the campus responsible for required system-upgrade costs, and explains potential effects on delivery and supply…
The Cayuga Data Campus would pay the system-upgrade costs required for reliable interconnection. Its large electricity consumption may spread fixed delivery costs across a larger base,…
pending
National Grid
NY Case 26-E-0045 tariff 2026-06-15 National Grid filed reply comments in the New York Public Service Commission’s Energize NY Development proceeding, supporting stronger forecasting discipline, financial commitments, and protections against non-materializing large loads while cautioning against one-size-fits-all mandates.
The proceeding may establish requirements for data-center load forecasting, financial commitments, credit support, interconnection cost allocation, and service classifications. No final…
pending
New York investor-owned utilities (statewide large-load interconnection reform)
NY other 2026-02 New York lawmakers proposed a three-year pause on approvals for new data centers above 20 MW. Governor Kathy Hochul directed the New York Public Service Commission to reform large-load interconnection rules, potentially addressing grid-upgrade costs, reliability, flexibility, on-site power, and…
Data center developers above 20 MW could face a three-year approval moratorium if the bill passes. Developers may also be required to bear more interconnection costs, operate flexibly,…
pending
Duke Energy
NC tariff Duke Energy filed a proposed “large load tariff” with the North Carolina Utilities Commission for data centers and other massive energy users. The proposal would require covered facilities to pay minimum monthly bills for at least 10 years and assume financial obligations supporting grid…
Data centers would face long-term minimum-payment obligations and would be required to pay for infrastructure such as substations and transmission lines built to serve their electricity…
contested
Dominion Energy South Carolina
SC 2026-9-E rate case 2026-07-02 PSC Order No. 2026-374 approved a large-load stipulation in Dominion Energy South Carolina’s general rate case. Dominion agreed to join and participate in generic Docket 2026-138-E, deferring issues involving new loads of 50 MW or more to that proceeding.
Data-center and other large-load arrangements will be reviewed in the statewide generic proceeding rather than resolved immediately in Dominion’s rate case. Developers may face future…
approved
Alabama Power
AL Docket 33709 special contract 2026-08-03 The Alabama Public Service Commission is deciding how to review contracts between Alabama Power and large data centers. Energy Alabama filed initial comments supporting a published large-load tariff, enforceable minimum obligations, public disclosure of power buyers, and an affirmative Commission…
Large data centers could be subject to a published large-load tariff and enforceable minimum obligations intended to keep risk with the data center rather than families and small…
pending
Tennessee Valley Authority (TVA)
TN tariff 2026-08-20 TVA planned to present a new large-load or data-center rate class to its Board for consideration on August 20, 2026. No final tariff or special rate class had been adopted as of July 17, 2026.
A dedicated large-load rate could establish different pricing and cost-allocation treatment for data-center customers. The final effect on data-center electricity costs remained…
pending
Entergy Louisiana
Entergy Corporation
LA U-37882 other 2026-03-27 Entergy Louisiana filed a proposal for more than 5,200 MW of generation across seven new gas combined-cycle plants, approximately 240 miles of 500kV transmission, battery storage, nuclear uprates, and up to 2,500 MW of Meta-funded renewables. The LPSC voted 4, 1 in April 2026 to fast-track the…
The proposal would add more than 5,200 MW of generation and related infrastructure for Meta Phase 2 and the Hyperion campus. The public application does not disclose the associated…
pending
Florida Power & Light (FPL)
FL PSC-2026-0022-S-EI tariff 2026-01 The Florida Public Service Commission approved FPL’s Large Load Contract Service tariffs, LLCS-1 and LLCS-2, effective January 1, 2026. LLCS-1 applies to new or incremental loads of 50 MW or more with an 85% or higher load factor in designated zones, while LLCS-2 applies outside those zones.
Data center developers in the LLCS-1 zones face a combined 3 GW cap, a $28.07 per kW per month incremental generation charge, a 20-year minimum term, a 70% minimum take-or-pay demand…
approved
Florida Power & Light
FL 20250011-EI tariff 2026-01-01 FPL’s Incremental Generation Charge was approved as part of a contested, non-unanimous settlement in its 2025 base-rate case. Rate schedules LLCS-1 and LLCS-2 apply to new or incremental load of 50 MW or more with a load factor of at least 85%.
New or incremental large-load customers, including data centers, must pay incremental generation costs in addition to embedded cost-based rates. Transmission interconnection is handled…
approved
Oklahoma Gas and Electric Co. (OG&E)
OK tariff 2026-06 OG&E submitted a proposed comprehensive large-load tariff to the Oklahoma Corporation Commission for high-energy users such as data centers. The proposal includes upfront infrastructure payments, customer protection charges, a proposed 15-year minimum service term, exit fees, financial security…
Data centers and other large-load customers would be required to bear allocated electricity-service and infrastructure costs, provide collateral, pay minimum charges tied to reserved…
pending
Unified Government Board of Public Utilities (BPU)
KS other 2025-05-29 Developers of a proposed $12.6 billion data center business park pledged to fund utility upgrades, including two BPU substations. The planning commission voted 4-2 to recommend approval, while Kansas approved a 20-year state sales tax exemption for qualifying data centers.
The project would require 600 megawatts of service, exceeding BPU’s stated 500-megawatt capability, and would require additional substations and power from the Southwest Power Pool. The…
contested
Nebraska Public Power District (NPPD)
NE rate case 2026-04-21 NPPD reported that it was evaluating a new large-load rate planned for a January 1, 2027 effective date to recover costs from new high-demand customers and protect existing customers. The rate was still under development and had not been board-approved.
A future NPPD large-load rate could require new high-demand customers, including data centers, to bear costs associated with serving their load and help protect existing customers from…
pending
South Central Public Power District
NE tariff 2025-01-01 The District revised and made effective Large Power Schedule LP-3, Rate Schedules 60, 61, and 62 (Sub 8), for Large Power Service Over 7,500 Installed KVA. The tariff establishes energy, demand, transmission, distribution, billing-demand, minimum-charge, power-factor, and…
Data centers requiring 7,500 kVA or more of installed transformer capacity may qualify for the tariff if located on or near the District’s qualifying facilities. Applicable costs include…
approved
Public Utility District No. 1 of Chelan County (Chelan PUD)
WA tariff 2024-06-01 Chelan PUD published tariff provisions for high-density and data-center-related loads. Rate 36 for data centers and similar loads became effective June 1, 2024, while Schedule 35 for high-density loads became effective February 1, 2024; commissioners also approved 3% electric rate increases…
Data centers and similar computing loads up to 3 MW are directed to Schedule 35 or Rate 36, which include demand charges, energy charges, and an upfront capital charge. A power-sales…
approved
HILCO Electric Cooperative, Inc.
TX other Infrakey DC Parks LLC and HILCO Electric Cooperative, Inc. signed a Memorandum of Understanding establishing a framework for 150 MW of dedicated nameplate power capacity for the Lacy Lakeview Data District in McLennan County, Texas. The parties intend to finalize definitive electric service…
The MoU provides a planned pathway for retail electric service and wholesale transmission service for the Lacy Lakeview Data District, targeting commercial operation on 2027-03-15. Power…
pending
Dominion Energy Virginia
Dominion Energy
VA PUR-2025-00058 rate case 2025-11 In its November 2025 final order in Dominion’s biennial rate review, the Virginia State Corporation Commission created the GS-5 rate class for new customers with demand of at least 25 MW on a contiguous site and a load factor of at least 75%. The order requires long-term contracts, minimum demand…
New qualifying AI data centers taking service after January 1, 2027 will face long-term minimum payment obligations, collateral requirements, and potential exit fees, shifting…
approved
Virginia Electric and Power Company (Dominion Energy Virginia)
Dominion Energy, Inc.
VA PUR-2026-00011 other 2026-02-02 Virginia Electric and Power Company filed an application with the Virginia State Corporation Commission seeking approval of Large-Load Connection Queue Process Standards. The proposed standards create a formal four-stage process for evaluating and connecting large-load delivery-point requests,…
Data-center developers and their electric distribution companies would need to submit delivery-point requests through Dominion Energy Virginia’s Delivery Point Exchange, provide specified…
pending
Virginia Electric and Power Company (Dominion Energy; VEPCO)
VA Case No. PUR 2023-2023-00217 IRP 2024 Dominion Energy’s 2024 Integrated Resource Plan establishes four resource portfolios through 2039 to meet projected demand, including extreme load growth from proposed data centers. The plan includes gas-fired generation, nuclear power, renewable energy, storage, and infrastructure investments,…
Data-center demand is projected to increase energy demand by 5.5% annually and double overall demand by 2039; without data centers, peak demand would grow by 0.47% annually. Infrastructure…
contested
Appalachian Power Company (APCo)
VA PUR-2026-00044 tariff 2025-03-24 APCo filed proposed modifications to its Large Power Service tariff, Rate Schedule L.P.S., for new large-load additions of at least 150 MW on an aggregated basis or 100 MW at an individual site. The SCC approved the schedule on 2026-06-01, with modifications to collateral requirements and exit fees.
Data center and other large-load developers using Schedule L.P.S. would face long-term contract commitments, advance notice requirements, minimum monthly billing demand, collateral…
approved
Virginia investor-owned utilities (statewide SCC technical conference)
VA other The Virginia State Corporation Commission scheduled a technical conference to evaluate the impacts of data centers and other large energy users. Potential regulatory changes include revised utility line-extension policies, direct assignment of transmission costs, and a tariff with minimum contract…
Data-center developers may face revised line-extension rules, direct assignment of transmission costs, minimum contract terms, and collateral requirements. These measures are intended to…
pending
PJM Interconnection
PJM tariff 2024-10 PJM Interconnection filed proposed tariff revisions with the Federal Energy Regulatory Commission in October 2024. The revisions would require new large loads exceeding 100 MW, primarily data centers, to execute a Firm Capacity Service Agreement and post financial security before receiving a firm…
Data centers exceeding 100 MW would generally need to post financial security of $15/kW, with the deposit subject to forfeiture if the project withdraws within 24 months of receiving a…
contested
Pacific Gas and Electric Company (PG&E)
CA Resolution E-5420 special contract 2025-10-30 The California Public Utilities Commission adopted Resolution E-5420 approving two agreements between PG&E and STACK Infrastructure to interconnect and energize STACK’s 90 MW Silicon Valley data center. The Commission modified the refund process to provide annual refunds equal to 75% of…
STACK must pay the actual costs of PG&E’s special facilities and transmission work as incurred, rather than making a one-time advance payment. STACK is ineligible for PG&E’s 50% discount…
approved
Pacific Gas and Electric (PG&E)
CA Resolution E-5455; PG&E Advice Letter 7785-E special contract 2025-12-18 PG&E asked the California Public Utilities Commission to approve an exceptional case agreement with Google LLC for a new 250 MW transmission-level retail load at 230 kV in San Jose. The CPUC delayed its vote on Advice Letter 7785-E, with the vote moved from August 13, 2026, to September 3, 2026.
The agreement would provide service for a 250 MW Google data center load at 230 kV. Its ratepayer protections could become de facto large-load terms for later hyperscaler or data-center…
pending
Portland General Electric (PGE)
OR tariff 2026-05-07 The Oregon Public Utility Commission approved PGE’s new large-load tariff framework. The tariff applies to new customers with loads exceeding 20 MW and requires customers creating the demand to bear the costs of serving their large loads, including necessary infrastructure.
The tariff may increase power costs for new data-center facilities while providing greater certainty around grid access and infrastructure-development timelines. It may also encourage…
approved
Salt River Project (SRP); Arizona Public Service (APS); Tucson Electric Power (TEP)
AZ statement 2026-04 SRP, APS, and TEP stated that large-load data center customers will be responsible for their infrastructure and service costs. The Arizona Corporation Commission opened a docket and held a workshop to consider policies for large-load customers and protections for ratepayers.
Data center developers must pay applicable infrastructure, minimum energy, forecasted demand, or full cost-of-service charges. SRP requires customers using more than 20 megawatts to pay…
pending
Cheyenne Light, Fuel & Power Company, doing business as Black Hills Energy
Black Hills Corp. (NYSE: BKH)
WY tariff Black Hills Energy serves qualifying Wyoming data center customers through its Large Power Contract Service tariff, which has been in place since 2016. The tariff was developed with an early data center customer to support growing industrial and data center load while protecting other customers…
The tariff provides customized energy solutions for data center operations, including support for mission-critical electric reliability and sustainability objectives. It is intended to…
approved
Cheyenne Light, Fuel and Power Company, doing business as Wyoming Electric and Black Hills Energy
Black Hills Corporation
WY special contract 2026-04-22 Wyoming Electric entered into a generation reservation agreement with a prospective customer seeking to construct a 1.8 GW data center under its Large Power Contract Service tariff. The agreement received refundable advances and was amended in July 2026 to increase those advances to $377 million…
The agreement supports procurement of long-lead-time generation equipment for the prospective data center while definitive service and generation arrangements remain under negotiation.
pending
No matches.

Interconnection queue

Large-load and data center cluster studies from state utility commissions and utility filings, and the data-center-flagged rows in the national generation and large-load queues. Source and resource breakdowns for the full 32,326-row queue are in the panel above.

Large-load and data center cluster studies

UtilityStateStudyRequested MWFiledStatusSource
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 1; announced load 3,500 MW and initial in-service date Q2 2031. Project name, type, city,…
3,500 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 2; announced load 3,210 MW and initial in-service date Q2 2028. Project name, type, city,…
3,210 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 3; announced load 3,000 MW and initial in-service date Q4 2027. Project name, type, city,…
3,000 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 4; announced load 2,000 MW and initial in-service date Q2 2028. Project name, type, city,…
2,000 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 5; announced load 2,000 MW and initial in-service date Q2 2028. Project name, type, city,…
2,000 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 6; announced load 2,000 MW and initial in-service date Q2 2028. Project name, type, city,…
2,000 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 7; announced load 1,600 MW and initial in-service date Q2 2030. Project name, type, city,…
1,600 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 8; announced load 1,500 MW and initial in-service date Q4 2027. Project name, type, city,…
1,500 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 9; announced load 1,463 MW and initial in-service date Q4 2027. Project name, type, city,…
1,463 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 10; announced load 1,400 MW and initial in-service date Q2 2032. Project name, type, city,…
1,400 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 11; announced load 1,400 MW and initial in-service date Q2 2028. Project name, type, city,…
1,400 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 12; announced load 1,200 MW and initial in-service date Q2 2028. Project name, type, city,…
1,200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 13; announced load 1,200 MW and initial in-service date Q2 2028. Project name, type, city,…
1,200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 14; announced load 1,200 MW and initial in-service date Q4 2027. Project name, type, city,…
1,200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 15; announced load 1,200 MW and initial in-service date Q4 2027. Project name, type, city,…
1,200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 16; announced load 1,200 MW and initial in-service date Q4 2027. Project name, type, city,…
1,200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 17; announced load 1,200 MW and initial in-service date Q4 2027. Project name, type, city,…
1,200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 18; announced load 1,115 MW and initial in-service date Q2 2028. Project name, type, city,…
1,115 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 19; announced load 1,020 MW and initial in-service date Q4 2027. Project name, type, city,…
1,020 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 20; announced load 1,000 MW and initial in-service date Q2 2028. Project name, type, city,…
1,000 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 21; announced load 910 MW and initial in-service date Q4 2027. Project name, type, city, county,…
910 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 22; announced load 910 MW and initial in-service date Q4 2027. Project name, type, city, county,…
910 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 23; announced load 910 MW and initial in-service date Q4 2027. Project name, type, city, county,…
910 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 24; announced load 860 MW and initial in-service date Q2 2029. Project name, type, city, county,…
860 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 25; announced load 840 MW and initial in-service date Q2 2029. Project name, type, city, county,…
840 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 26; announced load 750 MW and initial in-service date Q4 2027. Project name, type, city, county,…
750 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 27; announced load 725 MW and initial in-service date Q4 2027. Project name, type, city, county,…
725 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 28; announced load 725 MW and initial in-service date Q4 2027. Project name, type, city, county,…
725 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 29; announced load 651 MW and initial in-service date Q4 2027. Project name, type, city, county,…
651 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 30; announced load 648 MW and initial in-service date Q4 2027. Project name, type, city, county,…
648 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 31; announced load 648 MW and initial in-service date Q4 2027. Project name, type, city, county,…
648 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 32; announced load 600 MW and initial in-service date Q2 2028. Project name, type, city, county,…
600 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 33; announced load 600 MW and initial in-service date Q4 2027. Project name, type, city, county,…
600 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 34; announced load 600 MW and initial in-service date Q4 2027. Project name, type, city, county,…
600 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 35; announced load 600 MW and initial in-service date Q4 2027. Project name, type, city, county,…
600 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 36; announced load 576 MW and initial in-service date Q4 2027. Project name, type, city, county,…
576 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 37; announced load 567 MW and initial in-service date Q2 2030. Project name, type, city, county,…
567 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 38; announced load 550 MW and initial in-service date Q4 2027. Project name, type, city, county,…
550 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 39; announced load 550 MW and initial in-service date Q4 2027. Project name, type, city, county,…
550 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 40; announced load 550 MW and initial in-service date Q2 2030. Project name, type, city, county,…
550 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 41; announced load 500 MW and initial in-service date Q4 2027. Project name, type, city, county,…
500 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 42; announced load 500 MW and initial in-service date Q2 2029. Project name, type, city, county,…
500 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 43; announced load 500 MW and initial in-service date Q4 2027. Project name, type, city, county,…
500 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 44; announced load 500 MW and initial in-service date Q2 2030. Project name, type, city, county,…
500 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 45; announced load 481 MW and initial in-service date Q2 2029. Project name, type, city, county,…
481 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 46; announced load 480 MW and initial in-service date Q4 2027. Project name, type, city, county,…
480 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 47; announced load 455 MW and initial in-service date Q4 2027. Project name, type, city, county,…
455 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 48; announced load 455 MW and initial in-service date Q4 2027. Project name, type, city, county,…
455 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 49; announced load 455 MW and initial in-service date Q4 2027. Project name, type, city, county,…
455 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 50; announced load 455 MW and initial in-service date Q2 2029. Project name, type, city, county,…
455 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 51; announced load 450 MW and initial in-service date Q4 2027. Project name, type, city, county,…
450 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 52; announced load 450 MW and initial in-service date Q4 2027. Project name, type, city, county,…
450 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 53; announced load 450 MW and initial in-service date Q2 2030. Project name, type, city, county,…
450 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 54; announced load 432 MW and initial in-service date Q4 2027. Project name, type, city, county,…
432 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 55; announced load 420 MW and initial in-service date Q4 2027. Project name, type, city, county,…
420 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 56; announced load 405 MW and initial in-service date Q4 2027. Project name, type, city, county,…
405 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 57; announced load 365 MW and initial in-service date Q4 2027. Project name, type, city, county,…
365 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 58; announced load 365 MW and initial in-service date Q4 2027. Project name, type, city, county,…
365 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 59; announced load 360 MW and initial in-service date Q4 2027. Project name, type, city, county,…
360 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 60; announced load 360 MW and initial in-service date Q2 2029. Project name, type, city, county,…
360 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 61; announced load 350 MW and initial in-service date Q2 2028. Project name, type, city, county,…
350 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 62; announced load 350 MW and initial in-service date Q4 2027. Project name, type, city, county,…
350 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 63; announced load 325 MW and initial in-service date Q2 2028. Project name, type, city, county,…
325 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 64; announced load 300 MW and initial in-service date Q4 2027. Project name, type, city, county,…
300 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 65; announced load 300 MW and initial in-service date Q2 2028. Project name, type, city, county,…
300 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 66; announced load 264 MW and initial in-service date Q4 2027. Project name, type, city, county,…
264 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 67; announced load 252 MW and initial in-service date Q2 2028. Project name, type, city, county,…
252 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 68; announced load 250 MW and initial in-service date Q4 2027. Project name, type, city, county,…
250 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 69; announced load 240 MW and initial in-service date Q4 2027. Project name, type, city, county,…
240 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 70; announced load 240 MW and initial in-service date Q2 2029. Project name, type, city, county,…
240 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 71; announced load 230 MW and initial in-service date Q2 2029. Project name, type, city, county,…
230 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 72; announced load 216 MW and initial in-service date Q2 2029. Project name, type, city, county,…
216 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 73; announced load 216 MW and initial in-service date Q2 2029. Project name, type, city, county,…
216 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 74; announced load 200 MW and initial in-service date Q4 2027. Project name, type, city, county,…
200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 75; announced load 200 MW and initial in-service date Q4 2027. Project name, type, city, county,…
200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 76; announced load 180 MW and initial in-service date Q2 2029. Project name, type, city, county,…
180 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 77; announced load 180 MW and initial in-service date Q2 2028. Project name, type, city, county,…
180 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 78; announced load 175 MW and initial in-service date Q2 2028. Project name, type, city, county,…
175 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 79; announced load 144 MW and initial in-service date Q2 2029. Project name, type, city, county,…
144 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 80; announced load 50 MW and initial in-service date Q4 2027. Project name, type, city, county,…
50 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 81; announced load 50 MW and initial in-service date Q2 2029. Project name, type, city, county,…
50 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 82; announced load 45 MW and initial in-service date Q4 2027. Project name, type, city, county,…
45 2026-05-15 pending
Arizona Public Service
large load request
AZ ACC Data Center/Large Load Workshop Highlights
Docket E-00000A-25-0069
ACC workshop materials report APS's estimated large-customer peak-demand load at approximately 13.1 GW in 2026; APS has developed a prospective…
13,100 2026-04-20 pending
Salt River Project
large load request
AZ ACC Data Center/Large Load Workshop Highlights
Docket E-00000A-25-0069
ACC workshop materials state that SRP serves 59 large-load customers with nearly 7,000 MW combined load and has a prospective data-center queue;…
7,000 2026-04-20 approved
Xcel Energy, Colorado
other
CO Proposed Large Load Tariff
Xcel submitted a proposed Colorado large-load tariff for new customers or significant expansions of 50 MW or more; it requires interconnection and…
2026-04-02 pending
Dominion Energy Virginia
large load request
VA Large-Load Connection Queue Process Standards
Docket PUR-2026-00011
Dominion's aggregate large-load delivery-point queue was reported at about 70 GW, with approximately 45 GW under study and most requests tied to…
70,000 2026-02-02 pending
AEP Ohio
cluster study
OH AEP Ohio Schedule DCT Load Study, Cluster 1
Docket 24-508-EL-ATA
Aggregate formal-load-study cluster of new data-center projects totaling 5,454.5 MW. Individual customer names, MW values, and POIs were not…
5,454.5 2025-11-07 pending
AEP Ohio
cluster study
OH AEP Ohio Schedule DCT Load Study, Cluster 2
Docket 24-508-EL-ATA
Aggregate formal-load-study cluster of new data-center projects totaling 4,353.2 MW. Individual customer names, MW values, and POIs were not…
4,353.2 2025-11-07 pending
AEP Ohio
cluster study
OH AEP Ohio Schedule DCT Load Study, Cluster 3
Docket 24-508-EL-ATA
Aggregate formal-load-study cluster of new data-center projects totaling 3,215.0 MW. Individual customer names, MW values, and POIs were not…
3,215.0 2025-11-07 pending
Duke Energy Carolinas
integrated resource plan appendix
SC Carolinas Resource Plan revision for large site projects
Duke's revised forecast identifies 35 large site projects, including announced data centers, requiring 24.7 TWh/year by 2033. The public report does…
approved
ERCOT
cluster study
TX Batch Zero Interconnection Study Process for Large Loads
Docket PGRR145
ERCOT's Batch Zero process applies to large-load facilities of 75 MW or more. The public page gives process thresholds and deadlines but publishes…
pending
Xcel Energy
special contract
MN Meta / Amber Kestral enterprise data-center filing
Public reporting on an MPUC-related Xcel filing says the enterprise data-center project was expected to start at at least 10 MW and exceed 75 MW in…
pending
No matches.

Data center flagged queue rows

ProjectISO / utilityStateDeveloperMWResourceStatus
Giga Texas Data Center
Travis
ERCOT Giga Texas Energy, LLC 133 battery IA signed
Bullock Gas
Hill
ERCOT Bullock Data Center, LLC 1,400 gas study
Liberty Thermal Energy Center
Hill
ERCOT Liberty Data Center I, LLC 1,400 gas study
IRON MOUNTAIN WIND ENERGY
SAN BERNARDINO
CAISO CA 149.4 wind withdrawn
IRON MOUNTAIN SOLAR 1
RIVERSIDE
CAISO CA 49.5 solar withdrawn
IRON MOUNTAIN SOLAR 2
RIVERSIDE
CAISO CA 49.5 solar withdrawn
WARD VALLEY SOLAR ENERGY 2
SAN BERNARDINO
CAISO CA 250 solar withdrawn
MARTELLA SOLAR
KINGS
CAISO CA 20 solar withdrawn
North Country Data Center
St. Lawrence
NYISO NY North Country Data Center 435 other active
St Lawrence Data and Agricultural Center
St. Lawrence
NYISO NY ZeroC Data Centers, LLC 200 other study
SDC St. Lawrence
St. Lawrence
NYISO NY Sabey Data Center Properties, LLC 120 other study
Suffern Quarry Data Center
Rockland
NYISO NY Robert Delcalzo 200 other withdrawn
Hudson Valley Data Center
Rockland
NYISO NY Equity Suffern Developers, LLC 50 other withdrawn
Hudson Valley Data Center
Rockland
NYISO NY Robert Delcalzo 50 other study
New York State Artificial Intelligence Data Center
St. Lawrence
NYISO NY ZeroC Data Centers, LLC 300 other withdrawn
Olean Digital Data Center
Cattaraugus
NYISO NY Olean Digital LLC 300 other withdrawn
Greenidge 200 MW Data Center Project
Yates
NYISO NY Greenidge Generation, LLC 200 other study
New York State Artificial Intelligence Data Center
St. Lawrence
NYISO NY ZeroC Data Centers, LLC 300 other study
Wulf Compute Data Center II
Niagara
NYISO NY TeraWulf Brookings LLC 250 other study
1 Gig Data Center East Fishkill, NY
Dutchess
NYISO NY Donovan Drive Holdings LLC 1,000 other study
North East Data LLC Data Center
Niagara
NYISO NY North East Data LLC 500 other study
Brookhaven Data Center
Suffolk
NYISO NY Brookhaven Logistics Center, LLC 300 other withdrawn
Pontoon Bridge Road Data Center
St Lawrence
NYISO NY American Data Center Partners LLC 250 other study
Massena Development LLC Power Allocation
St; Lawrence
NYISO NY North Country Data Center LLC 200 other study
iPark 84 Data Center Interconnection
Dutchess
NYISO NY iPark East Fishkill LLC 150 other study
NYISO Load Interconnection Process - Data Center Inquiry
Horseheads
NYISO NY URI TALY 150 other study
Highwall Data Center
Clearfield
NYISO PA Highwall Energy, LLC 400 other study
Compass
Rockland
NYISO NY PPL Electric Utilities 0 other withdrawn
Cedar Lake Solar
St. Lawrence
NYISO NY Emeren US, LLC 8.4 hybrid withdrawn
Suffern Quarry Data Center
Rockland
NYISO NY Orange & Rockland 0 other withdrawn
Bethlehem Energy Center Uprate
Albany
NYISO NY GB II New York 875 gas withdrawn
Colora Tap
Cecil
PJM MD 465 gas other
Colora Tap
Cecil
PJM MD 465 gas other
Colora 34.5kV
Cecil
PJM MD 10 solar withdrawn
Hopewell-Surry 230kV
Surry
PJM VA 142.4 solar other
Dawson-South Justice 115kV
Alamance
PJM NC 60 solar other
Dawson-South Justice 115kV
Alamance
PJM NC 80 solar other
Dawson-South Justice 115kV
Halifax
PJM NC 20 solar withdrawn
Dawson-South Justice 115kV
Halifax
PJM NC 140 solar other
Colora 230 kV
Cecil
PJM MD 100.8 battery withdrawn
Colonial Trail 230 kV
Surry
PJM VA 160 battery withdrawn
Hopewell - Colonial Trail 230 kV
Surry
PJM VA 150 hybrid active
Colonial Trail - Surry 230 kV
Surry
PJM VA 80 solar withdrawn
New Halifax - Dawson 115 kV
Halifax
PJM NC 74.9 hybrid withdrawn
Dawson-South Justice 115kV
Halifax
PJM NC 140 solar withdrawn
Colora 230 kV
Cecil
PJM MD 100.8 battery withdrawn
No matches.

Public companies

Publicly traded issuers with material exposure to tracked projects or jurisdictions, with links to SEC EDGAR and the most recent disclosure on record.

TickerCompanyExposureEDGARMost recent disclosure
DLR Digital Realty Trust Multi-tenant Texas exposure via Dallas metro; commented favorably on Abbott initiative Aug 7, 2026 Filings ↗ 2026-08-07 · press: Digital Realty Welcomes Abbott Initiative
3 on record
APLD Applied Digital Texas-heavy HPC portfolio Filings ↗ 2026-07-29 · 10-K: Applied Digital fiscal 2026 annual report covering AI data center buildout and risk…
4 on record
IREN Iris Energy (IREN) Childress, TX facility Filings ↗ 2026-08-13 · 8-K: IREN delivers Horizon 1 50MW AI data center to Microsoft at Childress Texas
3 on record
RIOT Riot Platforms Rockdale + Corsicana + Navarro, TX Filings ↗ 2026-08-10 · 8-K: $9.1B AI lease at Rockdale + Q2 2026 results
5 on record
MARA Marathon Digital Texas presence via various JVs Filings ↗ 2026-08-06 · 10-Q: MARA second quarter 2026 report disclosing ERCOT Batch Zero and August 3 2026 Texas…
3 on record
CLSK CleanSpark Texas operations, filed explicit moratorium disclosure Filings ↗ 2026-08-06 · 10-Q: CleanSpark third quarter fiscal 2026 report disclosing August 3 2026 Abbott directive…
3 on record
BTDR Bitdeer Texas mining-to-HPC transition Filings ↗ 2026-08-10 · 6-K: Bitdeer reports unaudited second quarter 2026 results with AI cloud and HPC leasing update
3 on record
CORZ Core Scientific TX HPC exposure; recent AMD AI datacenter pact Filings ↗ 2026-08-14 · 8-K: Core Scientific reports update on merger with CoreWeave
4 on record
BE Bloom Energy On-site power partner Filings ↗ 2026-07-28 · 10-Q: Bloom Energy Q2 2026 Form 10-Q, quarterly report with data center fuel cell agreements
3 on record
AMZN Amazon (AWS) Texas 7.65 GW gas plant + Hobart lawsuit + Tucson cancellation Filings ↗ 2026-08-07 · news: Amazon confirmed as backer of 7.65 GW private gas power plant for Texas data centers
4 on record
MSFT Microsoft Stargate/Abilene + Wisconsin cancellations Filings ↗ 2026-07-29 · 10-K: Microsoft fiscal 2026 Form 10-K, annual report with cloud and AI infrastructure spending
3 on record
GOOGL Alphabet/Google Armstrong TX (BTM) + Pine Island MN (litigation) + Indiana cancellation Filings ↗ 2026-07-23 · 10-Q: Alphabet Q2 2026 Form 10-Q, quarterly report with technical infrastructure investment
4 on record
META Meta Platforms TX facility reported near Austin (unverified) Filings ↗ 2026-08-10 · news: Abbott data center agreement with Meta appears to have no impact on Northeast El Paso…
3 on record
ORCL Oracle Abandoned TX site March 2026; Wisconsin lawsuit; Shackelford Cty delay Filings ↗ 2026-08-17 · news: Oracle drops lawsuit challenging Wisconsin data center credit rules
3 on record
NVDA NVIDIA OpenAI datacenter lease disclosure (10-Q Aug 17) Filings ↗ 2026-08-17 · news: OpenAI to lease Ohio data center backed by NVIDIA guarantee
3 on record
No matches.

Filings and disclosures

SEC filings with delay or moratorium disclosure language, plus investor press releases and material news on record for watchlist issuers. Newest first.

TickerFormDateFiling
ORCL news 2026-08-17 Oracle drops lawsuit challenging Wisconsin data center credit rules
Litigation over data center tariffs, Port Washington project
NVDA news 2026-08-17 OpenAI to lease Ohio data center backed by NVIDIA guarantee
NVIDIA lease and power payment guarantee for AI data center
FRMI 10-Q 2026-08-14 Project Matador, Amarillo, Texas (private-grid AI data center and nuclear/gas power campus)
Fermi disclosed that Texas's evolving regulatory environment for data centers, including SB6, NOGRR 282, and NPRR 1308, and Governor Abbott's August 3, 2026 directive for PUCT/ERCOT to audit data centers advancing…
CORZ 8-K 2026-08-14 Core Scientific reports update on merger with CoreWeave
CoreWeave acquisition of Core Scientific
IREN 8-K 2026-08-13 IREN delivers Horizon 1 50MW AI data center to Microsoft at Childress Texas
Texas AI data center delivery milestone
IREN news 2026-08-13 IREN delivers Horizon 1 to Microsoft and achieves NVIDIA exemplar cloud status on GB300 NVL72
Texas AI cloud deployment milestone
CRWV 10-Q 2026-08-12 CoreWeave data center delivery / delayed data center site amortization
CoreWeave's Q2 2026 10-Q defines a 'delayed data center site amortization date' in its credit facility terms for data center sites that did not meet certain delivery requirements by a specified date, confirming…
RIOT 10-Q 2026-08-10 Corsicana Facility and Rockdale Facility, Texas (ERCOT interconnection)
Riot disclosed that on August 3, 2026 Texas Governor Abbott directed the PUCT and ERCOT to conduct a comprehensive audit of all data center projects advancing through ERCOT's interconnection process, which could delay…
RIOT 8-K 2026-08-10 $9.1B AI lease at Rockdale + Q2 2026 results
RIOT 8-K 2026-08-10 Riot second quarter 2026 results with Rockdale AI lease expansion and Corsicana 1 GW letter of intent
Texas AI lease expansion and Corsicana LOI
BTDR 6-K 2026-08-10 Bitdeer reports unaudited second quarter 2026 results with AI cloud and HPC leasing update
Q2 results, AI cloud and HPC leasing, Rockdale Texas
META news 2026-08-10 Abbott data center agreement with Meta appears to have no impact on Northeast El Paso project
Texas standards and incentive exposure for El Paso campus
DLR press 2026-08-07 Digital Realty Welcomes Abbott Initiative
DLR press 2026-08-07 Digital Realty welcomes Governor Abbott initiative for responsible Texas data center investment
Texas oversight, ERCOT, grid reliability commitment
AMZN news 2026-08-07 Amazon confirmed as backer of 7.65 GW private gas power plant for Texas data centers
Texas behind-the-meter gas power for AI data centers
CLSK 10-Q 2026-08-06 Sandersville, Georgia HPC data center (Sandersville Lease) and Texas ERCOT interconnection sites
CleanSpark disclosed the August 3, 2026 letter from Texas Governor Greg Abbott directing ERCOT and the PUCT to audit all data centers advancing through the ERCOT interconnection process before they can proceed, plus…
MARA 10-Q 2026-08-06 MARA behind-the-meter data center sites (Texas)
MARA's 10-Q references the ERCOT/CenterPoint 'Batch Zero' large-load interconnection review process affecting timing for its behind-the-meter data center power arrangements in Texas.
WULF 10-Q 2026-08-05 Cayuga Site, Lansing, New York (HPC data center development)
TeraWulf disclosed that in July 2026 New York Governor Kathy Hochul issued Executive Order No. 62, temporarily pausing certain discretionary permits and approvals for covered data center projects, directly implicating…
NI 10-Q 2026-08-05 NIPSCO data center contracts with Google/Alphabet (ADS Contract)
NiSource's 10-Q discloses material dependence on performance under its 'ADS Contract' data center agreement with Alphabet subsidiary ADS, warning that any decision by ADS or Alphabet to terminate or reduce committed…
BTDR 6-K 2026-08-05 Bitdeer reports AI and HPC colocation lease at Tydal Norway
AI/HPC colocation lease
CIFR 10-Q 2026-08-04 Odessa Facility, Texas (Luminant Lease Agreement) and 700MW HPC hyperscaler pipeline across Texas/Ohio
Cipher disclosed that operations require approval from Oncor, AEP, and/or ERCOT to energize each data center, and that deposits with Oncor and AEP for interconnection infrastructure are contingent on energizing sites…
WEC 10-Q 2026-08-04 WEC Energy large-scale data center customer projects (Wisconsin)
WEC Energy Group's 10-Q lists project termination, cancellation, or delay by data center and other large-scale customers as an explicit risk factor, alongside public opposition to data centers and failure to garner…
HUT 10-Q 2026-08-04 Hut 8 site-level ERCOT interconnection exposure
Hut 8's Q2 2026 10-Q incorporates by reference its annual report risk factor discussion regarding potential impacts from evolving data center regulatory and tax abatement scrutiny across its jurisdictions, without new…
ETR 10-Q 2026-07-31 Meta Platforms data center project, Richland Parish, Louisiana (Entergy Louisiana electric service agreement)
Entergy's 10-Q discloses that in June 2026 intervenors in a Louisiana Public Service Commission (LPSC) proceeding sought a subpoena of Meta Platforms to obtain information about its data center project's investment,…
D 10-Q 2026-07-31 Loudoun County, Virginia data center cluster ('Data Center Alley')
Dominion Energy's 10-Q specifically names Loudoun County, Virginia as a concentration risk for data center-driven demand growth, warning about the ability to obtain regulatory, environmental, and other permits to…
DLR 10-Q 2026-07-31 Digital Realty Trust Q2 2026 Form 10-Q, quarterly report with data center portfolio and development
Dallas metro and Texas development exposure
AMZN 10-Q 2026-07-31 Amazon.com Q2 2026 Form 10-Q, quarterly report with elevated data center capital expenditures
AWS data center buildout and capex
XEL 10-Q 2026-07-30 Xcel Energy data center customer tariffs (multi-state)
Xcel Energy's 10-Q discusses new data center-specific tariffs including minimum demand/revenue requirements and termination or exit fees, designed to ensure data center customers pay the incremental costs to serve…
META 10-Q 2026-07-30 Meta Platforms Q2 2026 Form 10-Q, quarterly report with data center and AI capital expenditures
Data center capex and El Paso venture context
APLD 10-K 2026-07-29 Applied Digital HPC data center campuses (Texas/North Dakota development pipeline)
Applied Digital's 10-K risk factors note that governmental authorities have historically imposed moratoria on data center development citing energy usage concerns, and that lessees may terminate leases if construction…
MSFT 10-K 2026-07-29 Microsoft fiscal 2026 Form 10-K, annual report with cloud and AI infrastructure spending
Data center capital commitments and lease disclosures
CORZ 10-Q 2026-07-28 Core Scientific data center delivery to CoreWeave
Core Scientific's 10-Q addresses ERCOT interconnection timing risk and community opposition to data center development as factors that could delay conversion of its Texas sites into HPC colocation capacity for…
BE 10-Q 2026-07-28 New York hyperscale data center moratorium (statewide)
Bloom Energy's 10-Q dedicates a section to 'Increasing Opposition to Data Center Development,' citing the July 2026 New York executive order creating a moratorium on new hyperscale data centers and temporarily pausing…
CMS 10-Q 2026-07-28 CMS Electric Supply Plan / Michigan data center load growth
CMS Energy's 10-Q flags risk that regulatory action could prohibit, delay, or impair implementation of its Electric Supply Plan, and that anticipated demand growth from data center expansion may not materialize as…
CORZ 8-K 2026-07-28 Core Scientific and AMD announce infrastructure partnership for up to 2.5 GW including Texas Pecos and Hunt…
Texas AMD AI data center leases
META press 2026-07-28 Meta announces strategic venture with BlackRock to develop El Paso Texas data center
Texas AI data center, 1 GW, over 10 billion dollar investment
GOOGL 10-Q 2026-07-23 Alphabet Q2 2026 Form 10-Q, quarterly report with technical infrastructure investment
Data center capex and buildout
CLSK 8-K 2026-07-14 CleanSpark secures twenty year Sandersville Georgia data center lease and Texas 885 MW portfolio letter of…
data center lease and Texas power portfolio LOI
CLSK press 2026-07-14 CleanSpark secures twenty year lease with high investment grade global technology company for data center in…
data center lease and Texas portfolio LOI
MARA 8-K 2026-07-09 MARA reports Volt Texas acquisition of Texas site with 2,000 MW power capacity subject to ERCOT approval
Texas data center site, ERCOT interconnection
ORCL 10-K 2026-06-22 Oracle Cloud Infrastructure data center expansion pipeline
Oracle's 10-K explicitly warns that government-imposed limits or moratoria on data center construction in a given market could hinder its ability to execute expansion plans, citing delays across design, engineering,…
HIVE 10-K 2026-06-02 HIVE data center sites in Canada, Sweden, and Paraguay
HIVE's 10-K warns that securing power interconnection agreements and permits for its data centers may be delayed, denied, or become cost-prohibitive due to regulatory processes, and that community opposition to siting…
GOOGL news 2026-05-26 Court halts construction on Google Pine Island Minnesota data center
Litigation, temporary restraining order over environmental review
IREN 10-Q 2026-05-08 IREN Texas and British Columbia data center sites
IREN's 10-Q flags 'large load interconnection' risk factors tied to ERCOT-region development, echoing the broader Texas regulatory scrutiny of data center interconnection queues affecting its Childress buildout.
CIFR 10-Q 2026-05-05 Cipher Texas/Ohio 4.4GW pipeline sites
Cipher's Q1 2026 10-Q reiterates 'large load interconnection' as a specific named risk category for its Texas and Ohio pipeline of 4.4GW across seven sites, noting substation and grid interconnection advancement as…
APLD 8-K 2026-05-05 Applied Digital reports completion of financing tied to CoreWeave North Dakota data center lease
AI data center lease financing
BTDR 20-F 2026-04-30 Bitdeer US data center / ASIC hosting facilities
Bitdeer's annual report references ERCOT interconnection exposure for its Texas hosting operations amid heightened regulatory scrutiny of large-load data center interconnection requests in the state.
MARA 8-K 2026-04-30 MARA reports transaction with FTAI Infrastructure for 485 MW co-located data center power asset
data center power asset transaction
BE press 2026-04-27 Oracle, BorderPlex and Bloom Energy to power Project Jupiter with fuel cell technology
On-site fuel cell power replacing gas turbines for Texas data center
APLD 10-Q 2026-04-08 Applied Digital data center campuses (construction supply chain)
Applied Digital disclosed that global supply logistics delays affecting power and cooling equipment for HPC/AI data centers have been, and may continue to be, impacted by tariffs, extending construction timelines.
GOOGL news 2026-04-07 Google to use natural gas to power off grid data center in Armstrong County Texas
Behind-the-meter gas power, Texas, Crusoe Goodnight campus
BITF 10-K 2026-03-31 Panther Creek, Nesquehoning, Pennsylvania (PJM interconnection) and Magog, Quebec lease termination
Bitfarms (now Keel Infrastructure) disclosed PJM's 2025 Regional Transmission Expansion Plan indicates transmission enhancements needed to serve new data center power demand could take more than five years, and…
GREE 10-K 2026-03-31 Greenidge/Vulcan data center and power generation facilities (New York, Texas)
Greenidge (now Vulcan Infrastructure & Power) references general data center construction and permitting delay risk in its 10-K following its corporate rebrand and pivot toward broader infrastructure/power generation…
BTBT 10-K 2026-03-27 WhiteFiber subsidiary data centers (MTL-1, MTL-2, MTL-3 Montreal; North Carolina)
Bit Digital's 10-K, discussing its WhiteFiber subsidiary, disclosed that development delays could arise from zoning and permitting requirements, and specifically from local community resistance or protests in response…
WYFI 10-K 2026-03-26 WhiteFiber Montreal (MTL-1/2/3) and North Carolina data centers
WhiteFiber's 10-K states its data center operations are currently limited to Montreal, Canada, with North Carolina coming online, and discloses that development activities face delays from zoning and permitting…
MSFT news 2026-03-24 Microsoft to rent Abilene Texas data center dropped by OpenAI and Oracle
Texas Stargate-adjacent lease, capacity reshuffle
ORCL news 2026-03-06 Oracle and OpenAI end plans to expand flagship Abilene Texas data center
Texas Stargate expansion abandoned
CORZ 10-K 2026-03-02 Core Scientific HPC/AI data center conversions (Texas colocation sites); Texas Senate Bill 6
Core Scientific disclosed that Texas enacted Senate Bill 6 in June 2025, introducing significant new requirements for large-load electricity customers exceeding 75MW in ERCOT, including new obligations to contribute to…
CRWV 10-K 2026-03-02 Third-party-provided data centers (widely reported to involve Core Scientific)
CoreWeave's 10-K explicitly discloses delays announced in November 2025 regarding delivery of certain data centers to be provided by a third-party data center provider, warning that failure by third-party providers to…
WULF 10-K 2026-02-27 Justified Data Campus (up to 480MW gross power availability)
TeraWulf's 10-K describes construction of the Justified Data Campus HPC/AI data center, noting the buildout is subject to site planning and phased construction beginning in 2026 extending through 2027, dependent on…
VST 10-K 2026-02-27 Vistra nuclear/gas generation serving data center large-load customers (ERCOT and PJM)
Vistra's 10-K discusses risks tied to serving large-load data center customers, including project termination, cancellation, or delay risk, and the need for regulatory approval of new tariffs designed to allocate…
HUT 10-K 2026-02-25 Hut 8 HPC data center sites (Texas/North America)
Hut 8's 10-K risk factors cite tax abatement scrutiny and local moratoria as increasing constraints on new data center development in jurisdictions where the company operates.
NVDA 10-K 2026-02-25 Customer/partner AI data center build-outs dependent on Nvidia hardware
NVIDIA's 10-K warns that power or water shortages, land or permitting constraints, or regulations limiting energy, water, or land availability could impair customers' ability to expand data center capacity and consume…
CIFR 10-K 2026-02-24 Cipher 5.3GW data center portfolio across 11 sites (Texas and Ohio)
Cipher's 10-K states its ~5.3GW portfolio across 11 sites is at various stages of interconnection, with 700MW of HPC facilities under development across three sites for hyperscaler tenants, and warns that community…
CEG 10-K 2026-02-24 Crane Clean Energy Center (Three Mile Island Unit 1 restart) for Microsoft PPA
Constellation's 10-K discloses that under its agreement, Microsoft will purchase the output of the restarted Crane Clean Energy Center (formerly Three Mile Island Unit 1, retired in 2019) to power its data centers,…
NRG 10-K 2026-02-24 PJM region data center large-load interconnection studies
NRG's 10-K discloses that all 13 PJM-region governors signed a Statement of Principles urging PJM to address revenue certainty for new generation and allocate new resource costs to data centers, and that project delays…
AMT 10-K 2026-02-24 American Tower data centers segment (ground-up builds and expansions)
American Tower's 10-K states that local authorities and community residents periodically oppose data center construction, which can delay or prevent new builds, and that power constraints, delays, and unfavorable…
DLR 10-K 2026-02-13 Digital Realty global data center development pipeline
Digital Realty's 10-K risk factors cite zoning and permitting delays, including public or government opposition, as risks that could delay completion of its global data center development pipeline (769 MW of projects…
IRM 10-K 2026-02-12 Iron Mountain Global Data Center Business
Iron Mountain's 10-K discloses that its Global Data Center Business is susceptible to regional/local power costs, shortages, and outages, and that connectivity interruptions or terminations could adversely affect its…
EQIX 10-K 2026-02-11 Equinix global colocation/interconnection data center portfolio
Equinix's 10-K risk factors discuss supply chain and procurement disruptions leading to construction delays, plus zoning, permitting, and community/government opposition risk affecting new data center construction…
BE 10-K 2026-02-09 FERC/DOE large load co-located generation rulemaking
Bloom Energy's 10-K discusses that grid constraints and permitting delays are extending time-to-power for traditional data center facilities and expansions, and that local moratoria, protests, or siting restrictions on…
RIOT 8-K 2026-01-16 Riot acquires Rockdale land and signs first data center lease with AMD in Texas
Rockdale Texas AMD data center lease
RIOT news 2026-01-16 Riot announces fee simple acquisition of land and first data center lease with AMD at the Rockdale site
Rockdale Texas AMD lease detail
BE news 2026-01-08 American Electric Power agrees to deploy up to 1 GW of Bloom Energy fuel cells
Utility-scale on-site power for data centers bypassing grid queue
AMZN news 2025-12-16 Hobart Indiana officials sued by residents over rezoning for Amazon data center
Litigation over data center rezoning
AMZN news 2025-12-02 Amazon pulls out of Project Blue data center campus in Tucson Arizona
Data center cancellation over water and power concerns
CLSK 10-K 2025-11-25 Sandersville, Georgia HPC data center campus
CleanSpark's 10-K risk factors warn that if it fails to complete the Sandersville facility on time under the Sandersville Lease, the customer may terminate the agreement, seek damages, or pursue other remedies, and…
NVDA 10-Q 2025-11-19 NVIDIA Q3 fiscal 2026 Form 10-Q, quarterly report noting no assurance of definitive OpenAI agreements
SEC risk disclosure on OpenAI data center commitment
IREN 8-K 2025-11-03 IREN secures approximately 9.7 billion dollar AI cloud contract with Microsoft at Childress Texas
Texas AI cloud contract with Microsoft
GOOGL news 2025-09-22 Google withdraws proposed data center in Franklin Township Indiana after opposition
Data center cancellation after community pushback
NVDA press 2025-09-22 OpenAI and NVIDIA announce strategic partnership to deploy 10 gigawatts of NVIDIA systems
Up to 100 billion dollar OpenAI data center investment
APLD 8-K 2025-08-29 Applied Digital finalizes additional 150MW CoreWeave lease at Polaris Forge 1 Ellendale campus
150MW AI/HPC lease, North Dakota
IREN 10-K 2025-08-28 Childress, Texas facility (Horizon 1 direct-to-chip liquid cooling deployment)
IREN disclosed that ERCOT issued a July 23, 2025 market notice requesting information on voltage ride-through capabilities for data center and crypto-mining loads of 75MW or greater, to determine reliable…
APLD 8-K 2025-06-02 Applied Digital announces 250MW AI data center lease with CoreWeave at Ellendale North Dakota
250MW AI/HPC lease, North Dakota
MSFT news 2025-03-21 Microsoft halts work on future phases of Wisconsin Mount Pleasant data center
Data center project pause and design reevaluation
TLN EX-99.1 2025-02-27 Susquehanna nuclear plant co-located data center campus (Pennsylvania)
Talen's earnings materials reference its data center campus adjacent to the Susquehanna nuclear generating station and the interconnection/regulatory review process for co-located large loads that FERC and PJM were…
CORZ press 2025-02-26 Core Scientific and CoreWeave announce 1.2 billion dollar expansion at Denton Texas site
Denton Texas HPC expansion
RIOT 8-K 2025-01-21 Riot Platforms launches formal evaluation of AI and HPC uses for remaining 600 MW at Corsicana Texas
Corsicana Texas AI/HPC evaluation
No matches.

Government releases

Official statements and regulatory notices from the Governor of Texas, ERCOT, the PUCT, and the Texas Legislature on the data center audit and large-load interconnection process. Newest first.

AuthorityDateRelease
Governor Greg Abbott 2026-08-13 Governor Abbott Announces Galaxy, Compass Datacenters and Montera Infrastructure Commit to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-12 Governor Abbott Announces Google, Rowan and CleanSpark Commit to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-12 Governor Abbott Announces Core Scientific, Vantage Data Centers and SB Energy Commit to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-11 Governor Abbott Announces Edge ConneX and Stream Data Centers Commit to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-10 Governor Abbott Announces Meta Commits to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-10 Governor Abbott Announces OpenAI Commits to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-07 Governor Abbott Announces Skybox, Digital Realty and MARA Commit to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-06 Governor Abbott Announces QTS Data Centers Will Meet Texas Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-03 Governor Abbott Directs Comprehensive Data Center Audit
August 3 directive to audit and verify all data center interconnections before approval
ERCOT 2026-08-03 Market Notice M-A080326-01, Update Regarding Batch Zero Timelines and Processes
Batch Zero pause, ERCOT will miss August 7 deadline and seek a good cause exception
Governor Greg Abbott 2026-07-24 Governor Abbott Announces PUC and ERCOT Actions Protecting Residential Ratepayers From Data Center Costs
PUC and ERCOT ratepayer protection actions on data center costs
Governor Greg Abbott 2026-07-23 East Texas Data Center Withdraws After Falling Short of Governor Abbott's Standards
First project withdrawal under the data center standards
ERCOT 2026-06-23 Market Notice M-B062326-01, Implementation of the Batch Zero Process, PGRR145 and NPRR1325
Establishes the Batch Zero large load interconnection study process
ERCOT 2026-06-23 Market Notice M-B062326-04, Ending the Large Load Interconnection Study process under PGRR115 and Batch Zero submission deadlines
Transition from the prior process to Batch Zero
Governor Greg Abbott 2026-06-10 Governor Abbott Directs PUC and ERCOT to Shield Texans From Data Center Infrastructure Costs
Initial directive that data centers fund their own infrastructure costs
PUCT 2026-03-12 Project 58481, Proposal for Publication of 16 TAC 25.194, large load interconnection standards
Proposed rule implementing SB6, including per megawatt security and nonrefundable interconnection fee
Texas Senate 2025-06-20 Senate Bill 6, 89th Legislature, large load interconnection, operation, and cost of service, signed by the Governor
Statute directing PUCT to set large load interconnection standards
No matches.

Methodology and scope

This watchlist tracks U.S. data center projects, operators, and jurisdictional actions that carry a documented public paper trail: securities filings, regulatory dockets, litigation, government statements, utility filings, and trade press. It is maintained as a neutral reference. Entries are recorded as observed; the tracker does not rank projects or advocate an outcome.

  • Status reflects the most recent public signal for each entry. Where a project continues on schedule, that is recorded as plainly as a delay.
  • Capacity is shown in megawatts where reported, and left blank where not disclosed.
  • Local restrictions, utility dockets, lawsuits, and federal actions are drawn from primary filings and reputable outlets, each linked to its source.
  • The ERCOT queue snapshot is extracted directly from the ERCOT GIS Report.
  • Signals are collected on a recurring basis and reconciled into a single source of truth before publication.

Every citation on one page: Sources and citations. Companion policy map: SAVRN Data Center Moratorium Tracker. Capital side: North American Data Center Capital Atlas. Founder essay: The Queue Was the Fiction.

What is the Nationwide Data Center Delay Watchlist?

It is a continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Each entry links to its documented public source, and it is maintained as a neutral reference.

How is a project's status determined?

Status reflects the most recent public signal for each entry: halted, delayed, cancelled, pending review, litigation active, audit paused, under appeal, or withdrawn. Where a project continues on schedule, that is recorded as plainly as a delay.

How are delay days measured?

Delay days are measured against the original announced target where available, or against the first documented delay date.

How often is the watchlist updated?

Signals are collected on a recurring basis from SEC EDGAR and trade-press feeds and reconciled into the single source of truth before publication.

How is this different from the Data Center Moratorium Tracker?

The Moratorium Tracker maps state and local policy measures. This watchlist tracks named projects, operators, public-company exposure, and securities filings, with delay status and cause for each. The two are companion references.