Nationwide Data Center Delay Watchlist
A continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, local restrictions, litigation, federal and utility dockets, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Every entry links to its documented public source.
National interconnection queue
Every ISO plus vertically integrated utilities with a public row-level queue, as of 2026-08-24. The full row-level queue is refreshed weekly. ERCOT Batch Zero row-level classifications are not yet published per Market Notice M-A080326-01.
Tracked projects
Named data center projects with a documented delay, cancellation, withdrawal, or active review. Status reflects the most recent public signal.
| Project | Location | MW | Status | Cause | Notes | Sources |
|---|---|---|---|---|---|---|
Diode Ventures Cedar Creek Lake Diode Ventures |
Cedar Creek Lake TX · ERCOT |
withdrawn | Pre-moratorium withdrawal, cited by Governor's office as example | |||
Project Matador (Amarillo) Fermi America (FRMI) |
Amarillo / Potter County TX · ERCOT |
11,000 | delayed | 11 GW at build-out; 600 MW gas turbines procured; 1 GW target by end of 2026. Not affected by moratorium (BTM). Continuing construction. | ||
GW Ranch (Fort Stockton) Pacifico Energy |
Fort Stockton TX · ERCOT |
5,000 | delayed | 5 GW off-grid gas + 1.8 GW battery. Bypasses ERCOT entirely. Not affected by moratorium. | ||
Amazon 7.65 GW Gas Plant / Self-Contained Island Amazon Web Services / partner (AMZN) |
TX TX · ERCOT |
5,000 | delayed | 35 turbines, 5 GW campus delivery, operates as self-contained energy island off ERCOT. Announced days AFTER moratorium, no delay impact. | ||
Stargate / Abilene (Phase 1) Crusoe (MSFT,ORCL) |
Abilene TX · ERCOT |
1,200 | delayed | 900 MW BTM gas microgrid + grid blend at 1.2 GW. Continuing. Additional 4.5 GW gas capacity secured by Crusoe. | ||
Good Data Center Campus (Armstrong County) Google (via developer) (GOOGL) |
Armstrong County TX · ERCOT |
delayed | Private natural gas turbines under state air permit. Not affected by moratorium. | |||
Voltagrid Shackelford County Voltagrid (ORCL) |
Shackelford County TX · ERCOT |
700 | delayed | 210 industrial gas gensets. 700 MW. Off-grid. Delayed to 2029 per SemiAnalysis due to gas pipeline permitting. | ||
Oracle/OpenAI Texas Expansion (Original Plan) Oracle (ORCL) |
TX TX · ERCOT |
withdrawn | Oracle/OpenAI abandoned Texas expansion March 6, 2026 over financing negotiations. Pre-moratorium. Microsoft later stepped in. | |||
CleanSpark Texas Operations (all) CleanSpark (CLSK) |
TX TX · ERCOT |
pending review | 10-Q risk factor disclosure: 'evaluating scope and enforceability of August 3, 2026 letter'. Only known public SEC disclosure explicitly referencing the moratorium. | |||
Lighthouse (Port Washington) Vantage Data Centers / Oracle / OpenAI (ORCL) |
Port Washington WI · MISO |
litigation active | $15B project. Sierra Club/Midwest Environmental Advocates lawsuit filed July 10, 2026 in Ozaukee County. Also April 2026 ballot referendum limited DC construction. | |||
Spring Valley Technology Park Active Infrastructure |
Loudoun County / near Beaverdam Reservoir VA · PJM |
780 | cancelled | 325-acre, 3.54M sq ft. Planning Commission voted unanimously to recommend denial. 500+ residents attended hearing. | ||
Dulles Cloud South |
Prince William County VA · PJM |
cancelled | Nearly 2,000-acre campus. Board of County Supervisors voted unanimously to deny rezoning. | |||
Mountain Road Technology Park Tract |
Hanover County VA · PJM |
cancelled | Board of Supervisors voted 4-3 to deny rezoning. Water concerns (up to 90% of local supply). | |||
Prince William 2,100-acre Campus (37 buildings) |
Prince William County VA · PJM |
cancelled | 37 buildings, gigawatt-scale; killed on public-notice technicality (notices not run 6 days apart) | |||
Project Blue (Amazon-linked) Beale Infrastructure (AMZN) |
Tucson AZ · WECC |
cancelled | City Council voted 7-0 to end negotiations and halt annexation. | |||
New Carlisle $13B Data Center |
St. Joseph County / New Carlisle IN · MISO |
cancelled | St. Joseph County Council rejected after 10-hour meeting. | |||
Hobart Amazon Data Center Amazon (AMZN) |
Hobart IN · MISO |
litigation active | Lawsuit filed to block fill permit alleging state law violations | |||
Project Tango |
Palm Beach County / Arden FL · SERC |
cancelled | Palm Beach commissioners voted 5-1 to deny after 12+ hour meeting. | |||
Pine Island Data Center Development |
Pine Island MN · MISO |
litigation active | TRO issued blocking construction pending MCEA challenge. Construction was to begin July 2026. | |||
T5 @ Chicago IV T5 Data Centers |
Lake County / Grayslake IL · PJM |
litigation active | Lawsuit filed July 31, 2026 alleging inconsistent with Comprehensive Plan. Initial status hearing Oct 30. | |||
Markley Group Lowell Expansion Markley Group |
Lowell MA · ISO-NE |
litigation active | MA Superior Court blocked installation of 4 new diesel generators pending resident lawsuit. | |||
Hexa Builders Monroe Township Hexa Builders LLC |
Monroe Township / Gloucester County NJ · PJM |
litigation active | Hexa filed $300M lawsuit against township for zoning ordinances banning DCs. | |||
DC BLOX Nashville (Grassmere Park) DC BLOX |
Nashville / Grassmere TN · SERC |
litigation active | Filed federal lawsuit Aug 11 challenging Nashville moratorium. Claims vested rights. | |||
Imperial Valley $10B AI Data Center Imperial Valley Computer Manufacturing LLC |
Imperial CA · CAISO |
litigation active | $10B project. Civil rights lawsuit filed against City of Imperial in fed court. | |||
Natelli Investments Wake County 250MW Natelli Investments |
Wake County NC · PJM |
250 | withdrawn | Withdrew annexation and rezoning applications early 2026. | ||
Hays County / San Marcos DC |
Hays County / San Marcos TX · ERCOT |
cancelled | San Marcos City Council voted 5-2 against zoning in February 2026. | |||
Eagan Capital Expansion Eagan Capital |
Eagan MN · MISO |
litigation active | Filed lawsuit June 15 against Eagan for moratorium exceeding city authority. | |||
DataBank Orangetown Phase 2 DataBank |
Orangetown / Orangeburg NY · NYISO |
delayed | Orangetown Planning Board voted unanimously to require EIS, delaying project indefinitely. | |||
Boulder City BLM Site |
Boulder City NV · WECC |
under appeal | Boulder City Council voted unanimously to appeal BLM approval. | |||
University of Michigan / Los Alamos Data Center |
Ypsilanti MI · MISO |
delayed | Ypsilanti Community Utilities Authority passed yearlong halt on water/sewer for DCs (April 2026) | |||
Prince William Digital Gateway (PW Digital Gateway) QTS Data Centers (Blackstone); Compass Datacenters (BX) |
Gainesville, Prince William County VA · PJM |
1,700 | cancelled | One of the world's largest planned data center clusters (34 buildings, 22M SF) next to Manassas National Battlefield Park was voided by courts over inadequate public notice for… | ||
Dulles Cloud South (Dulles South data center project) |
Gainesville, Prince William County VA · PJM |
cancelled | Nearly 2,000-acre, 43M-SF proposal to rezone farmland/residential land to industrial for data centers was rejected 8-0 by the Prince William Board of Supervisors, following on… | |||
Bristow Campus data center project Stack Infrastructure |
Bristow/Nokesville area, Prince William County VA · PJM |
delayed | Board of Supervisors hearing on this Nokesville Road/Broad Run Creek campus was deferred amid community opposition; a supervisor said backers "know they don't have the votes." | |||
PW Digital Gateway landowner tax litigation QTS Data Centers (BX) |
Gainesville, Prince William County VA · PJM |
litigation active | Landowners under contract to sell parcels to QTS for the Digital Gateway sued Prince William County over sharply increased tax assessments tied to the (litigation-blocked)… | |||
Loudoun County data center application pause |
Loudoun County VA · PJM |
pending review | Board of Supervisors voted to begin process of pausing all new data center applications, site plans and substations countywide (250 existing data centers, 53.3M SF) until new… | |||
Hiddenwood Lane / Hiddenwood Assemblage rezoning (Aldie) JK Technology Holdings / Aldie homeowner group |
Aldie, Loudoun County VA · PJM |
withdrawn | Group of Aldie homeowners on Hiddenwood Lane seeking industrial rezoning (756,000 SF data center potential) to sell out of an area surrounded by data centers indefinitely… | |||
Innovation Gateway |
Sterling, Loudoun County VA · PJM |
pending review | 700,000 SF data center plus affordable-housing rezoning near the Innovation Station Metrorail stop; Planning Commission recommended denial (5-2) as incompatible with the Urban… | |||
Oaklawn data center rezoning (Leesburg) Oaklawn, LLC |
Leesburg, Loudoun County VA · PJM |
cancelled | Leesburg Town Council denied 5-1-1 a rezoning to add up to 450,000 SF of data centers linked to affordable-housing units, citing inconsistency with the Zoning Ordinance and… | |||
Mountain Road Technology Park (Tract) Tract |
Route 33/Mountain Road, Hanover County VA · PJM |
900 | cancelled | Hanover Board of Supervisors rejected the conditional-use permit and A1-to-M1 rezoning for a 900MW/430-acre campus on May 27, 2026, after the Planning Commission had earlier… | ||
Chesterfield Tract data center park (Branders Road) Tract |
161 Branders Road, Chesterfield County VA · PJM |
withdrawn | Tract withdrew its zoning request for a 744-acre rural campus after the Planning Commission unanimously recommended against it, citing inadequate infrastructure and sole access… | |||
Chesterfield data center project (unnamed) paused amid county lawsuits |
Chesterfield County VA · PJM |
litigation active | Local reporting confirms an active Chesterfield County data center project paused amid county-level lawsuits, following the Zoning Appeals Board's denial of an appeal on a… | |||
Gigaland Data Center Campus GigaLand LLC |
Remington, Fauquier County VA · PJM |
800 | withdrawn | Fauquier Planning Commission voted to recommend denial of the original 800MW/2.2M-SF rezoning; the developer officially withdrew the application in July 2026 and plans a… | ||
Remington Digital Campus |
Remington, Fauquier County VA · PJM |
pending review | Fauquier Planning Commission recommended denial of a separate campus near Remington Technology Park adjoining the Meadows of Remington neighborhood; a related private turbine… | |||
Amazon Data Services Warrenton data center Amazon Data Services (AMZN) |
Warrenton, Fauquier County VA · PJM |
litigation active | Citizens for Fauquier County and 10 residents sued in Fauquier Circuit Court to overturn the Town Council's special-use-permit approval for a 220,000 SF Amazon facility, alleging… | |||
Bel Pre Tech Park (Brandy Station data center campus) Culpeper Acquisitions LLC |
Brandy Station, Culpeper County VA · PJM |
pending review | County planners denied the 4.6M-SF, nine-building rezoning application near the historic Brandy Station battlefield; applicant requested Board of Supervisors consideration be… | |||
Brandy Station data center proposal (David Martin parcel) |
Brandy Station, Culpeper County VA · PJM |
withdrawn | An 88-acre Brandy Station rezoning was withdrawn after an initial denial from the Culpeper County planning commission amid Brandy Station resident opposition. | |||
Red Ace Data Center Campus |
Culpeper County VA · PJM |
delayed | Application tabled by Culpeper County officials, per Data Center Dynamics reporting; no further detail on eventual outcome. | |||
Stafford County stricter data center rules (GWV Data Center reclassification context) |
Stafford County VA · PJM |
delayed | Following a marathon public hearing, Stafford County adopted stricter data-center zoning rules that developers and residents split over, raising the bar for future rezoning… | |||
Spotsylvania County data center special-use permit standards / statewide moratorium resolution |
Spotsylvania County VA · PJM |
pending review | Spotsylvania supervisors split on requiring special-use permits for data centers (March 2025) and by August 2026 the Board backed a call for a statewide moratorium on data… | |||
1500 Gateway Data Center Project Penzance Development / 1500 Gateway Venture, LLC |
City of Fredericksburg VA · PJM |
under appeal | Fredericksburg Planning Commission unanimously rejected (7-0) the 2.1M-SF rezoning and Special Use Permit in December 2025, its second denial after an initial February 2025… | |||
Emerald Lakes Estates data center (Great Bridge) Doug Fuller / Emerald Lakes Estates |
Great Bridge, City of Chesapeake VA · PJM |
cancelled | Would have been Hampton Roads' first major data center; Chesapeake City Council unanimously denied the agricultural-to-light-industrial rezoning for a 350,000 SF facility on… | |||
Chesapeake 8-month data center application pause |
City of Chesapeake VA · PJM |
pending review | Chesapeake City Council voted to approve an 8-month hold on all new data center application decisions amid growing calls for a statewide Virginia moratorium. | |||
Chesapeake data center zoning text amendment (Green Sea area) |
City of Chesapeake VA · PJM |
delayed | Chesapeake Planning Commission recommended against a data-center zoning text amendment in May 2025; a related zoning text amendment was indefinitely continued by the Planning… | |||
Mt. Airy Planned Innovation, Research and Technology data center campus VALCO (applicant); Thompson Family Office (landowner) |
Ruther Glen/Jericho Road, Caroline County VA · PJM |
withdrawn | Caroline County Board of Supervisors denied 5-1 a comprehensive-plan amendment for a 900-acre campus near the North Anna River; VALCO then withdrew its rezoning request. The… | |||
Google Botetourt County data center campus Google (GOOGL) |
Botetourt County VA · PJM |
litigation active | Western Virginia Water Authority stated it will not supply the 10-million-gallons/day Google sought; a FOIA lawsuit forced disclosure of secret water-use contracts (judge ordered… | |||
Campbell County data center rezoning (MESH Capital site) MESH Capital LLC |
Concord District, Campbell County VA · PJM |
cancelled | Campbell County Board of Supervisors voted 5-2 to reject removing 2000-era protective conditions from a 57-acre site marketed for up to three data centers, after dozens of… | |||
Surry County data center moratorium |
Surry County VA · PJM |
pending review | Surry County enacted an initial 60-day pause on data center approvals in June 2026, then extended it to a full two-year moratorium on July 21, 2026, while directing staff to… | |||
Powhatan County data center zoning proposal (Route 60/Page Road) Newport Equities / JMS Investments |
Powhatan County VA · PJM |
delayed | A community petition ("Preserve Powhatan") urged the Planning Commission to block a 120-acre data-center zoning proposal near the Chesterfield County line; the Board of… | |||
Amazon Louisa County data center (third project, cancelled) Amazon (AMZN) |
Louisa County VA · PJM |
cancelled | Amazon pulled a proposed third Louisa County data center project in July 2025 after strong community resistance, even as it continued building two other campuses in the county. | |||
Amazon Louisa County data center campus (Northeast Creek overlay, active construction) Amazon (AMZN) |
Louisa County VA · PJM |
litigation active | Homeowner Austin Newsom sued Amazon for private nuisance over brown water, dust and construction noise at Amazon's second Louisa County campus; a federal judge allowed the… | |||
Amazon Birchwood power plant data center campus Amazon (AMZN) |
Sealston, King George County VA · PJM |
litigation active | Board of Supervisors moved in April 2024 to re-rezone the old Birchwood power plant site back to agricultural, threatening Amazon's planned 19-building, 7.25M SF campus; Amazon… | |||
New Kent County data center-friendly technology overlay district |
New Kent County VA · PJM |
cancelled | Faced with widespread public disapproval at town-hall meetings, New Kent County supervisors spiked the plan to create a data-center-friendly overlay zone in July 2026,… | |||
Plaza 500 data center campus / Edsall Data Center Substation 2232 Starwood Capital Group (Starwood Digital Ventures) |
Lincolnia, Fairfax County VA · PJM |
pending review | Alexandria City Council formally asked Fairfax County to deny the Edsall Road substation feeding this 226,469 SF Starwood data center near the Bren Mar neighborhood; Rep. Don… | |||
Manassas National Battlefield adjacent data center litigation (American Battlefield Trust) QTS / Compass Datacenters (BX) |
Manassas/Gainesville, Prince William County VA · PJM |
cancelled | American Battlefield Trust sued to stop data center construction abutting Manassas National Battlefield Park; after a judge initially dismissed part of the suit (Nov 2024), the… | |||
Brightseat Tech Park (former Landover Mall site) Brightseat Associates LLC (Lerner Enterprises / The Tower Cos.) |
Landover, Prince George's County MD · PJM |
820 | pending review | Despite securing final approvals for 4.1M SF of data centers in Oct 2024, County Executive Aisha Braveboy ordered a temporary halt to all data center permitting on Sept 15, 2025… | ||
Prince George's County Qualified Data Centers moratorium (Brandywine area) |
Brandywine, Prince George's County MD · PJM |
pending review | Prince George's County Council initially voted against advancing data centers (Nov 2024) and enacted a countywide moratorium on "Qualified Data Centers" extended to expire June… | |||
Quantum Frederick |
Frederick County MD · PJM |
litigation active | Maryland Supreme Court blocked a citizen-driven referendum bid seeking to overturn a county ordinance that expanded the ~1,600-acre Quantum Frederick campus by 1,000 acres to… | |||
Charles County Zoning Text Amendment 25-187 (data center zoning enablement) |
Charles County MD · PJM |
withdrawn | Charles County Planning Commission twice recommended denial of ZTA 25-187, which would have permitted data centers in industrial zones, after hearings featuring "no data centers"… | |||
Penzance Bedington data center campus Penzance Management |
Bedington, Berkeley County WV · PJM |
delayed | Gov. Patrick Morrisey announced the $4B, 500+ acre Penzance data center near the Potomac River on Feb 26, 2026; more than 300 residents packed a March 20 county commission town… | |||
Jefferson County (WV) data center moratorium |
Jefferson County WV · PJM |
pending review | Jefferson County Board of Commissioners issued a 10-month moratorium (May 19, 2026) on new data center applications/rezonings, excepting sites already zoned via Planned… | |||
Microsoft New Albany / Heath / Hebron Licking County data center campuses Microsoft (MSFT) |
New Albany, Heath, Hebron, Licking County OH · PJM |
delayed | Microsoft paused all three Licking County data center sites (New Albany, Heath, Hebron; $1B combined, 700+ acres) in April 2025 while "evaluating sites in line with our… | |||
Amazon Data Services Sunbury data center campus Amazon (AMZN) |
Sunbury, Delaware County OH · PJM |
pending review | Sunbury has an active data center development moratorium (through Jan 31); residents are gathering signatures for a city charter amendment capping data center peak load at 25MW… | |||
Aligned Data Centers Pataskala facility Aligned Data Centers |
Pataskala, Licking County OH · PJM |
200 | delayed | Pataskala residents are collecting signatures for a municipal charter amendment capping data center peak load at 25MW, aimed squarely at blocking this proposed 200MW/89-acre… | ||
Pennhurst data center (East Vincent Township) Pennhurst Holdings LLC |
East Vincent Township, Chester County PA · PJM |
under appeal | East Vincent Township officials unanimously rejected a 1.9M-SF data center on the historic Pennhurst State School site; the developer plans to appeal to the Chester County Court… | |||
East Whiteland data center (Chesco) |
East Whiteland Township, Chester County PA · PJM |
litigation active | A controversial 1.6M-SF data center in East Whiteland faced community legal challenges over its approval; the project survived a court denial of the challengers' appeals in June… | |||
North Coventry boutique data center (Envision Land Use) Envision Land Use |
North Coventry Township, Chester County PA · PJM |
cancelled | North Coventry Township supervisors preemptively voted 3-2 to reject a proposed 120,000 SF data center near a PECO substation before a formal application was even filed,… | |||
Chester County temporary data center moratorium |
Chester County PA · PJM |
pending review | Chester County approved a temporary countywide moratorium on new data center project approvals to allow time for zoning study and regulation drafting. | |||
King of Prussia data center campus (Brian O'Neill applications) Brian O'Neill |
Upper Merion Township, Montgomery County PA · PJM |
litigation active | Developer Brian O'Neill sued Upper Merion Township; a Montgomery County judge issued an injunction (Aug 13, 2026) preventing the township from taking further action on his King… | |||
Keystone Trade Center AI data center campus (Amazon/NorthPoint) NorthPoint Development |
Falls Township, Bucks County PA · PJM |
delayed | Despite construction proceeding on the former U.S. Steel site (part of a $20B statewide Amazon investment), Falls Township residents organized a nearly 4,000-signature petition… | |||
Northampton County proposed data center farm conversions |
Northampton County PA · PJM |
delayed | Northampton County residents packed public meetings voicing fierce opposition ("I don't want you") to proposed data centers taking over farmland; a local coordinated "No Data… | |||
Homer City Energy Campus Homer City Redevelopment / Homer City Generation |
Homer City, Indiana County PA · PJM |
4,400 | pending review | Pennsylvania DEP fast-tracked and approved an air-quality permit (157 days vs. the projected 285) for this 4.4GW gas-fired data center campus at a former coal plant despite 500+… | ||
New Hill Digital Campus Natelli Holdings (Natelli Investments LLC) |
New Hill/Apex, Wake County NC · SERC |
300 | withdrawn | Developer withdrew annexation and rezoning applications for a 300MW campus near the Shearon Harris Nuclear Plant after a 2,000+ signature petition and intense resident backlash… | ||
Triangle Innovation Park West (TIP West) Eco TIP West LLC (Kirk Bradley / Lee-Moore Capital) |
Moncure, Chatham County NC · SERC |
750 | litigation active | Chatham County's 12-month moratorium on new data center/crypto-mine permits (adopted Feb 11, 2026) halted processing of TIP West's site plan; Eco TIP West sued the county in… | ||
Chatham County data center and crypto-mine moratorium |
Chatham County NC · SERC |
pending review | Chatham County commissioners unanimously approved a 12-month moratorium on new data center and cryptocurrency-mine permits (through February 2027) to draft new zoning rules and… | |||
Gates County data center moratorium |
Gates County NC · SERC |
pending review | Gates County's board of commissioners unanimously approved a one-year pause on new data center approvals amid growing statewide North Carolina opposition to hyperscale projects. | |||
Person County Microsoft data center Microsoft (MSFT) |
Person County NC · SERC |
delayed | Person County residents publicly demanded answers from Microsoft over a planned local data center; Microsoft hosted a community meeting in June 2026 amid rising central-NC… | |||
Hexa Builders Monroe Township data center (Black Horse Pike redevelopment) Hexa Builders LLC |
Williamstown, Monroe Township, Gloucester County NJ · PJM |
litigation active | After winning preliminary approval for two warehouses in January 2026, Hexa amended its application to swap in a 1M-SF data center; Monroe Township passed ordinances in April… | |||
Former Newton Airport site data center proposal |
Andover Township, Sussex County NJ · PJM |
litigation active | A developer sued Andover Township in state Superior Court (filed July 10, 2026) to overturn its data-center ban, alleging officials enacted the prohibition preemptively before… | |||
James City County data center special-use review policy |
James City County VA · PJM |
pending review | James City County supervisors moved to require special-use permit review for all data centers rather than by-right development, directing staff to draft a formal policy… | |||
Frederick County (VA) countywide data center ban consideration |
Frederick County VA · PJM |
pending review | Frederick County supervisors moved to consider a countywide ban on new data centers, following sustained opposition from Winchester-area residents citing six proposed projects;… | |||
DC Blox Indianapolis (Warren Township) DC Blox |
Warren Township, Indianapolis (Marion County) IN · MISO |
approved but citywide moratorium pending | One of three Indianapolis data centers drawing the most community opposition (energy, water, noise). Approved in July 2026 and would be exempt from the moratorium the City-County… | |||
Metrobloks Martindale-Brightwood Metrobloks |
Martindale-Brightwood, Indianapolis (Marion County) IN · MISO |
approved but citywide moratorium pending | Approved in May 2026 despite opposition; cited as one of three Indianapolis projects driving the citywide moratorium push. | |||
Sabey Data Center (Decatur Township) Sabey Data Centers |
Decatur Township, Indianapolis (Marion County) IN · MISO |
approved but citywide moratorium pending | Metropolitan Development Commission approved the $4B Sabey project in March 2026; one of the three flashpoint projects behind Indianapolis's moratorium debate. | |||
Google Franklin Township Campus (withdrawn) Google (GOOGL) |
Franklin Township, Indianapolis (Marion County) IN · MISO |
withdrawn | Google withdrew a proposal to rezone hundreds of acres in Franklin Township for a data center campus after contested opposition to the rezoning. | |||
New Carlisle $13B Data Center (St. Joseph County) Amazon (reported) (AMZN) |
New Carlisle, St. Joseph County IN · MISO |
rezoning denied | St. Joseph County Council voted 7-2 after a 10-hour, marathon meeting to deny rezoning ~1,000 acres of farmland off Chicago Trail. Opposition cited environmental impact,… | |||
Hobart Amazon Data Center Campus Amazon (AMZN) |
Hobart (Lake County), Ross Township IN · MISO |
active litigation | Hobart Plan Commission approved a fill permit Nov 6, 2025 for a 725-acre Economic Redevelopment Area near wetlands by Deep River. Residents sued alleging permit issued without… | |||
Microsoft Granger Data Center Microsoft (MSFT) |
Granger, St. Joseph County IN · MISO |
approved amid opposition | Approved Microsoft project in St. Joseph County drew continued resident protests at an open house over energy, water, and jobs concerns even after approval, part of broader… | |||
301 Digital Crossroads / CoreWeave (Hammond) CoreWeave / Decennial Group (CRWV) |
Hammond IN · MISO |
development agreement expired | City of Hammond announced the expiration of the $7B Development Agreement at 301 Digital Crossroads after required milestones were not met by the June 30, 2026 deadline; two… | |||
Clinton County Data Center / Precast Plant / Hydroponic Farm Unnamed developer |
Clinton County IN · MISO |
rezoning denied | Clinton County Board of Commissioners voted 3-0 to deny rezoning ~714.55 acres from A-1 agricultural to I-1 light industrial for a mixed data center, precast plant, and… | |||
Boone County Unincorporated Data Center Moratorium |
Boone County (unincorporated) IN · MISO |
moratorium in force | Boone County Board of Commissioners unanimously approved a one-year moratorium (effective June 16, 2026 to June 15, 2027) on new data center development in unincorporated Boone… | |||
Madison County Data Center Moratorium (extended) |
Madison County IN · MISO |
moratorium extended | Madison County commissioners unanimously extended a data-center moratorium to a full year to draft zoning rules, potentially including a permanent ban. Majority of residents at… | |||
Meta New Albany Data Center (Socrates South / AEP substation dispute) Meta (META) |
New Albany, Licking County OH · PJM |
250 | regulatory approval pending | Meta sought to draw 120-250MW from an idle AEP Ohio substation originally built for Intel's delayed chip fab (Intel now slated 2030-31, delayed from original date). AEP Ohio and… | ||
Microsoft Licking County Data Center (construction paused) Microsoft (MSFT) |
Licking County OH · PJM |
construction paused | Microsoft halted early-stage construction on a $1B Ohio site (three parcels; two reserved for farmland), citing reassessment of cloud/AI infrastructure needs, evolving… | |||
Amazon Data Services Sunbury Campus Amazon (AMZN) |
Sunbury, Delaware County OH · PJM |
proposed amid local moratorium and ballot fight | Sunbury has a data-center development moratorium in place until Jan 31 (2027); residents fear council could approve the $2B Amazon facility once it expires and are collecting… | |||
Conserve Ohio Statewide Data Center Ban Ballot Initiative |
Statewide (Ohio) OH · PJM |
signature gathering | Ohio Ballot Board approved a proposed constitutional amendment to prohibit large data center construction; Conserve Ohio needed 413,487 signatures from 44+ counties by July 1,… | |||
Lighthouse Campus (Port Washington), Oracle/Vantage/OpenAI Oracle / Vantage Data Centers (ORCL) |
Port Washington, Ozaukee County WI · MISO |
1,000 | active litigation | Nearly 1GW Stargate-partnership campus. Wisconsin PSC's April 2026 order required hyperscale operators (incl. Oracle) to post financial security before power service; estimated… | ||
Microsoft Mount Pleasant AI Campus (Foxconn site) Microsoft (MSFT) |
Mount Pleasant, Racine County WI · MISO |
construction partially paused | Built on former Foxconn site; total footprint ~1,121 acres across three parcels (215, 115, 791 acres); Microsoft now owns ~1,900 acres in Mount Pleasant. Microsoft paused… | |||
Microsoft Kenosha Data Center (proposed) Microsoft (MSFT) |
Kenosha, Kenosha County WI · MISO |
under council consideration | Residents packed multiple public forums urging Kenosha Common Council to slow consideration, citing water extraction, 24/7 noise, air quality tied to a linked 1,186 MW… | |||
QTS DeForest / Vienna Annexation ($12B, cancelled) QTS Data Centers (BAM) |
DeForest / Town of Vienna, Dane County WI · MISO |
cancelled | QTS's $12B proposal required annexing 1,600 acres from the Town of Vienna into DeForest. On Jan 27, 2026 village staff determined the project 'not feasible in DeForest' after ~7… | |||
Pine Island Data Center (Google) Ryan Companies (developer) (GOOGL) |
Pine Island, Goodhue County MN · MISO |
2,700 | construction halted by court | Could require up to 2,700MW. MCEA sued in October 2025 alleging environmental review only covered a generic 'technology center'/'light industrial' use, not disclosing Google as… | ||
Eagan Capital Expansion (Data Center Moratorium Suit) Eagan Capital |
Eagan, Dakota County MN · MISO |
active litigation | Eagan's development-pause ordinance (20MW+ new / 9MW+ expansion) is challenged by Eagan Capital, arguing the moratorium exceeds the city's authority; lawsuit filed to void the… | |||
Farmington Technology Park (Tract) Tract |
Farmington, Dakota County MN · MISO |
708 | active litigation | Denver-based Tract's 340-acre, up-to-12-building, 2.5M-sq-ft campus (~$5B at full buildout) on former golf-course/school land. Residents sued on technical and later environmental… | ||
Meta Rosemount Data Center (UMore Park) Jimnist LLC (Meta subsidiary) (META) |
Rosemount, Dakota County MN · MISO |
final decision paused | Planning Commission approved the site plan, but the City Council paused final action until after Dec 20 pending completion of a required 5-year Alternative Urban Areawide Review… | |||
Minneapolis Citywide Data Center Development Pause |
Minneapolis, Hennepin County MN · MISO |
moratorium in force | Minneapolis City Council approved a five-month pause on new data center development (excludes downtown centers under 350,000 sq ft) to study environmental, energy, and… | |||
Elk River Proposed Data Center |
Elk River, Sherburne County MN · MISO |
planning commission recommended denial | Elk River's planning commission recommended against a proposed data center despite advocates citing an estimated $800,000 in additional city revenue. | |||
Inver Grove Heights Proposed Data Center |
Inver Grove Heights, Dakota County MN · MISO |
final vote delayed | City council delayed a final vote after a packed, contentious meeting erupted in boos over the delay. | |||
University of Michigan / Los Alamos High-Performance Computing Facility University of Michigan / Los Alamos National Laboratory |
Ypsilanti Township, Washtenaw County MI · MISO |
100 | opposed planned | 144.5-acre site on Textile Road near Ford Lake Dam; $1.2B taxpayer-supported project planned to start construction 2027, operational by 2031. Ypsilanti City Council unanimously… | ||
Saline Township 'The Barn', OpenAI/Oracle Stargate Campus Related Digital (ORCL) |
Saline Township, Washtenaw County MI · MISO |
1,400 | rezoning denied then litigation settled | Part of OpenAI/Oracle's Stargate initiative; ~1,400MW from DTE Energy; 575 acres of farmland proposed for rezoning within a ~1,000-acre campus (two-thirds to remain open space).… | ||
Alterra Development Marshall Data Center (Brooks Industrial Park) Alterra Development |
Marshall, Calhoun County MI · MISO |
1,000 | moratorium delay | Alterra purchased 270 acres in Brooks Industrial Park near wetlands/a lake; original concept (gas plant + data center, ~1,000MW/1GW) later dropped the gas plant, cutting energy… | ||
Microsoft / Franklin Partners Covenant Business Park (Lowell-area township) Microsoft / Franklin Partners (MSFT) |
Township adjacent to Lowell (Kent County) MI · MISO |
rezoning paused | Estimated $500M-$1B investment over 3-5 years. Site needs rezoning from industrial PUD to light industrial. A December 2025 planning commission public hearing was… | |||
West Michigan Hyperscale Proposals (Solon, Lowell, Gaines Townships) |
Solon, Lowell, and Gaines Townships (Kent County) MI · MISO |
opposed proposed | Residents protested outside The Right Place's Developer Day (June 9-11, 2026) over multiple hyperscale proposals across three townships; criticism centered on private… | |||
Gotion Green Township Battery/Data Plant (abandoned) Gotion |
Green Township, near Big Rapids MI · MISO |
abandoned | Gotion abandoned its planned Green Township facility after legal challenges, environmental issues, and backlash over the company's China ties; Michigan had committed a $715M… | |||
T5 @ Chicago IV (Grayslake) T5 Data Centers |
Grayslake, Lake County IL · PJM |
1,550 | active litigation | Up to 472 acres within the $750M, 641-acre Cornerstone mixed-use development; ~1.55GW electrical demand from ComEd. Village Board approved between Sept 2024-May 2025. On July 31,… | ||
Project Vector / Endeavour Energy DeKalb Data Center Endeavour Energy |
DeKalb IL · PJM |
opposed pending council vote | Also referred to as the 'Edged data center'; ~560 acres along Route 23; Planning and Zoning Commission backed the project after a crowded hearing, but a Change.org petition drew… | |||
South Elgin Data Center (Whiterose Partners / Kenyon Brothers) Whiterose Partners / Kenyon Brothers Co. |
South Elgin, Kane County IL · PJM |
48 | opposed effectively stalled | 20-acre, 200,000-sq-ft, 48MW proposal at Kenyon Road/Route 25 requiring annexation, rezoning, and special-use permit. A petition gathered 4,800 signatures within 48 hours; a July… | ||
Aurora Data Center and Warehouse Moratorium |
Aurora, Kane/DuPage Counties IL · PJM |
moratorium in force | Aurora City Council enacted a 180-day moratorium (Sept 25, 2025) on new data center and warehouse development to research standards and draft zoning rules; applications can be… | |||
Project Cardinal (Yorkville) |
Yorkville, Kendall County IL · PJM |
active litigation | 1,037-acre planned campus, approved earlier in 2026. Residents (Preserve Our Yorkville & Community LLC) sued in April alleging the city failed to give required public notice,… | |||
Project Steel (Yorkville, Eldamain Corridor) |
Yorkville, Kendall County IL · PJM |
active litigation | Second Yorkville lawsuit, filed by residents including Teska Family Farm, along the Eldamain Corridor; land was annexed/rezoned from residential to manufacturing; suit alleges… | |||
Meyer Project / Yorkville Nexus V LLC Rezoning (withdrawn) Green Door Capital |
Yorkville, Kendall County IL · PJM |
withdrawn | ~130-acre rezoning request (91 acres west, 37 acres east) south of Project Steel; Planning and Zoning Commission rejected in January 2026; City Council vote postponed in March;… | |||
DC Blox Nashville Zoo-Area Data Center DC Blox |
Nashville, Davidson County TN · SERC |
active litigation | DC Blox filed a federal lawsuit against Metro Nashville after the city stopped processing permits under its temporary data-center moratorium (in effect through December 2026),… | |||
Hillwood Industrial/Data Center Development (Wilson County) Hillwood |
Wilson County TN · SERC |
rezoning rejected moratorium recommended | Texas-based Hillwood's proposed 1,380-acre, 10.35M-sq-ft industrial development (no data-center tenant named) near I-40 was rejected by Wilson County commissioners roughly 18… | |||
xAI Colossus 1 & 2 (Memphis) xAI / SpaceX |
Memphis, Shelby County TN · SERC |
active litigation | NAACP sued xAI on April 14, 2026 alleging air pollution from unpermitted gas turbines powering Colossus 1/2 in a majority-Black Memphis community; DOJ intervened on xAI's side… | |||
Serverfarm Clarksville ($6.6B) Serverfarm |
Clarksville, Montgomery County TN · SERC |
under construction amid scrutiny | $6.6B project beside Johnson Regional Medical Center advancing (cranes visible, hillside cleared as of January 2026) despite growing community scrutiny over communication, water… | |||
Douglas County I-20 Data Center Permit Denial (11-building/3-warehouse application) |
Douglas County (near I-20 / Carroll County line) GA · SERC |
permit denied | Douglas County commissioners voted 4-1 to deny a proposed data center permit near the Carroll County line/I-20 after a packed, contentious commission meeting. Separately, a… | |||
Project Sail (Coweta County) Prologis / Atlas Development (PLD) |
Coweta County (Sargent community, near Newnan) GA · SERC |
900 | approved active litigation | Nine-building, 4.34M-sq-ft, ~900MW campus on 829 acres of protected rural conservation land near Georgia Power's Plant Yates. First surfaced Dec 31, 2024; Coweta commissioners… | ||
Project Pegasus (Coweta County) American Real Estate Partners (backed) |
Coweta County GA · SERC |
delayed amid moratorium | Second Coweta County data-center proposal (Virginia-based American Real Estate Partners-backed developers) caught in the same 2025 county moratorium and zoning rewrite that… | |||
Newton County Data Center Application Moratorium |
Newton County (incl. Covington, Social Circle, Porterdale) GA · SERC |
moratorium in force | Newton County Board of Commissioners unanimously enacted a 30-day moratorium on new data-center applications to update ordinances amid a rapid influx of requests (does not affect… | |||
QTS Atlanta Data Center Expansion (Howell Station, tax break withdrawn) QTS Data Centers (BAM) |
Atlanta, Fulton County (Howell Station) GA · SERC |
tax incentive withdrawn | Development Authority of Fulton County had considered a $45M tax break for a QTS expansion near the Howell Station neighborhood; the request was withdrawn amid public outcry even… | |||
Project Tango (Palm Beach County) |
Palm Beach County (near Arden / Loxahatchee) FL · FRCC |
denied without prejudice | Palm Beach County commissioners denied the hyperscale AI data center 'without prejudice' after nearly 12 hours of debate, meaning the developer may revise and resubmit; site… | |||
XF Group Sarasota County Hyperscale Data Center Freeze XF Group |
Sarasota County (Cattlemen Road) FL · FRCC |
moratorium in force | Sarasota County commissioners voted July 8, 2026 to halt acceptance, review, and approval of hyperscale data centers (50MW+) until at least July 2027 along Cattlemen Road;… | |||
MIA-1 Data Center (Iron Mountain, Westview) Iron Mountain (IRM) |
Westview, unincorporated Miami-Dade County FL · FRCC |
16 | under construction amid opposition | 16MW, 150,000-sq-ft, $150M facility on a 3.4-acre industrial site in a predominantly Black community. Approved by-right under existing industrial zoning classified as a… | ||
Alachua Phoenix Commercial Park (rumored data center) |
Alachua, Alachua County FL · FRCC |
rumored no application filed | 104-acre Phoenix Commercial Park site east of San Felasco Tech City was listed as a 'high megawatt data center development site' and later relisted as an 'industrial… | |||
Meade County 138-Acre Data Center Rezoning (denied) |
Meade County (near Brandenburg) KY · SERC |
rezoning denied | 138-acre site along Joe Prather Highway; Planning and Zoning Commission voted unanimously against rezoning from agricultural to light industrial and the Fiscal Court agreed with… | |||
Lexington-Fayette Former Lexmark Property Data Center Moratorium |
Lexington-Fayette Urban County KY · SERC |
moratorium in force | Lexington-Fayette Urban County Government unanimously passed a moratorium on new data center development at a proposed site on the former Lexmark property, effective through… | |||
Burgin / Mercer County Proposed Data Center (draft ordinance pending) |
Burgin, Mercer County KY · SERC |
under review no zoning process | Residents allege developers targeted Burgin because it lacked a formal planning/zoning process; the Mercer County Joint Planning and Zoning Commission was set to discuss a draft… | |||
Meta Hyperion & Evest Data Centers (Richland Parish) Meta / Entergy (META) |
Richland Parish LA · SERC |
5,000 | regulatory disclosure dispute | Combined Hyperion and Evest campuses represent Meta's >5GW power request, described as the largest in Louisiana history; Entergy proposing 10 new gas plants (3 approved 2025, 7… | ||
xAI Southaven Data Center & Gas Turbine Plant (noise/class action) xAI / SpaceX (MZX Tech LLC) |
Southaven, DeSoto County MS · SERC |
active litigation | One of three xAI data centers in the Memphis metro built with 57 temporary gas turbines and a permit for 41 additional permanent turbines. Three Southaven residents filed a… | |||
Downtown Kansas City High-Rise Data Center (Quality Hill / Western Newspaper Union Building) Revitalization Unlimited |
Kansas City, Jackson County MO · SPP |
permit denied | Miami-based developer Revitalization Unlimited proposed a 384-foot, 20-story data center atop the historic Western Newspaper Union building in Quality Hill; Kansas City Plan… | |||
St. Charles County Data Center Moratorium |
St. Charles County MO · SPP |
moratorium in force | St. Charles County Council unanimously approved a six-month moratorium on new data centers after overwhelming public opposition; County Executive Steve Ehlmann said more research… | |||
Google Stillwater Data Center Campus (up to 6 buildings) Google (GOOGL) |
Stillwater, Payne County OK · SPP |
under construction amid water concerns | Google building up to six data centers; first two buildings expected to use ~2.7M gallons/day, rising to 8.1M gallons/day if all six are built (against ~7M gallons/day current… | |||
Project Anthem (East Tulsa) |
East Tulsa, Tulsa County OK · SPP |
phase vote delayed | Tulsa City Council voted unanimously (Mar 25, 2026) for a nine-month citywide data-center construction moratorium; Project Anthem's first and second phases were exempted, but the… | |||
Sand Springs Meta-Backed Data Center Meta (reported) (META) |
Sand Springs, Tulsa County OK · SPP |
opposed proposed | Tribal advocates and residents protested secrecy around a Meta-backed Sand Springs data center proposal; hundreds attended public meetings opposing the project. | |||
Project Pilot / Beale Infrastructure De Soto Campus Beale Infrastructure (Mount Sunflower Properties LLC) |
De Soto, Johnson County KS · SPP |
approved expanded amid opposition | Kansas' first hyperscale data center; ~300-acre site near the Panasonic EV battery plant on the former Flint Commerce Center/Ad Astra Park site. De Soto City Council approved the… | |||
Apple Waukee Data Center (extension) Apple (AAPL) |
Waukee, Dallas County IA · MISO |
delayed extension requested | $1.3B facility (400,000 sq ft) originally due to complete by August 2022; Apple requested a five-year extension to August 2027, citing need for more design/build time. Only… | |||
Linn County Unincorporated Area Data Center Moratorium |
Linn County (unincorporated, near Cedar Rapids) IA · MISO |
moratorium in force | Linn County Board of Supervisors approved an 18-month moratorium (2-1 vote, through Jan 1, 2028) for unincorporated county areas to update its data-center ordinance, conduct a… | |||
MidAmerican Energy Salix Data Center Exploration MidAmerican Energy (BRK.A) |
Salix, Woodbury County IA · MISO |
early stage amid county moratoriums | MidAmerican Energy annexed nearly 1,000 acres of farmland into Salix to explore data center development, even as neighboring Plymouth, Sioux, and Woodbury counties adopted… | |||
NorthMark Strategies / Valara Holdings Computing Center (former Kohler plant) NorthMark Strategies (Valara Holdings) |
Spartanburg County SC · SERC |
450 | permitting challenged | $2.8B conversion of a former Kohler kitchen/bath plant (also a longtime bitcoin-mining site) into a computing center. State regulators initially approved ~50MW; company sought to… | ||
Stream Data Centers Marion County (abandoned) Stream Data Centers |
Marion County SC · SERC |
400 | abandoned | Dallas-based Stream Data Centers dropped a planned 400MW, 400-acre, ~600,000-sq-ft campus in an industrial park near Marion, SC, citing 'utility timing constraints', MPD Electric… | ||
Greenwood County Data Center Moratorium |
Greenwood County SC · SERC |
moratorium in force | Greenwood County Council advanced a one-year moratorium on data centers in a 4-3 vote. | |||
Nebius Data Center (Oxmoor Valley, Birmingham) Nebius (NBIS) |
Birmingham, Jefferson County (Oxmoor Valley) AL · SERC |
active litigation | Under construction off Lakeshore Parkway. Jefferson County Circuit Judge ruled July 11, 2026 that Oxmoor Valley residents' lawsuit against the city's approval process can… | |||
Bessemer Proposed Data Center (Little Blue Creek) |
Bessemer, Jefferson County AL · SERC |
zoning request paused active litigation | Proposed site near ecologically sensitive Little Blue Creek and Five Mile Creek (habitat for the endangered watercress darter). Bessemer City Council removed the zoning item from… | |||
Jones Eagle / Jones Digital DeWitt Crypto Data Center Jones Eagle LLC / Jones Digital |
DeWitt, Arkansas County AR · SPP |
active litigation temporary block | Owner Qimin 'Jimmy' Chen (naturalized US citizen born in China) challenged Arkansas Act 636 (2023) and Act 174 (2024), which bar data-center/crypto-mining property ownership by… | |||
AVAIO Data Center Project (Pulaski County) AVAIO |
Pulaski County AR · SPP |
moratorium exemption rejected | Pulaski County Quorum Court rejected a proposed data-center moratorium that would have carved out an exemption specifically for the AVAIO project; separately, Little Rock's own… | |||
Grant County Data Center FOIA Dispute |
Grant County AR · SPP |
active litigation records dispute | Public-records (FOIA) litigation over a proposed Grant County data center; part of a broader pattern of Arkansas Democrat-Gazette records lawsuits seeking data-center contract… | |||
Imperial Data Center (Imperial Valley Computer Manufacturing / IVCM) Imperial Valley Computer Manufacturing, LLC (developer Sebastian Rucci) |
Imperial County (near city of Imperial) CA · CAISO |
delayed | Would be largest data center in California at ~1M sq ft; promoted as producing 2,500 construction jobs and $28.7M/yr tax revenue; county supervisors first approved parcel merger… | |||
GI Partners Santa Clara Data Center (2805 Bowers Avenue) GI Partners |
Santa Clara CA · CAISO |
delayed | Four-story data center; site cost $79M. Delayed ~5 months versus planned construction timeline before City Council approval on Aug 29, 2024. | |||
Coachella Valley Technology Campus Stronghold Power Systems |
Coachella (Riverside County) CA · CAISO |
cancelled | Six data centers proposed across 450 acres of agricultural land; was to anchor a new city-run utility agency; council unanimously voted to terminate the Stronghold agreement… | |||
Eight Form El Segundo Data Center (750 N. Nash Street) Eight Form |
El Segundo (Los Angeles County) CA · CAISO |
withdrawn | Proposed replacing a 15-year-old Hyatt Place hotel with 160-foot, five-story data center plus dedicated electrical substation. | |||
Monterey Park Data Center (HMC StratCap) HMC StratCap |
Monterey Park (Los Angeles County) CA · CAISO |
cancelled | 247,000 sq ft facility that would have used ~3x electricity of entire 60,000-person city; would have sat under 500 feet from nearest home; ban can only be overturned by another… | |||
Behring AI Campus / Data Center (415 20th St.) Behring Companies |
Oakland CA · CAISO |
20 | delayed | ~20,000 sq ft of an 83,000 sq ft, 4-story building; part of a larger complex with a proposed 39-story apartment tower above 19th St BART station. | ||
San Jose Data Center Pipeline (multiple Equinix and other projects) Multiple (incl. Equinix) (EQIX) |
San Jose CA · CAISO |
pending review | Environmental groups Green Foothills flagged 'grandfathering' risk since developers may rush applications ahead of new standards; active CEQA EIR review process for Equinix… | |||
High-Speed Rail Corridor Data Center Deals (Merced/Madera) California High-Speed Rail Authority (co-development partners TBD) |
Merced / Madera / Kern County CA · CAISO |
pending review | CEO Ian Choudri says hyperscalers in talks for Central Valley sites including Kern County; Madera mayor Cecilia Gallegos said city would reject data centers over water use. | |||
Project Blue (Tucson) Beale Infrastructure (originally Amazon Web Services-linked; AWS later withdrew) (AMZN) |
Pima County / Tucson AZ · WECC |
litigation active | Biggest development ever proposed in Pima County/southern Arizona; developer is San Francisco-based Beale Infrastructure; despite Tucson rejection and Amazon's exit, project is… | |||
Chandler AI Data Center (Sinema-lobbied project) Unnamed New York developer |
Chandler AZ · WECC |
cancelled | Chandler already hosts 10 data centers and adopted 2022 rules limiting where they can be built; vote drew national progressive praise as a rare rejection of major tech-industry… | |||
NTT Mesa Data Center NTT (9432.T) |
Mesa AZ · WECC |
delayed | NTT spent $300M on land in southeast Mesa (Pecos/Crismon roads) in March 2025; requesting minor modifications to city allowances. | |||
Casa Grande 480-Acre Data Center Campus (Willis/Barnes parcels) Undisclosed (landowners Dale Willis and Vernon Barnes; law firm representation) |
Casa Grande (Pinal County) AZ · WECC |
under appeal | No end user/tenant publicly identified; waiver includes 800 net acre-foot water cap, on-site power requirement, noise limits, decommissioning rules, $5M community contribution. | |||
Tract Goodyear/Buckeye Data Center Tract |
Goodyear and Buckeye (Maricopa County) AZ · WECC |
withdrawn | Company announced a replacement project near Buckeye airport in August 2024 with similar characteristics after securing mayoral support. | |||
Boulder City BLM Data Center (Townsite Solar 2 / Eldorado Valley) Townsite Solar 2 (subsidiary of Texas-based hedge fund) |
Boulder City NV · WECC |
litigation active | City stood to receive an estimated $2.3M/yr in lease/tax revenue but instead disclosed BLM rent of only $1,207.67 in 2023; former BLM policy chief called the process… | |||
Tract Northern Nevada Land Portfolio (Storey County/Reno area) Tract |
Storey County / Washoe County NV · WECC |
litigation active | Tract has purchased more than 12,000 acres across northern Nevada; company says it never sought subsidized costs and committed nearly $1B toward NV Energy infrastructure. Related… | |||
Reno Data Center Pipeline (city-wide moratorium) Multiple developers |
Reno NV · WECC |
halted | Initial 30-day moratorium adopted per city rules, then extended after a 9-hour public meeting with 5+ hours of comment; some council members want to study a permanent ban. | |||
Boardman Transmission Line / Amazon Data Center Support Infrastructure Amazon Web Services (AMZN) |
Boardman (Morrow County) OR · WECC |
litigation active | Decision on Boardman data center delayed in 2023 by new testimony; transmission line dispute continued into 2026 with regulatory challenges. | |||
Hillsboro Data Center Pipeline (city moratorium) Multiple developers |
Hillsboro (Washington County) OR · WECC |
halted | Hillsboro is one of Oregon's largest tech hubs (Intel/Silicon Forest); existing facilities may continue operating. | |||
Cascade Locks Data Center (Roundhouse Digital Infrastructure) Roundhouse Digital Infrastructure |
Cascade Locks (Hood River County) OR · WECC |
cancelled | Cited as an early precedent case for electoral backlash against data center approvals nationally. | |||
Umatilla County Eastern Oregon Data Center Moratorium Petition Multiple (Amazon and others) (AMZN) |
Umatilla County / Morrow County OR · WECC |
pending review | Part of broader statewide push including a legislature-considered one-year moratorium on data center tax breaks that Gov. Kotek has expressed support for. | |||
Seattle Data Center Pipeline (citywide moratorium) Multiple developers |
Seattle WA · WECC |
halted | Notable given Seattle is home to Amazon and Microsoft; part of a wider wave of Washington state municipal moratoria. | |||
Spokane Data Center Pipeline (citywide moratorium) Multiple (incl. Avista large-load customer) (AVA) |
Spokane WA · WECC |
halted | Data Center Coalition warned the moratorium sends a bad signal to a $1B+ minimum investment industry and could push Spokane out of site-selection conversations. | |||
Federal Way Data Center Moratorium Undisclosed |
Federal Way WA · WECC |
halted | Part of broader Puget Sound-region wave of municipal pauses. | |||
Grant County PUD Data Center Load Growth Cap Multiple (Microsoft and others in Quincy/Moses Lake corridor) (MSFT) |
Grant County (Quincy/Moses Lake) WA · WECC |
delayed | Quincy is historically Microsoft's flagship 'data centers gone right' market; new caps signal a shift even in the most data-center-friendly Washington jurisdiction. | |||
Broomfield Data Center Pipeline (18-month moratorium) Multiple developers |
Broomfield CO · WECC |
10 | halted | Threshold set at 10 MW; part of a wave of Front Range municipalities enacting pauses in 2026. | ||
Project Taurus (Colorado Springs) Raeden |
Colorado Springs (El Paso County) CO · WECC |
under appeal | Located along Garden of the Gods Road on a former microchip manufacturing site west of Centennial Boulevard; developer Jason Green (Raeden) touts water-efficient closed-loop… | |||
Douglas County / Parker Flexential Data Center Flexential |
Douglas County (Parker) CO · WECC |
litigation active | Tax rebate value approximate ($19M); denial and rebate approval reflect a split regulatory record in the same county within months. | |||
Aurora Data Center Pipeline (moratorium debate) Multiple (incl. Microsoft Aurora AI Campus) (MSFT) |
Aurora CO · WECC |
delayed | Councilwoman Amy Wiles championed a pause; council ultimately opted for regulation over outright ban, but process caused delay for pipeline projects including the Microsoft… | |||
Lex Developments Pocatello Data Center ($2.6B) Lex Developments |
Pocatello (Bannock County) ID · WECC |
under appeal | Proposed at a former polysilicon plant site; Idaho Conservation League highlighted unprecedented cumulative energy use concerns, comparing water use to an 18-hole golf course or… | |||
Meta Kuna Data Center Expansion Pause Meta (META) |
Kuna (Ada County) ID · WECC |
delayed | Original $800M facility reached 'peak construction' before expansion was paused; 2023 Idaho law nearly stripped Kuna's urban renewal incentive tied to the project. | |||
Stratos Project (Box Elder County) Undisclosed developer (backed by Kevin O'Leary) |
Box Elder County UT · WECC |
7,000 | litigation active | Roughly 20,000-acre hyperscale campus near the Great Salt Lake requiring an estimated 7 GW of power - more than double Utah's current statewide energy use; celebrity investor… | ||
West Jordan Facebook Data Center (historical, cancelled) Facebook (Meta) (META) |
West Jordan UT · WECC |
cancelled | Historical precedent case frequently cited in current Utah data center debates; included for completeness though outside the post-Jan 2024 window as background context. | |||
Project Jupiter (Santa Teresa / Doña Ana County) Yucca Growth Infrastructure (developer); Oracle and OpenAI (end users) (ORCL) |
Santa Teresa (Doña Ana County) NM · WECC |
litigation active | Bonds ($165B) issued for Oracle/OpenAI development before Planning & Zoning Commission had voted on zoning, per plaintiff allegations; judge dismissed pro se resident's second… | |||
Project Zenith (Roswell) Undisclosed |
Roswell (Chaves County) NM · WECC |
pending review | County framework would only apply to projects seeking public incentives; privately financed projects exempted. | |||
Meta Los Lunas Expansion (Phase 3) Meta (META) |
Los Lunas (Valencia County) NM · WECC |
pending review | Original Meta investment estimated at $3.3B in Los Lunas; expansion phase raised renewed local water-use scrutiny. | |||
New York Statewide Hyperscale Data Center Moratorium (Executive Order 62) Multiple developers statewide |
Statewide NY · NYISO |
halted | First state to enact such a moratorium; affects pending projects including STAMP (Genesee County), Tonawanda, and Niagara Falls proposals; legislature had separately passed its… | |||
STAMP Data Center (Stream U.S. Data Centers / Genesee County) Stream U.S. Data Centers (via Genesee County Economic Development Center) |
Town of Alabama, Genesee County (STAMP industrial park) NY · NYISO |
250 | litigation active | 2.2M sq ft facility; $1.46B in requested state/local sales tax breaks ($716M state + $716M local); Hochul had previously called it a 'local decision' she wouldn't override (March… | ||
Wildflower Yaphank Data Center Wildflower |
Yaphank, Town of Brookhaven (Suffolk County) NY · NYISO |
halted | Long Island Power Authority said it does not anticipate service issues, with infrastructure costs borne by the developer; Suffolk County Water Authority says no water application… | |||
Lysander Data Center Moratorium Undisclosed |
Lysander (Onondaga County, Syracuse area) NY · NYISO |
halted | Part of the broader Syracuse-area wave of caution following major Micron/semiconductor-adjacent development pressure in the region. | |||
Islip Data Center Moratorium Consideration Undisclosed |
Islip (Suffolk County) NY · NYISO |
pending review | Reflects a cascading pattern of Long Island towns adopting pauses in mid-2026. | |||
Markley Group Lowell Data Center Generator Expansion Markley Group |
Lowell MA · ISO-NE |
litigation active | This is a litigation update on the previously tracked Markley Group Lowell Expansion entry - court-ordered construction pause specifically targeting diesel backup generator… | |||
Westfield Data Center ($4B) Undisclosed developer |
Westfield MA · ISO-NE |
delayed | Case highlights retroactive political risk even for previously-approved projects as statewide sentiment on data centers shifts. | |||
Atlas Capital Group Bloomfield Data Center Atlas Capital Group |
Bloomfield (Hartford County) CT · ISO-NE |
pending review | Proposed 900,000 sq ft data center plus 127,000 sq ft substation (over 1M sq ft total) at 132 Griffin Road North; among the first major hyperscale-scale proposals in Connecticut. | |||
New Haven Data Center Moratorium Proposal Multiple (regulatory, no single named project) |
New Haven CT · ISO-NE |
pending review | Precautionary, policy-level pause rather than a response to one specific project; part of statewide CT data center policy debate. | |||
Nottingham Business Park Data Center Nottingham Business Park LLC (developer Thomas Moulton) |
Nottingham NH · ISO-NE |
withdrawn | One of the largest small-town grassroots petition campaigns against a single data center project nationally. | |||
Verrus Data Center (Mill Creek Corporate Center) Verrus |
Salem (Marion County) OR · WECC |
pending review | Same statewide wave as Hillsboro's 120-day moratorium, enacted the same week; large crowds filled the Salem Public Library auditorium for the hearing. | |||
Smithfield Data Center (Hanton City Investments) Hanton City Investments LLC |
Smithfield RI · ISO-NE |
litigation active | A test case for whether an in-process application filed shortly before a newly passed local ban can be grandfathered in. | |||
Bates Mill Data Center (Lewiston) Undisclosed developer |
Lewiston ME · ISO-NE |
cancelled | Proposed inside a historic mill building; project's secrecy (unnamed backers) fueled resident suspicion and contributed to rejection. | |||
Diode Ventures Cedar Creek Lake Data Center Diode Ventures |
Henderson County (Cedar Creek Lake / Cedar Creek Reservoir) TX · ERCOT |
withdrawn | Update/confirmation of previously tracked entry - confirms formal withdrawal date and cause; Cedar Creek Lake is a major regional drinking-water and recreation reservoir, which… | |||
Blueprint Data Centers Taylor Facility Blueprint Data Centers |
Taylor (Williamson County) TX · ERCOT |
litigation active | 135,000 sq ft facility; case highlights title/deed-restriction risk as an emerging litigation vector for Texas data center siting distinct from zoning or environmental claims. | |||
Meta Temple Data Center Meta (META) |
Temple (Bell County) TX · ERCOT |
delayed | Part of the same Meta redesign wave that paused the Kuna, Idaho facility. | |||
Project Patriot / Knox Ranch (Granbury) Bilateral Energy |
Granbury (Hood County) TX · ERCOT |
litigation active | One of several Hood County data center disputes (see also Comanche Circle/Sailfish and Project Red/Yellow entries) reflecting a concentration of Central Texas litigation around… | |||
Comanche Circle / Sailfish Investors Data Center Sailfish Investors (developer Ryan Hughes) |
Hood County TX · ERCOT |
delayed | Included here as a delay/opposition case even though ultimately approved, given the scale of community pushback documented in local coverage; distinct 2,100-acre parcel from the… | |||
Project Red and Project Yellow (Hood County) National CRE Holdings and Greenland Capital |
Hood County TX · ERCOT |
under appeal | Two related data center proposals in Hood County, adding to the county's concentration of contested projects alongside Comanche Circle and Project Patriot/Knox Ranch. | |||
Wichita Falls Data Center Rezoning (Data Nova X) Data Nova X (originally proposed under different developer branding) |
Wichita Falls TX · ERCOT |
cancelled | Rezoning rejection halted the project as proposed; local coverage noted skepticism over the developer's rebranding partway through the approval process. | |||
RCM Hill LLC Data Center (Hill County) RCM Hill LLC |
Hill County TX · ERCOT |
litigation active | Notable as a case where litigation pressure from the developer side successfully forced a county to reverse its own moratorium. | |||
Highlander SM One LLC Data Center (San Marcos) Highlander SM One LLC |
San Marcos (Hays County) TX · ERCOT |
cancelled | Distinct developer/parcel from the already-tracked Hays County/San Marcos data center entry; this project was rejected outright twice rather than approved. | |||
Skybox Datacenters San Angelo Project Skybox Datacenters |
San Angelo (Tom Green County) TX · ERCOT |
delayed | City-owned land angle distinguishes this from typical private-parcel disputes; raised transparency and public-benefit questions locally. | |||
Red Oak Data Center Rezoning (Compass Datacenters) Compass Datacenters |
Red Oak (Ellis County) TX · ERCOT |
delayed | Included as a documented opposition/delay case with a notable community-benefit concession, even though the rezoning was ultimately approved. | |||
Texas Statewide Data Center Interconnection Audit (ERCOT Batch Zero) Multiple (up to ~300 projects statewide, including Sherman/Grayson County pipeline) |
Statewide (ERCOT footprint, incl. Sherman/Grayson County) TX · ERCOT |
halted | Sherman/Grayson County is a major semiconductor and data-infrastructure growth corridor (Texas Instruments, GlobiTech) directly affected by the pause; this is a statewide… |
Jurisdictional actions
State, local, and federal moratoriums, executive orders, audits, and legislation affecting data center approval or interconnection.
| Jurisdiction | Action | Date | Status | Sources |
|---|---|---|---|---|
TX state · Governor Greg Abbott / PUCT / ERCOT |
Comprehensive verification and audit of all data centers in ERCOT interconnection process Timing: ERCOT told the PUCT at its August 20, 2026 open meeting that it aims to file the comprehensive verification and audit report by December 10, 2026, one week before the December PUCT open meeting. ERCOT stated the verification will take several months but less than nine, and that the Batch Zero transmission planning study will NOT be complete by its original April 9, 2027 target. |
2026-08-03 | audit in progress | |
NY state · Governor Kathy Hochul (Executive Order 62) / DEC |
Statewide pause on discretionary DEC permits for data centers ≥50 MW until Generic Environmental Impact Statement completes Timing: ~1 year (until GEIS complete) |
2026-07-14 | audit paused | |
Indianapolis / Marion County local · City-County Council |
Pause on all new data center construction city-wide through Dec 31, 2027 Timing: Through Dec 31, 2027 |
2026-08-10 | audit paused | |
Nashville / Metro Davidson local · Metro Nashville Council |
Moratorium on certain data center permits and appeals until at least December 1, 2026 Being challenged in federal court by DC BLOX |
2026-07-21 | litigation active | |
Loudoun County local · Board of Supervisors |
Board voted 6-1 to direct staff to prepare moratorium options for Sept 15 meeting; Dillon's Rule constrains authority Home to Data Center Alley, 250+ existing DCs. Virginia state law may not permit local moratorium. |
2026-07-23 | pending review | |
Seattle local |
One-year moratorium on new data centers | 2026-06-09 | audit paused | |
Spokane local |
One-year moratorium on new data centers | 2026-06-23 | audit paused | |
Broomfield local |
18-month pause on data centers | 2026-07-07 | audit paused | |
Prince George's County local |
Two-year pause on hyperscale data centers | 2026-07-07 | audit paused | |
Eagan local |
Moratorium on new data centers >20MW / expansions >9MW until Feb 17, 2027 Being challenged in court by Eagan Capital (filed June 15, 2026) |
2026-02-17 | litigation active | |
AZ state · Arizona Legislature (budget) |
Three-year moratorium on data center sales tax exemption Timing: Through June 30, 2029 |
2026-07-01 | audit paused | |
VA state · General Assembly (Bill) |
HB 1515, Moratorium on new DCs (1 MW+) until interconnection requests fulfilled or July 2028 Continued/still in committee |
2026-01-XX | pending review | |
Denmark (Energinet) national |
3-month grid connection pause | 2026-05-04 | audit paused | |
Ireland (EirGrid) national |
Freeze ended Dec 2025; new connections must bring own on-site power | 2025-12-XX | delayed | |
federal · FERC |
Show-cause orders to six RTOs (PJM, MISO, SPP, CAISO, ISO-NE, NYISO), 60 days to justify or reform large-load tariffs across 5 reform areas | 2026-06-18 | pending review | |
Texas (statewide) state · Gov. Greg Abbott / ERCOT / PUCT |
Governor Abbott directed a comprehensive audit of up to 300 pending large-load data center interconnection projects, pausing new approvals until ERCOT and PUCT complete energy and water usage review BNEF estimates the audit could delay 49.8 GW of data center load and cost projects up to $15 billion; Texas also enacted SB 6 (2025) creating large-load curtailment and cost-allocation… Timing: Pending audit completion |
2026-08-03 | audit paused | |
New York (statewide) state · Gov. Kathy Hochul / Executive Order No. 62 |
Executive Order 62 establishes the nation's first statewide temporary moratorium on new large (50MW+) hyperscale data center permitting while NYSDEC develops a Generic Environmental Impact Statement and siting framework Follows earlier legislative effort (S.9144/A.10141, 20MW threshold, 3-year pause) that stalled in committee; NYSDEC permitting for large data centers is paused under the EO. Timing: Until GEIS/permitting framework complete |
2026-07-14 | pending review | |
Arizona (statewide) state · Gov. Katie Hobbs / Arizona Legislature |
Arizona froze new data center sales-tax exemption applications for three years amid a state budget fight over cost of tax incentives Sparked a rush of incentive applications before the freeze deadline; existing exemptions unaffected. Timing: 3 years |
2026-06-13 | pending review | |
Virginia (statewide) state · Virginia General Assembly / Del. Shin (HB 1515) |
HB 1515 would prohibit localities from granting final approval for new data centers until pending AI data center interconnection requests are fulfilled or July 1, 2028; continued to 2027 session in House Rules Committee Virginia is a Dillon's Rule state; localities cannot impose moratoria on their own, so this would be the first statewide legislative pause. More than 60 data center bills considered in the… Timing: Through July 1, 2028 (if enacted) |
2026-02-06 | pending review | |
Maine (statewide) state · Maine Legislature / Gov. Janet Mills |
LD 307 would have imposed an 18-month moratorium on data centers over 20MW pending a coordination council review; passed legislature but vetoed by Gov. Mills on April 24, 2026; override vote failed 20-11 in Senate (short of two-thirds) Mills signed executive order creating 15-member Maine Data Center Advisory Council to deliver recommendations by early 2027. Local moratoria (Scarborough, Brunswick, Warren, Hot… Timing: 18 months (vetoed, not enacted) |
2026-04-24 | litigation active | |
Georgia (statewide) state · Georgia General Assembly / Public Service Commission |
HB 1059 proposed statewide ban on new data center permits until impact study completes; died in committee. Separately, Georgia PSC unanimously approved a rule requiring new Georgia Power customers above 100MW (chiefly data centers) to pay their own site-specific and upstream… Multiple GA counties/cities enacted their own moratoria (Cherokee County, Chamblee, Garden City, Newton County, DeKalb County, Athens-Clarke County, Camden County, Rockdale County). Timing: N/A (PSC rate rule enacted; legislative ban died) |
2026-01-26 | pending review | |
Ohio (statewide) state · Ohio ballot petitioners / Ohio General Assembly |
Proposed constitutional amendment to ban data centers over 25MW; petitioners gathered ~70,000 of 413,488 signatures required by July 1, 2026 deadline and failed to qualify for ballot; separately Substitute HB 646 (dedicated rate class, halved sales-tax exemption, closed-loop… At least 20+ Ohio municipalities/townships enacted their own moratoria independently (see Franklin, Delaware, Licking County entries). Timing: Ballot effort failed; backers plan retry in 2027 |
2026-04-03 | litigation active | |
Michigan (statewide) state · Michigan Legislature |
Statewide moratorium bills (HB 5594-5596, SB 1018-1020) reintroduced for a 1-year/365-day pause on data center construction alongside a Senate Democratic regulatory package; none enacted Gov. Whitmer has called a moratorium 'an automatic non-starter.' Timing: 365 days (if enacted) |
2026-06-24 | pending review | |
Pennsylvania (statewide) state · Gov. Josh Shapiro |
Gov. Shapiro announced a major shift sharply limiting data center development and expanding the review process for new projects, taking a hard line against 'predatory' developers, after PA House/Senate bills (model ordinance, 18-month local moratorium authorization, Sen. Muth's… PA Senate had separately advanced a bill allowing localities to enact up to 18-month data center moratoria. Timing: TBD (new review process) |
2026-08-17 | pending review | |
Vermont (statewide) state · Vermont Legislature (S.205) |
S.205 would impose a moratorium on data centers above 10MW until July 1, 2030, the longest pause window of any 2026 state bill In committee as of mid-2026; Vermont has minimal existing data center capacity, so bill is largely preventive. Timing: Until July 1, 2030 |
2026-01-01 | pending review | |
Oklahoma (statewide) state · Oklahoma Legislature (Sen. Standridge Sacchieri, SB 1488) |
SB 1488 would pause new data center construction statewide until November 1, 2029 while a study commission examines rural, ratepayer, and water impacts In committee as of mid-2026. Timing: Until Nov. 1, 2029 |
2026-01-22 | pending review | |
South Dakota (statewide) state · Gov. Larry Rhoden / SD Legislature |
SB 135 ('Data Center Bill of Rights for Citizens') and HB 1038 signed into law, not a moratorium, but requires 10MW+ facilities to pay for their own grid upgrades, disclose water/energy projections, and preserves local home-rule authority over siting/moratoria First enacted state-level data center restriction in the country (though framed as disclosure/cost-allocation rather than an outright pause). Timing: Permanent (enacted law) |
2026-03-24 | pending review | |
Florida (statewide) state · Florida Legislature / Governor |
SB 484 (Chapter 2026-65) signed into law effective July 1, 2026: affirms local land-use authority over large-load data centers, sets minimum utility tariff/service requirements, restricts certain water-use permits, and orders a state study of large-scale data centers Enables the wave of Florida county moratoria (Sarasota, Palm Beach). Timing: Permanent (enacted) |
2026-07-01 | pending review | |
Texas (statewide) state · Texas Legislature / Gov. Abbott (SB 6) |
SB 6 signed into law setting planning, interconnection, and cost-allocation rules for large electric loads including data centers, allowing ERCOT to curtail large loads during grid emergencies Predecessor/complement to the Aug. 2026 audit/pause; establishes legal basis for curtailment during the audit. Timing: Permanent (enacted) |
2025-06-01 | pending review | |
Loudoun County county · Loudoun County Board of Supervisors |
Phase 1 zoning rewrite eliminated by-right AI data center development countywide; every new data center now requires a Special Exception (SPEX) permit with public hearings. Board separately voted 6-1 (July 22, 2026) to direct staff to study a full pause on processing all data… County attorney says formal moratoria are not legal in VA except narrow circumstances; grandfathering for applications filed before Feb 12, 2025 more than 500ft from residential areas.… Timing: Phase 2 standards expected ~March 2027 |
2025-03-18 | pending review | |
Prince William County county · Prince William County Board of Supervisors |
Board initiated zoning text amendment (DPA2026-00006) on March 3, 2026 to eliminate by-right AI data center approval within the Data Center Opportunity Zone Overlay District (DCOZOD) and require a Special Use Permit (SUP) for all data centers; also closed the overlay to future… Follows controversial PW Digital Gateway rezoning approved without a water-use study; Board also unanimously denied rezoning for the ~2,000-acre Dulles Cloud South campus and abandoned… Timing: Pending final adoption |
2026-03-03 | pending review | |
Hanover County county · Hanover County Board of Supervisors |
Board voted 4-3 to deny rezoning and conditional-use permit for Tract's 430-acre Mountain Road Technology Park data center campus, citing water use, noise, and speculative nature of the project Hanover Planning Commission had earlier voted to deny the HHHunt-affiliated rezoning on Jan 15, 2026; Board also launched a broader public review of data center policy. Timing: N/A (project rejected) |
2026-05-28 | litigation active | |
Fairfax County county · Fairfax County Board of Supervisors |
Adopted Zoning Ordinance Amendment ZO 112.1-2024-9 imposing 200ft residential setback for buildings (300ft for equipment), a 1-mile Metrorail-station buffer requiring special exception, mandatory pre/post-construction noise studies, and building design standards for AI data… Projects with site plans submitted before July 16, 2024 grandfathered (e.g., Plaza 500 in Bren Mar). 4.4M sq ft of data centers under construction in Fairfax as of early 2024. Timing: Permanent (enacted ordinance) |
2024-09-11 | pending review | |
Prince George's County county · Prince George's County Council (Chair Oriadha) |
County Council approved a 2-year moratorium on new hyperscale data center development following a countywide task force review; extended the pause in early July Timing: 2 years |
2026-07-08 | pending review | |
Sarasota County county · Sarasota County Commission |
County blocked hyperscale data center applications for at least one year, with commissioners stating 'no, not now, never' regarding large AI data centers Sarasota County cities subsequently united in opposition to the fast-growing AI data center industry. Timing: At least 1 year |
2026-07-09 | pending review | |
Palm Beach County county · Palm Beach County Board of County Commissioners |
County halted new AI/large-scale data center applications under a moratorium directive, while carving out an exception allowing the pending 'Project Tango' application to proceed to a decision Zoning board separately recommended a formal one-year pause on new large-scale data centers. Timing: ~1 year (pending ULDC revisions) |
2026-07-07 | pending review | |
Chesterfield County county · Chesterfield County Board of Supervisors |
Board indicated it will not approve any more data centers in the county, effectively pausing new approvals amid growing local opposition One county data center project reportedly halted amid legal dispute. Timing: Indefinite |
2026-06-01 | pending review | |
Warrenton (Fauquier County) city · Warrenton Town Council |
Town Council took up data center regulation in 2025 amid opposition to an Amazon data center and transmission line proposal near Warrenton Timing: Ongoing review |
2025-01-01 | pending review | |
Manassas / Prince William County county · Virginia Court of Appeals |
Court of Appeals ruling blocked construction of 37 data centers proposed adjacent to Manassas National Battlefield Park, halting the Digital Gateway-linked project Prince William supervisors subsequently abandoned defense of the related Digital Gateway rezoning. Timing: Pending further appeal |
2026-04-07 | litigation active | |
Fauquier County county · Fauquier County Board of Supervisors |
County approved a policy curbing new data centers; officials also caused Amazon to 'indefinitely postpone' its proposed AWS data center in the county Timing: Ongoing |
2025-06-01 | pending review | |
Culpeper County county · Culpeper County Board of Supervisors |
County put new 'guardrails' on data centers even while approving the Red Ace Data Center campus (69.19 acres rezoned rural to light industrial); Piedmont Environmental Council urged a full ban in the draft zoning code Timing: Ongoing |
2025-01-01 | pending review | |
Berkeley County county · Berkeley County Council / residents |
Local residents organized opposition to a proposed $4 billion data center in Berkeley County; county officials (site of WV's first 'high impact' data center) sought clarity on tax-split rules amid growth concerns No formal moratorium yet identified, but active organized opposition and legislative scrutiny. Timing: Ongoing |
2026-03-23 | pending review | |
Front Royal / Warren County city · Front Royal Town Council / Warren County |
Front Royal adopted a moratorium in June 2026 and declared no data centers are permitted in the town's industrial areas, effectively ruling out data centers town-wide Timing: Indefinite |
2026-06-01 | pending review | |
Chesapeake city · Chesapeake City Council |
City Council approved an 8-month pause on data center applications, paired with a Comprehensive Plan amendment process Council had earlier rejected an AI data center rezoning in June 2025 over environmental/disruption concerns. Timing: 8 months |
2026-07-22 | pending review | |
Montgomery County county · Montgomery County Executive / Council |
County Executive paused new data center permit applications for 6 months by executive order in June 2026; County Council advancing a bill to extend the pause to 18 months and cap facility size Timing: 6 months (proposed extension to 18 months) |
2026-06-01 | pending review | |
Frederick County county · Frederick County Council |
Frederick County adopted a data center application pause similar to Montgomery County's Timing: Not specified |
2026-06-01 | pending review | |
Baltimore (city) city · Baltimore City Council |
City Council passed a one-year moratorium on new data center development pending a zoning study Timing: 1 year |
2026-05-12 | pending review | |
Baltimore County county · Baltimore County Council |
Baltimore County adopted a data center application pause similar to Montgomery and Frederick counties Timing: Not specified |
2026-06-01 | pending review | |
Washington County county · Washington County Board of Commissioners |
Western Maryland county approved a yearlong data center moratorium Timing: 1 year |
2026-07-01 | pending review | |
Calvert County county · Calvert County Board of Commissioners |
County board passed a 6-month moratorium on new data centers Timing: 6 months |
2026-08-01 | pending review | |
Indianapolis city · Indianapolis City-County Council |
Council approved a data center moratorium pausing approval of new data centers through the end of 2027, overriding Mayor Hogsett's earlier veto/endorsement position; awaits Metropolitan Development Commission sign-off Development committee had advanced it 10-3 before full council vote. Timing: Through end of 2027 |
2026-08-10 | pending review | |
Boone County county · Boone County Commissioners |
Commissioners approved a moratorium on new data center development Timing: Not specified |
2026-06-15 | pending review | |
Hobart city · Hobart residents / Circuit Court |
Residents/opponents filed suit challenging an Amazon data center project in Hobart, Indiana See lawsuits.json for docket detail. Timing: N/A (litigation) |
2025-01-01 | litigation active | |
Nashville (Metro Davidson County) city · Metro Council (BL2026-1448) |
Metro Council passed data center zoning and permit regulations that ban some data centers, pause the rest, and add new regulations, after a record-setting council meeting Related to DC BLOX v. Nashville litigation (see lawsuits.json). Timing: Not specified (permanent zoning changes plus pause) |
2026-07-21 | pending review | |
Wilson County county · Wilson County Commission |
County commission approved a six-month moratorium on data centers to study impacts on water and power Timing: 6 months |
2026-07-14 | pending review | |
McMinnville city · McMinnville City Council |
City adopted a new pause on data center applications Timing: Not specified |
2026-01-01 | pending review | |
Federal Way city · Federal Way City Council |
City passed a one-year data center moratorium Timing: 1 year |
2026-01-01 | pending review | |
Broomfield city · Broomfield City Council |
City Council passed an 18-month temporary ban on new or expanded data centers of 10MW or more Timing: 18 months |
2026-07-08 | pending review | |
Denver city · Denver City Council |
City Council unanimously passed a one-year moratorium on new data center construction Proposal first introduced March 31, 2026. Timing: 1 year |
2026-05-18 | pending review | |
Aurora city · Aurora City Council |
City Council rejected a proposed six-month data center moratorium and instead approved new siting rules and water regulations Aurora had earlier paused data center/warehouse development approvals temporarily in Sept. 2025. Timing: N/A (moratorium rejected; regulations adopted instead) |
2026-08-11 | pending review | |
Boulder County county · Boulder County Commissioners |
Commissioners declared a moratorium on new data center (and detention center) development while updating land-use code (docket DC-26-0003) Timing: Pending land-use code update |
2026-08-10 | pending review | |
Lochbuie city · Lochbuie Board of Trustees |
Town enacted a five-year data center moratorium, the longest local pause identified in Colorado Timing: 5 years |
2026-01-01 | pending review | |
Douglas County county · Douglas County Commissioners |
Commissioners kept data centers and crypto mines on hold pending new regulations, without adopting a formal moratorium Timing: Pending regulation development |
2026-04-25 | pending review | |
Minneapolis city · Minneapolis City Council |
City Council gave final approval to a data center development pause Timing: Not specified |
2026-06-25 | pending review | |
Inver Grove Heights city · Inver Grove Heights City Council |
City adopted a new pause on data center development Timing: Not specified |
2026-01-01 | pending review | |
Ypsilanti Township / Ypsilanti Community Utilities Authority utility · Ypsilanti Community Utilities Authority (YCUA) |
YCUA board approved a 12-month moratorium on supplying water/sewer service to new data centers (Resolution No. 2026-08) Ypsilanti City Council separately voted in support of the YCUA moratorium. Timing: 12 months |
2026-04-16 | pending review | |
Flint city · Flint City Council |
City adopted a new pause on data center development Timing: Not specified |
2026-01-01 | pending review | |
Chandler city · Chandler City Council (Ordinance No. 5033) |
City Council adopted Ordinance No. 5033 establishing zoning restrictions on data centers after years of resident complaints about noise and resource use Predates the 2024-2026 wave but remains in force and is frequently cited as a model. Timing: Permanent (enacted ordinance) |
2022-01-01 | pending review | |
Casa Grande city · Casa Grande City Council |
City Council approved data center waivers/exceptions to local rules amid state-level tax incentive pause, drawing debate over possible damages liability Timing: Not specified |
2026-08-03 | pending review | |
Tucson city · Tucson City Council |
City Council voted 7-0 to end negotiations and halt annexation for Project Blue, a 290-acre Amazon-linked data center campus (developer Beale Infrastructure), citing water supply and ratepayer concerns Developer subsequently pursued the site in unincorporated Pima County instead. Timing: N/A (project halted) |
2026-01-01 | pending review | |
Ravenna city · Ravenna City Council |
City Council unanimously adopted a one-year moratorium on new data centers, heading off a proposed facility on State Route 14 Part of a wave of Northeast Ohio moratoria. Timing: 1 year |
2026-01-01 | pending review | |
Lordstown (village) city · Lordstown Village Council (Ordinance 1-2026) |
Village Council passed an emergency 180-day moratorium on new data center permits after first enacting and then repealing an outright ban amid a developer's Ohio Supreme Court challenge; council later moved to extend the moratorium Underlying dispute reached the Ohio Supreme Court. Timing: 180 days (extended) |
2026-01-01 | litigation active | |
Franklin County (Prairie Township / Washington Township) county · Prairie Township Trustees / Washington Township Trustees |
Prairie Township enacted a 6-month moratorium on data center zoning applications; Washington Township separately paused new data centers to assess fire safety and emergency readiness Franklin County also convened a dedicated Data Center Moratorium Work Group. Timing: 6 months (Prairie Twp.) |
2026-04-01 | pending review | |
Sunbury (Delaware County) county · Sunbury City Council |
City Council passed a moratorium on data centers effective until 2027; residents separately petitioned to place a charter amendment banning data centers on the November 2026 ballot Neighboring Pataskala pursuing a similar fall ballot measure. Timing: Through 2027 |
2026-04-16 | pending review | |
St. Albans Township (Licking County) county · St. Albans Township / Licking County Planning Commission |
Township officials sought to ban data center complexes; Licking County Planning Commission approved St. Albans Township's plan to ban data centers Microsoft separately paused its own $1bn data center plans in Licking County. Timing: Not specified |
2026-01-01 | pending review | |
Sugar Grove (Kane County) county · Sugar Grove Village Board / Kane County officials |
Officials considering a moratorium on data centers in unincorporated Kane County; Sugar Grove weighing a data center crackdown Aurora, IL city council separately approved new data center regulations. Timing: Under consideration |
2026-04-06 | pending review | |
Lake County (unincorporated) county · Lake County Board |
County Board voted to temporarily ban new data centers in unincorporated Lake County; a subsequent proposed 8-month moratorium cleared its first procedural step in August 2026 Linked to Grayslake/T5 litigation (see lawsuits.json). Timing: 8 months (subsequent proposal) |
2026-06-20 | pending review | |
McHenry County county · McHenry County Board |
County considering data center regulatory requirements amid regional Chicagoland backlash against new projects Timing: Under consideration |
2026-06-01 | pending review | |
Chatham County county · Chatham County Board of Commissioners |
County enacted a 12-month moratorium on data centers and cryptocurrency mining A developer sued Chatham County over the moratorium (see lawsuits.json). Timing: 12 months |
2026-02-18 | litigation active | |
Apex (Wake County) city · Apex Town Council |
Town Council approved a yearlong pause on data center projects amid opposition to the proposed New Hill Digital Campus Developer subsequently withdrew the New Hill Digital Campus application. Timing: 1 year |
2026-03-11 | pending review | |
Wendell (Wake County) city · Wendell Board of Commissioners |
Town adopted a temporary moratorium on data centers while it rewrites zoning rules Timing: Pending zoning rewrite |
2026-03-01 | pending review | |
Boone city · Boone Town Council |
Town approved a data center development moratorium Timing: Not specified |
2026-03-23 | pending review | |
Woodfin (Buncombe County) city · Woodfin Town Council |
Council asked staff to draft a temporary moratorium on data centers as the Land Development Ordinance (LDO) is updated Timing: Pending LDO update |
2026-01-01 | pending review | |
Hot Springs (Madison County) city · Hot Springs Town Council |
Town imposed a data center moratorium as small towns weigh costs of development Timing: Not specified |
2026-07-23 | pending review | |
Stokes County county · Stokes County Planning Board |
Planning Board backed a pause on data center development Timing: Not specified |
2026-07-10 | pending review | |
Cherokee County county · Cherokee County Commission |
County approved a data center moratorium Timing: Not specified |
2026-07-22 | pending review | |
Chamblee city · Chamblee City Council |
City Council approved a pause on data center applications Timing: Not specified |
2026-07-22 | pending review | |
DeKalb County county · DeKalb County Commission |
Commission extended its data center moratorium by six months amid public health concerns; extended again through June 23, 2026 and later through September Commission also voted against an amendment that would have created permanent data center regulations, opting to continue the pause instead. Timing: Multiple extensions (through Sept. 2026) |
2025-12-16 | pending review | |
Rockdale County county · Rockdale County Commission |
County re-extended its data center moratorium multiple times, most recently through September 8, 2026 Timing: Through Sept. 8, 2026 (re-extended) |
2026-01-01 | pending review | |
Garden City city · Garden City Council |
City put the brakes on data centers with a new local restriction Timing: Not specified |
2026-06-16 | pending review | |
Athens-Clarke County county · Athens-Clarke County Commission |
County extended its temporary moratorium on new data centers through June 5, 2026 Timing: Through June 5, 2026 (extended) |
2026-01-01 | pending review | |
Camden County county · Camden County Commission |
County adopted a 9-month data center moratorium Kingsland city manager recommended a parallel measure. Timing: 9 months |
2026-05-05 | pending review | |
Monterey Park city · Monterey Park City Council |
City Council overwhelmingly voted to permanently ban new data centers, the first California city to do so Timing: Permanent |
2026-06-03 | pending review | |
Patterson city · Patterson City Council |
City adopted a 45-day moratorium chilling talks of data center construction Timing: 45 days |
2026-01-01 | pending review | |
Mendocino County county · Mendocino County Board of Supervisors |
Supervisors moved toward a data center moratorium Timing: Under consideration |
2026-07-01 | pending review | |
City of Imperial city · City of Imperial Council / local leaders |
Local leaders challenged a million-square-foot hyperscale data center project in Imperial, California amid moratorium conflict; underlying dispute proceeded to federal litigation (IVCM v. City of Imperial, see lawsuits.json) Timing: N/A (litigation) |
2026-01-01 | litigation active | |
Coachella city · Coachella City Council |
City Council unanimously approved a 45-day moratorium on new data center applications and voted to terminate the utility agreement behind the proposed Coachella Valley Technology Campus; moratorium later extended into 2027 while the city drafts a permanent ban Timing: Extended into 2027 |
2026-01-01 | pending review | |
Tulare County county · Tulare County Board of Supervisors |
County stalled data center developments with a moratorium that could be extended Timing: Could be extended |
2026-01-01 | pending review | |
Linn County county · Linn County Board of Supervisors |
Board of Supervisors voted 2-1 to impose an 18-month moratorium on new applications to rezone land into the county's large-scale data center district, months after adopting a data center zoning ordinance (1,000-ft residential setbacks, mandatory water study/agreement, noise and… Timing: 18 months |
2026-01-01 | pending review | |
Birmingham city · Birmingham City Council |
City Council enacted zoning rules for hyperscale data centers (500-ft setback from residential districts, closed-loop cooling capping water use, certified-mail notice to nearby owners), called Alabama's strictest data center ordinance Leeds, Homewood, Cullman, and Fort Payne also adopted new pauses. Timing: Permanent (enacted) |
2026-01-01 | pending review | |
Leeds city · Leeds City Council |
City adopted a new pause on data center development, part of a wave of four Alabama cities acting in 2026 See also Homewood, Cullman, Fort Payne. Timing: Not specified |
2026-01-01 | pending review | |
New Jersey (statewide) state · New Jersey Legislature / Governor |
Data Center Fair Share Act signed into law, requiring 50MW+ facilities to commit to paying at least 85% of projected power costs for a decade Timing: 10-year commitment period (permanent law) |
2026-07-07 | pending review | |
Monroe Township city · Monroe Township Council |
Township took regulatory action affecting data center development, subject of Hexa Builders litigation (see lawsuits.json) Timing: N/A (litigation) |
2025-01-01 | litigation active | |
East Windsor Township city · East Windsor Township Committee (Ordinance No. 2026-06) |
Township adopted Ordinance No. 2026-06 establishing a data center moratorium Timing: Not specified |
2026-01-01 | pending review | |
Neptune Township city · Neptune Township Committee |
Township banned data centers (and ICE detention facilities) via local ordinance Timing: Permanent (enacted) |
2026-07-13 | pending review | |
Andover city · Andover Township Committee |
Sussex County town officially banned data centers after public pushback Timing: Permanent (enacted) |
2026-05-29 | pending review | |
Oklahoma City city · Oklahoma City Council |
City Council approved a moratorium on new data centers, effective immediately and expiring Dec. 31, 2026, covering all new applications Timing: Through Dec. 31, 2026 |
2026-04-21 | pending review | |
Jackson County / Springfield county · Jackson County Legislature / Springfield City Council |
Jackson County and Springfield, Missouri both adopted new pauses on data center development Timing: Not specified |
2026-01-01 | pending review | |
Manitowoc County county · Manitowoc County Board |
County Board voted unanimously to impose an 18-month data center moratorium Timing: 18 months |
2026-04-29 | pending review | |
Dodge County county · Dodge County Board |
County adopted a new pause on data center development Timing: Not specified |
2026-01-01 | pending review | |
Champaign County county · Champaign County Board |
County Board approved a 1-year data center moratorium Timing: 1 year |
2026-04-24 | pending review | |
Valparaiso city · Valparaiso City Council |
Council voted 6-1 for a data center moratorium Timing: Not specified |
2026-07-15 | pending review | |
Fort Worth city · Fort Worth City Council |
City Council unanimously voted to take first steps toward a data center moratorium Timing: Under development |
2026-08-12 | pending review | |
Hill County county · Hill County Commissioners Court |
Hill County adopted a one-year moratorium on data center development, then rescinded it roughly three weeks later (June 5, 2026) amid a $100 million developer lawsuit, replacing it with a checklist of requirements for applicants Developer filed a $100M suit challenging the moratorium. Timing: Rescinded |
2026-06-05 | litigation active | |
Nottingham city · Nottingham Town Meeting |
Town approved a 12-month moratorium on data center development via town meeting vote Timing: 12 months |
2026-07-03 | pending review | |
Gray city · Gray Town Council |
Gray joined a growing list of Maine towns adopting data center moratoriums, following Scarborough, Brunswick, and Warren after the statewide LD 307 override failed Timing: Not specified |
2026-08-06 | pending review | |
Reading city · Reading City Council |
City adopted a 180-day pause on data centers Timing: 180 days |
2026-07-01 | pending review | |
York County county · York County Planning Commission |
Planning Commission recommended data center moratorium/regulation Timing: Not specified |
2026-01-01 | pending review | |
Pulaski County county · Pulaski County Quorum Court |
Data center moratorium measure remained unresolved after an earlier vote-count failure Timing: Unresolved |
2026-01-01 | pending review | |
Reno city · Reno City Council |
City extended its existing data center moratorium into 2027 Timing: Through 2027 |
2026-01-01 | pending review | |
Memphis city · Memphis City Council |
Memphis data center moratorium proposal begins City Hall process Separately, DOJ moved to intervene and dismiss the NAACP's Clean Air Act suit over gas turbines powering xAI's Memphis Colossus 2 site on national-security grounds (see lawsuits.json). Timing: Under process |
2026-08-01 | pending review | |
Waterloo city · Waterloo City Council |
City considering a three-month data center moratorium Timing: 3 months (proposed) |
2026-01-01 | pending review | |
Denmark (national) national · Danish national grid operator / government |
Denmark paused new data center grid connections amid mounting power grid strain, with total connection requests reaching roughly 60GW Denmark built one of Europe's cleanest grids; AI data center demand is straining that capacity. Timing: Not specified |
2026-05-04 | pending review | |
Ireland (national) national · Commission for Regulation of Utilities (CRU) / EirGrid |
Ireland ended its multi-year moratorium on new power connections to data centers, publishing a final policy on data centre grid connections via CRU; EirGrid had previously pulled the plug on roughly 30 Irish data center projects during the pause Data centers reportedly account for roughly 21% of Ireland's electricity consumption. Timing: Ended (moratorium lifted) |
2025-12-12 | pending review | |
Amsterdam city · Amsterdam Municipality |
Amsterdam halted new data center construction citywide via a municipal moratorium, later easing restrictions gradually with Haarlemmermeer before formally resuming construction after roughly a year's pause Dutch Data Center Association criticized the rules as 'symbol politics.' Timing: ~1 year (lifted with restrictions) |
2025-04-18 | pending review | |
Germany (national) national · German Bundestag / Energy Efficiency Act |
Germany's Energy Efficiency Act mandates heat-reuse requirements as a data center siting gate and imposes broader energy efficiency restrictions on new data centers, described as the first regulated data center market in Europe Timing: Permanent (enacted law) |
2026-01-01 | pending review | |
Singapore (national) national · Infocomm Media Development Authority (IMDA) / Economic Development Board |
Singapore lifted its longstanding data center moratorium via a pilot phase accepting new applications, subject to strict environmental sustainability standards and conditions Precedent frequently cited as the model for 'lifting with conditions' after a construction pause. Timing: Moratorium lifted; new conditional framework in place |
2022-01-01 | pending review |
Local restrictions
County, city, township, and borough measures: moratoriums, zoning denials, permit pauses, and ordinances affecting data centers. Newest first.
| Jurisdiction | State | Action | Date | Status | Sources |
|---|---|---|---|---|---|
Santa Clara city · Planning Commission |
CA | Uphold denial of GI Partners data center on appeal Santa Clara Planning Commission denied a 72MW data center permit at 2805 Bowers Ave (3-2 in favor; failed the required 4-vote majority, so the permit was denied). Chair noted the city has… |
2024-03-06 | in force | |
Adair County county · Board of Supervisors/County Commission |
IA | Impose 1200-foot data center setbacks in Adair County Applied Digital proposed a 200MW, $1.5B data center with two 300,000 sq ft buildings adjacent to a NextEra substation connected to wind farms in Guthrie and Audubon counties. Supervisors… |
2024-04-24 | in force | |
Town of Chesterton city · City Council |
IN | Community pressure forces Provident Realty Advisors to withdraw in Town of Chesterton Provident Realty Advisors proposed a $1.3B data center on the 200-acre former Brassie Golf Course site along Pearson Road. The plan called for eight buildings at 150,000 sq ft each with… |
2024-06-01 | expired | |
DeKalb County county · Board of Supervisors/County Commission |
TN | Impose 5000-foot data center setbacks in DeKalb County DeKalb County, Tennessee, Commission, considered data center regulations proposed by County Mayor Matt Adcock after receiving an inquiry about a nuclear-powered data center. The proposed… |
2024-06-01 | expired | |
Clinton County county · Board of Supervisors/County Commission |
IA | Pause wind energy projects in Clinton County pending regulations Clinton County enacted a moratorium on wind project applications on June 10, 2024, extended multiple times through September 2025, prompted by NextEra Energy and Sky Pilot Wind/Ranger… |
2025-12-08 | in force | |
City of Atlanta city · City Council |
GA | Ban data centers near MARTA stops and Beltline in Atlanta Atlanta City Council enacted data center zoning restrictions in phases. In September 2024, data centers were prohibited within 2,640 feet of high-capacity transit stops and banned within… |
2024-09-01 | in force | |
Fairfax County county · Board of Supervisors/County Commission |
VA | Impose 200-foot data center setbacks in Fairfax County Fairfax County Board of Supervisors adopted a Data Centers Zoning Ordinance Amendment on September 10, 2024, requiring a special exception for almost all data centers. The amendment… |
2024-09-10 | in force | |
Morton County county · Board of Supervisors/County Commission |
ND | Impose indefinite data centers moratorium in Morton County Morton County adopted a moratorium on data centers and cryptocurrency mining facilities in September 2024. The moratorium prevents permitting of these facilities until the county… |
2024-09-01 | in force | |
Jackson County county · Board of Supervisors/County Commission |
IA | Pause data centers in Jackson County pending regulations Jackson County enacted a data mining facility moratorium in September 2024 (Resolution #1066), which was lifted in November 2024 after supervisors and county staff studied the issue. The… |
2024-09-17 | expired | |
City of Thorndale city · City Council |
TX | Pass resolution opposing Data Factory Austin bitcoin mine Data Factory Austin proceeded with bitcoin mining near Thorndale despite city opposition. The city passed a resolution voicing concerns about the 15 MW facility, and residents launched a… |
2024-10-01 | expired | |
City of Peculiar city · Planning Commission |
MO | Restrict Diode Ventures 500-acre data center in City of Peculiar Peculiar originally added a 'data center' definition to its light industrial zoning, enabling Diode Ventures' proposed $1.5B Harper Road Technology Park, a 500-acre campus with multiple… |
2024-10-01 | expired | |
Jones County county · Board of Supervisors/County Commission |
IA | Pause data centers and crypto mining in Jones County pending regulations Jones County enacted a moratorium on data center development circa October 2024. The moratorium was replaced by a permanent Cryptocurrency and Data Center Ordinance restricting such… |
2025-05-13 | expired | |
Osceola County county · Board of Supervisors/County Commission |
FL | Block US Development rezoning of 434 acres of farmland US Development filed to rezone 434 acres from agricultural to industrial near Yeehaw Junction for a nine-building, 7+ million sq ft data center campus, with each three-story building… |
2024-10-01 | in force | |
Gilmer County county · Planning Commission |
GA | Ban commercial crypto mining in Gilmer County Gilmer County residents successfully blocked a proposed cryptocurrency server farm on Eller Road in Ellijay. Cyndie Roberson, cofounder of Gilmer County Citizens Against Crypto Mining,… |
2024-11-01 | in force | |
Pima County county · Board of Supervisors/County Commission |
AZ | Require conditional use permits in Pima County The Pima County Board of Supervisors approved Project Blue's CUP zoning amendment and the sale of 290 acres for nearly $21M to Beale Infrastructure on Christmas Eve 2025, despite… |
2025-12-16 | in force | |
Oliver County county · Board of Supervisors/County Commission |
ND | Halt data centers and crypto mining in Oliver County after Applied Digital proposal Over 200 people packed the Betty Hagel Memorial Civic Center in Center, ND as Oliver County leaders debated a proposed moratorium on data centers and cryptocurrency mining. The Oliver… |
2024-12-12 | expired | |
Fort Worth city · City Council |
TX | Restrict Black Mountain Power 530-acre data center in Fort Worth Black Mountain Power LLC has obtained rezoning approval for over 450 acres in southeast Fort Worth for a $10B data center. The City Council approved zoning changes in multiple phases: 141… |
2025-01-01 | pending | |
Milam County county · Board of Supervisors/County Commission |
TX | Ban data centers in designated zones in Milam County Milam County (TX) has become a flashpoint for data center buildout as SB Energy (SoftBank) and partners advance the Stargate / Milam County campus near Sharp (Rockdale / Thorndale area), a… |
2026-01-09 | in force | |
Reno city · City Council |
NV | Deny Webb Data Center's 82,000 sq ft facility in Reno on appeal Sierra Club Toiyabe Chapter appealed the Planning Commission's approval of Webb Data Center's 82,000 sq ft facility, arguing the city established zoning guidelines without public input and… |
2025-01-22 | in force | |
Hitchcock County county · Board of Supervisors/County Commission |
NE | Impose 1-year data centers and crypto mining moratorium in Hitchcock County Hitchcock County passed a one-year moratorium on data center and cryptocurrency mining development via resolution in February 2025, responding to crypto companies seeking cheap power and… |
2025-02-01 | expired | |
Reno city · City Council |
NV | Propose data centers moratorium in Reno (rejected) Reno Planning Commission voted 4-2 in February 2025 to recommend a temporary moratorium on new data center permits, citing concerns about energy use, water consumption, and the city's lack… |
2025-02-05 | in force | |
Ada County county · Board of Supervisors/County Commission |
ID | Adopt data center zoning standards in Ada County Ada County proactively developed data center zoning standards following Meta's data center in nearby Kuna and Diode Ventures' 620-acre Gemstone Technology Park (approved 3-2 by Kuna City… |
2025-11-01 | in force | |
Clayton County county · Board of Supervisors/County Commission |
IA | Pause data centers and crypto mining in Clayton County pending regulations Clayton County Board of Supervisors approved a temporary moratorium on rezoning requests and conditional use permits for digital asset mining/data centers in February 2025. The moratorium… |
2025-02-25 | in force | |
Kootenai County county · Board of Supervisors/County Commission |
ID | Convert Kootenai County moratorium into permanent ban Kootenai County lifted its 182-day moratorium on data center building permits after adopting permanent regulations that ban data centers from being located over the Spokane Valley-Rathdrum… |
2025-03-02 | expired | |
Nassau County county · Board of Supervisors/County Commission |
NY | Propose battery energy storage systems moratorium in Nassau County Nassau County towns imposed moratoriums on battery energy storage systems (BESS). Jupiter Power (owned by BlackRock) cancelled its contract for the proposed 275 MW Oyster Shore Energy… |
2025-04-01 | in force | |
Town of Burns Harbor city · Planning Commission |
IN | Block Provident Realty Advisors rezoning of 102 acres in Town of Burns Harbor Provident Realty Advisors, after being rejected in Chesterton, proposed a seven-building, 102-acre data center campus at the corner of S. Babcock and Haglund Roads on the Worthington Steel… |
2025-05-05 | expired | |
Reno city · City Council |
NV | Oppose StoneGate data center in Reno StoneGate proposed converting 1,767 acres in Reno's Cold Springs area approved for ~5,000 homes into industrial/data center use, reducing housing to ~1,350 units. The Planning Commission… |
2025-05-21 | in force | |
Henrico County county · Board of Supervisors/County Commission |
VA | Create data center overlay zone in Henrico County The Henrico County Board of Supervisors adopted the Data Center Comprehensive Plan Amendment on June 10, 2025, incorporated into the Vision 2026 Comprehensive Plan. As of January 2025, all… |
2025-06-01 | in force | |
Little Rock city · City Council |
AR | Block AVAIO Digital Partners rezoning of 760 acres in Little Rock AVAIO Digital's 'Project Leo', a $6B, 760-acre hyperscale data center campus near Little Rock, has broken ground with a fully approved Site Plan. The first phase (150 MW) is expected to be… |
2025-06-01 | in force | |
Cherokee County county · Board of Supervisors/County Commission |
SC | Restrict Cielo Digital Infrastructure 86-acre data center in Cherokee County Cielo Digital Infrastructure's $2.1B data center was approved by Cherokee County Council. The development at Ford Road in Gaffney will include four 400,000 sq ft facilities with an… |
2025-06-01 | in force | |
Clark Township township · Township Board |
MI | Impose 1-year data centers moratorium in Clark Township Clark Township enacted a 1-year moratorium on data center development in June 2025, making it one of the earliest communities in Michigan to take preemptive action, months before the… |
2025-06-01 | in force | |
Commercial Point / Scioto Township township · Township Board |
OH | Deny K-NOVA 450MW data center permit in Commercial Point / (moratorium on data center development). K-NOVA LLC's proposal for the Rickenbacker Exchange development in Commercial Point stalled when a related ordinance 'died due to a lack of motion' in the Village Council. K-NOVA's… |
2026-03-01 | in force | |
City of La Grange city · City Council |
KY | Impose 150-day data centers moratorium in City of La Grange (Western Hospitality Partners) La Grange passed a 150-day moratorium on data centers and private utilities on June 2, 2025, later extended by another 150 days. Response to "Project Lincoln," a proposed $6 billion… |
2025-06-02 | expired | |
Millard County county · Board of Supervisors/County Commission |
UT | Block Creekstone Energy rezoning of 1100 acres of farmland Millard County Commission unanimously approved Creekstone Energy's rezoning of ~1,200 acres from agricultural to heavy industrial on June 3, 2025, despite public opposition at the hearing.… |
2025-06-03 | in force | |
City of Johnson City city · City Council |
TN | Impose 1-year data centers and crypto mining moratorium in City of Johnson City (BrightRidge) BrightRidge electric utility announced in May 2025 a moratorium on data center project proposals in its service area, including a south Johnson City Bitcoin mining/data center site,… |
2026-05-22 | in force | |
Clarke County county · Board of Supervisors/County Commission |
IA | Impose indefinite data centers and solar moratorium in Clarke County Clarke County Board of Supervisors approved a temporary moratorium on data center construction in unincorporated areas in June 2025, prompted by Applied Digital's interest in a 200 MW,… |
2025-06-23 | in force | |
Town of Warrenton city · City Council |
VA | Ban data centers in designated zones in Town of Warrenton Warrenton Town Council voted unanimously (5-0) on July 8, 2025 to amend the zoning ordinance, striking all references to data centers from Articles 3, 9 and 12, effectively banning new… |
2025-07-08 | in force | |
Perry Township township · Village Board |
OH | Require use permit for Province Group data center in Perry Township Province Group formally withdrew its zoning application for a data center campus in Perry Township/Perry Village as of July 2025. The developer had signed an agreement to purchase 163… |
2025-07-01 | expired | |
Oldham County county · Board of Supervisors/County Commission |
KY | Impose 150-day data centers moratorium in Oldham County (Western Hospitality Partners) Western Hospitality Partners proposed 'Project Lincoln: OC Data Center,' a $6B, 600MW facility initially planned for 267 acres at 3557 North Highway 53. Due to fierce opposition from 'We… |
2025-07-02 | expired | |
Gilroy city · City Council |
CA | Ban data centers in designated zones in Gilroy Amazon Web Services received approval on July 3, 2025 for a 218,000 sq ft, 49 MW data center requiring 25 emergency generators on a 56-acre site in Gilroy, California. Two Change.org… |
2026-06-15 | in force | |
Mesa city · City Council |
AZ | Require use permit for CyrusOne data center in Mesa Mesa City Council adopted new zoning rules on July 8, 2025, restricting data centers to General Industrial and Heavy Industrial zones (roughly 4.1% of city land) and requiring special use… |
2025-07-08 | in force | |
St. Charles city · City Council |
MO | Convert St. Charles moratorium into permanent citywide ban After CRG withdrew its data center proposal from St. Charles, the Festus City Council unanimously annexed 240 acres for data center development. At least two residents filed lawsuits; Wake… |
2026-05-19 | in force | |
Augusta Charter Township township · Township Board |
MI | Force public referendum on Thor Equities data center in Augusta Charter Thor Equities proposed a $1 billion data center on 810 acres (building on about 20%) near Milan. Despite the Planning Commission recommending denial, the Board of Trustees unanimously… |
2025-08-01 | in force | |
Wake County county · City Council |
NC | Impose 12-month data centers and crypto mining moratorium in Wake County (Natelli Investments) Natelli Investments LLC withdrew its annexation and rezoning applications for the New Hill Digital Campus on March 5, 2026, a 190-acre, 250-300 MW data center on Shearon Harris Road near… |
2025-08-01 | expired | |
Bessemer city · City Council |
AL | Oppose Logistics Land Investment data center in Bessemer Bessemer City Council voted 5-2 on November 18, 2025 to approve the Project Marvel data center on ~700 acres. The decision followed extensive community opposition. [Update 2026-07-14]: The… |
2026-07-13 | in force | |
Yerington county · Board of Supervisors/County Commission |
NV | Oppose Copia Power Devco data center in Yerington Copia Power Devco LLC (backed by Carlyle) received 4-1 approval from Lyon County commissioners for a Master Plan Amendment to build the Monarch Data Center - 4.6 million sq ft across 14… |
2025-12-04 | in force | |
Lebanon county · Board of Supervisors/County Commission |
IN | Rally against Meta data center in Lebanon Meta officially broke ground on its $10B+, 1500-acre data center campus at the LEAP Innovation and Research District in Lebanon, Indiana on February 11, 2026. The campus will feature 13… |
2025-08-01 | in force | |
North Tonawanda city · City Council |
NY | Impose two-year moratorium on crypto mining and data centers in North Tonawanda North Tonawanda Common Council unanimously approved a two-year moratorium on all new crypto mining and data center developments in July 2024, expiring July 2026. The ban covers new… |
2026-06-16 | in force | |
Clayton County county · Board of Supervisors/County Commission |
GA | Halt data centers in Clayton County after TA Realty proposal Clayton County Board of Commissioners approved a moratorium on new data center applications through December 31, 2025, citing resident concerns about rapid data center growth. On December… |
2025-09-01 | in force | |
Troup County county · Board of Supervisors/County Commission |
GA | Impose 90-day data centers moratorium in Troup County (Fertile Ground Investments) Troup County enacted a 90-day moratorium on data center applications on September 16, 2025, after Fertile Ground Investments proposed a 600 MW data center on 437 acres near Hogansville.… |
2025-09-01 | in force | |
City of LaGrange city · City Council |
GA | Impose 180-day data centers moratorium in City of LaGrange (Thor Equities / Form8tion) LaGrange City Council passed a 180-day moratorium on new data center applications in September 2025 amid community backlash. The moratorium expired in March 2026. On March 27, 2026, the… |
2025-09-23 | expired | |
Pike County county · Board of Supervisors/County Commission |
GA | Halt data centers in Pike County after Amazon/AWS proposal Pike County enacted a 6-month data center moratorium in September 2025 as part of a wave of Georgia county ordinances (alongside Lamar, Troup, and Clayton counties), prompted by Amazon/AWS… |
2025-09-01 | in force | |
Lamar County county · Board of Supervisors/County Commission |
GA | Halt data centers in Lamar County after Amazon/AWS proposal Lamar County enacted a 6-month moratorium on data center development in September 2025 after AWS purchased 985 acres for $270 million, the largest real estate transaction in county… |
2025-09-01 | in force | |
Hampden Township township · Township Board |
PA | Deny Undisclosed data center permit in Hampden Township Hampden Township Commissioners unanimously rejected a proposed zoning ordinance amendment that would have designated office-park zones for data centers. Some 300 residents signed a… |
2025-09-01 | expired | |
St. Louis city · City Council |
MO | Propose data centers moratorium after Contour proposal On April 21, 2026, the St. Louis Board of Public Service unanimously approved the permit for a 120 MW data center adjacent to the historic Armory in Midtown St. Louis, weeks after Mayor… |
2026-04-21 | in force | |
Griffin county · City Council |
GA | Impose 180-day data centers moratorium in Griffin Griffin City Council unanimously passed a 180-day moratorium on data centers and other technological facilities, prompted in part by interest from Hillwood and other developers. The… |
2026-01-13 | in force | |
Jerome Township township · Township Board |
OH | Impose 9-month data centers moratorium in Jerome Township (Amazon/AWS) Jerome Township trustees unanimously approved a 9-month moratorium after residents complained of persistent noise from existing Amazon/AWS data centers. Up to four new projects were… |
2025-09-03 | expired | |
Louisville city · City Council |
KY | Propose data centers moratorium after Poe Companies proposal One 525MW data center project in southwest Louisville has been cleared to proceed, built by Poe Companies and PowerHouse Data Centers (starting at 100MW, expanding to 400MW). District 17… |
2025-09-11 | expired | |
Blakely city · City Council |
PA | Block Kriger / Alpesh 'Al' Patel data center through opposition in Blakely Developers proposed a data center campus offering up to 1.5GW of capacity on 209 acres in Blakely Borough, requiring power equivalent to the entire output of the nearby Lackawanna Energy… |
2025-09-12 | expired | |
College Station city · City Council |
TX | Deny Priority Power 600MW data center permit in College Station College Station residents mounted strong opposition to Priority Power's proposed 600MW datacenter on 200 acres of Midtown Drive. More than 75 individuals registered to speak in person and… |
2025-09-12 | expired | |
Town of Tarboro city · City Council |
NC | Reject 300MW Energy Storage Solutions data center permit in Tarboro by 7-1 vote The Tarboro Town Council rejected a Special Use Permit for Energy Storage Solutions' proposed 300MW, eight-phase data center on a 52-acre site near Anaconda and McNair roads by a 7-1 vote.… |
2025-09-15 | expired | |
Social Circle city · City Council |
GA | Impose 90-day data centers moratorium in Social Circle (Multiple) Social Circle approved a 90-day moratorium on new data center applications after being overwhelmed with seven applications. Despite the moratorium, the council approved a controversial… |
2025-09-18 | in force | |
Menomonie city · City Council |
WI | Oppose Balloonist data center in Menomonie Menomonie signed an NDA with Balloonist LLC in February 2024, over a year before announcing the $1.6B data center proposal in July 2025. Over the following six months, residents… |
2025-09-24 | expired | |
White County county · Board of Supervisors/County Commission |
IN | Halt data centers in White County after Undisclosed proposal White County's Board of Commissioners passed a moratorium on data center development on October 20, 2025, after residents packed public meetings in opposition. The moratorium was prompted… |
2025-10-01 | in force | |
Village of Yorkville city · Village Board |
WI | Reject Microsoft-linked backup data center proposal in Village of Yorkville A developer proposed a backup data center at Kuiper Farm (2400 55th Drive) in the Village of Yorkville, about five miles from Microsoft's AI data center under construction in Mount… |
2025-12-08 | expired | |
Jones County county · Board of Supervisors/County Commission |
GA | Impose 90-day data centers moratorium in Jones County (EagleRock Partners) EagleRock Partners withdrew its rezoning application for the 600+ acre Crooked Creek Technology Park after organized opposition under the 'No Data Centers in Jones County' campaign.… |
2025-10-22 | in force | |
Columbia city · City Council |
MO | Block Undisclosed rezoning of 63 acres of farmland A landowner sought to rezone 63 acres of farmland near U.S. 63 for a potential data center. The Planning & Zoning Commission voted 5-2 to recommend the change, but the City Council… |
2025-11-19 | expired | |
Preble County county · Planning Commission |
OH | Deny Patrick Scanlon (developer) rezoning of 300 acres of farmland Preble County Planning Commission unanimously (11-0) denied rezoning of 300 acres of farmland for a data center. The developer withdrew his application in October after residents organized… |
2025-10-01 | expired | |
Mason County county · Planning Commission |
KY | Oppose 2,000-acre data center ordinance adoption in Mason County via We Are Mason County coalition Mason County, Kentucky, planning commission approved a zoning ordinance paving the way for a 2,080-acre data center campus north of AA Highway, west of Maysville, by an undisclosed Fortune… |
2026-03-27 | in force | |
Platte County county · Board of Supervisors/County Commission |
MO | Study data center impacts on water resources in MO Project Kestrel, a $100B multi-phase data center campus by Shenandoah Computing LLC (linked to Google), proposes six hyperscale data centers totaling 1.8 million sq ft on 379 acres at the… |
2025-10-01 | in force | |
Lordstown city · City Council |
OH | Impose 180-day data centers moratorium in Lordstown (Bristolville 25 Developer) Lordstown, OH data center opposition. OpenAI is involved in a SEPARATE nearby Stargate project, not this one. Hyperscaler and MW figures previously attached were incorrect conflations. |
2025-10-01 | in force | |
Conshohocken / Plymouth Township township · Township Board |
PA | Petition to block Brian O'Neill (developer) data center in Conshohocken / A developer attempted to convert the Cleveland Cliffs steel plant on 66 acres of Plymouth Township's riverfront corridor into a data center for undisclosed Big Tech tenants. Over 1,000… |
2025-10-01 | expired | |
Lackawanna County county · Board of Supervisors/County Commission |
PA | Propose data centers moratorium after 1778 Rich Pike proposal Lackawanna County Commissioner Bill Gaughan asked Governor Shapiro and the PA General Assembly for a three-year statewide moratorium on new large-scale data center approvals. The county… |
2025-10-01 | in force | |
East Vincent Township township · Planning Commission |
PA | Deny Penn Hurst Holdings DE data center on 125 acres in East Vincent East Vincent's planning commission recommended rejection of a proposed 1.9 million sq ft data center at the former Pennhurst State School and Hospital for the second time. Commission cited… |
2025-10-01 | expired | |
Gordon County county · Board of Supervisors/County Commission |
GA | Pause data centers in Gordon County pending regulations Gordon County enacted a preemptive data center moratorium, despite no active data center proposals. County officials studied ordinances in Jackson, Spalding, and Wayne counties to develop… |
2026-02-04 | in force | |
Albemarle County county · Board of Supervisors/County Commission |
VA | Create data center overlay zone in Albemarle County Albemarle County proposed a zoning overlay for data centers that would designate five areas as appropriate. The Piedmont Environmental Council raised concerns. The county paused the… |
2025-10-01 | pending | |
Muscogee county · Tribal Government |
OK | Deny Undisclosed data center on 5500 acres in Muscogee Jordan Harmon and Mackenzie Roberts (both Muscogee Nation citizens) organized town halls after plans emerged to build a massive AI data center on 5,500 acres of Muscogee Nation land (the… |
2025-10-01 | expired | |
Dundee Township township · Township Board |
MI | Impose 90-day data centers moratorium in Dundee Township (Cloverleaf Infrastructure) Dundee Township enacted a 90-day moratorium on data center development in October 2025 in response to Cloverleaf Infrastructure's proposal. The moratorium was extended six months in… |
2025-10-02 | in force | |
City of Bristol city · City Council |
TN | Impose 2-year data centers moratorium in City of Bristol The City of Bristol unanimously approved a 2-year moratorium on data processing centers in September-October 2025, passing on both readings. The moratorium will remain in effect through… |
2025-10-07 | in force | |
Village of Caledonia city · Village Board |
WI | Petition to block Microsoft data center in Village of Caledonia Microsoft cancelled its 244-acre, 900 MW Caledonia data center (Project Nova) after a 2,000-signature petition and strong community opposition forced a rethinking of the plan. Microsoft… |
2025-10-09 | expired | |
Meade County county · Board of Supervisors/County Commission |
KY | Deny Thomas A. Hobbs Living Trust rezoning of 138 acres of farmland Thomas A. Hobbs Living Trust requested rezoning of a 138-acre site along Joe Prather Highway (25025 Joe Prather Hwy, Ekron) from Agricultural/Residential to Light Industrial for data… |
2025-10-14 | expired | |
Manchester Township township · Township Board |
MI | Impose 2-year data centers moratorium in Manchester Township Manchester Township enacted a 2-year data center moratorium beginning October 14, 2025, one of the longest moratorium durations among Michigan communities. By Feb 2026, at least 27… |
2025-10-14 | in force | |
Logan County county · Board of Supervisors/County Commission |
CO | Impose 180-day battery energy storage systems moratorium in Logan County Logan County Commissioners unanimously approved a 180-day moratorium on solar, wind, data center, and battery energy storage development in October 2025 after Granite Renewables (New… |
2025-10-21 | in force | |
Douglas County county · Board of Supervisors/County Commission |
GA | Impose 90-day data centers moratorium in Douglas County (DC BLOX) Douglas County imposed a 90-day data center moratorium in a 4-1 vote in March 2025, later extended in August 2025 to study ratepayer impacts. DC BLOX closed $1.15B in green loan financing… |
2025-10-22 | in force | |
Stafford County county · Board of Supervisors/County Commission |
VA | Impose 750-foot data center setbacks in Stafford County Stafford County adopted Virginia's strictest data center regulations in a 4-2-1 vote on October 22, 2025, including a 750-foot setback from residences (up from 100 ft), 200-foot vegetative… |
2025-10-22 | in force | |
Putnam County county · Board of Supervisors/County Commission |
IN | Halt data centers and solar in Putnam County after Undisclosed proposal Putnam County passed a one-year moratorium on wind, solar, data centers, and small modular nuclear reactor projects in November 2025. As of March 2026, commissioners are reviewing… |
2025-11-01 | in force | |
Campbell County county · Board of Supervisors/County Commission |
VA | Deny Mesh Capital data center on 57 acres in Campbell County Mesh Capital LLC sought to remove a protective proffer from a 57-acre property on Cabin Field Road. Supervisors voted 5-2 to deny the request in October 2025. However, since data centers… |
2025-11-01 | in force | |
Lufkin city · City Council |
TX | Deny Amp Z 175MW data center permit in Lufkin Denver-based Amp Z proposed Project Lufkin, a multi-gigawatt data center on 1,000+ acres at the former Southland Paper Mill site near the Neches River in Angelina County, TX. Total… |
2025-11-01 | in force | |
Rockford city · City Council |
IL | Petition to block Monarch Energy data center in Rockford Monarch Energy's proposed $12B, 800 MW data center on 1,100+ acres near Chicago-Rockford International Airport is advancing. Monarch Rock Air LLC was formed April 2025. On February 17,… |
2025-11-01 | in force | |
York County county · Board of Supervisors/County Commission |
SC | Petition to block QTS Data Centers data center in York County QTS is building a nine-building $1 billion campus near Lake Wylie, threatening the 95-acre Penland Christmas Tree Farm next door. Residents are concerned about noise, blinding security… |
2026-07-13 | in force | |
South Strabane Township township · Planning Commission |
PA | Ban data centers in designated zones in South Strabane South Strabane Township began drafting data center regulations after CNX Resources' 1,400-acre tract (with 400 buildable acres) was marketed by JLL for data center development. 'No Data… |
2025-11-01 | in force | |
Cumberland County county · Board of Supervisors/County Commission |
NC | Petition to block Energy Storage Solutions data center in Cumberland County Energy Storage Solutions (ESS) is planning a 'NetZero' data center off Dunn Road in Fayetteville (Cumberland County, NC), built in 8 phases with $6.4B investment as part of ESS's $19.2B… |
2025-11-01 | in force | |
Lyon County county · Planning Commission |
NV | Block Tract rezoning of 1060 acres in Lyon County Tract acquired 1,060 acres near Silver Springs in Lyon County to develop a datacenter park with up to 1.6GW capacity. The Lyon County Planning Commission unanimously approved the rezoning… |
2025-11-01 | in force | |
Jonesborough borough · City Council |
TN | Impose 2-year crypto mining moratorium in Jonesborough | 2025-11-03 | in force | |
Norton city · City Council |
OH | Propose data centers moratorium after Quantum HPC proposal Norton City Council introduced a 180-day moratorium on data center zoning certificates after rejecting Quantum HPC's proposed 485,000 sq ft data center ('Project Triton') at the former PPG… |
2025-11-03 | in force | |
Wiscasset city · City Council |
ME | Oppose Undisclosed (under NDA) data center in Wiscasset Wiscasset Selectboard voted in November 2025 to pause conversations about a $5B data center on town-owned land along the Back River after resident Richard Davis launched 'Protect… |
2025-11-04 | in force | |
Johnson County county · Board of Supervisors/County Commission |
IA | Impose one-year moratorium on data center rezoning and permits in unincorporated Johnson County Johnson County Board of Supervisors unanimously approved a one-year moratorium on data center rezoning and permits in unincorporated areas on Nov. 8, 2025. The moratorium runs through… |
2025-11-08 | in force | |
Tama County county · Board of Supervisors/County Commission |
IA | Pause data centers in Tama County pending regulations Tama County Board of Supervisors approved moratoriums on both data mining/centers and battery storage on November 10, 2025. Applies to all proposed facilities regardless of size,… |
2025-11-10 | in force | |
Barberton city · City Council |
OH | Impose indefinite data centers moratorium after Quantum HPC proposal Barberton City Council approved an indefinite moratorium on data centers in November 2025. In neighboring Norton, Quantum HPC's Project Triton proposal for the old PPG mine on Limestone… |
2025-11-10 | in force | |
Mitchell County county · Board of Supervisors/County Commission |
IA | Pause data centers and solar in Mitchell County pending regulations Mitchell County approved moratoriums on utility-scale solar (Resolution #1326-25, Nov 12, 2025, unanimous) and data centers until Dec 31, 2026 (Resolution #1336-25, Nov 25, 2025, 4-1… |
2025-11-25 | in force | |
Pittsfield Township township · Township Board |
MI | Impose 180-day data centers moratorium in Pittsfield Township Pittsfield Township enacted a 180-day data center moratorium in November 2025, one of at least 27 Michigan communities to do so. Township representative Morgan Foreman is co-sponsoring the… |
2025-11-18 | in force | |
Sullivan County county · Board of Supervisors/County Commission |
TN | Impose 4-month crypto mining moratorium in Sullivan County Sullivan County Commissioner Jessica Means introduced a 4-month moratorium resolution on data mining and crypto mining centers on November 20, 2025. The commission deferred the vote at… |
2025-11-20 | pending | |
Howell Township township · Township Board |
MI | Halt data centers in Howell Township after Meta proposal Township enacted a unanimous six-month moratorium on Nov. 20, 2025 after ~2 hours of public comment. Trustee Bob Wilson confirmed Meta was behind the project, estimating a $9B investment… |
2025-11-20 | expired | |
Marshall County county · Board of Supervisors/County Commission |
IN | Halt data centers in Marshall County after Undisclosed proposal On April 20, 2026, Marshall County Commissioners voted to enact a permanent ban on data centers across the county, replacing the prior one-year moratorium. The action is reported as the… |
2026-04-20 | in force | |
Wilmington city · City Council |
OH | Require use permit for Amazon/AWS data center in Wilmington Amazon/AWS proposed a $4B datacenter on 471 acres in Wilmington with a 30-year, 100% property tax abatement (effective 70% abatement). On April 23, 2026, Wilmington residents Jessica Sharp… |
2025-11-26 | in force | |
Monroe County county · Board of Supervisors/County Commission |
GA | Impose moratorium on data centers in Monroe County after rejecting $5.8B Bolingbroke campus Monroe County passed a data center moratorium on unincorporated land after commissioners unanimously rejected the 900-acre, $5.8 billion Bolingbroke Technology Campus. Nearly 900 residents… |
2025-12-01 | in force | |
Athens-Clarke County county · Board of Supervisors/County Commission |
GA | Propose data centers moratorium after FAE Clark (end-user unknown) proposal Athens-Clarke County Commission originally imposed an emergency moratorium on data centers in December 2025, extended it to June 5, 2026, and used the time to develop permanent… |
2026-04-09 | in force | |
Town of Carlton township · Township Board |
WI | Force Cloverleaf Infrastructure to scrap data center plans in Carlton after public opposition Cloverleaf Infrastructure scrapped plans in Carlton (Kewaunee County) after local residents objected to the idea. Town Chairman David Hardtke told Cloverleaf 'if this is such a good thing… |
2025-12-01 | expired | |
Big Rapids Township township · Township Board |
MI | Ban data centers in Big Rapids Township's airport industrial park Big Rapids Township passed an ordinance banning data centers in its 120-acre airport industrial park, part of a wave of at least 27 Michigan communities enacting moratoria or zoning… |
2025-12-01 | in force | |
Edgecombe County county · Board of Supervisors/County Commission |
NC | Oppose Energy Storage Solutions data center over water in Edgecombe County Energy Storage Solutions (ESS) plans a $19.2B, 900 MW, 300-acre data center and energy storage campus at the Kingsboro Business Park, Tarboro, NC, part of ESS's ~$38B North Carolina… |
2026-07-14 | expired | |
Sioux Falls city · City Council |
SD | Force public referendum on Gemini Capital data center in Sioux Falls Gemini Capital proposed a $1.9B, 500 MW hyperscale data center on 164 acres in eastern Sioux Falls. The City Council voted 7-0 on Jan. 6, 2026 to rezone the farmland for light industrial… |
2025-12-01 | in force | |
Lawrence County county · Board of Supervisors/County Commission |
OH | Halt data centers in Lawrence County after Strata Expanse proposal Houston-based Strata Expanse hosted a ribbon cutting for an AI data center in the Haverhill area at 1476 County Road 1A. A petition gathered 5,570 signatures voicing concerns about the… |
2025-12-01 | in force | |
Moorestown city · City Council |
NJ | Deny New Urban data center on 25 acres in Moorestown Moorestown Township Council opted out of data center development on a 25-acre vacant site (former Pulverizer Services / New Albany Business Park Redevelopment Area) along New Albany Road.… |
2025-10-31 | expired | |
Monroe Township township · City Council |
NJ | Remove data centers from Hexa Builders Redevelopment Plan permitted uses in Monroe Township Monroe Township (Gloucester County) introduced Ordinance O:20-2026 on April 8, 2026 to ban data centers from the Hexa Redevelopment Plan on Black Horse Pike. Final adoption vote scheduled… |
2026-04-08 | pending | |
Breckinridge County county · Board of Supervisors/County Commission |
KY | Pause data centers and solar in Breckinridge County pending regulations Breckinridge County Fiscal Court passed an AI Data Center Moratorium ordinance in November 2025. Meanwhile, TeraWulf is advancing a $3-4B large-scale data center campus in nearby… |
2025-11-17 | in force | |
Tyrone Township township · Township Board |
MI | Impose 6-month data centers moratorium in Tyrone Township Tyrone Township (Livingston County) enacted a 6-month moratorium on data center development on December 2, 2025. The township is located near Howell Township, where a major $1 billion Meta… |
2025-12-02 | in force | |
Starke County county · Planning Commission |
IN | Halt data centers in Starke County after ABEI Energy proposal Starke County Planning Commission unanimously advanced a one-year moratorium on hyperscale data centers exceeding 5,000 sq ft in December 2025, making it the fourth Indiana county to act.… |
2025-12-04 | in force | |
Green Charter Township township · Township Board |
MI | Halt data centers in Green Charter after Undisclosed proposal Green Charter Township adopted a one-year moratorium on data center development on Dec. 9, 2025, citing concerns about water consumption, energy usage, and noise. The township was among… |
2025-12-09 | in force | |
St. Joseph County county · Board of Supervisors/County Commission |
IN | Deny Amazon/AWS rezoning of 1200 acres of farmland On December 10, 2025 the St. Joseph County Council voted 7-2 to deny a $12B data center from an undisclosed developer. Amazon has separate already-approved projects in the region (an… |
2025-12-10 | expired | |
City of Chandler city · City Council |
AZ | Deny Active Infrastructure 150MW data center permit in City of Chandler City Council voted 7-0 on December 12, 2025 to reject Active Infrastructure's $2.5B, 150 MW AI data center proposal on 40 acres near Queen Creek and Dobson roads. The city received over… |
2025-12-12 | expired | |
Coweta County county · Board of Supervisors/County Commission |
GA | Oppose 900MW Prologis data center on 832 acres in Coweta County Coweta County's moratorium on data center applications expired December 17, 2025, and the Board adopted a data center ordinance on December 16. On April 10-11, 2026, Coweta County… |
2026-06-16 | in force | |
DeKalb County county · Board of Supervisors/County Commission |
GA | Impose 100-day data centers moratorium in DeKalb County (PCC-DeKalb) DeKalb County, Georgia Commission extended its data center moratorium until June 23, 2026 at the December 16, 2025 meeting due to community concerns about public health and environmental… |
2026-06-09 | in force | |
Lewiston city · City Council |
ME | Deny MillCompute 24MW data center permit in Lewiston Lewiston City Council voted 7-0 on December 16, 2025 to reject a $300M AI data center proposed by MillCompute LLC and building owner Bill Johnson's Twin Cities LLC for the historic Bates… |
2025-12-16 | expired | |
Gates County county · Board of Supervisors/County Commission |
NC | Halt data centers and crypto mining in Gates County after Undisclosed proposal Gates County passed a 12-month moratorium on data centers and cryptocurrency mining facilities after receiving two inquiries from PACE, a firm that prepares ordinances and land use… |
2025-12-17 | in force | |
Waterville Township township · Township Board |
OH | Impose 12-month data centers moratorium in Waterville Township (Undisclosed) Waterville Township trustees unanimously approved a 12-month moratorium on Dec. 17, 2025, citing concerns about electrical grid strain, water supply, and quality of life. The city of… |
2025-12-17 | in force | |
Lowell Township township · Township Board |
MI | Ban data centers in designated zones in Lowell Township Franklin Lowell LLC applied to rezone 235 acres at Covenant Business Park near Grand Rapids for a data center. A public hearing was abandoned when the venue couldn't hold the opposition… |
2025-12-18 | in force | |
South Bloomfield city · Village Board |
OH | Impose 180-day data centers moratorium in South Bloomfield South Bloomfield Village Council adopted a 180-day moratorium on data center construction and a new zoning code that does not list data centers as a permitted use, effectively preemptively… |
2025-12-19 | in force | |
Vineland city · City Council |
NJ | Cap data center water consumption in NJ ~100 people gathered to protest a 350 MW hyperscale AI data center under construction in Vineland, which will have roughly Empire State Building-sized footprint and nearly double the… |
2025-12-23 | in force | |
Oshtemo Township township · Township Board |
MI | Halt battery energy storage systems in Oshtemo Township after Undisclosed proposal Oshtemo Charter Township (Kalamazoo County) is formally considering a data center moratorium as of early 2026, joining Portage and at least 27 other Michigan communities with active… |
2026-01-01 | in force | |
Luther city · City Council |
OK | Propose data centers moratorium after Beltline Energy proposal Beltline Energy is eyeing a 400-acre parcel near an OG&E power plant for a data center, with discussions ongoing since mid-2025. As of early 2026, no formal application has been filed,… |
2026-06-17 | in force | |
Conewago Township township · Township Board |
PA | Block Elysian Partners rezoning of farmland in Conewago Township Residents of Conewago Township in York County, Pennsylvania object to plans by Elysian Partners to rezone agricultural and residential land for AI data centers. The petition argues the use… |
2026-01-01 | in force | |
City of Taylor city · City Council |
MI | Impose 1-year data centers moratorium in City of Taylor Taylor enacted a 1-year data center moratorium in January 2026. Separately, Sens. Rosemary Bayer (D-West Bloomfield), Erika Geiss (D-Taylor), and Sue Shink (D-Northfield Twp.) introduced… |
2026-01-01 | in force | |
Dorr Township township · Township Board |
MI | Halt data centers in Dorr Township after Microsoft proposal Dorr Township (Allegan County) enacted a moratorium on data center development while the planning commission develops an ordinance to regulate the facilities, expected to take about six… |
2026-01-01 | in force | |
Caledonia Township township · Township Board |
MI | Impose 6-month data centers moratorium in Caledonia Township Caledonia Township (Kent County) implemented a 6-month moratorium on data center and data mining operations effective January 1, 2026, running through June. The moratorium follows… |
2026-01-01 | in force | |
Shippingport city · City Council |
PA | Contest Aligned Data Centers approval at former nuclear plant site Aligned Data Centers (acquired by BlackRock/GIP for $40B) received conditional use approval from Shippingport Borough Council in January 2026 for 'Project Phoenix,' a $10B data center… |
2026-01-28 | in force | |
Wood County county · Board of Supervisors/County Commission |
OH | Halt data centers in Wood County after Meta proposal Meta revealed plans for an $800M, 715,000 sq ft data center on 280 acres in Middleton Township. 7 of Wood County's 19 townships have adopted temporary moratoriums, with 8 more discussing… |
2026-01-06 | in force | |
Northville city · City Council |
MI | Impose 12-month data centers moratorium in Northville The Northville City Council unanimously approved a 12-month preemptive moratorium on data centers on January 6, 2026, halting any data center applications. Unlike other communities,… |
2026-01-06 | in force | |
Henry County county · Board of Supervisors/County Commission |
GA | Ban data centers in designated zones in Henry County Henry County began drafting strict data center regulations following interest from developers including Hampton Technology Park. Proposed rules include 200-foot buffers, 1,000-foot… |
2026-01-06 | in force | |
Springfield Township township · Township Board |
MI | Impose 180-day data centers moratorium in Springfield Township Springfield Township (Oakland County) Board of Trustees approved a 180-day moratorium on data center plans on January 7, 2026, three days after planners with consulting firm Giffels… |
2026-01-07 | in force | |
Ironton city · City Council |
OH | Halt data centers in Ironton after Strata Expanse proposal Strata Expanse (Houston), RAVEL, and Supermicro held a ribbon-cutting in December 2025 for an AI Center of Excellence and data center at 1476 County Road 1A in Lawrence County's Haverhill… |
2026-01-09 | in force | |
Saline Township township · City Council |
MI | Halt data centers in City of Saline after Related Digital proposal The Michigan Public Service Commission voted 3-0 in December 2025 to conditionally approve DTE Energy's 19-year, 1.4 GW power supply agreement for the Stargate data center campus in Saline… |
2026-01-12 | in force | |
Stokes County county · Board of Supervisors/County Commission |
NC | Ban data centers in designated zones in Stokes County Stokes County Board of Commissioners approved (3-2 vote) in January 2026 the rezoning of approximately 1,845 acres of residential-agricultural land along the Dan River for heavy industrial… |
2026-01-12 | expired | |
Roswell city · City Council |
GA | Impose 90-day data centers moratorium in Roswell Roswell City Council approved a 90-day emergency moratorium on new data centers (through April 12) as one of its first acts under a new mayor and three new council members. The Community… |
2026-01-12 | in force | |
Village of Greenleaf city · Village Board |
WI | Legal challenge to Cloverleaf Infrastructure data center in Village of Greenleaf Houston-based Cloverleaf Infrastructure offered $120,000 per acre for approximately 600 acres to build the first AI data center in northeast Wisconsin, directly across from Ledgestone… |
2026-01-13 | expired | |
City of Madison city · City Council |
WI | Halt data centers in City of Madison after QTS Data Centers proposal City of Madison, WI adopted a data center moratorium on January 13, 2026. This was a policy-driven, preventative action, not tied specifically to the QTS/DeForest proposal. QTS figures… |
2026-01-13 | in force | |
Birmingham city · City Council |
AL | Impose 180-day data centers moratorium in Birmingham (Nebius) Birmingham City Council unanimously approved a 270-day moratorium on applications for new or expanding hyperscale data centers on March 3, 2026. Facilities under 20 megawatts are exempt.… |
2026-03-03 | in force | |
Harvey County county · Board of Supervisors/County Commission |
KS | Pause data centers and crypto mining in Harvey County pending regulations Harvey County Commission unanimously approved a moratorium on data center construction in unincorporated areas through the end of 2028 (roughly three years). Commissioner Don Schroeder… |
2026-01-13 | in force | |
City of Saginaw city · City Council |
MI | Impose 6-month data centers moratorium in City of Saginaw Saginaw City Council unanimously approved a resolution enacting a 6-month blanket prohibition on data centers on January 13, 2026. Councilwoman Carly Rose Hammond proposed the motion,… |
2026-01-13 | in force | |
Armada Township township · Township Board |
MI | Impose 180-day data centers moratorium in Armada Township Armada Township enacted a 180-day moratorium on data center development starting January 14, 2026. The moratorium gives the township time to review zoning, infrastructure capacity, and… |
2026-01-14 | in force | |
Sedgwick County county · Board of Supervisors/County Commission |
KS | Impose 3-year data centers moratorium in Sedgwick County (Monarch Energy) Sedgwick County Commissioners unanimously voted on March 4, 2026 to extend the moratorium on data center permit applications to June 11, 2026. Two companies, Monarch Energy (San Diego) and… |
2026-01-15 | in force | |
Villa Ridge county · Board of Supervisors/County Commission |
MO | Ban data centers in designated zones in Villa Ridge Change.org petition with 6,140+ signatures voicing concerns about a proposed data center on Robertsville Road in Villa Ridge, near Shaw Nature Reserve. The land (613 acres total) is owned… |
2026-01-15 | pending | |
Yukon city · Planning Commission |
OK | Block Gamma Resources rezoning of 295 acres in Yukon Yukon (OK) faces opposition to a Gamma Resources data center proposal near I-40. As of early 2026, the project is currently STALLED, zoning hearings have been deferred TWICE due to local… |
2026-01-15 | in force | |
Kansas City city · City Council |
MO | Restrict Multiple 700MW data center in Kansas City Kansas City, Missouri, Council unanimously approved zoning changes reclassifying data centers as industrial facilities, limiting them to specific zoning districts, revoking by-right status… |
2026-01-16 | in force | |
Coweta city · City Council |
OK | Deny Beale Infrastructure rezoning of 295 acres in Coweta In Coweta, Oklahoma, Beale Infrastructure's $800M Project Atlas proposed 295 acres for an Amazon/AWS data center with 400MW capacity. The Planning Commission voted 4-1 to deny rezoning on… |
2026-01-19 | expired | |
Village of Godfrey city · Village Board |
IL | Impose 180-day data centers moratorium in Village of Godfrey Village of Godfrey, Illinois, unanimously approved a 180-day moratorium on data center construction applications on January 20, 2026, after Cloverleaf Infrastructure proposed a 500MW data… |
2026-01-20 | in force | |
Monterey Park city · City Council |
CA | Impose 45-day data centers moratorium in Monterey Park (HMC Capital (StratCap)) Monterey Park, California, City Council unanimously adopted a 45-day moratorium on data center development on January 21, 2026, prompted by a proposed 250,000 sq ft data center at Saturn… |
2026-01-21 | in force | |
Naperville city · City Council |
IL | Deny Karis Critical 36MW data center permit in Naperville Naperville, Illinois, City Council voted 6-1 to deny Karis Critical's proposal for a 145,000 sq ft data center on the former Nokia/Lucent campus (36 MW, $250M, 40 acres). A Change.org… |
2026-01-21 | expired | |
City of Pontiac city · City Council |
MI | Halt data centers in City of Pontiac after Concord Infrastructure proposal In City of Pontiac, Michigan, Pontiac City Council unanimously passed a six-month moratorium on the consideration of data centers 'pending further study and enactment of city regulation,'… |
2026-01-21 | in force | |
Grand Blanc Township township · Township Board |
MI | Impose 1-year data centers moratorium in Grand Blanc Township Grand Blanc Township Board of Trustees passed a one-year moratorium on data center development on January 21, 2026, rejecting all applications until the period expires unless shortened or… |
2026-01-21 | in force | |
Sylvan Township township · Township Board |
MI | Impose 6-month data centers moratorium in Sylvan Township Sylvan Township (near Chelsea, Washtenaw County) enacted a 6-month moratorium on data centers on January 22, 2026. Supervisor Amanda Nimke stated: 'We clearly can't stop them, but we can… |
2026-01-22 | in force | |
El Paso city · City Council |
TX | Terminate city contracts with Meta and halt $10B data center expansion in El Paso Meta expanded its El Paso data center investment from $1.5B to $10B (1GW capacity, 1,000 acres). Construction began November 2025 with completion targeted February 2029. El Paso Electric… |
2026-06-18 | expired | |
Village of Romeo city · Village Board |
MI | Pause data centers in Village of Romeo pending regulations The Village of Romeo enacted a data center moratorium on January 26, 2026, joining the wave of Macomb County communities (including nearby Armada Township, Lenox Township, and Sterling… |
2026-01-26 | in force | |
Pekin city · City Council |
IL | Ban data centers from using Mahomet Aquifer groundwater via SB 4004 In Illinois, Hundreds of residents packed a city council meeting to challenge a data center proposed on the Lutticken Farm along the Mahomet Aquifer, Which serves nearly 1 million people… |
2026-03-09 | expired | |
Larimer County county · Board of Supervisors/County Commission |
CO | Impose 30-day data centers moratorium in Larimer County Larimer County extended its temporary moratorium on data center facilities to August 25, 2026, following a public hearing on February 9, 2026. The pause allows staff time to develop… |
2026-01-27 | in force | |
New Orleans city · City Council |
LA | Halt data centers and crypto mining in New Orleans after MS Solar Grid Data proposal The New Orleans City Council voted unanimously 6-0 on January 28, 2026 to impose a one-year moratorium on construction of data centers, server farms, and cryptocurrency mining facilities,… |
2026-01-28 | in force | |
Fayetteville city · Planning Commission |
GA | Block Corvus Investment Group rezoning of 240 acres in Fayetteville Fayetteville's Planning & Zoning Commission denied Corvus Investment Group's request to rezone 240+ acres along Highway 85 North and Highway 314 to Business Park, a classification that… |
2026-01-27 | in force | |
Carroll County county · Board of Supervisors/County Commission |
GA | Block Atlas Development rezoning of 350 acres in Carroll County Atlas Development filed a Development of Regional Impact for 'Project Bus,' a 12-building data center campus on approximately 350 acres in Temple (northern Carroll County, Georgia,). The… |
2026-01-28 | expired | |
Barrington Hills city · City Council |
IL | Force Brennan Investment Group to withdraw $2B data center proposal in Barrington Hills Brennan Investment Group withdrew its $2 billion data center proposal for land south of Penny Road and west of Pond Gate Drive in Barrington Hills, Illinois, a suburb northwest of Chicago… |
2026-01-29 | expired | |
Sangamon County county · Board of Supervisors/County Commission |
IL | Propose data centers moratorium in Sangamon County (rejected) Sangamon County Board voted 17-10 on April 7, 2026 to approve CyrusOne's $500M data center on 280 acres of farmland near Waverly, ~14 miles southwest of Springfield, despite hundreds of… |
2026-02-01 | in force | |
Carroll County county · Board of Supervisors/County Commission |
MD | Pause data centers in Carroll County pending regulations Carroll County Board of Commissioners voted to draft a deferral ordinance placing a temporary moratorium on data center projects, despite no developers having applied. The preemptive… |
2026-02-01 | in force | |
Champaign County county · Board of Supervisors/County Commission |
OH | Petition to block Thor Equities data center in Champaign County Thor Equities proposed a $1 billion, 500MW data center (Urbana Technology Hub) on 48+ acres in Champaign County, Ohio, near Urbana. On March 3, 2026, the Urbana City Council voted 6-1 to… |
2026-03-03 | in force | |
Vienna Township township · Township Board |
OH | Pause data centers in Vienna Township pending regulations Vienna Township in northeast Ohio is using a pause on data centers to develop lasting zoning changes rather than a temporary moratorium. Trustee Phil Pegg requested zoning to place a limit… |
2026-02-01 | in force | |
Pecos County county · Board of Supervisors/County Commission |
TX | Rally against Pacifico Energy data center in Pecos County Pacifico Energy's GW Ranch project in Pecos County, Texas, ~17 miles north of Fort Stockton, received TCEQ approval in early 2026 as the 'largest permitted data center campus' in the U.S.… |
2026-02-01 | in force | |
Solon Township township · Township Board |
MI | Impose 6-month data centers moratorium in Solon Township Solon Township, Michigan, (Kent County) Board unanimously approved a 6-month moratorium on new data center proposals in early February 2026, extended from an initial 90-day proposal after… |
2026-02-01 | in force | |
Dickerson county · Board of Supervisors/County Commission |
MD | Halt data centers in Dickerson after Atmosphere Data Centers proposal California-based Atmosphere Data Centers plans a $2 billion, 300MW data center complex on 170 acres at the site of a decommissioned coal-fired power plant in Dickerson, Maryland,.… |
2026-02-01 | in force | |
Citrus County county · Planning Commission |
FL | Block Deltona Corp rezoning of 813 acres in Citrus County In Citrus County, Florida, Deltona Corp proposed an 813-acre AI data center near CR 491 and Tram Road in Lecanto. The Planning & Development Commission voted 4-3 to postpone any decision.… |
2026-05-26 | in force | |
Saugatuck Township township · Township Board |
MI | Pause data centers in Saugatuck Township pending regulations Saugatuck Township in Allegan County placed a moratorium on data center development in February 2026, part of a wave of at least 27 Michigan communities enacting temporary pauses. The… |
2026-02-01 | in force | |
Montgomery County county · Board of Supervisors/County Commission |
MD | Require use permit for Atmosphere Data Centers data center in Montgomery County Montgomery County, Maryland, enacted a moratorium on new data center development through the end of 2026, prompted by Atmosphere Data Centers' proposed 300MW complex on 170 acres in… |
2026-02-02 | in force | |
Baltimore County county · Board of Supervisors/County Commission |
MD | Halt data centers in Baltimore County after Security Land and Development proposal Baltimore County, Maryland, Council unanimously passed a moratorium temporarily freezing data center development through January 1, 2027, blocking permits until the Planning Board studies… |
2026-02-02 | in force | |
Maumee city · City Council |
OH | Impose 12-month data centers moratorium in Maumee (Meta) Maumee City Council approved a 12-month moratorium on Feb. 2, 2026, joining the wave of northwest Ohio communities responding to Meta's $800M data center in nearby Middleton Township.… |
2026-02-02 | in force | |
Ashville county · Village Board |
OH | Deny EdgeConneX 1800MW data center permit in Ashville The Ashville, Ohio, Village Council voted 4-2 to deny EdgeConneX's annexation request for a 490-acre parcel needed for a $10 billion, 680-acre, 1.8GW data center campus about 17 miles… |
2026-02-02 | in force | |
Lenox Township township · Township Board |
MI | Impose 4-month data centers moratorium in Lenox Township Lenox Township Board of Trustees adopted a 4-month moratorium on new data center development effective February 2, 2026, with the option for one additional 4-month extension. The… |
2026-02-02 | in force | |
Hancock County county · Board of Supervisors/County Commission |
KY | Shield residential ratepayers from data center costs in KY In Hancock County, Kentucky, Change.org petition with 1,052 signatures voicing concerns about TeraWulf's data center at the former Century Aluminum smelter site in Hawesville. TeraWulf… |
2026-02-02 | in force | |
City of Mason city · City Council |
MI | Force public referendum on data center in City of Mason In City of Mason, Michigan, residents submitted a referendum petition with 700+ signatures against Ordinance 266 (M-3 Technology Innovation zoning district). On March 16, 2026, Mason City… |
2026-02-03 | in force | |
Village of DeForest city · Village Board |
WI | Deny QTS Data Centers 1600MW data center permit in Village of DeForest In the Village of DeForest, Wisconsin, QTS Data Centers proposed a $12B project involving five data center buildings on nearly 1,600 acres of farmland in the Town of Vienna. The 'No Data… |
2026-02-03 | expired | |
Sterling Heights city · City Council |
MI | Propose data centers moratorium in Sterling Heights The Sterling Heights City Council unanimously voted to impose a one-year moratorium on any new data centers proposed in the city. Officials noted that the city's zoning restrictions,… |
2026-02-03 | in force | |
Lodi Township township · Township Board |
MI | Impose 180-day data centers moratorium in Lodi Township Lodi Township (Washtenaw County) enacted a 180-day moratorium on data center development on February 3, 2026, joining a sweeping wave of at least 27 Michigan communities now pausing data… |
2026-02-03 | in force | |
Covington Township township · Township Board |
PA | Halt 1778 Rich Pike / Quantm Group's 35-building, 1.5GW data center on 1,000 acres in Covington Township 1778 Rich Pike LLC / Quantm Group plans 'Project Gouldsboro,' a $14.25 billion, 35-building, 1.5GW data center campus across Clifton and Covington townships on nearly 1,000 acres. Clifton… |
2026-02-03 | in force | |
New Castle County county · Board of Supervisors/County Commission |
DE | Uphold denial of Starwood Digital Ventures data center on appeal In New Castle County, Delaware, Starwood Digital Ventures proposed 'Project Washington,' a $10 billion, 1.2GW datacenter on 580 acres near Delaware City. The facility would consume as much… |
2026-02-04 | in force | |
Mt. Orab city · City Council |
OH | Impose 180-day data centers moratorium in Mt. Orab (DB STU) In Mt. Orab, Ohio, Village Councilman Eric Lang introduced two ordinances for a 180-day data center moratorium amid community outcry over a mysterious 1,000-acre 'mega site' project… |
2026-02-04 | in force | |
Muhlenberg Township township · Township Board |
OH | Impose 12-month data centers moratorium in Muhlenberg Township (Pacifico Energy) Muhlenberg Township, Ohio, (Pickaway County, near Circleville) passed a 12-month moratorium on new data centers after a petition gathered 700+ signatures (proposed by Pacifico Energy) (120… |
2026-02-06 | in force | |
Montour County county · Board of Supervisors/County Commission |
PA | Deny Talen Energy / Amazon rezoning of 800 acres of farmland Montour County, Pennsylvania, commissioners unanimously denied Talen Energy's request to rezone 800+ acres from agricultural to industrial to allow a co-located data center near the… |
2026-02-10 | expired | |
Hood County county · Board of Supervisors/County Commission |
TX | Propose data centers and crypto mining moratorium in Hood County (rejected) Hood County (40 miles SW of Fort Worth) has received at least five data center applications (proposed by Sailfish Development). Commissioners voted down a proposed moratorium 3-2, twice,… |
2026-02-10 | expired | |
City of Oregon city · City Council |
OH | Deny Capacity 500MW data center permit in City of Oregon In City of Oregon, Ohio, Oregon City Council initially voted 3-2 with one abstention against granting Capacity LLC a six-month extension for a proposed $2 billion, 500MW data center on 170… |
2026-02-10 | in force | |
Hayes Township township · Township Board |
MI | Impose 180-day data centers moratorium in Hayes Township Hayes Township, Michigan, (Charlevoix County) Board of Trustees unanimously enacted a 180-day moratorium on data centers on February 10, 2026, despite no current data center proposals.… |
2026-02-10 | in force | |
City of South Lyon city · City Council |
MI | Impose 12-month data centers moratorium in City of South Lyon In City of South Lyon, Michigan, South Lyon City Council adopted a 12-month moratorium on new data center applications on February 10, 2026, extending it beyond the original proposal of… |
2026-02-10 | in force | |
Erie Township township · Township Board |
MI | Pause data centers in Erie Township pending regulations Erie Township (Monroe County) enacted a limited moratorium on data center development on February 10, 2026, joining nearby Dundee Township which has had a moratorium since October 2025 in… |
2026-02-10 | in force | |
Bernalillo County county · Board of Supervisors/County Commission |
NM | Adopt data center zoning standards in Bernalillo County Bernalillo County guardrails resolution (proposed by Commissioner Eric Olivas) passed 4-1 (Benson dissent) on February 11, 2026. Project Jupiter (Oracle / $50B / ~1,400 acres) is a… |
2026-02-11 | in force | |
Town of Canton city · City Council |
NC | Impose 12-month data centers and crypto mining moratorium in Town of Canton (Unknown) In Town of Canton, North Carolina, Canton Board of Aldermen approved a 12-month moratorium on data center construction, cryptocurrency mining, and server farms after about 50 residents… |
2026-02-11 | in force | |
Blanchester city · City Council |
OH | Impose moratorium in Blanchester after surrounding AWS and data center proposals Blanchester Village Council unanimously approved a moratorium on Feb. 12, 2026, after AWS proposed a $3B data center in nearby Wilmington (which was tabled) and other projects emerged in… |
2026-02-12 | in force | |
Walla Walla County county · Board of Supervisors/County Commission |
WA | Oppose Port of Walla Walla's $36M land sale to AWS for $4.8B data center campus In Walla Walla County, Washington, Port of Walla Walla unanimously approved $36M sale of 553 acres at Wallula Gap Business Park to AWS for a $4.8B, 16-building, 3.4M sq ft data center… |
2026-02-12 | in force | |
York Township township · Township Board |
MI | Impose 6-month data centers moratorium in York Township (Sansone Group) York Township, Michigan, (Washtenaw County) enacted a 6-month moratorium on data center development on February 12, 2026, after representatives for developer Sansone Group discussed a… |
2026-02-12 | in force | |
Chatham County county · Board of Supervisors/County Commission |
NC | Impose 12-month data centers and crypto mining moratorium in Chatham County Chatham County, North Carolina, approved a 12-month moratorium on the development of new data centers and cryptocurrency mining facilities on February 13, 2026, after Natelli Investments… |
2026-02-13 | in force | |
Dickson City city · City Council |
PA | Restrict data centers to industrial zones in Dickson City Dickson City, Pennsylvania, Borough Council adopted regulations that define, regulate and restrict data centers as special exceptions in the town's light manufacturing district, limiting… |
2026-02-13 | in force | |
Hubbard Township township · Township Board |
OH | Impose 12-month data centers moratorium in Hubbard Township (Bristolville 25 Developer) Hubbard Township, Ohio, trustees voted 2-1 to approve a resolution placing a one-year moratorium on data centers entering the township in February 2026 (proposed by Bristolville 25… |
2026-02-15 | in force | |
Lowndes County county · Board of Supervisors/County Commission |
GA | Block DC BLOX rezoning of 720 acres in Lowndes County DC BLOX is the company behind the Lowndes County, Georgia, data center proposal (720 acres). DC BLOX's CEO informed the landowner (Pope Langdale) the facility could create up to 400 jobs… |
2026-02-17 | in force | |
Richfield Township township · Township Board |
OH | Impose 12-month data centers moratorium in Richfield Township Richfield Township (Lucas County) passed a 12-month data center moratorium on Feb. 17, 2026, part of a wave across northwest Ohio triggered by Meta's $800M data center in nearby Middleton… |
2026-02-17 | in force | |
Ann Arbor Township township · Township Board |
MI | Impose 12-month data centers moratorium in Ann Arbor Township Ann Arbor Township Board of Trustees passed a 12-month moratorium on data centers. No developer has approached township officials about a data center; the moratorium is a proactive measure… |
2026-02-17 | in force | |
Columbiana county · City Council |
AL | Impose 300-foot data center setbacks in Columbiana Columbiana City Council unanimously approved a new ordinance imposing zoning restrictions on future data centers, becoming the first Alabama municipality to pass such restrictions ($200M).… |
2026-02-17 | in force | |
Monclova Township township · Township Board |
OH | Impose 12-month data centers moratorium in Monclova Township Monclova Township trustees unanimously approved a 12-month moratorium on Feb. 18, 2026 after residents packed multiple meetings. Although no data center has been proposed in the township,… |
2026-02-18 | in force | |
Elmwood Township township · Township Board |
MI | Impose 9-month data centers moratorium in Elmwood Township Elmwood Township, Michigan, Board unanimously approved a 9-month moratorium on data centers (reduced from originally proposed 12 months). No known data center plans exist for the county;… |
2026-02-18 | in force | |
Middleton Township township · Township Board |
OH | Demand transparency on Meta's $800M data center under construction in Middleton Township A Meta data center spanning 715,000 sq ft under construction in Middleton Township, Ohio, was revealed in April 2025, anticipated operational in 2027 with 100 employees (350 MW, 280… |
2025-04-01 | in force | |
New Brunswick city · City Council |
NJ | Deny Amzak Capital Management data center on 22 acres in New Brunswick New Brunswick, New Jersey, City Council voted unanimously on Feb 19, 2026 to remove data centers as a permitted use from the Jersey-Sandford Redevelopment Plan, killing the Amzak… |
2026-02-19 | in force | |
Mercer County county · Board of Supervisors/County Commission |
KY | Enact one-year moratorium on data center applications in Mercer County The Mercer County Commission voted 3-2 on March 3, 2026 to enact a one-year moratorium on data center applications, halting all activity relating to data center projects in the county.… |
2026-02-19 | in force | |
Aurora city · City Council |
IL | Adopt strictest-in-Illinois data center noise and setback regulations in Aurora Aurora (IL) is debating what supporters describe as the strictest-in-Illinois data center noise and setback ordinance. The February 19, 2026 Planning & Development Committee meeting did… |
2026-02-19 | pending | |
Town of Dryden city · City Council |
NY | Ban commercial crypto mining in Town of Dryden Town of Dryden, NY adopted a preventative data center zoning restriction on February 19, 2026. The TeraWulf Cayuga project referenced in earlier coverage is in Lansing, not Dryden,… |
2026-02-19 | in force | |
Manitowoc County county · Board of Supervisors/County Commission |
WI | Pause data center permits for statewide study in WI Three northeast Wisconsin towns -- Two Creeks, Two Rivers, and Mishicot -- passed resolutions calling on Manitowoc County to place a one-year moratorium on new data center permits and… |
2026-02-20 | in force | |
North Coventry Township township · Township Board |
PA | Deny Envision Land Use data center on 18 acres in North Coventry In North Coventry Township, Pennsylvania, Township supervisors voted 3-2 to reject a 120,000 sq ft, three-story 'boutique' data center on 18 acres off Route 724 before the proposal was… |
2026-02-23 | in force | |
Denver city · City Council |
CO | Halt data centers in Denver after CoreSite proposal Denver City Council planning committee approved on March 31, 2026 a measure for a one-year moratorium on acceptance/processing of data center permit and site development applications.… |
2026-02-24 | in force | |
Lincoln County county · Board of Supervisors/County Commission |
SD | Propose data centers moratorium after Gemini Data Center SD proposal Lincoln County Commissioner Joel Arends proposed a one-year moratorium on hyperscale data centers requiring 100+ MW, calling it an opportunity to 'press pause and further research' the… |
2026-02-24 | expired | |
Sunbury city · Planning Commission |
OH | Block Amazon/AWS rezoning of 330 acres in Sunbury On April 15, 2026, Sunbury City Council unanimously passed a moratorium on data centers effective until January 31, 2027, pausing the proposed $2 billion AWS data center project at the… |
2026-04-15 | in force | |
Cobb County county · Board of Supervisors/County Commission |
GA | Impose 180-day data centers moratorium in Cobb County (Grindcap (MMM Acquisitions)) Cobb County, Georgia, Board of Commissioners voted unanimously to implement a 180-day moratorium on new data center permits and rezoning applications in unincorporated areas, prompted by… |
2026-02-24 | in force | |
Franklin County county · Board of Supervisors/County Commission |
IN | Halt data centers in Franklin County after ABEI Energy proposal Franklin County, Indiana, Commissioners voted unanimously to extend the data center moratorium through February 2027, preventing new applications while the county gathers information and… |
2026-02-24 | in force | |
West Rockhill Township township · Township Board |
PA | Restrict data centers to industrial zones in West Rockhill West Rockhill Township Board of Supervisors unanimously adopted a zoning ordinance regulating data centers on April 15, 2026, limiting them to the township's Planned Industrial district by… |
2026-04-15 | in force | |
East Rockhill Township township · Township Board |
PA | Restrict data centers to industrial zones in East Rockhill East Rockhill supervisors advanced a preemptive data center ordinance (no application yet received). Restricts data centers to industrial districts at Pennridge Airport, requires 50-acre… |
2026-02-24 | in force | |
City of Portage city · City Council |
MI | Pause battery energy storage systems in City of Portage pending regulations In City of Portage, Michigan, Portage enacted a temporary moratorium on data centers and battery energy storage facilities through end of year to allow the city to review zoning rules and… |
2026-02-25 | in force | |
Pacific city · City Council |
MO | Force Beltline Energy to table $16B, 16-building data center campus on 500 acres in Pacific Atlanta-based Beltline Energy pitched a $16B, 16-building datacenter campus on 500 acres requiring annexation into Pacific (1.3GW). Hundreds of residents packed Pacific High School in… |
2026-02-25 | pending | |
Phillipsburg city · City Council |
NJ | Ban data centers in all zones in Phillipsburg Phillipsburg, NJ Town Council unanimously adopted Ordinance 2026-08 on April 14, 2026 banning data centers in all zoning districts. The final vote followed a February 24 first reading.… |
2026-02-25 | in force | |
Dearborn County county · Board of Supervisors/County Commission |
IN | Pause data centers and solar in Dearborn County pending regulations Dearborn County, Indiana, Board of Commissioners approved a one-year moratorium on rezoning proposals for commercial solar, battery storage, and data centers effective February 26. The… |
2026-02-25 | in force | |
Fort Meade county · Board of Supervisors/County Commission |
FL | Block Stonebridge rezoning of 1330 acres in Fort Meade Community members rallied outside Fort Meade, Florida, City Hall to protest a proposed $2.6 billion, 1.2-gigawatt, 4.4-million-square-foot hyperscale data center on over 1,330 acres being… |
2026-02-25 | in force | |
City of Kings Mountain city · City Council |
NC | Halt data centers in City of Kings after T5 Data Centers proposal In City of Kings Mountain, North Carolina, Kings Mountain City Council voted 5-2 to approve a six-month moratorium on new data centers while the city studies impacts on water supplies,… |
2026-02-26 | in force | |
Spring Hill city · City Council |
KS | Block rezoning of 316 acres in Spring Hill Spring Hill, Kansas, City Council voted on October 23, 2025 to move forward with rezoning 316 acres from Rural Residential to M-1 Industrial for a potential data center, though no end user… |
2026-03-25 | in force | |
East Whiteland Township township · City Council |
PA | Declare data center zoning invalid and pause new applications for 180 days to draft updated regulations East Whiteland Township (Chester County) held an April 15, 2026 hearing on the developer's expanded 887,000 sq ft data center plan as the township advances its curative amendment process… |
2026-02-26 | in force | |
Brookings city · City Council |
SD | Deny Sequitor Edge data center permit in Brookings Brookings, South Dakota, City Council voted unanimously to reject a $644K sales-tax rebate for Sequitor Edge's proposed $41 million co-location data center. The denial came alongside… |
2026-02-26 | expired | |
Hall County county · Board of Supervisors/County Commission |
GA | Impose 180-day data centers moratorium in Hall County Hall County, Georgia, Commission voted 4-0 on February 26, 2026, to approve a 180-day moratorium on data centers, planned industrial development, and detention centers, prompted by… |
2026-02-26 | in force | |
Spartanburg County county · Board of Supervisors/County Commission |
SC | 4000-signature petition opposing NorthMark Strategies data center TigerDC formally withdrew its $3 billion 'Project Spero' AI data center from Tyger River Industrial Park after Spartanburg County Council unanimously voted down two Fee-In-Lieu-Of-Tax… |
2026-02-27 | expired | |
Weld County county · Board of Supervisors/County Commission |
CO | Restrict Global AI 438-acre data center in Weld County Weld County, Colorado, commissioners PASSED Code Ordinance 2026-01 on a 4-1 vote on April 6, 2026. The ordinance prohibits data centers on agricultural land and requires site plan or… |
2026-04-06 | in force | |
Leland city · City Council |
NC | Block rezoning of 1385 acres in Leland The Town of Leland initiated a preemptive text amendment to regulate data center facilities, requiring closed-loop cooling systems, a 60% renewable energy mandate, and restricting data… |
2026-02-27 | pending | |
Linn County county · Board of Supervisors/County Commission |
IA | Impose 1000-foot data center setbacks in Linn County Linn County Board of Supervisors unanimously approved one of the most comprehensive local data center zoning ordinances in the country on Feb. 18, 2026, in response to Google's proposed $7… |
2026-03-01 | in force | |
Charles County county · Planning Commission |
MD | Restrict TeraWulf 250-acre data center in Charles County The Charles County Planning Commission voted to recommend denial of Zoning Text Amendment #25-187, which would have established zoning regulations for data centers in the county (proposed… |
2026-03-02 | in force | |
Fulton County county · Board of Supervisors/County Commission |
IN | Halt data centers in Fulton County after Decennial Group proposal Fulton County, Indiana, Commissioners approved a one-year moratorium on data center construction on March 3, 2026, after a heated public hearing where residents voiced concerns about the… |
2026-03-03 | in force | |
Lyon Township township · Township Board |
MI | Impose 180-day data centers moratorium in Lyon Township (Verrus) Lyon Township, Michigan, (Oakland County) board voted unanimously to enact a 180-day moratorium on data centers and all proposed developments 100,000+ sq ft on March 3, 2026. The… |
2026-03-03 | in force | |
Anchorage city · City Council |
AK | Restrict data centers to industrial zones in Anchorage The Anchorage Assembly adopted Ordinance AO 2026-27 on March 27, 2026, establishing a new land use and permitting framework for data centers before receiving any large-scale applications.… |
2026-03-27 | in force | |
Blanchard city · City Council |
LA | Halt data centers in Blanchard after Amazon/AWS proposal Rural communities in North Caddo Parish organized a boycott of the official community meeting for Amazon/AWS's proposed $12 billion data center campus on 810 acres in Blanchard, Louisiana,… |
2026-03-03 | in force | |
Delta County county · Planning Commission |
MI | Impose 12 month data centers and crypto mining moratorium in Delta County Delta County, Michigan, Planning Commission considered a resolution to suspend data center and cryptocurrency mining projects for 12 months while a zoning ordinance is developed.… |
2026-03-03 | pending | |
Penn Forest Township township · Township Board |
PA | Ban data centers in designated zones in Penn Forest Township Penn Forest Township, Pennsylvania, supervisors approved a comprehensive data center ordinance at a well-attended meeting at Penn's Peak (proposed by Mele Brothers Realty). The ordinance… |
2026-03-03 | in force | |
Mercer County county · Board of Supervisors/County Commission |
ND | Halt data centers in Mercer County after NextEra Energy Resources proposal Mercer County Commission voted 3-2 for a one-year moratorium after NextEra subsidiary Boulevard Associates had been quietly acquiring land options on roughly 530 acres under NDA (proposed… |
2026-03-03 | in force | |
Calvert County county · Board of Supervisors/County Commission |
MD | Impose 24-month data centers moratorium in Calvert County (Amazon) Calvert County Board of Commissioners voted 2-3 against a proposed 24-month moratorium on data center permits. Commissioner Hart had proposed the moratorium after Amazon AWS began… |
2026-03-03 | expired | |
Urbana city · City Council |
OH | Impose 12-month data centers moratorium in Urbana (Thor Equities) Urbana City Council voted 6-1 to approve a 12-month moratorium on data centers over 10,000 sq ft, halting a proposed 460,000 sq ft Thor Equities facility off Routes 55 and 68 (400 MW, 133… |
2026-06-17 | in force | |
Palo city · City Council |
IA | Block Google from annexing into Palo to evade Linn County's strict data center ordinance Google abandoned unincorporated Linn County and is pursuing annexation into the City of Palo, Iowa (pop. 1,407) to avoid the county's strict data center zoning. Palo held a town hall on… |
2026-06-15 | in force | |
Champaign County county · Board of Supervisors/County Commission |
IL | Propose data centers moratorium in Champaign County On April 23, 2026, the Champaign County Board passed a 12-month moratorium on new large-scale data centers (≥10,000 sq ft of processing area) in unincorporated areas, reversing the… |
2026-04-23 | in force | |
Pittsylvania County county · Board of Supervisors/County Commission |
VA | Deny 2,200-acre, 84-building data center campus with 3,500MW gas plant in Pittsylvania County The Pittsylvania County Board of Supervisors voted to deny a massive 2,200-acre datacenter campus proposal that would have included 84 datacenter buildings and a 3,500MW natural gas power… |
2025-04-01 | expired | |
Louisa County county · Board of Supervisors/County Commission |
VA | Require use permit for Amazon data center in Louisa County Amazon Web Services withdrew a conditional use permit application for a 7.2 million-square-foot data center campus on 1,370 acres in Louisa County's Mineral area (south of Davis… |
2025-07-25 | expired | |
Spotsylvania County county · Board of Supervisors/County Commission |
VA | Require conditional use permits in Spotsylvania County Spotsylvania County has approved data centers and is trying to implement regulations (873 acres). In December 2025, the board voted 4-3 to approve design standards requiring special-use… |
2025-11-01 | in force | |
Fauquier County county · Board of Supervisors/County Commission |
VA | Deny Gigaland 600MW data center permit in Fauquier County GigaLand withdrew its original datacenter application in Fauquier County, Virginia, after significant community opposition, but resubmitted a scaled-down proposal in early 2026, reduced by… |
2026-07-16 | pending | |
Fauquier County county · Board of Supervisors/County Commission |
VA | Deny Headwaters Site Development data center on 67 acres in Fauquier County Headwaters Site Development LLC withdrew its rezoning application for a $400M, four-building data center on 67 acres at Catlett Road and Gaskins Lane in Fauquier County on July 15, three… |
2024-07-15 | expired | |
Frederick County county · Board of Supervisors/County Commission |
VA | Deny Winchester Gateway data center on 749 acres in Frederick County In June 2025, the Frederick County Board of Supervisors voted by consensus against moving forward with applications for two large data centers: the proposed 644-acre Meadow Brook… |
2025-06-25 | expired | |
Mecklenburg County county · Board of Supervisors/County Commission |
VA | Pause data centers in Mecklenburg County pending regulations Mecklenburg County Board of Supervisors voted in March 2025 to end by-right zoning for data centers, requiring all data center applications to undergo staff-level review, a public hearing,… |
2025-03-01 | in force | |
Orange County county · Board of Supervisors/County Commission |
VA | Adopt data center setback and noise-limit standards in Orange County Orange County adopted new zoning regulations restricting data center development after community opposition. The county initially proposed a 'floating zone' approach that would allow… |
2025-09-01 | in force | |
Fluvanna County county · Board of Supervisors/County Commission |
VA | Pause data centers in Fluvanna County pending regulations Fluvanna County, Virginia, enacted a moratorium on data center development while studying zoning changes to address proposals spreading from Louisa and Albemarle counties. The Planning… |
2025-11-19 | in force | |
Sprigg Township township · Township Board |
OH | Halt data centers in Sprigg Township after 68 Yards proposal Sprigg Township, Ohio, trustees in Adams County passed a one-year voluntary moratorium on data centers on March 2, 2026, targeting a proposed facility at the former Stuart power plant site… |
2026-03-02 | in force | |
Scioto Township township · Township Board |
OH | Impose 12-month moratorium on data centers in Scioto Township while overhauling zoning code Scioto Township trustees in Pickaway County enacted a 12-month moratorium on data center applications in March 2026, joining at least 15 Ohio communities resisting AI industry expansion.… |
2026-03-06 | in force | |
Cincinnati city · City Council |
OH | Create data center overlay zone in Cincinnati Cincinnati, Ohio, City Council enacted an interim development control overlay after discovering data centers are currently interpreted as 'self storage' under existing zoning code, meaning… |
2026-02-06 | in force | |
Dexter Township township · Township Board |
MI | Impose 180-day data centers moratorium in Dexter Township Dexter Township adopted a 180-day moratorium on data center applications via Resolution #26-705, joining at least 19 Michigan communities that have paused data center development.… |
2026-02-01 | in force | |
Zeeland Township township · Planning Commission |
MI | Pause data centers in Zeeland Township pending regulations Zeeland Township's planning commission approved a one-year moratorium on data center applications in early 2026 while developing regulations for large-scale energy projects. The moratorium… |
2026-01-01 | in force | |
Lansing city · City Council |
MI | Block Deep Green rezoning of 2.7 acres in Lansing Deep Green withdrew its $120M downtown Lansing data center application on April 6, 2026, hours before the City Council was scheduled to vote on selling and rezoning the land. CEO Mark Lee… |
2026-04-06 | expired | |
Lancaster City city · City Council |
PA | Require special exception permits for CoreWeave data center conversion of former R.R. Donnelly plants in Lancaster City CoreWeave announced a $6 billion commitment to build an AI data center in Lancaster, converting former R.R. Donnelley/LSC Communications printing plants into a state-of-the-art facility… |
2025-10-06 | in force | |
Hazle Township township · Township Board |
PA | Deny NorthPoint Development data center on 1280 acres in Hazle Township Hazle Township, Pennsylvania, Board of Supervisors unanimously rejected NorthPoint Development's 1,280-acre, 15-building 'Project Hazelnut' data center campus in Luzerne County after more… |
2025-11-18 | expired | |
New Castle Township township · Township Board |
PA | Restrict KRNL Data Centers data center via zoning in New Castle Township KRNL Data Centers, a New York City-based developer, proposed a five-building campus on ~100 acres of conservation-zoned forest in New Castle Township, Schuylkill County. 'Save Frackville'… |
2025-09-10 | in force | |
Dorrance Township township · Township Board |
PA | Halt data centers in Dorrance Township after Brewster Land Company proposal Dorrance Township adopted a zoning ordinance amendment on September 22, 2025, allowing data centers only in industrial zones. Brewster Land Company LLC owns a 155-acre parcel zoned B-2… |
2025-08-11 | in force | |
Luzerne County county · Board of Supervisors/County Commission |
PA | Impose 500-foot data center setbacks in Luzerne County Luzerne County, Pennsylvania, proposed a zoning amendment covering 20 municipalities that rely on county zoning. Defines three data center tiers, Hyperscale (100,000+ sq ft, up to 200 MW),… |
2026-02-02 | pending | |
East Manchester Township township · Township Board |
PA | Pause data center zoning after public opposition in East Manchester East Manchester Township approved two ordinances: one regulating siting, design, construction, and operation of data centers; another establishing a data center overlay district near… |
2025-10-14 | in force | |
East Windsor city · City Council |
NJ | Deny data center permit in East Windsor East Windsor, New Jersey, Council voted down a redevelopment plan after a standing-room-only meeting where residents from the Twin Rivers community raised questions about a data center… |
2025-11-25 | expired | |
Lubbock city · Planning Commission |
TX | Deny Texas Solar Works data center on 936 acres in Lubbock Planning and Zoning Commission voted 4-3 to reject a 936-acre hyperscale AI data center zoning change from Low Density Single Family to General Industrial, requested by Hugo Reed and… |
2026-01-08 | expired | |
Cascade Township township · Township Board |
MI | Impose 6-month data centers moratorium in Cascade Township Cascade Township Board voted unanimously on February 26, 2026 for a 6-month moratorium on data center permits, with an option for a 6-month extension. The action was preemptive, no data… |
2026-02-26 | in force | |
Gaines Charter Township township · Planning Commission |
MI | Block Microsoft rezoning of 356 acres in Gaines Charter In Gaines Charter Township, Michigan, Microsoft seeking to rezone 316 acres (purchased from Steelcase for $45.3M) for data center. Dec 2025 hearing canceled when 250+ overflowed venue.… |
2026-03-03 | expired | |
Newton County county · Board of Supervisors/County Commission |
GA | Impose 30-day data centers moratorium in Newton County In Newton County, Georgia, Board of Commissioners unanimously enacted 30-day moratorium on data center applications. Existing ordinance limits DCs to Stanton Springs overlay, but… |
2026-01-20 | in force | |
City of Industry city · City Council |
CA | Oppose City of Industry zoning amendments enabling data center conversion of Puente Hills Mall City of Industry's Planning Commission voted in December 2025 to recommend zoning changes allowing data centers citywide (proposed by EdgeCore) (62 acres). City Manager Joshua Nelson wrote… |
2025-01-15 | in force | |
City of Oakley city · City Council |
CA | Rally against data center in City of Oakley In City of Oakley, California, Oakley City Council approved the 164-acre Bridgehead Industrial Project on March 11, 2026 in a 4-1 vote, but with an amendment excluding data centers after… |
2026-03-11 | expired | |
City of El Monte city · City Council |
CA | Impose 45-day data centers moratorium in City of El Monte In City of El Monte, California, On March 12, 2026, the City Council postponed action on data center moratorium evaluation after a verbal altercation during public comment led police to… |
2026-03-19 | in force | |
Harlingen city · City Council |
TX | Restrict Eneus Energy 1785-acre data center in Harlingen Harlingen city commissioners on April 1, 2026 called for public hearings and signaled plans to impose a 120-day moratorium on data centers to study impact on residents, resources and… |
2026-02-26 | in force | |
New Castle County county · Board of Supervisors/County Commission |
DE | Adopt comprehensive data center regulations with 1,000-foot residential buffers and open-loop cooling ban in New Castle County New Castle County Council passed 12-0 (with one absent) first-of-their-kind data center regulations after 7 months of debate. Requires 1,000-foot buffer from residential zones (reducible… |
2026-03-11 | in force | |
Town of Apex city · City Council |
NC | Propose data centers moratorium in Town of Apex The Apex Town Council voted unanimously on April 14, 2026 to adopt a one-year moratorium on data center development, following the March 5 withdrawal of Natelli Investments' New Hill… |
2026-03-10 | in force | |
Moore County county · Board of Supervisors/County Commission |
TN | Pause data centers in Moore County pending regulations The Moore County, Tennessee, Metro Council is considering a two-year moratorium on data center construction and expansion, which would take effect April 20, 2026. During the moratorium,… |
2026-03-01 | pending | |
Caddo Parish county · Board of Supervisors/County Commission |
LA | Propose data centers moratorium in Caddo Parish Following Governor Jeff Landry's announcement of Amazon's $12 billion investment in three interconnected data center campuses across Caddo, Louisiana, and Bossier parishes, Commissioner… |
2026-02-02 | expired | |
Warrenton city · City Council |
MO | Approve conditional use permit for Crusoe 340-acre data center in Warrenton with conditions The Warrenton, Missouri, Board of Aldermen voted unanimously in January 2026 to approve a conditional use permit for a Crusoe data center on a 340-acre parcel, consisting of two… |
2026-01-20 | in force | |
Troy city · City Council |
IL | Halt data centers in Troy after Cloverleaf Infrastructure proposal The Troy, Illinois, Planning Commission approved a six-month moratorium on data processing centers in March 2026, following the collapse of Cloverleaf Infrastructure's proposal for a… |
2026-03-12 | in force | |
Ashville city · Village Board |
OH | Impose 180-day data centers moratorium in Ashville (EdgeConneX) Ashville, Ohio, Village Council unanimously passed a 180-day emergency moratorium on December 20, 2025, in response to EdgeConneX's proposal on 680 acres including an on-site 200-megawatt… |
2025-12-20 | in force | |
Tulsa city · City Council |
OK | Propose data centers moratorium in Tulsa Tulsa City Council unanimously passed a NINE-month data center moratorium (through December 31, 2026) on March 26, 2026. Originally proposed by Councilor Laura Bellis as a 365-day… |
2026-03-26 | in force | |
Shreveport city · City Council |
LA | Deny Franks Investment Company conditional use permit in Shreveport Shreveport, Louisiana, Metropolitan Planning Commission denied a special use permit for a 2.8 million sq ft Franks Investment Company LLC data center at 7340 Greenwood Road (Resilient… |
2025-12-03 | in force | |
Henrico County county · Board of Supervisors/County Commission |
VA | Uphold denial of Centra Logistics data center on appeal In Virginia, Henrico County's Board of Zoning Appeals unanimously denied Centra Logistics' vested rights claim for a data center complex on nearly 200 acres along Darbytown Road in the… |
2026-02-27 | expired | |
Chesterfield County county · Board of Supervisors/County Commission |
VA | Require use permit for WestDulles Properties data center in Chesterfield County Reston-based developer WestDulles Properties filed an appeal in March 2026 of Chesterfield County staff's determination that a Conditional Use Permit (CUP) is required before its 170-acre… |
2026-01-01 | in force | |
Powhatan County county · Board of Supervisors/County Commission |
VA | Block Province Group rezoning of 181 acres in Powhatan County Powhatan County, Virginia, Board of Supervisors voted 5-0 on Oct. 29, 2025 to approve rezoning of approximately 61 additional acres to expand the planned Province Group data center campus… |
2025-10-29 | in force | |
DeKalb County county · Board of Supervisors/County Commission |
TN | Ban data centers in designated zones in DeKalb County DeKalb County, Tennessee, Commission is considering data center regulations proposed by County Mayor Matt Adcock after receiving an inquiry about locating a nuclear-powered data center in… |
2026-03-01 | pending | |
Maricopa County county · Board of Supervisors/County Commission |
AZ | Block data center rezoning in Maricopa County The Maricopa County, Arizona, Board of Supervisors unanimously approved a modernized zoning ordinance establishing specific rules for data center development, effective January 9, 2026.… |
2025-12-10 | in force | |
Millard County county · Board of Supervisors/County Commission |
UT | Rezone 4,400+ acres from agricultural for Creekstone Energy solar farm powering AI data centers Millard County, Utah, Commission approved rezoning of 4,400+ acres from agricultural to forest/range for Creekstone Energy solar farm to power AI data centers, despite resident opposition.… |
2026-04-22 | in force | |
Falls Township township · Township Board |
PA | Oppose Amazon data center in Falls Township Amazon is building a 1-million-square-foot data center on 1,800 acres at the Keystone Trade Center in Falls Township, Bucks County, fast-tracked through Governor Shapiro's PA Permit Fast… |
2026-02-20 | in force | |
Bryan city · City Council |
TX | Adopt data center zoning standards in Bryan Bryan, Texas, City Council proactively annexed 162 acres near the RELLIS campus and adopted a Planned Development zoning district allowing data centers with stricter-than-normal standards… |
2025-09-16 | in force | |
Newark county · Board of Supervisors/County Commission |
DE | Block 847,000 sq ft data center replacing White Clay Corporate Center in Newark Verdantas/Shelbourne proposed an 847,000 sq ft data center complex on a 44-acre site at the White Clay Center Industrial Park off Ogletown Road in Newark, DE. The proposal would demolish… |
2026-01-30 | in force | |
Grant County county · Board of Supervisors/County Commission |
IN | Impose 24-month data centers moratorium in Grant County Grant County Commissioners passed a 24-month moratorium on data centers on March 2, 2026. The Area Plan Commission began drafting ordinance language focusing on transparency, resource… |
2026-03-02 | in force | |
Lake County county · Board of Supervisors/County Commission |
IN | Impose 55 dB noise limit on data centers in Lake County Lake County, Indiana, Council approved stringent data center regulations: only permitted in industrial zones with special approval, 200-ft setbacks from residential/agricultural, 55dB… |
2026-02-18 | in force | |
Thomas County county · Board of Supervisors/County Commission |
GA | Impose 12-month data centers moratorium in Thomas County Thomas County, Georgia, Board of Commissioners unanimously approved a 12-month moratorium on AI data center construction in January 2026. Commission Chair Mark NeSmith said the board was… |
2026-01-20 | in force | |
Irwin County county · Planning Commission |
GA | Petition to block Google data center in Irwin County Google proposed a 1GW data center on 546 acres near Irwinville in an agricultural zone. The Irwin County, Georgia, Planning Commission voted to recommend approval on Feb 26, 2026. However,… |
2026-03-02 | expired | |
Nobles County county · Board of Supervisors/County Commission |
MN | Reject data centers in agricultural preservation district and pursue environmental review in Nobles County Nobles County (MN) Board of Commissioners voted 3-2 on April 21, 2026 to deny a zoning change that would have allowed Geronimo Power's proposed $4 billion, ~640-acre data center campus on… |
2026-04-21 | expired | |
Culpeper County county · Board of Supervisors/County Commission |
VA | Require conditional use permits in Culpeper County Culpeper County, Virginia, unanimously required conditional use permits for data centers on industrial land in September 2025, impacting 3,000+ acres across 140+ parcels that previously… |
2025-09-02 | in force | |
Reno city · City Council |
NV | Deny Oppidan 5MW data center permit in Reno Oppidan proposed a 5MW data center on a 7-acre site in the Stead area of Reno, Nevada,. The Sierra Club Toiyabe Chapter raised environmental, grid, and water concerns. Despite opposition,… |
2025-03-12 | in force | |
Lowell city · City Council |
MA | Impose 360-day moratorium on Markley Group data center expansion Lowell City Council voted 10-0 on March 10, 2026 to enact a one-year moratorium on data center development, the first such municipal moratorium in Massachusetts. Championed by community… |
2026-03-11 | in force | |
Gibraltar city · City Council |
MI | Halt data centers in Gibraltar after Raeden proposal Gibraltar, Michigan, City Council unanimously approved a year-long moratorium in March 2026, freezing a proposed 100 MW data center at the former McLouth Steel site (27800 W. Jefferson… |
2026-03-09 | in force | |
Essex city · City Council |
IL | Block Constellation Energy rezoning of 600 acres in Essex Constellation Energy purchased over 600 acres near Essex, Illinois, and is seeking rezoning and annexation. Much of the land was sold by village board members or their relatives. The Essex… |
2025-11-01 | in force | |
Kosciusko County county · Board of Supervisors/County Commission |
IN | Deny Prologis rezoning of 554 acres of farmland Kosciusko County, Indiana, Area Plan Commission unanimously denied (8-0) Prologis's rezoning request for 554 acres of farmland near Leesburg from agricultural to industrial for a… |
2025-04-22 | expired | |
Washington Township township · Township Board |
OH | Impose 90-day data centers moratorium in Washington Township Washington Township in northwestern Franklin County passed a 90-day moratorium on data centers in unincorporated parts of the township on December 8, 2025. The township also asked the city… |
2025-12-08 | in force | |
St. Albans Township township · Township Board |
OH | Ban data centers in designated zones in St. Albans Township St. Albans Township, Ohio, held a public hearing on March 10, 2026 on a proposal to become the first township in Licking County to ban data centers. The township sits on the eastern edge… |
2026-03-10 | in force | |
Two Creeks township · Township Board |
WI | Impose 6 month data centers moratorium in Two Creeks Two Creeks, along with Two Rivers and Mishicot, held a joint town board meeting and approved identical resolutions calling on Manitowoc County to adopt a one-year moratorium on data center… |
2026-02-01 | in force | |
Two Rivers township · Township Board |
WI | Impose one-year moratorium on data center permits in Two Rivers, Two Creeks, and Mishicot Two Rivers, Wisconsin, joined Two Creeks and Mishicot at a joint town board meeting on February 12, 2026 in approving identical resolutions calling for a one-year moratorium on data center… |
2026-02-01 | in force | |
Mishicot township · Township Board |
WI | Impose 6-month data centers moratorium in Mishicot Mishicot, Wisconsin, joined Two Creeks and Two Rivers at a joint town board meeting after several hundred people packed the Grey Fox Bar and Grill on January 26, 2026 for an informational… |
2026-02-01 | in force | |
Forsyth County county · Board of Supervisors/County Commission |
GA | Restrict data center water usage in Forsyth County Forsyth County, Georgia, enacted a strict data center ordinance that prohibits data center cooling systems from using the county water system, one of the most restrictive approaches among… |
2025-10-01 | in force | |
Covington city · City Council |
GA | Impose 180-day data centers moratorium in Covington The City of Covington, Georgia, council imposed a 180-day moratorium on new data center requests on January 5, 2026 (by 3Rivers Development). During the moratorium, city staff will review… |
2026-01-05 | in force | |
Newton County county · Board of Supervisors/County Commission |
GA | Pause data centers in Newton County pending regulations Newton County Board of Commissioners unanimously enacted an emergency moratorium on data center applications in February 2026, joining a wave of Georgia moratoriums. Previously, SC… |
2025-11-01 | in force | |
Ottawa city · City Council |
IL | Impose 180-day data centers moratorium in Ottawa Ottawa City Council established a 180-day moratorium on data centers across all zoning districts, the first such moratorium in the Illinois Valley. Mayor Robert Hasty cited the need for… |
2026-03-03 | in force | |
Forney city · City Council |
TX | Require conditional use permits in Forney The City of Forney, Texas, is considering new zoning rules that would formally regulate data center development within city limits. A public hearing is scheduled for March 17, 2026 on a… |
2026-03-17 | pending | |
Brazoria County county · Board of Supervisors/County Commission |
TX | Deny Nightpeak Energy data center on 158 acres in Brazoria County Brazoria County, Texas, commissioners unanimously rejected a package of tax abatements sought by Nightpeak Energy for its proposed $3.5 billion Old Ocean Data Center campus outside Sweeny,… |
2026-03-13 | expired | |
Fredericksburg city · Planning Commission |
VA | Deny Penzance Development 600MW data center permit in Fredericksburg Penzance Development / 1500 Gateway LLC proposed a 600 MW data center on 84 acres in Fredericksburg, Virginia. Residents of the Great Oaks Lane neighborhood objected to the project, citing… |
2025-12-11 | expired | |
City of Provo city · City Council |
UT | Deny B+F Timpanogos Tech rezoning of 9 acres in City of Provo The Provo City, Utah, Council voted unanimously (7-0) on March 11, 2026 to deny a zoning change for a proposed AI data center at 1507 S. 180 East in the East Bay area. Developer B+F… |
2026-03-11 | expired | |
Fayetteville city · City Council |
NC | Ban data centers in all zones in Fayetteville Fayetteville, North Carolina, City Council voted in early March 2026 to remove data centers as a permitted use from ALL zoning categories within city limits. A pending application by CHI… |
2026-03-05 | pending | |
Washington Township township · Planning Commission |
MI | Block Prologis rezoning of 312 acres in Washington Township Prologis is seeking to rezone 312 acres on 32 Mile Road for a Microsoft data center. The Planning Commission has postponed the rezoning decision four times (Jan -> Feb -> April -> June 11)… |
2026-03-11 | in force | |
Olyphant Borough borough · City Council |
PA | Adopt data center zoning standards in Olyphant Borough Olyphant Borough Council on April 14, 2026 rejected a proposed data center zoning amendment after residents argued the regulations were too lax (covering setbacks, noise, water usage,… |
2026-04-14 | pending | |
Londonderry Township township · Township Board |
PA | Create data center overlay zone in Londonderry Township Londonderry Township, Pennsylvania, tabled a zoning ordinance that would create a data center overlay district after overwhelming resident opposition at a packed public hearing. Proposed… |
2026-02-11 | in force | |
City of Scranton city · City Council |
PA | Adopt data center zoning standards in City of Scranton Scranton City, Pennsylvania, Council introducing an amendment to the 2023 zoning ordinance to regulate data centers, following advice from Lackawanna County planners that municipalities… |
2026-03-17 | pending | |
Wilmington city · City Council |
OH | Block Ardent Technologies rezoning of 545 acres in Wilmington Wilmington, Ohio, City Council voted 5-2 on Feb 20 to rezone 545 acres from rural residential to light industrial for a second data center campus by Ardent Technologies (affiliated with… |
2026-02-20 | in force | |
Minooka city · Village Board |
IL | Restrict Equinix 340-acre data center in Minooka Equinix was approved for a $2B, 368-acre, 700MW campus in Minooka, Illinois, about 50 miles southwest of Chicago, requiring 3 million gallons of water per day from a $1.54 billion Lake… |
2025-10-01 | in force | |
Logan County county · Board of Supervisors/County Commission |
IL | Block Hut 8 rezoning of 200 acres in Logan County The Logan County (IL) Board voted 9-2 in February 2026 to approve a 60-day moratorium on accepting data center applications, prompted by Hut 8 Corp's proposal for a $5B, 500 MW data center… |
2025-12-01 | in force | |
Lee County county · Board of Supervisors/County Commission |
NC | Rally against Deep River Data data center in Lee County Lee County commissioners voted 6-1 on March 16, 2026 to begin drafting a moratorium on data centers and cryptomining, following a packed public meeting. On April 20, 2026, after a roughly… |
2026-03-16 | in force | |
Blakely county · Board of Supervisors/County Commission |
GA | Oppose QTS Technology Services data center over water in Blakely QTS filed a Developments of Regional Impact application for a 12 million sq ft QTS Technology Services data center campus on the outskirts of Blakely, Georgia, the 'Peanut Capital of the… |
2026-03-01 | in force | |
New Kent County county · Board of Supervisors/County Commission |
VA | Create data center overlay zone in New Kent County Following Goochland's lead, New Kent County, Virginia, is proposing a 1,800-acre Technology Overlay District along the Route 33 corridor. Controversial fast-track process would skip… |
2026-02-17 | pending | |
Franklin County county · Board of Supervisors/County Commission |
MO | Block rezoning of 800 acres in Franklin County Franklin County, Missouri, Planning & Zoning Commission is considering county-wide data center regulations including 1,000-ft setbacks from residential areas. The commission will hold its… |
2026-03-17 | pending | |
Meade County county · Board of Supervisors/County Commission |
KY | Halt data centers in Meade County after PowerHouse Industries proposal Meade County, Kentucky, Fiscal Court adopted Ordinance 2025-07 on January 13, 2026, establishing a moratorium on data center development while the county reviews its zoning ordinance and… |
2026-01-13 | in force | |
Monterey Park city · City Council |
CA | Ban data centers in all zones in Monterey Park Monterey Park, California, City Council voted unanimously to place a permanent data center ban on the June 2, 2026 ballot (by HMC Capital / HMC StratCap). If approved by voters, it would… |
2026-03-04 | pending | |
Warren County county · Board of Supervisors/County Commission |
NJ | Distribute model data center ordinance in Warren County Warren County Commissioner James R. Kern III, a member of the county Planning Board, distributed an advisory model data center siting ordinance to mayors and governing bodies across all… |
2026-01-15 | in force | |
Logan County county · Board of Supervisors/County Commission |
CO | Restrict Granite Renewables 4198-acre data center in Logan County Logan County, Colorado, adopted new data center regulations on February 18, 2026, lifting its moratorium and allowing Granite Renewables' proposed $15B, 2GW project on 4,198 acres to… |
2026-02-18 | in force | |
Lyon County county · Board of Supervisors/County Commission |
NV | Block Monarch Data Center rezoning of 505 acres in Lyon County Copia Power's Monarch Data Center, backed by Carlyle Group, won approval for an $11B, 1,000 MW campus on 505 acres rezoned from agriculture in Mason Valley. The 14-building, 4.6M sq ft… |
2025-12-07 | in force | |
East Lansing city · City Council |
MI | Impose 6-month data centers moratorium in East Lansing East Lansing City Council enacted a 6-month moratorium on data center development in March 2026, pausing new applications while the city studies potential impacts on the community. The… |
2026-03-17 | in force | |
Detroit city · City Council |
MI | Pause data centers in Detroit pending regulations Detroit, Michigan, City Council voted 6-2 on March 18, 2026 for a resolution asking Mayor Mary Sheffield to halt all data center permits for two years while the city studies environmental… |
2026-03-10 | in force | |
Monroe County county · Board of Supervisors/County Commission |
WV | Resist data center siting in Monroe County after state law preempted local authority Monroe County residents organized opposition to potential data center development (by Undisclosed developer (state-facilitated)). The Monroe County Commission denied ongoing data center… |
2026-02-01 | in force | |
Clinton County county · Board of Supervisors/County Commission |
IN | Petition to block Logistix Realty data center in Clinton County Logistix Realty proposed a data center near Frankfort, first petitioning to rezone land within city limits (withdrawn July 2025), then filing a new request in December 2025 to rezone 715… |
2025-12-01 | expired | |
Elkhart County county · City Council |
IN | Oppose Pinnacle Properties data center over water in Elkhart County Pinnacle Properties, representing landowner Christine Truee Wilhelm, sought to rezone 247 acres of farmland on County Road 23 in Bristol, Indiana, for a data center campus of 800,000 to… |
2024-09-01 | in force | |
Cass County county · Board of Supervisors/County Commission |
MI | Petition to block Hyperscale Data data center in Cass County Hyperscale Data (parent of Alliance Cloud Services) operates a 30 MW data center in Dowagiac and plans expansion to 70 MW by 2027 and 340 MW by 2029, enough energy to power 100,000+ homes.… |
2025-12-01 | in force | |
Kalkaska County county · Board of Supervisors/County Commission |
MI | Community pressure forces Rocklocker to withdraw in Kalkaska County Rocklocker LLC (headed by Traverse City geologist Matt Rine) proposed a gigawatt-scale hyperscale data center on 1,440 acres of state-owned land near Island Lake and South River roads,… |
2025-11-01 | expired | |
Crawford County county · Board of Supervisors/County Commission |
GA | Impose 6-month data centers moratorium in Crawford County Crawford County, Georgia, Board of Commissioners passed a 6-month (180-day) moratorium on data center permits on January 6, 2026, by a unanimous 5-0 vote, on the recommendation of Planning… |
2026-01-06 | in force | |
Town of Boone city · City Council |
NC | Pause data centers and crypto mining in Town of Boone pending regulations Boone Town, North Carolina, Council voted 5-0 to approve a one-year moratorium on data center and cryptocurrency mining development on March 23, 2026, cheered by a capacity crowd at town… |
2026-03-23 | in force | |
Washington County county · Board of Supervisors/County Commission |
TN | Impose moratorium on data centers and crypto mining in Washington County through June 2027 Washington County, Tennessee, Commission voted 13-2 on March 23, 2026 to enact a moratorium on data center construction, operation, and permitting, including cryptocurrency mines, through… |
2026-03-23 | in force | |
Baltimore City city · City Council |
MD | Impose one-year moratorium on 10MW+ data centers as prohibited zoning use in Baltimore City Baltimore City Council President Zeke Cohen introduced a one-year moratorium on data centers with 10MW+ electrical demand on March 23, 2026. The legislation would classify such facilities… |
2026-03-23 | pending | |
Monroe Township township · Township Board |
OH | Impose 12-month moratorium on data centers and small modular nuclear reactors in Monroe Township Monroe Township, Ohio, trustees unanimously passed a 12-month moratorium on new proposals and development of data centers and small modular nuclear reactors. Monroe Township is the second… |
2026-03-09 | in force | |
Chesterfield County county · Board of Supervisors/County Commission |
VA | Require conditional use permit for WestDulles' 430-acre data center in Chesterfield County WestDulles is appealing a determination that its proposed 430-acre data center complex near Chester requires a Conditional Use Permit under Chesterfield County's new zoning ordinance that… |
2026-03-09 | in force | |
Watauga County county · Board of Supervisors/County Commission |
NC | County-wide moratorium on data centers in Watauga County pending regulations Watauga County, North Carolina, Commissioners unanimously voted on March 24, 2026 to schedule a public hearing on April 21 for a potential county-wide data center moratorium. This follows… |
2026-03-24 | pending | |
Archbald Borough borough · City Council |
PA | Deny conditional use permit for 18-building data center campus in Archbald Council voted down Provident Realty Advisors' application to build a giant data center after months of growing outcry. About 200 residents showed up wearing yellow shirts. Archbald (pop.… |
2026-03-27 | expired | |
Apple Valley city · Planning Commission |
MN | Deny data center zoning and permits that conflict with Apple Valley 2040 Comprehensive Plan Apple Valley, Minnesota, Planning Commission recommended denial on March 18, 2026 of three key components of the Apple Valley Technology Park data center project: the Preliminary Plat,… |
2026-03-18 | expired | |
City of Fayetteville city · Planning Commission |
GA | Block data center construction on Highway 85 in Fayetteville Crow Holdings Development and CHI Acquisitions LP officially withdrew their appeal on March 18, 2026 to build a 300,000 sq ft data center on 37.4 acres on Highway 85 North near Fayette… |
2026-03-18 | expired | |
City of Liberty city · City Council |
MO | Scrutinize $202M in data center tax abatements approved in Liberty without public referendum Liberty City, Missouri, Council approved $1.4 billion in bonds and $202.7 million in tax abatements over 25 years for Metrobloks, an LA-based developer, to build three buildings totaling… |
2026-03-24 | in force | |
Pemberton Township township · Township Board |
NJ | Ban data center construction and operation throughout Pemberton Township Pemberton Township became the first municipality in New Jersey to outright ban data centers when it passed Ordinance 10-2026 on February 20, 2026, prohibiting the construction and… |
2026-02-20 | in force | |
Lawton city · City Council |
OK | Restrict data center development to 2MW by-right limit with council review for larger facilities Lawton City Council voted 5-3 on February 24, 2026 to approve a zoning ordinance amendment setting one of the most restrictive data center limits in the country: data centers with peak… |
2026-02-24 | in force | |
Habersham County county · City Council |
GA | Oppose Big Red Apple data center development in Cornelia The Big Red Apple Innovation Corridor, a proposed $300 million, 284-acre mixed-use development by Cook Communities at 1900 Level Grove Road in Cornelia, Habersham County, included a data… |
2025-12-01 | expired | |
Fort Worth city · City Council |
TX | Delay and add conditions to Edged Data Centers tax abatement at Veale Ranch Fort Worth City Council unanimously voted on March 31, 2026 to delay a decision on a 10-year, 50% tax abatement worth ~$18.2 million for Edged Data Centers' proposed $1.1 billion data… |
2026-03-31 | pending | |
Saline County county · Board of Supervisors/County Commission |
KS | Three-year pause on data centers, nuclear, and hydrogen facilities in unincorporated Saline County Saline County Board of Commissioners voted 4-0 on March 18, 2026 to enact a three-year moratorium on data centers, nuclear power generation facilities, and hydrogen-based energy plants in… |
2026-03-18 | in force | |
Plain Township township · Township Board |
OH | 12-month pause on data center construction in Plain Township to study impacts Plain Township trustees in Stark County, Ohio enacted a 12-month moratorium on data center construction on March 27, 2026, to assess potential impacts on health, safety, utilities, and… |
2026-03-27 | in force | |
Huron County county · Board of Supervisors/County Commission |
MI | Expand data center moratorium from 6 months to 3 years to develop county regulations Huron County, Michigan, Planning Commission voted unanimously on April 1, 2026 to expand its data center moratorium from six months to three years, following a public hearing where… |
2026-04-01 | pending | |
Manitowoc County county · Board of Supervisors/County Commission |
WI | County-wide one-year moratorium on data center permits in Manitowoc County Manitowoc County Planning and Parks Commission unanimously approved a 1-year moratorium on data center permits on March 31, 2026, following petitions from Three Towns (Two Creeks, Two… |
2026-03-31 | pending | |
Massillon city · City Council |
OH | Develop data center zoning recommendations for Massillon before proposals arrive Massillon, Ohio, City Council hired an outside attorney on March 31, 2026 to develop data center zoning recommendations as interest from data center developers grows across Stark County.… |
2026-03-31 | pending | |
Hanover Township township · City Council |
PA | Regulate data center location, noise, water, and power demand in Hanover Township Township passed data center ordinance regulating location, noise, water usage, power demand, and emergency management. Most likely site is Starpointe Industrial Park. Community members… |
2026-03-31 | in force | |
Montgomery Township township · City Council |
PA | Declare zoning ordinance invalid to proactively adopt data center regulations before developers seek court approval Supervisors declared township zoning ordinance 'substantively invalid' for lacking data center provisions, triggering the curative amendment process under PA Municipalities Planning Code.… |
2026-03-23 | in force | |
Jenkins Township township · City Council |
PA | Create 550-acre Data Center Overlay District limited to CenterPoint industrial zone with conditional use requirement Jenkins Township, Luzerne County, Pennsylvania, held a public hearing on March 31, 2026 for a proposed zoning amendment creating a 550-acre Data Center Overlay District limited to the… |
2026-03-31 | pending | |
Phillipsburg city · City Council |
NJ | Ban data centers from all zoning districts in Phillipsburg Phillipsburg, NJ Town Council UNANIMOUSLY adopted Ordinance 2026-08 on April 14, 2026, banning data centers in all zoning districts townwide. Residents cited concerns about a potential… |
2026-03-26 | in force | |
Yorkville city · City Council |
IL | Block third data center rezoning near Caledonia residential subdivision in Yorkville Yorkville Nexus V LLC / Green Door Capital WITHDREW the 91-acre Meyer Property data center rezoning application on April 14-15, 2026, following the city council's April 1 tabling and… |
2026-04-01 | expired | |
City of Carver city · City Council |
MN | Preemptive moratorium on data center development in Carver, MN Carver City Council unanimously approved a 1-year moratorium on data center development on April 6, 2026. This is a preemptive action, no specific data center project was pending, to allow… |
2026-04-06 | in force | |
Sault Ste. Marie Tribe of Chippewa Indians county · Tribal Government |
MI | Indefinite moratorium on AI data centers on Sault Tribe lands The Sault Tribe Board of Directors voted unanimously on April 7, 2026 to approve an indefinite moratorium on AI data center development on tribal lands, citing concerns about resource… |
2026-04-07 | in force | |
Brentwood city · City Council |
MO | Classify data centers as conditional use requiring public hearings and monitoring Brentwood, Missouri Board of Aldermen held the first reading on April 6, 2026 of a bill to classify data centers as conditional use in the light industrial district, requiring public… |
2026-04-06 | pending | |
Northfield city · City Council |
MN | Strict data center environmental efficiency standards as regulatory model Northfield, Minnesota, highlighted as a potential model for data center regulation with the strictest environmental efficiency standards in the state, covering noise, lighting, building… |
2026-04-08 | in force | |
Pike County county · Board of Supervisors/County Commission |
OH | Scrutinize what could be the country's largest data center in an economically distressed region On April 21, 2026, AEP Ohio announced plans to build approximately 50 miles of 765-kV high-voltage transmission line across Pike, Jackson, and Gallia counties in southern Ohio to power a… |
2026-04-21 | pending | |
Hutto city · City Council |
TX | Oppose rezoning of 40 acres from apartments to data center On April 17, 2026, Zydeco Development withdrew its rezoning application for a proposed 950,000-square-foot data center at the southeast corner of County Road 119 and Limmer Loop in Hutto,… |
2026-04-17 | expired | |
Cochise County county · Board of Supervisors/County Commission |
AZ | Adopt data center regulations requiring special use authorization and water/noise impact plans Cochise County Board of Supervisors voted 3-0 on April 7, 2026 to adopt new data center regulations requiring special use authorization, noise impact analyses, water use plans, proof that… |
2026-04-07 | in force | |
York County county · Board of Supervisors/County Commission |
VA | Establish data center zoning standards in York County VA York County (Virginia) Planning Commission unanimously advanced data center zoning amendments to the Board of Supervisors on April 8, 2026. The amendments increase maximum building height… |
2026-04-08 | pending | |
Swain County county · Board of Supervisors/County Commission |
NC | Pass 12-month data center moratorium in Swain County Swain County held a packed public hearing on April 1, 2026 (the most crowded meeting ever in their building) with 30+ speakers over two hours, only one opposed the moratorium. Triggered by… |
2026-04-01 | in force | |
Town of Clyde city · City Council |
NC | Pass data center moratorium in Town of Clyde The Town of Clyde, NC passed a one-year moratorium on data center development at its April 16, 2026 meeting following a public hearing. This follows neighboring Canton's similar moratorium… |
2026-04-16 | in force | |
Vance County county · Board of Supervisors/County Commission |
NC | Block data center rezoning in Vance County After a delayed April 6, 2026 vote and a unanimous April 12-13 planning board recommendation, the Vance County Board of Commissioners voted 6-1 on April 20, 2026 to approve a rezoning… |
2026-04-20 | in force | |
City of Rocky Top city · City Council |
TN | Restrict data centers to industrial zones in Rocky Top Rocky Top, TN: Ordinance 620 (data center zoning restrictions) second reading was NOT held on April 16, 2026 as previously scheduled. Mayor Templin confirmed the vote has been moved to May… |
2026-04-01 | pending | |
Bangor city · City Council |
ME | Six-month moratorium on data center construction to update Land Development Code Bangor city councilors unanimously passed a six-month moratorium on data center construction on April 13, 2026. The freeze gives the city time to adjust its Land Development Code before… |
2026-04-13 | in force | |
Lowhill Township township · Township Board |
PA | Establish conditional use zoning requirements for data centers Board of Supervisors adopted data center regulations titled 'Digital Infrastructure Facility,' permitting data centers as conditional use in the Regional Use Overlay 2 district. Includes… |
2026-04-08 | in force | |
Smithfield city · Planning Commission |
RI | Ban data center development in Smithfield Smithfield Planning Board voted on April 13, 2026 to advance a data center ban, giving a positive recommendation to the Town Council. The Town Council vote is scheduled for May 5, 2026.… |
2026-04-01 | pending | |
Ravenna city · City Council |
OH | Pause data centers in Ravenna pending zoning and grid study Ravenna, OH City Council held a special meeting on April 20, 2026 that advanced a 12-month data center moratorium. The second reading and public hearing are scheduled for May 18, 2026. The… |
2026-04-10 | pending | |
Shawnee Township township · Township Board |
OH | Pause data centers, BESS, and solar in Shawnee Township for 18 months Shawnee Township trustees (Allen County, Ohio) enacted an 18-month moratorium on April 13, 2026 covering data centers, battery energy storage systems (BESS), and utility-scale solar. The… |
2026-04-13 | in force | |
Botkins city · City Council |
OH | Ban data center development in the Village of Botkins The Village of Botkins, Ohio held the first reading of legislation to ban data center development during the week of April 13, 2026. If adopted, it would be one of the first outright bans… |
2026-04-14 | pending | |
DeKalb County county · Planning Commission |
IN | Pause data centers in DeKalb County, Indiana for 6 months The DeKalb County, Indiana Plan Commission recommended a 6-month data center moratorium on April 14, 2026, sending the measure to the County Commissioners for final action. The… |
2026-04-14 | pending | |
New Buffalo Township township · Township Board |
MI | Block Project Maize data center in New Buffalo Township for 1 year New Buffalo Township, Michigan (Berrien County) passed a 1-year data center moratorium on April 8, 2026, blocking an investment group's 'Project Maize' data center proposal and giving the… |
2026-04-08 | in force | |
Detroit city · City Council |
MI | Draft data center zoning, grid, and environmental standards in Detroit Following the Detroit City Council's March 18, 2026 resolution requesting a two-year data center permitting pause, the city convened a zoning policy working group in mid-April 2026 to… |
2026-04-14 | in force | |
Otoe County county · Planning Commission |
NE | Pause data centers in Otoe County pending zoning standards On April 16, 2026, the Otoe County Planning Commission voted to recommend a moratorium on data center construction in the county. Resident Wynne Benedict cited environmental and health… |
2026-05-19 | in force | |
North Franklin Township township · Township Board |
PA | Proactive data center and crypto mining regulation ordinance North Franklin Township (Washington County) adopted a proactive ordinance on April 14-16, 2026 regulating cryptocurrency mining and data center operations. No developer has filed a project… |
2026-04-14 | in force | |
Montour County county · Board of Supervisors/County Commission |
PA | 26-page zoning amendment covering crypto, AI, and hyperscaler data centers Montour County Commissioners approved a notice of intent on April 14, 2026 to adopt a 26-page zoning amendment covering cryptocurrency mining, AI data centers, and hyperscaler facilities.… |
2026-04-14 | pending | |
Rowan County county · Board of Supervisors/County Commission |
NC | Temporary pause on new data center approvals in Rowan County Rowan County (NC) Board of Commissioners approved a 1-year data center moratorium 4-0 on April 21, 2026, effective May 4, 2026. The Long Ferry Road project (EDC Charlotte LLC) is exempted… |
2026-04-21 | in force | |
Clay Township township · Township Board |
OH | Preemptive 12-month moratorium on data center development in rural Clay Township Clay Township (Highland County, OH) trustees adopted a 12-month data center moratorium on April 20, 2026. Board Chair Angela Howell cited concerns that rural communities are becoming hot… |
2026-04-20 | in force | |
City of Oakley city · City Council |
CA | 45-day urgency moratorium (extensible up to 2 years) on new data center approvals Oakley, CA (Contra Costa County) became the first Bay Area city to pass a data center moratorium, with City Council unanimously adopting a 45-day urgency ordinance on April 14-15, 2026.… |
2026-04-15 | in force | |
Centralia city · City Council |
MO | Restrict data centers to conditional use in M-1 industrial zone in Centralia On April 21, 2026, the Centralia Board of Aldermen unanimously passed an ordinance that defines and regulates data centers, requiring conditional use permits and permanent buildings (no… |
2026-04-21 | in force | |
Mansfield city · City Council |
OH | Reject EnergiAcres data center / power plant due to lack of coordination and scope creep. Mansfield Mayor Jodie Perry announced on April 21, 2026 that the city will 'no longer pursue' the proposed EnergiAcres data center and power plant project sited north of Mansfield in… |
2026-04-21 | expired | |
Washington Township township · Township Board |
OH | Pause data center zoning approvals to study utility, noise, and infrastructure impacts. On April 21, 2026, Washington Township trustees (Montgomery County, Dayton area) approved a 360-day moratorium on issuance and processing of zoning permits and approvals for data center… |
2026-04-21 | in force | |
Tiffin city · City Council |
OH | Pause data center establishments to study zoning standards. On April 21, 2026, Tiffin City Council voted 6-0 (and a separate 6-0 emergency declaration) to approve Resolution 2026-42 imposing a 12-month moratorium barring the establishment of, or… |
2026-04-21 | in force | |
Findlay city · City Council |
OH | Temporarily ban new data center establishments to review codes. On April 21, 2026, Findlay City Council approved a 12-month data center moratorium (Ordinance 2026-42) by a 9-1 vote, with Councilman B.J. Preston casting the lone 'nay' vote, arguing data… |
2026-04-21 | in force | |
Dayton city · Planning Commission |
OH | Recommend a 180-day moratorium and ban on large data centers within city limits. On April 14, 2026, the Dayton City Plan Board recommended adopting a 180-day moratorium on data center applications and a zoning code text amendment that would prohibit large data centers… |
2026-04-14 | pending | |
Plainfield city · Village Board |
IL | Pause data center applications pending state legislation and local regulations. On April 21, 2026, Plainfield Village Board unanimously approved a 180-day moratorium on data center and warehouse-for-computing-infrastructure proposals. The moratorium pauses… |
2026-04-21 | in force | |
Tonopah county · Board of Supervisors/County Commission |
AZ | Rezone 638 acres to enable 2.25 million sq ft data center campus. On April 15, 2026, the Maricopa County Board of Supervisors approved a request to rezone a 638-acre site at the northeast corner of 491st Avenue and Thomas Road outside Tonopah (west of… |
2026-04-15 | in force | |
Oklahoma City city · City Council |
OK | Pause new data center rezoning through end of 2026. On April 22, 2026, the Oklahoma City Council unanimously approved a moratorium on new data center developments through December 31, 2026, prohibiting rezoning requests intended for data… |
2026-04-22 | in force | |
Reno city · City Council |
NV | Initiate text amendment to revise data center siting, noise, water, and environmental rules. On Earth Day (April 22, 2026), the Reno City Council voted unanimously to initiate a text amendment to Title 18 of the Annexation and Land Development Code to revise data center… |
2026-04-22 | in force | |
Orange County county · Board of Supervisors/County Commission |
NC | Pause new data centers via 12-month moratorium On April 21, 2026, the Orange County Board of Commissioners voted unanimously 6-0 to approve a one-year moratorium on large-scale data centers covering AI training facilities,… |
2026-04-21 | in force | |
Glynn County Board of Commissioners county · Board of Supervisors/County Commission |
GA | Restrict data center water use under new zoning ordinance On April 17, 2026, the Glynn County Board of Commissioners unanimously approved new zoning ordinances that include a section permitting data centers, rejecting calls from the planning… |
2026-04-16 | in force | |
Jackson City Council city · City Council |
MS | Pause data center development with 183-day moratorium On April 21, 2026, Jackson City Council President Brian Grizzell introduced a draft ordinance establishing a 183-day moratorium on construction, expansion, permitting, or site-plan… |
2026-07-14 | in force | |
Tredyffrin Township township · Township Board |
PA | Authorize draft zoning amendments to regulate data centers in Tredyffrin Township The Tredyffrin Township Board of Supervisors voted unanimously on April 21, 2026 to authorize township staff and the solicitor to draft zoning amendments regarding data centers. No… |
2026-04-21 | pending | |
Harford County Council county · Board of Supervisors/County Commission |
MD | Enact 90-day moratorium on data center development in Harford County (Bill 26-005) Councilmember Jacob Bennett officially introduced Bill 26-005 at the Harford County Council meeting on Tuesday, April 21, 2026, proposing a 90-day moratorium on data center development.… |
2026-04-21 | pending | |
Memphis City Council city · City Council |
TN | Approve land sale to xAI for Colossus Water Recycle Plant The Memphis City Council gave final approval to sell 13 acres south of the T.E. Maxson Wastewater Treatment Plant to xAI for $820,000 to build the $80M 'Colossus Water Recycle Plant.'… |
2025-03-04 | in force | |
Memphis City Council city · City Council |
TN | Direct 25% of xAI city property tax to surrounding neighborhoods The Memphis City Council unanimously passed Mayor Paul Young's ordinance allocating 25% of xAI's city property tax revenue, estimated at $3M-$3.2M of $13M first-year revenue, up to $100M… |
2025-08-01 | in force | |
Saline Township Planning Commission township · Planning Commission |
MI | Deny rezoning of 575 farmland acres for Stargate data center After an August 5, 2025 first public hearing dominated by opposition, the Saline Township Planning Commission tabled Related Digital's 'conditional rezoning' application for 575 acres from… |
2025-08-12 | expired | |
Saline Township Board township · Township Board |
MI | Deny rezoning for Stargate data center The Saline Township Board voted 4-1 to deny the rezoning of 575 acres of agricultural land needed for the Stargate data-center campus. Treasurer Jennifer Zink stated the project conflicted… |
2025-09-10 | expired | |
Saline Township Board township · Township Board |
MI | Rescind I-1 industrial designation to block citizen referendum At an overflow special meeting, the Saline Township Board voted 5-0 to rescind its prior I-1 industrial designation and revert the data-center property back to A-1 Agricultural zoning,… |
2026-01-28 | in force | |
City of Port Washington city · City Council |
WI | Annex 500 acres and create I-3 Technology Campus zoning for data center Port Washington's city authorities unanimously approved annexing 500 acres from the Town of Port Washington and creating a new I-3 Technology Campus District zoning classification… |
2025-05-01 | in force | |
Port Washington Common Council city · City Council |
WI | Approve $8B Vantage development agreement with $175M public infrastructure reimbursement The Port Washington Common Council unanimously approved the development agreement with Vantage Data Centers for what was then announced as an $8 billion data-center campus on 672 acres on… |
2025-08-19 | in force | |
Port Washington Plan Commission city · Planning Commission |
WI | Establish TID No. 5 boundaries / project plan for $458M Vantage TIF The Port Washington Plan Commission, after hours of public comment, approved Resolution 2025-3 establishing the boundaries and project plan for Tax Incremental District No. 5, the $458… |
2025-10-16 | in force | |
Port Washington Common Council & Joint Review Board city · City Council |
WI | Create $458M TID No. 5 for Vantage Lighthouse The Port Washington Common Council formally voted to create Tax Incremental District (TID) No. 5, a $458 million TIF, for the Vantage Lighthouse data center. On November 18, 2025, the… |
2025-11-04 | in force | |
Port Washington Plan Commission city · Planning Commission |
WI | End 24-hour construction at Lighthouse site After months of resident complaints, including reports of 110-decibel noise, incessant backup beeping, and bright work lights shining 24 hours a day into nearby homes, the Port Washington… |
2026-03-25 | in force | |
Village of Mount Pleasant Village Board city · Village Board |
WI | Approve $13.3B Microsoft 15-building expansion site plans The Mount Pleasant Village Board unanimously approved two site plans for Microsoft's $13.3B expansion, adding 15 data-center buildings on two new campuses, after the Plan Commission… |
2026-01-26 | in force | |
Niles city · City Council |
OH | Block Bitdeer 300 MW annexation and adopt moratorium in Niles On Monday April 20, 2026, the City of Niles announced it would take "no further action" on a proposed annexation of three Weathersfield Township parcels submitted by Whitetail Creek LLC (a… |
2026-04-20 | expired | |
Harnett County county · Board of Supervisors/County Commission |
NC | Pause data center development in Harnett County pending regulations Harnett County Commissioners on April 21, 2026 voted to schedule a public hearing for May 4, 2026 on a proposed one-year data center moratorium and authorized modifications to the county's… |
2026-04-21 | pending | |
Cumberland County county · Board of Supervisors/County Commission |
NC | Pause data center development in Cumberland County pending regulations The Cumberland County (NC) Board of Commissioners voted 6-0 (one absent) on April 20, 2026 to schedule a public hearing on May 18 at 6:45 p.m. on a proposed data center moratorium.… |
2026-06-15 | in force | |
Bethel Township township · Planning Commission |
PA | Develop data center zoning ordinance for Bethel Township Bethel Township Planning Commission unanimously voted on April 21, 2026 to begin developing a draft data center ordinance, with Chairman Dale Snader noting "It's coming, and I suppose we… |
2026-04-21 | pending | |
Plymouth Township township · Township Board |
PA | Resolve dispute over 43 zoning conditions attached to proposed AI data center at Cleveland-Cliffs site Developer Brian O'Neill resubmitted a zoning application in May 2026 to build a 2M-sq-ft, 10-building AI data center across 66 acres of the former Cleveland-Cliffs steel mill site in… |
2026-07-27 | pending | |
Montgomery County county · Board of Supervisors/County Commission |
MD | Impose a data center permit moratorium and ban hyperscale facilities countywide Montgomery County Council member Evan Glass introduced Bill 19-26 in May 2026 as a 6-month data center permit freeze, prompted partly by a proposed 360 MW campus at a former coal plant… |
2026-07-28 | in force | |
Town of Brookhaven township · Township Board |
NY | moratorium After backlash over a rumored AI data center in Yaphank, Supervisor Dan Panico proposed an 18-month moratorium and the Brookhaven Town Board voted unanimously on May 29, 2026 to schedule a… |
2026-05-29 | pending | |
Cranford Township township · Township Board |
NJ | ordinance + zoning restriction Cranford announced it will introduce a land-use ordinance amendment on June 8, 2026 to explicitly prohibit AI data centers, reversing its August 2025 broadening of permitted uses in the… |
2026-06-09 | pending | |
City of Summit city · City Council |
NJ | ordinance + zoning restriction Summit Common Council introduced an ordinance amending prohibited land uses to ban AI data centers, with debate over a 20-MW peak-power threshold. Council Member Jamel Boyer voted against… |
2026-06-16 | in force | |
City of Allentown city · City Council |
PA | zoning restriction + public comment/hearing Allentown City Council tabled Bill 20 on June 3, 2026 after ~4 hours of testimony from a standing-room-only crowd. The bill would permit data centers in G-I and I-M districts by special… |
2026-06-03 | pending | |
Town of Scarborough borough · City Council |
ME | moratorium On June 3, 2026, the Scarborough Town Council unanimously approved a 180-day data center moratorium, retroactive to April 1, halting a ~52-acre data center proposal submitted in April and… |
2026-06-03 | in force | |
City of Westbrook city · City Council |
ME | moratorium On June 1, 2026, the Westbrook City Council unanimously approved a 180-day data center moratorium; the planning board will review the land-use ordinance and report back. It is part of a… |
2026-06-01 | in force | |
City of Fort Worth city · City Council |
TX | zoning restriction + ordinance Fort Worth city staff presented proposed citywide data center rules on June 2, 2026: ban cryptocurrency mining as a primary data center use; require a 250-ft setback from homes (300-ft for… |
2026-06-02 | pending | |
Pinal County county · Board of Supervisors/County Commission |
AZ | project withdrawal/rejection + public comment/hearing Facing ~60 opposed public comments and ~50 emails, the developer’s attorney told the Pinal County Board of Supervisors on May 28, 2026 that the owner wants the “La Osa” campus made… |
2026-05-28 | pending | |
Dane County county · Board of Supervisors/County Commission |
WI | moratorium The Dane County Board unanimously approved Sub 1 to RES-039 on June 4, 2026, an 18-month moratorium pausing zoning permit applications for hyperscale data centers (defined as 5,000+… |
2026-06-04 | in force | |
Brown County county · Board of Supervisors/County Commission |
WI | moratorium On June 2, 2026, the Brown County Planning, Development & Transportation Committee unanimously declined to advance Supervisor Christopher Welch’s proposed countywide data center… |
2026-06-02 | expired | |
Shawano County county · Board of Supervisors/County Commission |
WI | moratorium On June 3, 2026, the Shawano County Planning, Development & Zoning Committee unanimously recommended a one-year moratorium for unincorporated (county-zoned) areas after a public hearing at… |
2026-06-03 | pending | |
Jackson County county · Board of Supervisors/County Commission |
MO | moratorium On June 1, 2026 the Jackson County (Missouri) Legislature held over two competing data center moratorium proposals (Ord. 6074, a 120-day pause incl. battery storage; Ord. 6087, a year-long… |
2026-06-22 | in force | |
City of Virginia Beach city · City Council |
VA | zoning restriction On June 2, 2026, the Virginia Beach City Council voted unanimously to direct staff to draft a zoning ordinance amendment making traditional and hyperscale data centers non-permitted uses… |
2026-06-02 | pending | |
Newberry County county · Board of Supervisors/County Commission |
SC | moratorium + permit_denial On June 4, 2026, the Newberry County Council voted unanimously to deny an ordinance that would have let a developer purchase county land for a potential data center, and enacted a one-year… |
2026-06-04 | in force | |
Hernando County county · Board of Supervisors/County Commission |
FL | moratorium In early June 2026, the Hernando County Commission approved a one-year data center moratorium. No company is named. [Validation: status corrected to pending, June 2 was a first-reading… |
2026-06-04 | pending | |
Holmes County county · Board of Supervisors/County Commission |
FL | moratorium + study_or_report On June 2, 2026, the Holmes County Commission directed the county attorney to draft a permanent ban on AI data centers, with a public hearing set for June 16. |
2026-06-02 | pending | |
Iron County county · Board of Supervisors/County Commission |
UT | moratorium On May 26, 2026, the Iron County Commission adopted a 180-day pause (the maximum allowed under Utah law) on accepting or processing new or incomplete land-use applications for data… |
2026-05-26 | in force | |
Howard County county · Board of Supervisors/County Commission |
MD | moratorium The Howard County Council passed CB31-2026, a temporary moratorium pausing data center development through November 2027 to modernize the county's roughly 1993-era zoning regulations… |
2026-06-02 | in force | |
McMinnville city · City Council |
TN | moratorium On June 3, 2026, the McMinnville Board of Mayor and Aldermen unanimously approved on first reading an 18-month moratorium covering data centers, Bitcoin mining, and microchip… |
2026-06-09 | in force | |
Town of Hillsborough borough · City Council |
NC | moratorium The Town of Hillsborough enacted a 60-day moratorium on AI data centers and data mining to update its land-use ordinances, joining recent actions by Orange County, Chatham County, and the… |
2026-06-01 | in force | |
Little Rock city · City Council |
AR | ordinance + zoning restriction On June 3, 2026, Little Rock's Board of Directors unanimously approved new citywide data center regulations during an hours-long meeting that featured heavy criticism of a proposed ~$1B… |
2026-06-03 | in force | |
Reno city · City Council |
NV | moratorium On June 1, 2026, the Reno City Council voted 6-1 to extend its data center moratorium into 2027, described as the first such extension in Nevada, while the city continues work on a Title… |
2026-06-01 | in force | |
Grove City city · City Council |
OH | moratorium On June 1, 2026, Grove City passed a 12-month (1-year) moratorium on data center development, amended to create a task force to study impacts and develop regulations during the pause. |
2026-06-01 | in force | |
City of Brawley city · City Council |
CA | moratorium On May 19, 2026, the Brawley City Council voted 3-2 (Grass and Kelley dissenting) to approve Ordinance No. 2026-03, an immediate moratorium on data centers requiring more than 50 MW of… |
2026-05-19 | in force | |
City of Imperial city · City Council |
CA | moratorium On May 20, 2026, the City of Imperial council voted 4-0 to direct staff to return with a moratorium on hyperscale data centers within city limits; the item returned June 3 with the council… |
2026-05-20 | pending | |
City of Calexico city · City Council |
CA | moratorium The Calexico City Council was scheduled to consider a proposed data center moratorium at its June 3, 2026 meeting (alongside a public-safety budgeting mandate). No specific data center… |
2026-06-03 | pending | |
Imperial County county · Board of Supervisors/County Commission |
CA | moratorium + zoning restriction On June 2, 2026, after 1+ hour of public comment and 296 emailed comments, the Imperial County Board of Supervisors declined to adopt staff-drafted 'Data Center Development Guidelines' (21… |
2026-06-16 | in force | |
Town of Brunswick city · City Council |
ME | moratorium On June 1, 2026 the Brunswick, Maine Town Council unanimously approved a 180-day moratorium (through ~Dec 2026) on processing applications for new or expanded data centers with electrical… |
2026-06-01 | in force | |
Moosic Borough borough · Village Board |
PA | ordinance + zoning restriction Moosic Borough (Lackawanna County) is finalizing one of the county's most comprehensive data center ordinances, with a Borough Council public hearing targeted for its June 8, 2026 meeting.… |
2026-06-08 | pending | |
Warren Township, Somerset County township · Township Board |
NJ | zoning restriction + ordinance The Warren Township (Somerset County, NJ) Committee approved the first reading (May 18, 2026) of an ordinance, introduced by Committeeman Daniel Croson, that would prohibit data centers as… |
2026-06-18 | in force | |
Lexington-Fayette Urban County county · City Council |
KY | opposition action + moratorium On June 8, 2026 Lexington Mayor Linda Gorton announced the city will not provide public incentives to DartPoints, which closed a ~$29M private purchase of the former Lexmark property (745… |
2026-06-08 | in force | |
Fayetteville city · City Council |
AR | zoning restriction + ordinance On June 4, 2026 Fayetteville Mayor Molly Rawn (with Councilman Scott Berna) announced proposed ordinance amendments making data centers a conditional use across all zoning districts… |
2026-06-16 | in force | |
Clay County county · Board of Supervisors/County Commission |
FL | moratorium + public comment/hearing On June 9, 2026 the Clay County (FL) Commission held the first of two required public hearings on a proposed 12-month moratorium halting rezoning and permitting for data centers in… |
2026-06-23 | in force | |
Gardner city · City Council |
KS | moratorium On June 1, 2026 a proposed six-month data center moratorium FAILED at the Gardner (KS) City Council, Councilmember Kelly Johnson's motion died for lack of a second; Vice President Kacy… |
2026-06-01 | expired | |
City of Edmond city · City Council |
OK | moratorium On June 8, 2026 the Edmond (OK) City Council voted 5-0 to enact an immediate moratorium on accepting new data center applications through Dec 31, 2026, giving the city ~5 months to study… |
2026-06-08 | in force | |
Box Elder County county · Board of Supervisors/County Commission |
UT | moratorium On June 10, 2026 the Box Elder County Commission unanimously approved a 180-day moratorium on new data center development in unincorporated Box Elder County (zoned and unzoned land), to… |
2026-06-17 | in force | |
Montgomery County county · Board of Supervisors/County Commission |
MD | moratorium + executive_action On June 13, 2026 Montgomery County Executive Marc Elrich signed an executive order imposing a six-month moratorium on new data center permits, directing the Department of Permitting… |
2026-06-13 | in force | |
Borough of Red Bank borough · City Council |
NJ | ordinance + zoning restriction + opposition action On June 11, 2026 the Red Bank Borough Council unanimously voted to ban data centers (final adoption) and unanimously passed an 'AI Accountability Proclamation' calling on the State of New… |
2026-06-11 | in force | |
Old Bridge Township township · Township Board |
NJ | opposition action + zoning restriction After a heated, packed public meeting (~June 9), the Old Bridge Township (Middlesex County) Council moved to draft an ordinance that would permanently ban data centers township-wide,… |
2026-06-12 | pending | |
Anderson County county · Board of Supervisors/County Commission |
TN | moratorium On June 15, 2026 the Anderson County (TN) Commission approved a two-year moratorium on new cryptocurrency mining, data processing, and battery storage development (facilities ≥20,000 sq ft… |
2026-06-15 | in force | |
Spartanburg County county · Board of Supervisors/County Commission |
SC | moratorium On June 15, 2026 the Spartanburg County (SC) Council unanimously directed the county manager and attorney to draft a data center moratorium/ban ordinance while awaiting state legislation.… |
2026-06-22 | pending | |
Greenwood County county · Board of Supervisors/County Commission |
SC | moratorium In the June 16-17, 2026 window the Greenwood County (SC) Council took up a proposed one-year data center moratorium, saying it wants preemptive regulations though no projects are currently… |
2026-07-07 | in force | |
Edgerton city · Planning Commission |
KS | permit_denial + moratorium Two-part Edgerton (KS) action: on June 11, 2026 the Planning Commission DENIED (3-2) Dubai-based DAMAC Digital's ~$860M data center (a conversion of a ~400,000-sq-ft warehouse at Logistics… |
2026-06-11 | in force | |
Council Bluffs city · City Council |
IA | moratorium On June 15, 2026 the Council Bluffs (IA) City Council voted unanimously to DENY a proposed one-year data center moratorium, opting for a wastewater-management plan instead as the city… |
2026-06-15 | expired | |
Yankton County county · Board of Supervisors/County Commission |
SD | moratorium On June 16, 2026 the Yankton County (SD) Commission held a first reading of a resolution for a temporary moratorium of up to 12 months on data centers and Bitcoin-mining facilities… |
2026-06-16 | pending | |
Liberty Township, Butler County township · Planning Commission |
OH | zoning restriction Around June 15, 2026 the Liberty Township (Butler County, OH) Zoning Commission approved a proposed change requiring data center projects to go through the planned-unit-development (PUD)… |
2026-06-15 | pending | |
Hood County county · Board of Supervisors/County Commission |
TX | zoning restriction + opposition action Hood County (TX) commissioners approved the Comanche Circle data center (Sailfish Development; up to ~9 campuses / ~2,600 acres near Tolar, up to 5 GW) WITHOUT conditions after the… |
2026-06-17 | in force | |
Santa Fe County county · Board of Supervisors/County Commission |
NM | moratorium Santa Fe County (NM) commissioners are advancing a yearlong moratorium on data center developments, with a public hearing and vote expected in late June; Commissioner Lisa Cacari Stone… |
2026-06-16 | in force | |
City of Holyoke city · City Council |
MA | ordinance + zoning restriction Holyoke became the first Massachusetts city to enact a citywide ban on AI data centers. The City Council voted 9-4 on June 16-17 to prohibit any AI data center development over 12… |
2026-06-18 | in force | |
Sayreville Borough borough · City Council |
NJ | moratorium Sayreville Borough Council introduced an 18-month moratorium on data center construction on June 15, 2026, with five members voting yes; the freeze would block new data center facilities… |
2026-06-15 | pending | |
Bernards Township township · Township Board |
NJ | ordinance + zoning restriction Bernards Township (Basking Ridge) is advancing Ordinance No. 2599, which would remove 'data processing centers' as a permitted use in the township's E1-E5 office zones and prohibit data… |
2026-06-18 | in force | |
City of Asbury Park city · City Council |
NJ | ordinance + opposition action On June 10, 2026, the Asbury Park City Council unanimously passed a resolution banning data centers within city limits and calling on Gov. Mikie Sherrill to enact a statewide moratorium on… |
2026-06-10 | in force | |
Chester County county · Board of Supervisors/County Commission |
SC | moratorium + ordinance On June 15, 2026 the Chester County (SC) Council approved FIRST READING of a six-month pause on accepting new data center applications, to study power-grid demand, local utility capacity,… |
2026-06-15 | pending | |
Warren County county · Board of Supervisors/County Commission |
TN | moratorium Warren County (TN) scheduled a June 22, 2026 vote on a temporary data center ban/moratorium covering its entire jurisdiction, following the City of McMinnville's (in Warren County)… |
2026-06-22 | pending | |
Butler County county · Board of Supervisors/County Commission |
OH | moratorium On Tuesday June 16, 2026 the Butler County (Ohio) Commissioners voted unanimously to approve a six-month moratorium on data centers, effective immediately, covering the six townships under… |
2026-06-16 | in force | |
La Crosse County county · Board of Supervisors/County Commission |
WI | moratorium On Thursday June 18, 2026 the La Crosse County (Wisconsin) Board of Supervisors approved an 18-month moratorium on new data center decisions and development by a 26-2 vote (two members… |
2026-06-18 | in force | |
City of Springfield county · City Council |
OH | moratorium At its June 16, 2026 regular meeting, Springfield (Ohio / Clark County) Commissioner Larry Ricketts said he is working with city staff to draft an ordinance for a six-month moratorium on… |
2026-06-16 | in force | |
Winnebago County county · Board of Supervisors/County Commission |
WI | moratorium Announced June 16, 2026, Winnebago County (Wisconsin) Executive Gordon Hintz introduced a proposed 12-month data center moratorium that would initially cover four towns (Nekimi, Neenah,… |
2026-06-16 | pending | |
Broken Arrow city · City Council |
OK | moratorium The Broken Arrow City Council voted unanimously on Monday, June 15, 2026 to enact a six-month moratorium on data center proposals, effective immediately and expiring December 31, 2026,… |
2026-06-15 | in force | |
City of Henderson city · City Council |
NV | moratorium The Henderson City Council introduced Bill No. 3927 at its June 16, 2026 meeting, a 180-day moratorium on conditional-use-permit applications for new data centers, which would make… |
2026-06-16 | expired | |
Skagit County county · Board of Supervisors/County Commission |
WA | moratorium Skagit County's Board of Commissioners voted June 1, 2026 to adopt a six-month interim moratorium on accepting data center permit applications in unincorporated/rural parts of the county,… |
2026-06-01 | in force | |
Jefferson County county · Board of Supervisors/County Commission |
CO | moratorium The Jefferson County (CO) Board of Commissioners voted May 19, 2026 to impose a 10-month moratorium on new data center development, running through roughly March 2027. The moratorium… |
2026-05-19 | in force | |
Carroll County county · Board of Supervisors/County Commission |
AR | moratorium + ordinance NEW fight. On June 17 the Carroll County (AR) Quorum Court unanimously passed a 12-month emergency moratorium blocking construction and authorization of 'high-impact industrial and… |
2026-06-17 | in force | |
Versailles city · City Council |
KY | moratorium NEW fight. On June 16 the Versailles (Woodford County) City Council voted unanimously to enact a data center moratorium halting all related development through December 31, 2026, brought… |
2026-06-16 | in force | |
Franklin Park Borough borough · Village Board |
PA | ordinance + zoning restriction NEW preemptive regulation. On June 17 the Franklin Park Borough Council adopted Ordinance No. 697-2026 establishing a data center overlay district in the borough zoning map even though no… |
2026-06-17 | in force | |
Bowling Green city · City Council |
KY | zoning restriction + moratorium NEW item (no existing Bowling Green KY entry found). On June 16 the Bowling Green City Commission adopted data center zoning regulations (energy/water limits, noise controls, 1,500-ft… |
2026-06-16 | in force | |
Clark County county · Board of Supervisors/County Commission |
NV | zoning restriction + opposition action The Clark County Commission, sitting as the zoning board, voted unanimously on June 18, 2026 to approve Switch's nearly 57,000-sq-ft data center expansion on nine acres along Warm Springs… |
2026-06-18 | in force | |
Lordstown county · Village Board |
OH | moratorium + infrastructure_opposition Separately from the data center freeze, Lordstown Village Council is advancing a 180-day moratorium on permits for businesses using small mobile (modular) reactors or battery energy… |
2026-06-15 | pending | |
Village of Wrightstown city · Village Board |
WI | Pause new data center development in Wrightstown pending an advisory referendum Wrightstown Village Board unanimously adopted a one-year moratorium on data center projects, extending a prior resolution that had paused planning pending an August advisory referendum. |
2026-07-07 | in force | |
Dodge County Board of Supervisors county · Board of Supervisors/County Commission |
WI | Pause new data center applications in Dodge County pending an ordinance Dodge County Board of Supervisors voted 29-2 for an 18-month pause on data center development to allow drafting of a county ordinance. One outlet (Daily Dodge) disputes whether the vote… |
2026-06-22 | in force | |
Linn County Board of Supervisors county · Board of Supervisors/County Commission |
IA | Pause new EU-3 data center rezoning applications in Linn County pending utility/technical studies Linn County Board of Supervisors voted 2-1 (Sami Scheetz opposed) for an 18-month pause on new rezoning applications to the county's EU-3 large-scale data center district, distinct from… |
2026-07-01 | in force | |
Woodbury County Board of Supervisors county · Board of Supervisors/County Commission |
IA | Pause new data center applications in unincorporated Woodbury County Woodbury County Board of Supervisors voted 5-0 for a 12-month moratorium on data center applications in unincorporated county land, prompted by the town of Salix's April annexation of ~900… |
2026-06-23 | in force | |
Seward County Board of Commissioners county · Board of Supervisors/County Commission |
NE | Pause data center permitting and construction in Seward County for one year Seward County Board of Commissioners unanimously passed a one-year moratorium on data center permits and construction, becoming roughly the 10th-11th Nebraska county with a data center… |
2026-06-25 | in force | |
Bourbon County Commission county · Board of Supervisors/County Commission |
KS | Pause utility-scale power generation, crypto mining, and data center development in Bourbon County Bourbon County Commission approved a 365-day development moratorium (Resolution 24-26) by a 3-0 vote, with Commissioners Joe Allen and Gregg Motley abstaining, covering utility-scale power… |
2026-06-15 | in force | |
Dublin City Council city · City Council |
OH | Strip data centers as a permitted use across Dublin's West Innovation District Dublin City Council voted 5-2 to rezone 370 acres, formally stripping data centers as a permitted use across the West Innovation District near Ballantrae and creating a new ID-6 'Research… |
2026-07-01 | in force | |
Cache County Council county · Board of Supervisors/County Commission |
UT | Pause data center applications in Cache County pending regulatory review Cache County Council voted 6-0 (one member absent) for a 180-day pause on accepting or reviewing any data center applications on unincorporated land, explicitly citing the neighboring Box… |
2026-06-23 | in force | |
Frederick County Board of Supervisors county · Board of Supervisors/County Commission |
VA | Block Equus Capital Partners' Virginia Technology Park data center rezoning Frederick County Planning Commission recommended denial 10-0 (2026-06-03) of Equus Capital Partners' ~220-acre Virginia Technology Park data center campus near Clear Brook, which would… |
2026-07-08 | pending | |
Front Royal Town Council city · City Council |
VA | Pause data center applications in Front Royal for 90 days Front Royal Town Council voted 6-0 for a 90-day moratorium on data center applications. The moratorium followed a June 22, 2026 unanimous Town Council denial of a text amendment that would… |
2026-07-07 | in force | |
Douglas County Commission county · Board of Supervisors/County Commission |
GA | Block a 4.4M sq ft data center campus rezoning in Douglas County Douglas County Commission voted 4-1 to deny a ~700+ acre, 4.4M sq ft data center campus rezoning. Hyperscaler unconfirmed. The 6-building campus, partly within the Dog River Basin (the… |
2026-07-07 | expired | |
DeKalb County Board of Commissioners county · Board of Supervisors/County Commission |
GA | Adopt setback and environmental-review standards for DeKalb County data centers A 12-month, four-draft Data Center Text Amendment (500-ft setbacks, environmental review) failed at the DeKalb County Board of Commissioners after a year of development. |
2026-06-23 | expired | |
Colleton County Council county · Board of Supervisors/County Commission |
SC | Pause new data center development in Colleton County pending regulatory review Colleton County Council finalized a 6-month data center moratorium; the Southern Environmental Law Center agreed to pause its related lawsuit against the county for the moratorium's… |
2026-07-07 | in force | |
Spartanburg County Council county · Board of Supervisors/County Commission |
SC | Pause new data center applications in Spartanburg County for one year Spartanburg County Council passed the first reading of a 12-month data center moratorium unanimously; it does not affect the already-under-construction NorthMark project. [Update… |
2026-07-20 | pending | |
Knox County Commission county · Board of Supervisors/County Commission |
TN | Pause data center development in Knox County for one year Knox County Commission unanimously (10-0) approved a one-year moratorium on data centers. |
2026-06-22 | in force | |
Knoxville City Council city · City Council |
TN | Pause large (>=10MW) data center development in Knoxville for one year Knoxville City Council passed a one-year moratorium on large data centers (>=10 MW), following Knox County's own June 22 moratorium. |
2026-07-07 | in force | |
Loudon County Commission county · Board of Supervisors/County Commission |
TN | Pause large (>=50MW) data center development in Loudon County for 6 months Loudon County Commission passed a 6-month data center moratorium for facilities with >=50 MW peak demand. |
2026-06-30 | in force | |
Cullman City Council city · City Council |
AL | Pause data center development in Cullman for one year and consider an outright ban Cullman City Council unanimously passed a 1-year moratorium on data centers and directed staff to draft a potential outright prohibition. |
2026-06-22 | in force | |
Oldham County Fiscal Court county · Board of Supervisors/County Commission |
KY | Block Project Lincoln via a 150-day countywide data center moratorium Oldham County passed a 150-day moratorium (until 2026-11-28) after removing a draft carve-out that would have exempted in-progress projects, directly blocking Western Hospitality Partners'… |
2026-07-01 | in force | |
Butler County Fiscal Court county · Board of Supervisors/County Commission |
KY | Pause data center development in Butler County for one year Butler County passed a 1-year data center moratorium, the third south-central Kentucky county to do so after Edmonson and Allen counties. Exact vote date is approximate. |
2026-06-30 | in force | |
Monroe Township Council township · City Council |
NJ | Remove 'data processing facilities' as a permitted zoning use in Monroe Township Council discussed 'Ordinance 013,' which would strike references to 'data processing facilities' from local land-use/planning documents, effectively closing a zoning pathway. No developer… |
2026-06-29 | pending | |
City of Westfield city · City Council |
MA | Pause new data center construction and permitting in Westfield for one year Westfield City Council unanimously passed a 1-year moratorium on new data center construction/permitting after standing-room-only public comment; this was the second of two required votes… |
2026-07-06 | in force | |
Middleton Township township · Township Board |
OH | Rezone parcels bordering the Meta data center for supporting construction logistics/parking Trustees voted 2-1 (Moulton, Vetter for; Petrea against) to rezone 13 parcels (~32 acres) from residential/agricultural to M-1 industrial to support the adjacent Meta data center,… |
2026-07-07 | in force | |
Houghton city · City Council |
MI | Enact a 1-year citywide moratorium on data center facilities in Houghton, MI City Council unanimously enacted a one-year moratorium on permitting, approval, and installation of data center facilities citywide, to allow the planning commission to study best… |
2026-07-09 | in force | |
St. Charles County county · Board of Supervisors/County Commission |
MO | Impose a 6-month countywide moratorium on data centers in St. Charles County, MO County Council unanimously approved a 6-month moratorium on data centers larger than 100,000 sq ft or exceeding 5 MW demand, following the City of St. Charles's earlier… |
2026-07-14 | in force | |
Joplin city · City Council |
MO | Adopt special-use-permit zoning requirements for future data centers in Joplin, MO City Council voted 9-0 to table a proposed ordinance requiring special-use permits (rather than by-right industrial zoning) for data centers, sending it back to Planning & Zoning to… |
2026-07-06 | pending | |
Bell County county · Board of Supervisors/County Commission |
TX | Halt Murray Industries data center construction for two years Commissioners passed a two-year construction moratorium halting a project by Murray Industries, which had already begun clearing land. It is unclear whether the moratorium covers Meta's… |
2026-07-02 | in force | |
Goodyear city · City Council |
AZ | Establish first-time zoning setback/noise standards for data centers and battery storage Goodyear City Council passed the city's first zoning ordinance overhaul since 1999, adding first-time data center and battery energy storage system (BESS) standards. Data centers now… |
2026-07-06 | in force | |
Grand County county · Board of Supervisors/County Commission |
UT | Pause new data center applications for 180 days pending permanent standards The Grand County Commission unanimously passed a 180-day moratorium pausing acceptance of new data center applications while permanent zoning standards are developed. |
2026-07-07 | in force | |
Missoula County county · Board of Supervisors/County Commission |
MT | Pause countywide data center development for one year pending regulations Missoula County approved a one-year, countywide pause on data center development -- Montana's first county-level moratorium. Distinct from the site-specific Krambu/Bonner Mill fight… |
2026-07-09 | in force | |
Marietta City Council city · City Council |
GA | Block Powers Ferry Place data center rezoning and pause new Marietta data center applications After a Planning Commission 4-3 recommendation to approve, Marietta City Council tabled Prime Group Holdings' Powers Ferry Place rezoning -- a proposal to convert part of a 90,000 sq ft… |
2026-07-08 | pending | |
Lakeland City Commission city · City Council |
FL | Establish a moratorium on new data centers and large-load electric customers in Lakeland The City of Lakeland released a proposed ordinance creating a temporary moratorium on data centers and large-load electric customers (over 50 MW/month); a public hearing was held July 6,… |
2026-07-06 | pending | |
Burgin City Council city · City Council |
KY | Enable a hyperscale data center via Burgin annexation of Mercer County farmland Burgin City Council voted 3-2 to give first reading to an ordinance annexing farmland from Mercer County -- roughly doubling the town's size (pop. ~1,000) -- to enable a hyperscale data… |
2026-07-09 | pending | |
Little Rock Board of Directors city · City Council |
AR | Pause new hyperscale data center approvals in Little Rock through year-end A measure by City Directors Kathy Webb and Capi Peck to pause new hyperscale data center approvals through year-end was deferred to August 4, 2026 at the sponsors' request. As drafted, it… |
2026-07-07 | pending | |
New Haven Board of Alders city · City Council |
CT | Pause new data center development/conversions in New Haven for 12 months pending zoning standards Alderman Richard Furlow introduced a 12-month moratorium ordinance on new data center development and conversions, scheduled for City Plan Commission review on 2026-07-15. The ordinance… |
2026-07-06 | pending | |
Wausau city · City Council |
WI | Adopt zoning ordinance restricting data centers to industrial zones with conditional use review and a residential setback City Council approved a first-of-its-kind data center zoning ordinance for Wausau: restricts data centers to medium/heavy-industrial zones (none permitted by right), requires a conditional… |
2026-07-14 | in force | |
Oshkosh city · City Council |
WI | Direct staff to draft a formal data center construction moratorium ordinance Common Council advanced a pause on data center construction, directing staff to draft a formal moratorium ordinance. No project is currently proposed for the city, but a local petition… |
2026-07-14 | pending | |
Mankato city · City Council |
MN | Impose a 1-year moratorium on data centers and high-impact utility consumers pending a study City Council voted 7-0 to pass a one-year moratorium on data centers and other 'high-impact utility consumers,' to allow a research study on localized water, power, farming, and climate… |
2026-07-13 | in force | |
Broken Bow city · City Council |
NE | Impose a 6-month moratorium on new data center construction applications City Council unanimously approved a 6-month moratorium on new data center construction applications, giving officials time to develop formal regulations. Per Zoning Administrator Jacob… |
2026-07-14 | in force | |
Americus / Lyon County county · Board of Supervisors/County Commission |
KS | Halt new data center and solar-farm permits in Lyon County pending a six-month moratorium Americus City Council held a listening session on the proposed Flint Hills Digital Campus (developer Kanza Park Place; publicly described as a potential gigawatt-scale, roughly 1,000-acre… |
2026-07-15 | in force | |
Roane County county · Board of Supervisors/County Commission |
TN | Direct the regional planning commission to draft a two-year moratorium on data centers, crypto-mining, and battery storage in Roane County The Roane County Commission approved a resolution directing the regional planning commission to draft a two-year moratorium -- amended up from an initially proposed 180 days -- on new data… |
2026-07-14 | in force | |
Lincoln County county · Board of Supervisors/County Commission |
NE | Block data centers in Lincoln County via a proposed moratorium Lincoln County Commissioners voted 3-2 against a proposed data center moratorium, with Hewgley, Bruns, and Woodruff opposed and Weems and Wuehler in favor. A recall drive targeting the… |
2026-07-13 | in force | |
Cass County county · Planning Commission |
NE | Recommend a data center moratorium to the Cass County Board The Cass County Planning Commission voted in favor of recommending a data center moratorium (no specific duration set) to the County Board, which holds final approval authority. The vote… |
2026-07-13 | pending | |
Jersey City city · City Council |
NJ | Ban data centers as a primary permitted use in Jersey City's Industrial Districts Mayor James Solomon and the City Council introduced Ordinance 26-057 on first reading, which would ban data centers as a primary principal use in Jersey City's Industrial Districts.… |
2026-07-15 | pending | |
Mercer County Fiscal Court county · Board of Supervisors/County Commission |
KY | Draft a new moratorium on data centers in unincorporated Mercer County pending a joint zoning ordinance The Mercer County Fiscal Court voted unanimously on July 14, 2026 (motion by Magistrate Susan Barrington) to direct the County Attorney to draft a new data-center moratorium covering… |
2026-07-14 | pending | |
Lansing city · City Council |
MI | Impose a 182-day moratorium on new data center development in Lansing, MI Lansing City Council voted 7-1 (Jeremy Garza dissenting) on July 15, 2026 to enact a 182-day moratorium on new data center development, effective July 27, 2026 through January 25, 2027.… |
2026-07-15 | in force | |
Warren county · City Council |
MI | Request a data center moratorium in Warren, MI after storm-related power outages Warren City Council Secretary Mindy Moore requested that a data-center moratorium be placed on a future council agenda after a July 3, 2026 storm knocked down 60+ power lines across the… |
2026-07-14 | pending | |
Logan County county · Board of Supervisors/County Commission |
NE | Impose a 12-month moratorium on data centers and other energy-intensive development in Logan County, NE The Logan County Board of Commissioners approved a 12-month moratorium on new data center, wind, solar, and cryptocurrency-mining development on July 16, 2026, becoming the twelfth… |
2026-07-16 | in force | |
Surry County county · Board of Supervisors/County Commission |
NC | Pause new data center development in Surry County for two years pending an impact study Surry County commissioners voted unanimously on July 21, 2026 to enact a two-year moratorium on new data center development, extending a prior 60-day pause. A steering committee will be… |
2026-07-21 | in force | |
Southport city · Planning Commission |
NC | Recommend a 15-month moratorium on data center development in Southport pending zoning rulemaking The Southport Planning Board voted unanimously on July 16, 2026 to recommend the city adopt a 15-month moratorium on data center development rather than proceeding directly to a zoning… |
2026-07-16 | pending | |
Cherokee County county · Board of Supervisors/County Commission |
GA | Pause new data center applications in Cherokee County pending a longer-term moratorium decision Cherokee County's Board of Commissioners unanimously approved an initial 30-day moratorium on new data center applications on July 22, 2026; an extension to 180 days (through mid-February… |
2026-07-22 | in force | |
Dougherty County county · Board of Supervisors/County Commission |
GA | Pause new data center projects in Dougherty County for 45 days Dougherty County commissioners approved a 45-day pause on new data center projects on July 20, 2026, amid rising regional concern about aquifer and grid impacts in the Albany area. |
2026-07-20 | in force | |
Albany city · City Council |
GA | Determine the length of a proposed moratorium on new data center development in Albany At a July 21, 2026 work session, the Albany City Commission directed staff to return with three moratorium-length options (180 days, 12 months, or 18 months) on new data center… |
2026-07-21 | pending | |
Brookwood city · City Council |
AL | Oppose a 1,200-acre data center rezoning near Brookwood Middle School A roughly 1,200-acre data center rezoning request near Brookwood Middle School is headed to an August 11, 2026 vote. The mayor denied a request to pause the process for a referendum. Black… |
2026-08-11 | pending | |
Neptune Township township · Township Board |
NJ | Ban data centers and ICE/DHS detention facilities townshipwide Neptune Township's Township Committee voted 3-1 on 2026-07-13 to ban both data centers and DHS/ICE immigration detention facilities townshipwide, becoming the 25th New Jersey municipality… |
2026-07-13 | in force | |
Weatherford county · Board of Supervisors/County Commission |
TX | Prevent Black Mountain from siting a second hyperscale data center campus in Parker County near Weatherford Black Mountain, the Fort Worth-based energy consortium developing the separate $10B, 530-acre data center campus in southeast Fort Worth (see fort-worth-southeast-tx-2025-01-01), purchased… |
2026-06-09 | pending | |
Milwaukee city · City Council |
WI | Pass a 1-year moratorium on new data center development in Milwaukee Milwaukee's Zoning, Neighborhoods & Development Committee postponed a proposed 1-year data center moratorium after the City Attorney's office said it lacked the required public… |
2026-07-28 | pending | |
Town of Janesville township · Township Board |
WI | Adopt a moratorium on data center development to preserve agricultural land The Town of Janesville's Planning & Zoning Committee recommended a moratorium on data center development to preserve agricultural land, following a heavily-attended public meeting. This is… |
2026-07-29 | pending | |
City of Lawrence county · City Council |
KS | Adopt a 2-year moratorium on large-scale data centers and close a zoning loophole The Lawrence City Commission unanimously approved a 2-year moratorium on large-scale data centers, extended from an originally proposed 1-year moratorium, and initiated a text amendment to… |
2026-07-14 | in force | |
City of Emporia county · City Council |
KS | Establish a digital infrastructure district via ordinance; citizen petition to prohibit data centers pending The Emporia City Commission approved three ordinances establishing a digital infrastructure district. Commissioners declined to act on a citizen petition to prohibit data centers, which… |
2026-07-23 | in force | |
Orangeburg County county · Board of Supervisors/County Commission |
SC | Pause new data center construction and development in Orangeburg County pending study Orangeburg County Council unanimously passed first reading of a data center construction and development moratorium after learning a company was scouting a Brentwood Drive site for a… |
2026-07-23 | pending | |
Falls Township township · Township Board |
PA | Rewrite data-center zoning rules via curative amendment while shielding the township from developer validity challenges Falls Township's Board of Supervisors voted to declare portions of Chapter 209 of the zoning ordinance -- covering data-center districts, setbacks, noise, and water/power requirements, and… |
2026-07-27 | pending | |
Cherry Hill Township township · Township Board |
NJ | Ban large-scale data centers townshipwide via zoning ordinance Cherry Hill Township Council voted unanimously on 2026-07-28 to ban large-scale data centers, designating them a non-permitted land use townshipwide while still allowing small in-house… |
2026-07-28 | in force | |
Cullman city · City Council/Board of Supervisors |
AL | One-year data center moratorium One-year data center moratorium (In force). |
2026-06-01 | in force | |
Fort Payne city · City Council/Board of Supervisors |
AL | Six-month data center moratorium Six-month data center moratorium (In force). |
2026-06-01 | in force | |
Independence County county · City Council/Board of Supervisors |
AR | Five-year data center moratorium Five-year data center moratorium (In force). |
2026-08-01 | in force | |
Pulaski County county · City Council/Board of Supervisors |
AR | Data center moratorium Data center moratorium (failed) (Failed / vetoed). |
2026-08-01 | expired | |
Russellville city · City Council/Board of Supervisors |
AR | Six-month data center moratorium Six-month data center moratorium (In force). |
2026-07-01 | in force | |
Union County county · City Council/Board of Supervisors |
AR | One-year data center moratorium One-year data center moratorium (In force). |
2026-06-01 | in force | |
Calipatria city · City Council/Board of Supervisors |
CA | Permanent data center ban Permanent data center ban (in development) (Proposed). |
2026-07-01 | pending | |
Coachella city · City Council/Board of Supervisors |
CA | Data center moratorium moving toward permanent ban Data center moratorium moving toward permanent ban (In force). |
2026-06-01 | in force | |
Indio city · City Council/Board of Supervisors |
CA | Urgency data center moratorium Urgency data center moratorium (In force). |
2026-06-01 | in force | |
Boulder County county · City Council/Board of Supervisors |
CO | Six-month data center moratorium Six-month data center moratorium (In force). |
2026-06-01 | in force | |
Monument city · Local government |
CO | Six-month data center pause Six-month data center pause (In force). |
2026 | in force | |
Woodland Park city · Local government |
CO | 18-month data center pause 18-month data center pause (In force). |
2026-07-01 | in force | |
Groton city · City Council/Board of Supervisors |
CT | Permanent zoning cap replacing 2022 moratorium Permanent zoning cap replacing 2022 moratorium (In force). |
2023 | in force | |
Dover city · Local government |
DE | Proposed 18-month pause on data center reviews Proposed 18-month pause on data center reviews (Proposed). |
2026-08-01 | pending | |
Nassau County county · City Council/Board of Supervisors |
FL | Up to 12-month data center moratorium Up to 12-month data center moratorium (In force). |
2026 | in force | |
Pasco County county · City Council/Board of Supervisors |
FL | One-year data center moratorium One-year data center moratorium (In force). |
2026-06-01 | in force | |
Santa Rosa County county · City Council/Board of Supervisors |
FL | 12-month data center moratorium 12-month data center moratorium (in development) (Proposed). |
2026-06-01 | pending | |
Zephyrhills city · City Council/Board of Supervisors |
FL | One-year data center moratorium One-year data center moratorium (In force). |
2026-06-01 | in force | |
Marietta city · City Council/Board of Supervisors |
GA | Six-month data center moratorium Six-month data center moratorium (In force). |
2026-07-01 | in force | |
City of Bloomington city · City Council/Board of Supervisors |
IL | Six-month data center moratorium Six-month data center moratorium (In force). |
2026-05-01 | in force | |
City of Carbondale city · City Council/Board of Supervisors |
IL | One-year data center moratorium One-year data center moratorium (In force). |
2026-06-01 | in force | |
City of Effingham city · City Council/Board of Supervisors |
IL | 12-month data center and crypto moratorium 12-month data center and crypto moratorium (In force). |
2026 | in force | |
City of West Chicago city · City Council/Board of Supervisors |
IL | 180-day moratorium 180-day moratorium (Ordinance 26-O-0011) (In force). |
2026-07-01 | in force | |
Town of Normal city · City Council/Board of Supervisors |
IL | Six-month data center moratorium Six-month data center moratorium (In force). |
2026-05-01 | in force | |
Boone County county · City Council/Board of Supervisors |
IN | One-year data center moratorium One-year data center moratorium (Ordinance 2026-08) (In force). |
2026-06-01 | in force | |
Jeffersonville city · City Council/Board of Supervisors |
IN | One-year data center moratorium One-year data center moratorium (In force). |
2026-08-01 | in force | |
New Albany (Floyd County) county · City Council/Board of Supervisors |
IN | One-year data center moratorium One-year data center moratorium (In force). |
2026-07-01 | in force | |
City of Peosta city · City Council/Board of Supervisors |
IA | Six-month data center moratorium Six-month data center moratorium (In force). |
2026-06-01 | in force | |
Dubuque County county · City Council/Board of Supervisors |
IA | 12-month data center moratorium 12-month data center moratorium (In force). |
2026-05-01 | in force | |
Madison County county · City Council/Board of Supervisors |
IA | One-year data-processing-facility moratorium One-year data-processing-facility moratorium (In force). |
2026-06-01 | in force | |
Plymouth County county · City Council/Board of Supervisors |
IA | One-year revocable data center moratorium One-year revocable data center moratorium (In force). |
2026-06-01 | in force | |
Sioux County county · City Council/Board of Supervisors |
IA | One-year data center and BESS moratorium One-year data center and BESS moratorium (In force). |
2026-06-01 | in force | |
Woodbury County county · City Council/Board of Supervisors |
IA | 12-month data center moratorium 12-month data center moratorium (Resolution 14064) (In force). |
2026-06-01 | in force | |
Riley County county · City Council/Board of Supervisors |
KS | Temporary data center moratorium Temporary data center moratorium (In force). |
2026-05-01 | in force | |
Bell County county · City Council/Board of Supervisors |
KY | Two-year data center moratorium Two-year data center moratorium (In force). |
2026-07-01 | in force | |
Boyle County county · City Council/Board of Supervisors |
KY | One-year data center moratorium One-year data center moratorium (In force). |
2026-06-01 | in force | |
Bullitt County county · City Council/Board of Supervisors |
KY | One-year data center moratorium One-year data center moratorium (In force). |
2026-07-01 | in force | |
Cave City city · City Council/Board of Supervisors |
KY | One-year data center moratorium One-year data center moratorium (In force). |
2026-06-01 | in force | |
Daviess County county · City Council/Board of Supervisors |
KY | 12-month data center moratorium 12-month data center moratorium (In force). |
2026-05-01 | in force | |
Edmonson County county · City Council/Board of Supervisors |
KY | One-year moratorium One-year moratorium (Ordinance EC26-18) (In force). |
2026-06-01 | in force | |
Louisville-Jefferson County Metro county · City Council/Board of Supervisors |
KY | Six-month moratorium on new data centers Six-month moratorium on new data centers (In force). |
2026-08-01 | in force | |
Nelson County county · City Council/Board of Supervisors |
KY | One-year data center moratorium One-year data center moratorium (In force). |
2026-07-01 | in force | |
Nicholasville city · City Council/Board of Supervisors |
KY | Six-month data center moratorium Six-month data center moratorium (In force). |
2026-08-01 | in force | |
Frederick County county · Local government |
MD | Data center permitting pause through end of 2026 Data center permitting pause through end of 2026 (In force). |
2026-07-01 | in force | |
Washington County county · City Council/Board of Supervisors |
MD | 12-month data center moratorium 12-month data center moratorium (In force). |
2026-06-01 | in force | |
Flint city · City Council/Board of Supervisors |
MI | 12-month data center moratorium 12-month data center moratorium (In force). |
2026-06-01 | in force | |
Meridian Township township · City Council/Board of Supervisors |
MI | Six-month data center and battery storage moratorium Six-month data center and battery storage moratorium (In force). |
2026-05-01 | in force | |
Orion Township township · City Council/Board of Supervisors |
MI | Six-month data center moratorium Six-month data center moratorium (In force). |
2026-06-01 | in force | |
Waterford Township township · City Council/Board of Supervisors |
MI | Temporary data center moratorium Temporary data center moratorium (Ord. 2026-Z-003) (In force). |
2026 | in force | |
Minneapolis city · City Council/Board of Supervisors |
MN | Six-month large data center moratorium Six-month large data center moratorium (In force). |
2026-05-01 | in force | |
City of Jackson city · City Council/Board of Supervisors |
MS | 183-day data center moratorium 183-day data center moratorium (In force). |
2026-07-01 | in force | |
City of Camdenton city · City Council/Board of Supervisors |
MO | One-year data center moratorium One-year data center moratorium (In force). |
2026-05-01 | in force | |
City of Neosho city · City Council/Board of Supervisors |
MO | One-year data center moratorium One-year data center moratorium (In force). |
2026 | in force | |
City of St. Peters city · City Council/Board of Supervisors |
MO | One-year data center moratorium One-year data center moratorium (In force). |
2026-05-01 | in force | |
Nodaway County county · City Council/Board of Supervisors |
MO | Six-month data center moratorium Six-month data center moratorium (Proposed). |
2026-07-01 | pending | |
Webster County county · City Council/Board of Supervisors |
MO | Six-month moratorium Six-month moratorium (data centers and energy facilities) (In force). |
2026 | in force | |
Cherry County county · City Council/Board of Supervisors |
NE | Six-month conditional-use-permit moratorium Six-month conditional-use-permit moratorium (In force). |
2026 | in force | |
Seward County county · City Council/Board of Supervisors |
NE | One-year data center moratorium One-year data center moratorium (In force). |
2026-06-01 | in force | |
Galloway Township township · City Council/Board of Supervisors |
NJ | Proposed six-month data center moratorium Proposed six-month data center moratorium (Proposed). |
2026 | pending | |
Sayreville city · City Council/Board of Supervisors |
NJ | 18-month data center moratorium 18-month data center moratorium (In force). |
2026-06-01 | in force | |
Sierra County county · City Council/Board of Supervisors |
NM | 18-month data center moratorium 18-month data center moratorium (In force). |
2026 | in force | |
Socorro County county · City Council/Board of Supervisors |
NM | One-year data center moratorium One-year data center moratorium (In force). |
2026-06-01 | in force | |
Town of East Fishkill city · City Council/Board of Supervisors |
NY | Three-year data center moratorium Three-year data center moratorium (In force). |
2026-06-01 | in force | |
Town of Lysander city · City Council/Board of Supervisors |
NY | Six-month data center moratorium Six-month data center moratorium (In force). |
2026-05-01 | in force | |
Town of Manlius city · City Council/Board of Supervisors |
NY | 12-month data center and crypto moratorium 12-month data center and crypto moratorium (In force). |
2026-07-01 | in force | |
Town of Oneonta city · City Council/Board of Supervisors |
NY | One-year data center and crypto moratorium One-year data center and crypto moratorium (In force). |
2026-05-01 | in force | |
Town of Perth city · City Council/Board of Supervisors |
NY | One-year data center moratorium One-year data center moratorium (In force). |
2025-06-01 | in force | |
Town of Salina city · City Council/Board of Supervisors |
NY | One-year data center moratorium One-year data center moratorium (In force). |
2026 | in force | |
Town of Van Buren city · City Council/Board of Supervisors |
NY | One-year data center moratorium One-year data center moratorium (In force). |
2026 | in force | |
Alamance County county · City Council/Board of Supervisors |
NC | Proposed large-data-center moratorium Proposed large-data-center moratorium (Proposed). |
2026-08-01 | pending | |
Charlotte city · City Council/Board of Supervisors |
NC | 150-day data center moratorium 150-day data center moratorium (In force). |
2026-06-01 | in force | |
City of Durham city · City Council/Board of Supervisors |
NC | Data center moratorium Data center moratorium (60-day, extended to 12 months) (In force). |
2026-05-01 | in force | |
City of Wilson city · City Council/Board of Supervisors |
NC | One-year data center moratorium One-year data center moratorium (In force). |
2026-05-01 | in force | |
Davie County county · City Council/Board of Supervisors |
NC | One-year data center moratorium One-year data center moratorium (In force). |
2026-07-01 | in force | |
Greensboro city · City Council/Board of Supervisors |
NC | Proposed 120-day moratorium for 10 MW+ data centers Proposed 120-day moratorium for 10 MW+ data centers (Proposed). |
2026-08-01 | pending | |
Town of Waxhaw city · City Council/Board of Supervisors |
NC | 12-month data center moratorium 12-month data center moratorium (In force). |
2026-08-01 | in force | |
Yadkin County county · City Council/Board of Supervisors |
NC | Proposed one-year data center moratorium Proposed one-year data center moratorium (Proposed). |
2026-08-01 | pending | |
Barnes County county · City Council/Board of Supervisors |
ND | Six-month data center moratorium Six-month data center moratorium (In force). |
2026-05-01 | in force | |
Alliance city · City Council/Board of Supervisors |
OH | 18-month data center moratorium 18-month data center moratorium (In force). |
2026-07-01 | in force | |
Cleveland city · Local government |
OH | Three-month pause on standalone data centers Three-month pause on standalone data centers (In force). |
2026-07-01 | in force | |
Conneaut city · City Council/Board of Supervisors |
OH | One-year data center moratorium One-year data center moratorium (failed) (Failed / vetoed). |
2026-08-01 | expired | |
Kent city · City Council/Board of Supervisors |
OH | Temporary AI data center permit moratorium Temporary AI data center permit moratorium (Ord. 2026-31) (In force). |
2026 | in force | |
Cherokee Nation (tribal and trust lands) city · City Council/Board of Supervisors |
OK | Ban on hyperscale data centers Ban on hyperscale data centers (In force). |
2026-08-01 | in force | |
City of Hillsboro city · City Council/Board of Supervisors |
OR | 120-day data center land-use moratorium 120-day data center land-use moratorium (In force). |
2026-07-01 | in force | |
Bensalem Township township · City Council/Board of Supervisors |
PA | 180-day data center curative-amendment moratorium 180-day data center curative-amendment moratorium (In force). |
2026-06-01 | in force | |
Charlestown city · City Council/Board of Supervisors |
RI | Zoning ban on data centers and battery storage Zoning ban on data centers and battery storage (In force). |
2026-08-01 | in force | |
Coffee County county · City Council/Board of Supervisors |
TN | One-year data center moratorium One-year data center moratorium (In force). |
2026-06-01 | in force | |
Knox County county · City Council/Board of Supervisors |
TN | One-year data center moratorium One-year data center moratorium (through June 30, 2027) (In force). |
2026-07-01 | in force | |
Knoxville city · City Council/Board of Supervisors |
TN | One-year moratorium on large data centers One-year moratorium on large data centers (10 MW+) (In force). |
2026-07-01 | in force | |
Hill County county · City Council/Board of Supervisors |
TX | One-year data center moratorium One-year data center moratorium (rescinded) (Failed / vetoed). |
2026-06-01 | expired | |
Cache County county · City Council/Board of Supervisors |
UT | 180-day data center moratorium 180-day data center moratorium (In force). |
2026-06-01 | in force | |
Snohomish County county · City Council/Board of Supervisors |
WA | Emergency six-month data center moratorium Emergency six-month data center moratorium (In force). |
2026-06-01 | in force | |
City of Superior city · City Council/Board of Supervisors |
WI | One-year data center moratorium One-year data center moratorium (In force). |
2026-06-01 | in force | |
Village of Bellevue city · City Council/Board of Supervisors |
WI | 12-month data center moratorium 12-month data center moratorium (In force). |
2026-08-01 | in force | |
Village of Cottage Grove city · City Council/Board of Supervisors |
WI | 12-month data center moratorium 12-month data center moratorium (In force). |
2026-07-01 | in force | |
Village of Greenville (Outagamie County) county · City Council/Board of Supervisors |
WI | One-year data center moratorium One-year data center moratorium (10,000 sq ft+) (In force). |
2026-07-01 | in force |
Lawsuits
Filed or active litigation over data center projects, moratoriums, permits, and environmental review.
| Parties | Court | Cause | Filed | Status | Sources |
|---|---|---|---|---|---|
DC BLOX v. Metro Nashville (Metropolitan Government of Nashville and Davidson County) DC BLOX alleges Nashville officials obstructed its proposed data center near Nashville Zoo by enacting a moratorium, pausing permit processing, and… |
U.S. District Court for the Middle District of Tennessee | zoning | 2026-08-11 | active | |
Sierra Club Wisconsin (represented by Midwest Environmental Advocates) v. Wisconsin Department of Natural Resources (DNR) Challenges DNR's decision to issue permits for Vantage Data Centers' $15B Port Washington campus without a full Environmental Impact Statement… |
Ozaukee County Circuit Court, Wisconsin | environmental | 2026-07-10 | active | |
Eagan Capital v. City of Eagan, Minnesota Challenges city's data center moratorium, alleging the city overstepped its authority by effectively regulating electricity consumption via… |
Minnesota state court (venue not specified in coverage) | zoning | 2026-07-06 | active | |
Preservation of Community Well-being Collective (residents of Saddlebrook Farms, Grayslake, Mundelein, Round Lake Park) v. Village of Grayslake; T5 Data Centers; Alter Asset Management Company Alleges the village obfuscated the nature of the 472-acre T5@Chicago development during approvals and proceeded without proper notice/public input.… |
Illinois state court, Lake County (venue not explicitly confirmed in coverage) | zoning | 2026-08-06 | active | |
Hexa Builders LLC; 3043 Williamstown Urban Renewal LLC v. Mayor and Township Council of Monroe (Gloucester County, NJ); Planning Board of Monroe Township; township officials Challenges Monroe Township's redevelopment-plan amendment and township-wide data center ban as arbitrary/capricious and violating equal protection,… |
Superior Court of New Jersey, Gloucester County, Law Division GLO-L-805-26 |
civil rights | 2026-06-09 | active | |
Imperial Valley Computer Manufacturing LLC (IVCM) v. City of Imperial, CA; City Council member Katherine Burnworth; City Manager Dennis Morita; City Attorney Kathrine Turner; Planning Director Othon Mora Civil-rights suit alleging coordinated administrative obstruction and retaliation to derail a permitted $10B AI data center; claims include failure… |
U.S. District Court, Southern District of California 3:26-cv-00128 |
civil rights | 2026-01-12 | active | |
Imperial Valley Computer Manufacturing LLC (IVCM) / related developer v. Imperial Irrigation District and associated water authorities Developer sues seeking access to Colorado River water allocations for the Imperial Valley AI data center project amid broader water-rights disputes… |
California / federal court (venue as reported) | environmental | 2026-06-15 | active | |
Sierra Club v. Imperial County, California Challenges Imperial County's approval of the massive IVCM data center complex, alleging inadequate CEQA environmental review. |
California state court (Imperial County venue presumed) | environmental | 2026-05-27 | active | |
Lowell residents (including Alex Solange, Mary Wambui and others) v. Markley Group; Massachusetts Department of Environmental Protection (permit referenced) Massachusetts' first lawsuit against a data center; challenges MassDEP's permit for 8 additional diesel generators at Markley's Lowell facility,… |
Massachusetts state court (Superior Court, Middlesex County presumed) | environmental | 2026-05-07 | active | |
Lowell residents (class action) v. Markley Group Class-action nuisance/environmental suit filed against Markley Lowell data center over noise and generator pollution, separate from the MassDEP… |
Massachusetts state court | environmental | 2026-07-19 | active | |
Minnesota Center for Environmental Advocacy (MCEA) v. City of Pine Island, Minnesota; Ryan Companies US, Inc. Alleges the city's Alternative Urban Areawide Review (AUAR) for the Google-linked Project Skyway data center violated the Minnesota Environmental… |
District Court of Goodhue County, Minnesota, First Judicial District 25-CV-25-2298 |
environmental | 2025-10-16 | TRO granted | |
Hobart, Indiana residents (incl. Soriano, Venegas/Koteles, Joseph Conn per garbled court coverage) v. Hobart city officials; Hobart City Council; Hobart Commission; landowner/Amazon Data Services (referenced) Sought to block a fill permit and earthmoving for a proposed 168-acre Amazon data center site, alleging local-regulation and due-process violations.… |
Lake Superior Court, Indiana | zoning | 2025-12-10 | dismissed | |
Coalition to Protect Prince William County / American Battlefield Trust-aligned groups v. Prince William County Board of Supervisors (and, in a companion posture, the County itself co-litigated against the developer) Challenged the county's rezoning approval for the ~2,100-acre Prince William Digital Gateway data center corridor near Manassas Battlefield.… |
Virginia Circuit Court, Prince William County (with appeal to Court of Appeals of Virginia) | zoning | 2024-01-12 | dismissed | |
Bristow-area residents v. Prince William County / Devlin Technology Park developer Residents sued to block the Devlin Technology Park data center project approval near Bristow, VA. |
Virginia Circuit Court, Prince William County | zoning | 2024-01-01 | active | |
Citizens for Fauquier County v. Town of Warrenton, VA; Amazon Data Services Challenges Warrenton's approval of an Amazon data center, alleging improper zoning board process. Court of Appeals of Virginia sided with the… |
Virginia Circuit Court (Fauquier), with appeal to Court of Appeals of Virginia | zoning | 2023-12-13 | active | |
Louisa County, VA homeowner v. Amazon Data Services Homeowner alleges brown well water, dust, and constant loud noise caused by nearby Amazon data center construction. |
Virginia Circuit Court, Louisa County | environmental | 2026-07-28 | active | |
American Battlefield Trust / Manassas Battlefield preservation coalition v. Prince William County, VA (rezoning approvals) Virginia Court of Appeals blocked approvals covering roughly 37 data centers near Manassas Battlefield, a decision closely tied to the broader… |
Court of Appeals of Virginia | zoning | 2026-04-07 | preliminary injunction | |
Chesterfield County, VA residents/opposition group v. Chesterfield County Board of Supervisors Lawsuit opposing a data center project (linked to Meta-area development) alleges numerous Virginia Freedom of Information Act (Sunshine Law)… |
Virginia Circuit Court, Chesterfield County | civil rights | 2026-04-01 | active | |
Coweta County, Georgia residents v. Project Sail data center developer / Coweta County Residents sue to block the Project Sail data center development in Coweta County, GA. |
Georgia state court (Coweta County) | zoning | 2026-05-11 | active | |
Community groups (Stokes County, NC) v. Stokes County / data center developer Community groups sue over a planned data center in Stokes County, North Carolina. |
North Carolina state court | zoning | 2026-03-13 | active | |
Joliet, IL residents/opposition group v. City of Joliet, Illinois Lawsuit challenges the zoning and approval process for a proposed Joliet, IL data center. |
Illinois state court (Will County) | zoning | 2026-05-26 | active | |
Fort Meade, FL residents v. City of Fort Meade, Florida Residents sue the city to block a hyperscale data center land deal, alleging governance/procedural improprieties. |
Florida state court (Polk County) | civil rights | 2026-06-23 | active | |
Franklin Coalition v. Data center developers (Franklin/Simpson County, KY area) Franklin Coalition sues data center developers challenging the local approval process. |
Kentucky state court | zoning | 2026-04-15 | active | |
Michigan residents (Dowagiac-area data center neighbors) v. Data center operator (unnamed in initial coverage) Residents sue over constant 24/7 noise emitted by a data center, citing health concerns; a related class action was filed in Dowagiac, MI. |
Michigan state court | environmental | 2026-05-29 | active | |
Wisconsin residents v. Microsoft Corporation Residents sue Microsoft over noise caused by a new data center; a related public-records suit sought disclosure of projected water use by… |
Wisconsin state court | environmental | 2026-03-01 | active | |
Southaven, MS-area residents (class action) v. xAI; SpaceX Class action alleges data center 'nuisance' (noise/pollution) from co-located xAI/SpaceX facility in Southaven, Mississippi. |
Federal court (N.D. Mississippi, per Reuters coverage) | environmental | 2026-06-09 | active | |
NAACP (Memphis chapter / national) v. xAI (Colossus / Colossus 2 gas turbines, Memphis, TN) NAACP sued over unpermitted gas turbines at xAI's Memphis Colossus data center under the Clean Air Act. The Trump administration/DOJ moved June 2026… |
Federal court (W.D. Tennessee, per reporting) | environmental | 2025-06-01 | active | |
Sierra Club Wisconsin Chapter; Clean Wisconsin; Port Washington residents v. Wisconsin DNR (air permit for Vantage Data Centers) Environmental groups formally challenge/comment against air quality permits for the Port Washington data center, separate from the broader EIS… |
Wisconsin DNR administrative process / Ozaukee County Circuit Court | environmental | 2026-06-01 | active | |
Environmental groups (Georgia) v. Georgia Environmental Protection Division / Plant Bowen gas turbine operators (data center-linked power) Environmental groups challenge the air permit for gas turbines at Plant Bowen tied to Georgia data center power buildout; separate reporting covers… |
Georgia state administrative/court proceeding | environmental | 2026-03-02 | active | |
Rise St. James; allied environmental groups v. Louisiana Department of Environmental Quality; Meta (Hyperion data center-linked gas power) Challenge to air pollution permitting tied to Meta's Hyperion data center gas-power buildout in Louisiana; judge dismissed the challenge to Meta's… |
Louisiana state court / administrative appeal | environmental | 2026-02-01 | dismissed | |
Earthjustice and allied groups v. Formosa Plastics; Louisiana Department of Environmental Quality Groups sue over Formosa Plastics' permit extensions in Louisiana's industrial corridor, part of the broader wave of air-permit litigation tied to… |
Louisiana state/administrative appeal | environmental | 2026-01-15 | active | |
Data center opposition group v. Missouri city government; proposed data center developer Opposition group sues a Missouri city and the proposed data center developer over project approval. |
Missouri state court | zoning | 2026-04-20 | active | |
New Jersey neighbors (unspecified township) v. Data center operator (unnamed) Neighbors sue over persistent humming noise emitted by a nearby New Jersey data center. |
New Jersey state court | environmental | 2026-04-01 | active | |
Environmental/community groups (North Carolina) v. Amazon; Duke Energy Amazon-Duke Energy diesel backup power plans for an NC data center face legal pushback from environmental and community advocates over permitting. |
North Carolina state administrative/court proceeding | environmental | 2026-08-01 | active | |
Federal Energy Regulatory Commission (Commission-initiated) v. PJM Interconnection; MISO; SPP; CAISO; ISO-NE; NYISO (and associated transmission owners) FERC issued Section 206 show-cause orders directing all six RTOs/ISOs to justify or reform large-load/co-location interconnection rules for data… |
Federal Energy Regulatory Commission (administrative proceeding, not a court) RM26-4-000 |
regulatory | 2026-06-18 | show cause | |
Data center developer v. Chatham County, North Carolina Developer sues Chatham County over its data center moratorium/restrictive ordinance, alleging harm to a planned project. |
North Carolina state court | zoning | 2026-05-01 | active | |
Data center developer v. Hill County, Texas Developer filed a $100M lawsuit against Hill County, Texas after the county rescinded prior data center approvals/incentives amid moratorium activity. |
Texas state court | contract | 2026-06-01 | active | |
Citizens for Fauquier County v. Warrenton, VA Board of Zoning Appeals CFFC's zoning board appeal on the Amazon data center was rejected, which the group alleged occurred illegally, leading to further litigation (see… |
Virginia Circuit Court, Fauquier County | zoning | 2023-08-01 | dismissed | |
Loudoun County, VA homeowners v. Dominion Energy; Virginia State Corporation Commission (as regulator) Homeowners challenged Dominion Energy's data-center-driven transmission line siting; reporting indicates homeowners appear to have lost before the… |
Virginia State Corporation Commission / Virginia courts | zoning | 2026-07-01 | dismissed |
Federal actions
FERC dockets, congressional bills, and executive actions affecting large-load interconnection and data center power.
| Authority | Docket / bill | Title | Date | Status | Sources |
|---|---|---|---|---|---|
| FERC | RM26-4-000 | Show-Cause Orders to PJM, MISO, SPP, CAISO, ISO-NE, and NYISO on Large-Load/Co-Location Interconnection Rules FERC issued Section 206 show-cause orders directing all six RTOs/ISOs (PJM, MISO, SPP, CAISO, ISO-NE, NYISO) to justify or reform their large-load and… |
2026-06-18 | show cause | |
| FERC | EL24-something (Talen-PJM-Amazon Interconnection Service Agreement) | FERC Rejects Interconnection Service Agreement for Talen-Amazon Susquehanna Nuclear Data Center Co-Location FERC rejected a proposed interconnection service agreement that would have allowed Amazon Web Services' data center to draw expanded co-located load directly… |
2024-11-01 | passed | |
| FERC | EL26-63 (PJM co-located load complaint) | Constellation FERC Complaint Seeking PJM Rules for Data Center Co-Located Load Constellation Energy filed a FERC complaint asking for clear PJM tariff rules governing co-located data center load at power plants (following the… |
2025-01-01 | pending | |
| FERC | Related to RM26-4-000 / PJM market monitor filings | PJM Market Monitor: No More Data Centers Unless They Can Be Reliably Served PJM's Independent Market Monitor raised reliability concerns before FERC, arguing no additional data center interconnections should proceed unless reliable… |
2026-07-27 | pending | |
| FERC | ER25-/EL25- PJM co-located generation tariff compliance | FERC Orders PJM to Reform Tariff for Co-Located Generation and Load FERC directed PJM to file tariff revisions establishing clear rules for co-located generation and large-load service, building on the agency's prior 2025… |
2026-01-15 | passed | |
| DOE | DOE directive to FERC re large-load interconnection | DOE Directs FERC to Act on Large-Load Interconnection Rulemaking The Department of Energy directed FERC to act on a large-load interconnection rulemaking affecting data centers, with FERC subsequently committing to June… |
2026-04-01 | passed | |
| DOE | 2026 DOE Section 202(c) Emergency Orders | 2026 DOE Section 202(c) Emergency Grid Orders DOE issued a series of 2026 Federal Power Act Section 202(c) emergency orders addressing grid reliability strain, several tied to regions facing rapid data… |
2026-01-01 | passed | |
| DOE | National Transmission Needs Study (2026 Supplement) | DOE National Transmission Needs Study: Supplemental Material (July 2026) DOE released supplemental material to its National Transmission Needs Study identifying transmission constraints and expansion needs nationally, explicitly… |
2026-07-01 | pending | |
| EPA | EPA AI data center regulatory policy shift | EPA Steps Back from AI Data Center Regulation, Hands Oversight to States/Communities EPA announced it is stepping back from direct regulation of AI data center emissions and infrastructure, deferring to states and local communities to develop… |
2026-06-01 | passed | |
| CEQ | Executive Order 14318 | Executive Order 14318: Accelerating Federal Permitting of Data Center Infrastructure President Trump signed EO 14318 directing federal agencies (via CEQ/NEPA processes) to accelerate permitting for data center infrastructure projects,… |
2025-07-01 | passed | |
| Congress | S.3585 | DATA Act of 2026 Sponsored by Sen. Tom Cotton (R-AR); would amend the Federal Power Act to exempt consumer-regulated (co-op/municipal) electric utilities from federal… |
2026-01-07 | pending | |
| Congress | S.4806 | POWER Up Act Sponsored by Sen. Cynthia Lummis (R-WY); would modernize rules for high-power grid connections, targeting faster and clearer processes for large electricity… |
2026-06-17 | pending | |
| Congress | S.3682 | Power for the People Act of 2026 Sponsored by Sen. Chris Van Hollen (D-MD); would promote creation of data-center-specific load queues and rate classes to mitigate the cost impact of data… |
2026-01-15 | pending | |
| Congress | H.R.8241 | Power for the People Act of 2026 (House companion) House companion to S.3682, promoting data-center-specific rate classes and load queues to protect residential and small-business ratepayers from… |
2026-01-15 | pending | |
| Congress | H.R.8033 | No Harm Data Centers Act Sponsored by Rep. Greg Landsman (D-OH); would ensure American families are protected from the impacts of data centers on the electric grid. Referred to House… |
2026-03-20 | pending | |
| Congress | H.R.9340 | Ratepayer Protection Act Sponsored by Rep. Gabe Evans (R-CO); would amend the Public Utility Regulatory Policies Act of 1978 to establish a federal standard requiring recovery of the… |
2026-06-18 | pending | |
| Congress | S.3852 | GRID Act Sponsored by Sen. Josh Hawley (R-MO); would impose requirements on data centers to ensure prioritization of residential ratepayers over large-load commercial… |
2026-02-11 | pending | |
| Congress | H.R.9825 | Data Center Water and Energy Transparency Act of 2026 Sponsored by Rep. Lauren Underwood (D-IL); would require disclosure/transparency of data center water and energy usage. Referred to House Energy and Commerce… |
2026-07-22 | pending | |
| Congress | S.4214 | Artificial Intelligence Data Center Moratorium Act Sponsored by Sen. Bernie Sanders (I-VT); would impose a federal moratorium on new large AI data center construction/permitting pending further study.… |
2026-03-25 | pending | |
| Congress | H.R.9442 | Artificial Intelligence Infrastructure-related bill (119th Congress) A 119th Congress House bill addressing AI infrastructure siting/permitting; full text available via Congress.gov. Included in the wider 2026 wave of data… |
2026-07-01 | pending | |
| Congress | H.R.8488 | AI Data Center Site Selection Transparency Act of 2026 House bill requiring greater transparency in AI data center site-selection decisions, including disclosure of incentive negotiations and community-impact… |
2026-02-01 | pending | |
| Congress | H.R.8037 | Protect American AI Act of 2026 House bill framed around protecting domestic AI infrastructure development and competitiveness; text available via GovInfo. Part of the broader 119th Congress… |
2026-02-01 | pending | |
| Congress | S.5054 | Data Center Tax Accountability and Disclosure Act of 2026 Senate bill requiring disclosure and accountability around tax incentives granted to data center developers, part of the 2026 legislative wave addressing data… |
2026-07-15 | pending |
Utility actions
Utility and public-utility-commission dockets, tariff filings, and statements creating data center rate classes, cost-allocation rules, and interconnection conditions.
| Utility | State | Docket | Type | Filed | Action | Status | Sources |
|---|---|---|---|---|---|---|---|
Seattle City Light |
WA | tariff | 2026-06-12 | Seattle City Light proposed a New Large Data Center Load Policy creating a new rate class for data centers requesting new or expanded electric service of 10 MVA or more. The policy would require cost-based rates, customer responsibility for infrastructure and related costs, service through a queue… New large data centers would no longer qualify for general service rates and would pay rates reflecting the incremental cost of procuring and delivering power. Developers would be… |
pending | ||
Baltimore Gas and Electric Company (BGE) Exelon Corporation (NYSE: EXC) |
MD | statement | 2025-02-20 | BGE submitted a favorable-with-amendments position statement supporting Maryland House Bill 900, which would require electric companies to submit PSC-approved data-center rate schedules. BGE requested amendments concerning load-ramp periods, risk-mitigation measures such as CIAC payments, letters… Data centers would be subject to specific rate schedules, contract requirements, and financial obligations intended to protect existing utility customers if projected demand is not… |
pending | ||
Maryland electric utilities (statewide - Large Load Tariff Workgroup) |
MD | PC 72 Large Load Tariff Workgroup | tariff | 2026-03-03 | House Bill 1532 proposes lowering the monthly maximum demand threshold for customers required to take service under a new large-load tariff from 100 MW to 25 MW. The proposal includes requirements such as a load ramp period, minimum service term, collateral requirement, and exit fee. Data centers with monthly demand of 25 MW or more would be subject to the proposed large-load tariff requirements, including potential minimum service terms, collateral obligations, and… |
pending | |
Potomac Edison |
MD | RM 93 | tariff | 2026-01-21 | The Maryland Office of People’s Counsel filed comments on the Maryland Public Service Commission’s proposed Large Load Tariff Workgroup regulations under Section 4-212 of the Public Utilities Article. The comments request revisions concerning infrastructure-cost allocation, electric and… The proposed protections would require large-load customers, including data centers, to bear infrastructure buildout costs caused by their interconnection and provide contracts and… |
contested | |
Maryland electric utilities (statewide - HB 1532) |
MD | other | HB 1532 proposes lowering the applicability threshold for Maryland’s large-load tariff from more than 100 MW of monthly maximum demand at a single location to 25 MW. The testimony supports requiring more large-load users, including data centers, to contribute to the costs they create. Data centers with monthly maximum demand of 25 MW or more at a single location would fall under the proposed large-load tariff. This could require them to contribute to grid-related costs… |
pending | |||
Pennsylvania electric distribution companies (statewide model tariff) |
PA | M-2025-3054271 | tariff | 2026-04-30 | The Pennsylvania Public Utility Commission voted 5-0 to adopt a modified final order establishing a model Large Load Tariff Framework for customers exceeding 50 MW individually or 100 MW in aggregate, including data centers. The framework addresses cost responsibility, financial assurances,… Data centers would be responsible for utility upgrades required for interconnection and would need to provide deposits, collateral, or other financial assurances covering infrastructure… |
approved | |
PPL Electric Utilities Corporation |
PA | R-2025-3057164 | rate case | The Pennsylvania Public Utility Commission voted 5-0 to modify and approve a Joint Petition for Settlement resolving PPL Electric’s base rate proceeding. The settlement includes tariff provisions for certain large-load customers, including data centers, with long-term service commitments, minimum… Data centers and other high-demand facilities may be subject to long-term service commitments and minimum demand guarantees. The provisions are intended to align large-load customer costs… |
approved | ||
Duquesne Light Co.; FirstEnergy Pennsylvania; PECO Energy Company; PPL Electric |
PA | M-2025-3054271 | other | 2025-03-27 | The Pennsylvania Public Utility Commission approved convening an en banc hearing to examine interconnection and tariff issues for large-load customers, including data centers. The proceeding is considering financial security, construction-cost contributions, contract terms, study fees and timing,… Data center developers and other large-load customers may face future requirements concerning financial security, construction-cost contributions, minimum contract terms,… |
pending | |
Pennsylvania electric distribution companies (statewide model tariff) |
PA | M-2025-3054271 | other | 2025-11-06 | The Pennsylvania Public Utility Commission issued a Tentative Order proposing a statewide model tariff for connecting large electric customers, including hyperscale data centers, to the grid and allocating related costs. The PUC voted 3-2 to advance the review and adopted the Tentative Order. Data-center customers would be expected to contribute toward interconnection and related system costs, provide tiered collateral, and accept minimum contract terms. The proposal is… |
pending | |
Each electric public utility in New Jersey |
NJ | tariff | A796 would require each New Jersey electric public utility to file an application with the Board of Public Utilities within 180 days to establish a tariff for serving large load data centers. The tariff must protect non-data-center ratepayers from costs caused by data-center demand and incentivize… Beginning one year after the act takes effect, the tariff would apply to every qualifying large load data center in a utility’s service area. The BPU could establish rates and conditions… |
pending | |||
New Jersey electric public utilities (statewide - A2770) |
NJ | tariff | Assembly Bill A2770 would require electric public utilities serving large load data centers to file updated tariffs with the New Jersey Board of Public Utilities, including a surcharge during periods of peak electrical-grid demand. Surcharge revenues would be deposited into a newly established… Large load data centers with actual or projected monthly demand of at least 50 megawatts would be subject to a Board-approved peak-demand surcharge. The surcharge revenues would fund… |
pending | |||
Alliant Energy |
WI | 6680-TE-115 | special contract | 2025-04 | Alliant Energy filed an application in April 2025 for approval of an Electric Service Agreement under its existing Individual Contract Rate Tariff to serve a data center in Beaver Dam. On May 7, 2026, the Public Service Commission of Wisconsin approved the agreement with modifications, including… The Beaver Dam data center must operate under the modified Electric Service Agreement, including enhanced termination charges, reporting and financial safeguards, and contributions to… |
approved | |
We Energies |
WI | 6630-TE-113 | tariff | 2025-03 | We Energies filed an application in March 2025 seeking approval of Very Large Customer and Bespoke Resources Tariffs for large data center customers. On April 24, 2026, the Public Service Commission of Wisconsin modified and approved the tariffs, including a 15-year minimum initial term, a 100 MW… Data centers covered by the Very Large Customer tariff must pay 100% of their costs under the approved Full-Benefits resource model. The tariff applies to customers with an energy demand… |
approved | |
Xcel Energy |
MN | 25-289 | tariff | The Commission defined “very large customers” for Xcel Energy’s tariffs as new loads of 100 MW or greater. The class also includes new customers with loads of at least 20 MW but less than 100 MW if they are system intensive and require significant system modifications or other expenditures before… Data center developers with loads of 100 MW or more, or with loads between 20 MW and less than 100 MW that are system intensive, would fall within this very large customer tariff class.… |
approved | ||
Evergy Metro, Inc. d/b/a Evergy Missouri Metro and Evergy Missouri West, Inc. d/b/a Evergy Missouri West |
MO | EO-2025-0154 | tariff | 2025-10-29 | Evergy sought approval of new and modified tariffs for large-load customers, including customers with annual peak demand of at least 100 MW, through a proposed Large Load Power Service tariff. The Data Center Coalition requested approval of a non-unanimous stipulation and rejection of the Missouri… The proposed stipulation would provide large-load customers with a 12-year contract term, an optional five-year load ramp, an 80% minimum billing demand, collateral requirements, exit… |
contested | |
Ohio Power Company |
OH | 24-508-EL-ATA | tariff | 2025-07-09 | The Commission approved, by a 5-0 vote, a proposed opinion and order concerning Ohio Power Company. The order addresses central Ohio’s rapid data center growth while seeking to protect ratepayers from increased system-load and potential stranded costs. The order supports new economic development associated with data center growth, while emphasizing reliability, price stability, dependable electric service, least-cost planning, and… |
approved | |
Union Electric Company d/b/a Ameren Missouri Ameren Corporation (NYSE: AEE) |
MO | ER-2026-0291 | rate case | 2026-06-26 | Ameren Missouri filed a general rate increase request seeking approximately $343 million in additional annual electric base-rate revenues. The filing proposes a new 14(M) Large Load Customer Service classification under the Powering Missouri Growth Plan. New data centers would receive no electric-rate discounts and would be required to pay 100% of grid-connection infrastructure costs upfront. Ameren Missouri states that commitments from… |
pending | |
Union Electric Company d/b/a Ameren Missouri |
MO | ET-2025-0184 | tariff | 2025-05-14 | Ameren Missouri proposed a Large Load Customer Rate Plan, including modifications to its Large Primary Service tariff, four new tariff riders, and changes to the Fuel Adjustment Clause. The proposed subclass would apply to customers with expected or actual demand of at least 100 MW taking… Data centers meeting the 100 MW demand and above-115-kV transmission-service thresholds would be eligible for the proposed subclass and revised tariff structure. The proposal includes… |
contested | |
Consumers Energy |
MI | Case No. U-21859 | tariff | 2025-02 | The Michigan Public Service Commission approved Consumers Energy’s application to amend its Rate GPD tariff by establishing terms and conditions for data centers and other similarly energy-intensive, very large electric customers. The tariff applies to customers with a minimum service threshold of 100 MW, including aggregated loads consisting of individual sites of at least 20 MW with the same common owner. Covered… |
approved | |
DTE Electric Co. |
MI | Case No. U-21990 | special contract | 2025-12-18 | The Michigan Public Service Commission conditionally approved DTE Electric Co.’s application for special contracts to supply power to a 1,383-megawatt data center in Saline Township, Washtenaw County. The approval requires DTE to bear unrecovered costs and prioritize reducing or interrupting the… The contracts require a minimum 19-year term, minimum billing demand equal to 80% of contracted electricity use, and a termination payment of up to 10 years of minimum billing demand if… |
approved | |
Kentucky Power Company |
KY | Case No. 2022-00387 | special contract | 2023-08-28 | The Kentucky Public Service Commission rejected a proposed special contract between Kentucky Power Company and Ebon International, LLC, a cryptocurrency project, because the contract did not properly protect customers from power costs. Special contracts for cryptocurrency or other large-load facilities may be denied unless they adequately protect utility customers from the facilities’ power costs. |
denied | |
New York investor-owned utilities (statewide large-load proceeding) |
NY | Case 26-E-0045 | other | 2026-05-13 | The City of New York filed initial comments in the New York Public Service Commission proceeding on large-load interconnection reforms. The comments recommended financial and reporting requirements, binding load forecasts, development milestones, financial security and withdrawal penalties,… Data centers and similar large loads may need to demonstrate project readiness through permits, financing, site control, design plans, or construction and materials contracts before… |
pending | |
New York investor-owned utilities (Energize NY Development initiative) |
NY | tariff | The New York State Public Service Commission instituted a proceeding to advance Governor Hochul’s Energize NY Development initiative. The proceeding will review interconnection processes, cost-allocation mechanisms, and tariff structures for integrating large loads into New York’s transmission and… Data centers and other large energy users may face revised interconnection rules, cost-allocation structures, and tariffs, potentially requiring them to pay for grid upgrades and other… |
pending | |||
Virginia Electric & Power Co. |
VA | PUR-2025-00058 | tariff | 2025-11-25 | The Virginia State Corporation Commission approved a dedicated rate class for customers with demands of 25 MW or greater in Application of Va. Elec. & Power Co., Case No. PUR-2025-00058. Data center and other large-load customers with demands of 25 MW or greater may be placed in a dedicated rate class. The specific rates, charges, and interconnection requirements were not… |
approved | |
Central Hudson Gas & Electric Corporation; Consolidated Edison Company of New York, Inc.; New York State Electric & Gas Corporation; Niagara Mohawk Power Corporation d/b/a National Grid; Orange & Rockland Utilities, Inc.; Rochester Gas and Electric Corporation |
NY | Case No. 26-E-0045 | other | 2026-06-15 | The Joint Utilities filed reply comments addressing planning, interconnection, and cost-allocation frameworks for large electric loads. They supported standardized tariff terms, beneficiary-pays cost allocation, meaningful financial commitments, NYISO-led coordination, and forecasting that… Data-center developers may face standardized interconnection and tariff requirements, financial commitments such as collateral or minimum bills, long-term contracts, exit fees,… |
pending | |
Niagara Mohawk Power Corporation d/b/a National Grid |
NY | Case 26-E-0045 | other | 2026-05-13 | National Grid filed comments with the New York Public Service Commission in response to the February 12, 2026 Order Instituting Proceeding and Soliciting Comments in Case 26-E-0045. The comments propose reforms for large-load interconnection and cost allocation, including upfront customer funding,… Data center developers could benefit from more predictable interconnection planning, standardized designs, digital application tools, and potentially faster connections through… |
pending | |
National Grid Ventures |
NY | Case 26-E-0045 | tariff | 2026-05-13 | National Grid Ventures filed comments in Case 26-E-0045 regarding interconnection reforms for large loads. The comments propose stricter requirements, including demand ratchets, long-term contract commitments, collateral, dedicated rate classes, cost responsibility for sole-use upgrades,… Data centers and similar large-load facilities could be required to provide collateral, sign long-term contracts, pay minimum bills based on contract demand, fund sole-use interconnection… |
pending | |
Consolidated Edison Company of New York, Inc. (Con Edison) and Orange and Rockland Utilities, Inc. (O&R) |
NY | Case No. 26-E-0045 | other | 2026-05-13 | Con Edison and O&R filed comments responding to the New York Public Service Commission’s request for comments on a regulatory framework for large-load customers and interconnection reforms. They proposed measures including large-load deposits, withdrawal or modification fees, minimum billing or… Data center developers could face more detailed load-forecasting requirements, deposits, minimum billing or fixed charges, and enhanced financial-security obligations. They may also be… |
pending | |
New York Power Authority (NYPA) |
NY | Case 26-E-0045 | other | 2026-05-13 | NYPA submitted comments to the New York Public Service Commission on large-load interconnection. It recommended standardized requirements, realistic study assumptions, beneficiary-pays cost allocation, collateral and project-development commitments, enhanced modeling, cluster studies, grid… Large data-center loads seeking interconnection could face clearer size thresholds, detailed load-characteristic reporting, operational requirements, project milestones, deposits,… |
pending | |
Duke Energy Carolinas, LLC |
NC | tariff | Duke Energy Carolinas offers an optional High Load Factor tariff for large customers with a minimum contract demand of 1 MW, a one-year contract term, and minimum billing demand equal to 75% of contract capacity. Its service regulations authorize performance and credit provisions for customers… Data centers and other large high-load-factor customers may use the tariff, but it does not include financial-assurance or contribution provisions. The tariff includes an early termination… |
approved | |||
Duke Energy |
NC | statement | 2026-07-23 | Duke Energy joined the federal administration’s Ratepayer Protection Pledge. North Carolina officials are urging Duke Energy to make the pledge’s commitments legally binding before the North Carolina Utilities Commission, including separate rate structures and customer responsibility for… Data centers and other large-load customers would be expected to pay for the generation, electricity, and power-delivery infrastructure needed to serve them, including resources they… |
contested | ||
Georgia Power |
GA | 55378 | tariff | 2025-01-23 | The Georgia Public Service Commission unanimously approved a new Georgia Power rule for customers using more than 100 megawatts. The rule allows recovery of site-specific and upstream generation, transmission, and distribution costs, permits contracts of up to 15 years, establishes minimum billing… Data centers exceeding 100 MW may be required to pay costs for electricity acquisition and infrastructure built specifically for their needs. They may also face longer contract terms,… |
approved | |
Georgia Power |
GA | rate case | 2025-12-19 | The Georgia Public Service Commission approved an agreement between its Public Interest Advocacy Staff and Georgia Power certifying construction of 9,985 MW of new energy generation, approximately 80% of which is expected to serve data centers. Georgia Power agreed to financially backstop… Data centers are expected to account for approximately 80% of the approved new generation. Georgia Power must absorb associated costs through 2031 if projected data-center contracts do not… |
approved | ||
Georgia Power Company |
GA | 55378 | other | 2024-11-18 | Georgia Power Company filed a Large Load Economic Development Report for Q3 2024 PD in parent docket 55378. The filing does not state a specific impact on data-center developers or operators, including impacts related to large-load tariffs, interconnection, cost allocation, or data-center… |
pending | |
Virginia Electric and Power Company (VEPCO) Dominion Energy |
VA | IRP | Dominion’s 2024 Integrated Resource Plan highlighted a modeled VCEA-compliance case with no new gas and no fossil-fuel retirements by 2045. Dominion stated that the case was infeasible because of the unrealistic amount of imports and renewable construction required, creating reliability concerns. Dominion forecast data-center peak demand reaching 9 GW within the next 10 years, contributing to a 25% increase above current total system peak. This growth creates concerns about the… |
contested | |||
Kentucky Utilities Company and Louisville Gas and Electric Company |
KY | Case No. 2025-00045 | tariff | 2025-09-17 | The Companies filed a post-hearing reply brief requesting approval without modification of a stipulation supporting generation resources including the Brown 12 and Mill Creek 6 natural-gas combined-cycle units. The filing addressed a forecast including 1,750 MW of data-center load by 2031 and… Approval would allow the Companies to advance generation resources intended to serve projected data-center and other large-load growth, subject to Commission oversight and prudence review.… |
contested | |
Liberty Utilities |
MO | tariff | 2025 | Liberty Utilities’ large-load tariff case is currently in progress. The tariff is required under Senate Bill 4 to reflect large-load customers’ share of costs and prevent other customers from being charged unjust or unreasonable costs associated with serving them. Data centers served by Liberty Utilities would be subject to large-load rates intended to make them pay their share of costs. The provisions are designed to protect residential and… |
pending | ||
Public Service Company of Oklahoma (PSO) |
OK | 124090 | complaint | 2026-05-22 | Rep. Tom Gann appealed the Oklahoma Corporation Commission’s preapproval of approximately $1.3 billion in new PSO generation and storage capacity intended in part to serve proposed large-load customers, including data centers in eastern Oklahoma. AARP and the Oklahoma Industrial Energy Consumers… The preapproval could allow PSO to develop generation and storage capacity for proposed eastern Oklahoma data centers. The appeal challenges whether residential customers could bear costs… |
contested | |
Oklahoma investor-owned utilities (statewide - Data Center Customer Ratepayer Protection Act) |
OK | tariff | The Oklahoma Corporation Commission regulates qualifying “Large Load Customers” under the Data Center Customer Ratepayer Protection Act of 2026, codified at 17 O.S. §§ 900, 906. The act applies to new data centers, cryptocurrency mining operations, and artificial-intelligence computing facilities… Data center and other qualifying large-load developers adding 75 megawatts or more must comply with the act. Certain land purchasers must provide certified-mail notice to the Oklahoma… |
pending | |||
ERCOT transmission/distribution utilities (statewide PURA §37.0561 rulemaking) |
TX | Project No. 58481 | other | 2025-07-31 | The Public Utility Commission of Texas opened a rulemaking to implement large-load interconnection standards under PURA §37.0561. The proceeding addresses interconnection processes, agreements, fees, security postings, planning-guide revisions, batch studies, and related cost and reliability issues. The proposed standards would affect how large loads, including data centers, interconnect and obtain service in Texas, including requirements for studies, security postings, and related… |
pending | |
El Paso Electric |
TX | rate case | El Paso Electric is seeking Public Utility Commission of Texas approval to amend its existing Economic Development Rate for data centers. The El Paso City Council authorized intervention, including retaining legal counsel and technical experts, to evaluate whether the proposed changes comply with… The proposed changes would establish or modify the rate structure applicable to data centers and other large-load customers. The City will advocate for protections to prevent costs… |
pending | |||
Austin Energy |
TX | tariff | 2025-12-23 | The City’s memorandum describes Austin Energy’s implementation of Texas Senate Bill 6 for data centers and other large loads. Loads exceeding 75 MW require a full interconnection study, must fund identified interconnection and transmission upgrades, and may be subject to remote curtailment… Data centers requesting more than 75 MW must complete a full interconnection study and cannot bring their entire load online until required system upgrades are completed. Projects may also… |
approved | ||
Austin Energy |
TX | other | 2025-10-07 | At an Austin Energy Utility Oversight Committee meeting, Interim General Manager Stewart Riley presented an overview of ERCOT large-load growth and Austin Energy’s challenges in serving large customers, including data centers and industrial facilities. The discussion addressed capacity… Data-center developers may face transmission and generation capacity constraints, with infrastructure and equipment deployment potentially taking approximately 3, 5 years while customers… |
pending | ||
Pacific Gas and Electric Company (PG&E); Southern California Edison Company (SCE); San Diego Gas & Electric Company (SDG&E); Bear Valley Electric Service, Inc.; Liberty Utilities (CalPeco Electric) LLC; PacifiCorp |
CA | Rulemaking 26-04-xxx | other | 2026-04 | The California Public Utilities Commission proposed instituting a rulemaking on California Advanced Electric Rate Design. The proceeding will consider rate designs and tariffs for data centers and other large-load customers, including measures to prevent stranded costs and cost shifting and to… Data-center developers may face new or revised tariffs, service terms, demand charges, and cost-allocation requirements. The proceeding may also establish rate signals for large-load… |
pending | |
Southern California Edison Company (U 338-E) |
CA | Application 24-06-014; Application 24-12-008 | tariff | 2024-06-26 | Southern California Edison Company filed an application for approval of a Large Power Dynamic Pricing Rate and a consolidated application for approval of Marginal Cost-Based Dynamic Pricing Rates in compliance with Decision 22-10-022 and Load Management Standards. The filing does not specifically mention data centers or identify impacts on data-center developers or operators. It concerns dynamic pricing rates for large-power and marginal-cost-based… |
pending | |
Arizona Public Service Company (APS); Salt River Project (SRP); Tucson Electric Power (TEP)/Unisource Electric (UNS) |
AZ | E-00000A-25-0069 | other | 2026-04-16 | At an Arizona Corporation Commission workshop, APS, SRP, and TEP/UNS reported on prospective large-load and data-center demand, queue processes, and capacity constraints. Proposed policies included an extra high load factor rate, “bring your own power” requirements, and standard contracts… Data-center developers may face utility queue screening, eligibility requirements for large-load rates, direct responsibility for new generation and infrastructure costs, and up-front… |
pending | |
Tucson Electric Power (TEP); Salt River Project (SRP); Arizona Public Service (APS) |
AZ | E-00000A-25-0069 | tariff | 2026-04-16 | The Arizona Corporation Commission hosted a Large Load Users Development Workshop addressing the integration of data centers and other large load customers into the electric grid. The workshop discussed utility-specific extra-high-load tariffs and energy service agreements, including direct… Data centers and other large load users are expected to pay the costs they cause so existing ratepayers do not bear them. Potential protections include longer contract terms, minimum… |
pending | |
Arizona Public Service Company (APS) |
AZ | rate case | The APS rate case addressed proposed changes to the Extra High Load Factor tariff for large-load users, including manufacturing companies and data centers, and APS’s request to implement a Formula Rate Adjustment Mechanism (FRAM). The Administrative Law Judge is expected to issue a Recommended… Changes to the Extra High Load Factor could alter rate treatment for data centers and other large-load users. FRAM authorization could affect how APS rates are adjusted, but the specific… |
pending | |||
Tucson Electric Power Company (TEP) |
AZ | E-01933A-25-0187 | special contract | 2025-12-03 | The Arizona Corporation Commission voted 4-1 to approve a 10-year Energy Supply Agreement, also described as a Special Contract, between TEP and Humphrey’s Peak Power LLC for a planned data center campus in Pima County. The agreement includes minimum monthly billing, an 18-month gradual load… The agreement requires minimum billing payments and termination fees and makes the developer financially responsible for infrastructure serving the data center campus. These provisions are… |
approved | |
Tri-State G&T |
WY | tariff | 2026-03-26 | Tri-State refiled its High Impact Load Tariff with FERC on March 26, 2026, after an initial rejection in October 2025 without prejudice. The tariff establishes a process for evaluating and integrating loads greater than 45 MW, or loads expected to exceed 45 MW within four years, and includes a… Data centers exceeding 45 MW, or expected to reach that level within four years, may use the tariff process for grid integration. The tariff includes evaluation fees and a security deposit… |
pending | ||
PPL Electric Utilities PPL Corp. |
PA | M-2025-3054271 | tariff | 2025-05 | The Pennsylvania Public Utility Commission voted 3-2 to propose a statewide model tariff that electricity providers can adopt for large-load customers, including data centers. The proposal includes cost-causation measures, infrastructure contributions, collateral requirements, minimum contract… Data center developers would receive clearer interconnection rules and rates but may have to contribute toward infrastructure and low-income customer-support programs, provide tiered… |
pending | |
AEP Ohio |
OH | tariff | 2025-07 | The Public Utilities Commission of Ohio approved AEP Ohio’s data center tariff. The tariff generally requires large new data centers to pay for at least 85% of reserved capacity for 12 years, provide proof of financial viability, and potentially pay an exit fee equal to 36 months of minimum charges. A data center reserving 100 megawatts but using 65 megawatts would still be billed for at least 85 megawatts. Developers must make long-term financial commitments and bear more of the… |
approved | ||
ERCOT |
TX | Project No. 54445 | tariff | 2025-05-15 | The PUCT approved ERCOT-sponsored NPRR1234, establishing interconnection, modeling, visibility, study, and Subsynchronous Oscillation requirements for Large Loads and certain other load additions. Large Loads are defined as one or more facilities at a single site with aggregate peak demand of 75… Data center developers with large loads may face new ERCOT interconnection, modeling, study, visibility, and Subsynchronous Oscillation requirements, particularly for sites with aggregate… |
approved | |
Sacramento Municipal Utility District (SMUD) |
CA | statement | SMUD is developing a policy for customers with electrical loads of 50 megawatts or more. The policy would establish processes for extending service, evaluating transmission costs and grid impacts, and assigning related costs to large customers to protect existing customers from cost shifts. Data center projects requesting 50 MW or more will undergo transmission studies before moving forward, and proposed locations will be evaluated based on available capacity and grid… |
pending | |||
Sacramento Municipal Utility District (SMUD) |
CA | other | 2026-06-17 | SMUD began a Board discussion on policies for large loads of 50 MW or higher, including pricing, commodity and renewable-energy costs, infrastructure-cost recovery, financial security, environmental costs, and risk mitigation. SMUD presented potential pathways involving Board policy, rate… Data-center developers with loads of 50 MW or higher may be subject to future customized pricing, infrastructure-cost recovery, minimum contract terms or billing demands, exit fees,… |
pending | ||
Grant County Public Utility District |
WA | other | 2025 | Grant County Public Utility District will implement limits on the growth of electricity demand from data centers receiving power from the utility. Similar limits may apply to other large industrial customers because anticipated demand could exceed the electrical distribution and transmission… Data centers may continue current operations and grow up to their assigned load limits; the utility is not asking customers to curtail or reduce existing load. The utility anticipates… |
pending | ||
Interstate Power and Light Company |
IA | tariff | 2024-09-20 | Interstate Power and Light Company issued Rider ICR, Individual Customer Rate, effective October 1, 2024. The tariff establishes eligibility requirements, negotiated or marginal-cost-based demand and energy pricing, curtailment obligations, excess-facilities charges, service-agreement filing… Data-center developers with projected or expanding demand of at least 25,000 kW may qualify for an individual service agreement if they meet the tariff’s requirements. Eligible customers… |
approved | ||
Xcel Energy |
WI | tariff | 2026-06-22 | Xcel Energy filed a proposal with the Public Service Commission of Wisconsin to establish a Large Load Tariff for new customers or significant load expansions of 100 MW or greater, including potential new data centers. The proposal would require these customers to pay all costs needed to serve… New data centers of 100 MW or greater would be required to bear the full cost of necessary service infrastructure, preventing costs from being shifted to other customers if approved as… |
pending | ||
Indiana Michigan Power (I&M) American Electric Power (AEP) |
IN | tariff | The Indiana Utility Regulatory Commission approved a joint settlement concerning I&M’s large load tariff, with one modification. The terms require new large load customers, including data centers, to make long-term financial commitments proportional to their size, and require IURC review before… Data center developers and other new large load customers must make long-term financial commitments intended to ensure that service costs are recovered from them rather than existing… |
approved | |||
DTE Energy |
MI | special contract | DTE states that it has two data-center contracts, one approved and one pending approval by the Michigan Public Service Commission. The contracts require data centers to cover new costs needed to serve them, including renewable energy and battery storage costs. Data centers in DTE’s service territory are represented as not increasing existing customers’ rates. Developers are expected to pay for new energy resources and other costs required to… |
pending | |||
Alabama Power |
AL | statement | Alabama Power states that data centers and other large-load customers must pay the full cost of serving their energy needs, undergo engineering and planning studies before service begins, and enter agreements that may include minimum bills and minimum-term provisions. The Alabama Public Service… Data-center developers are responsible for dedicated facilities, delivery upgrades, and customer-specific capacity costs, which are not shifted to existing customers. Developers must… |
pending | |||
Entergy Louisiana, LLC |
LA | U-36959 | tariff | Entergy Louisiana, LLC issued the First Revised Large Load, High Load Factor Power Service Rate Schedule LLHLFPS-L, effective August 30, 2024, superseding the version effective October 17, 2019. Data center developers seeking service under this schedule must contract for at least 70 MW of firm load, maintain at least an 80% average monthly electric load factor, and take… |
approved | ||
Entergy Louisiana, LLC |
LA | tariff | 2025-04-04 | Entergy Louisiana, LLC’s Second Revised Large Power High Load Factor Service Rate Schedule LPHLF-G became effective on April 4, 2025. It superseded the version effective August 30, 2024, and was authorized by a Staff Acceptance Letter dated April 4, 2025. The tariff is available to customers contracting for at least 200,000 kW, subject to adequate-capacity facilities and suitable phase and voltage. Charges include a $1,665,947 monthly… |
approved | ||
Entergy Mississippi; Entergy Arkansas; Entergy Louisiana Entergy (NYSE: ETR) |
AR | statement | Entergy stated that agreements with data center customers are expected to deliver approximately $5 billion in savings over 20 years for customers in Arkansas, Louisiana, and Mississippi. The agreements received regulatory approval, acknowledgement, or oversight from the relevant state public… Data center customers must pay incremental costs, existing-grid costs, and other costs required to serve their facilities, while meeting contract, credit, resource-adequacy, and… |
approved | |||
Portland General Electric (PGE) |
OR | UM2377 | tariff | 2026-06 | PGE filed new rates under docket UM2377 to implement Oregon’s POWER Act. The Oregon Public Utility Commission approved a new data center rate schedule on July 7, 2026, with updated rates effective July 8, 2026. Large-load data center customers receive a 29% rate increase under the new schedule. The framework allocates growth-related infrastructure costs to data center customers through a “growth… |
approved | |
Nevada Power Company dba NV Energy |
NV | Docket Nos. 23-02010 and 23-02011 | tariff | 2024-09-20 | NV Energy’s Schedule No. LCMPE establishes the Large Customer Market Price Energy tariff for non-Residential Service Customers with an average annual hourly load of 10 megawatts or more. The tariff requires Commission approval of Energy Supply Agreements addressing cost allocation, reliability,… A data-center load may qualify if it is a non-Residential Service Customer with an average annual hourly load of at least 10 megawatts and meets the other eligibility requirements. The… |
approved | |
Arizona Public Service Company (APS) |
AZ | Decision No. 79293; A.C.C. No. 6067 | tariff | 2024-03-08 | Arizona Public Service Company’s Rate Schedule XHLF, General Service Extra High Load Factor, became effective under Decision No. 79293. The tariff applies to customers with monthly maximum demand of at least 5,000 kW and a qualifying 92% or higher load factor, with additional requirements for… Large-load data-center developers may qualify for XHLF service if they meet the demand, load-factor, carbon-free activity, and other requirements and execute an Electric Supply Agreement.… |
approved | |
Arizona Public Service (APS) |
AZ | E-01345A-25-0105 | rate case | 2025-06 | APS filed a rate-case request with the Arizona Corporation Commission proposing an increase of more than 45% for extra-large energy users, including data centers. APS also proposed annual formula-rate reviews to assign data-center growth costs to those customers. Data centers and other extra-large energy users would face proposed rates intended to cover their costs of service. Annual formula-rate reviews could result in future rate increases or… |
pending | |
Delmarva Power & Light Company |
DE | Docket No. 25-0826 | tariff | 2025-09-03 | The Delaware Public Service Commission opened a docket to establish a large-load tariff for customers with monthly maximum demand of 25 MW or greater. Commission Staff must conduct stakeholder workshops, after which DPL must file revised tariff pages before interconnecting any new qualifying… Prospective data centers and other large-load customers in DPL’s service territory forecasting or planning for monthly maximum demand of 25 MW or greater must comply with the revised… |
pending | |
Delmarva Power & Light |
DE | tariff | 2025-09-03 | The Delaware Division of the Public Advocate and Delaware Public Service Commission Staff petitioned the Commission to establish a large load tariff requiring facilities such as data centers to pay their share of energy infrastructure costs. The Commission opened a docket and paused… New large load facilities, including data centers, cannot interconnect in Delmarva territory while the tariff is being developed. The tariff is intended to require such facilities to pay… |
pending | ||
Mon Power; Potomac Edison FirstEnergy Corp. (NYSE: FE) |
WV | IRP | 2025-10-01 | Mon Power and Potomac Edison submitted an Integrated Resource Plan to the Public Service Commission of West Virginia covering how they will provide reliable, cost-effective power over the next decade. The preferred plan includes keeping the Fort Martin and Harrison power stations operational,… The IRP identifies data centers and advanced manufacturing as drivers of growing electricity demand in West Virginia. Proposed new dispatchable generation would help meet rising demand,… |
pending | ||
Evergy Kansas Central, Inc.; Evergy Kansas South, Inc.; and Evergy Metro, Inc. d/b/a Evergy Kansas Metro |
KS | 25-EKME-315-TAR | tariff | 2025-02-11 | Evergy filed an application seeking approval of a Large Load Power Service (LLPS) rate plan and associated tariffs for customers seeking to interconnect at loads over 100 MW. The Kansas Corporation Commission approved the unanimous settlement agreement and LLPS tariff provisions, including annual… Data-center developers seeking to interconnect at loads over 100 MW may use the approved LLPS rate offering. The provisions require a minimum term of five years of an optional transitional… |
approved | |
Evergy Kansas Metro, Inc.; Evergy Kansas South, Inc.; Evergy Kansas Central, Inc. |
KS | 25-EKME-315-TAR | tariff | 2025-02-11 | The Evergy Kansas operating companies filed an application seeking approval of a Large Load Service Rate Plan and associated tariffs. The filing proposes a large-load service rate plan that could apply to data centers, but the record does not specifically identify data centers, developers, or the plan's particular impact… |
pending | |
Alabama Power |
AL | special contract | A generic proceeding is being established to create a process for considering electric-service contracts between Alabama Power and large-load data center customers. The proceeding concerns how Alabama Power may consider electric-service contracts for large-load data center customers. Specific impacts on rates, interconnection, cost allocation, or… |
pending | |||
Cleco Power LLC Cleco Corporate Holdings LLC |
LA | rate case | 2026-06-22 | Cleco Power is seeking a $102.8 million revenue-requirement increase and a new 2027 Formula Rate Plan. It also intends to file a Data Center Application seeking approval of an electric service agreement and related credit support with Applied Digital Corporation, bridge capacity, a new… The proposed project would add 430 MW of new electric load in Rapides Parish and is expected to begin service in mid-2027, subject to regulatory approvals. Cleco states that the load could… |
pending | ||
Pacific Gas and Electric Company (PG&E) |
CA | A.24-11-007 | tariff | 2024-11-21 | PG&E filed an application with the California Public Utilities Commission to establish Electric Rule 30, a streamlined approach for energizing new transmission-level retail customers. The proposal would require large-load customers to fund initial interconnection facilities and costs, with refunds… Data center developers seeking transmission-level service would generally need to pay interconnection costs upfront, with potential refunds tied to revenues generated by their load. The… |
contested | |
Idaho Power Company |
ID | IPC-E-26-07 | other | Idaho Power Company filed a petition to evaluate its class cost-of-service methodology, consider alternative class cost-of-service studies, and determine cost-of-service considerations for new large-load customers. The proceeding addresses cost-of-service considerations for new large-load customers, which may include data centers. No specific data-center tariff, rates, interconnection treatment,… |
pending | ||
Tucson Electric Power (TEP) |
AZ | special contract | 2025-12 | The Arizona Corporation Commission approved TEP’s energy supply agreement for the first phase of a potential data center development southeast of Tucson. The agreement provides up to 286 megawatts, includes a gradual ramp-up, and requires separate agreements and regulatory review for future phases. The first phase can be served using TEP’s existing energy portfolio and solar and battery storage projects under development without affecting reliability for other customers. The data… |
approved | ||
Tucson Electric Power (TEP) UNS Energy |
AZ | special contract | TEP submitted an energy supply agreement for Arizona Corporation Commission review to serve the potential data center previously known as Project Blue. The agreement would use an Arizona Corporation Commission-approved large-customer tariff, minimum monthly billing for reserved capacity, and… The data center would pay TEP’s full cost of service, remain responsible for reserved capacity even if energy use falls below contracted levels, and fund infrastructure needed for its… |
pending | |||
Tri-State Generation and Transmission Association |
CO | tariff | 2025-08-28 | Tri-State Generation and Transmission Association filed a proposed High Impact Load Tariff and Agreement with the Federal Energy Regulatory Commission. The proposal would establish a process for adding high-impact loads exceeding 45 MW, including data centers, with security payments, minimum… Data-center developers seeking service from Tri-State members would face the proposed high-impact-load process if their projects exceed 45 MW or are forecast to do so within four years.… |
pending | ||
Chelan PUD |
WA | other | Chelan PUD states that it evaluates requests from power-intensive industries, including data centers, under established policies, engineering requirements, and rate structures. It is not considering a data-center growth moratorium at this time. Data centers must secure and pay for the electricity they need before Chelan PUD will serve them. Large-load customers generally pay for studies, equipment, and system upgrades required… |
pending | |||
Duquesne Light Co. |
PA | tariff | Duquesne Light told the Pennsylvania Public Utility Commission that large-load developers should pay the costs of studies and infrastructure investments that provide no benefit to other customers. It also recommended that large-load customers generate their own power to reduce impacts on existing… Data center developers may be required to bear study and infrastructure costs that benefit no other customers and may face pressure to provide their own generation. |
pending | |||
PSEG |
NJ | statement | PSEG reported that large-load interconnection requests had increased 47% since Q1 to 9.4 GW, with more than 90% related to data centers, and said it expects only 10, 20% of requests to come online. A proposed New Jersey bill would require electric utilities to develop a special rate structure and… Certain new data centers could be subject to special utility rules and a dedicated rate structure intended to prevent non-data-center customers from bearing increased costs. The 9.4 GW… |
pending | |||
Wisconsin Electric Power Co. and Wisconsin Gas LLC (We Energies) WEC Energy Group Inc. (NYSE: WEC) |
WI | 5-UR-112 | rate case | We Energies filed a rate request with the Public Service Commission of Wisconsin that includes a Customer Protection Plan requiring data centers to pay nearly $1.9 billion in 2027 and 2028 toward the infrastructure, equipment, and energy needed to serve them. The filing states that these… Data centers are expected to pay their allocated infrastructure, equipment, and energy costs associated with service in 2027 and 2028, protecting other We Energies customers from those… |
pending | ||
We Energies |
WI | tariff | The Public Service Commission of Wisconsin unanimously approved a special rate plan governing how data center-scale customers in We Energies’ service territory pay for electricity and infrastructure built to serve their demand. The PSC modified the proposal by extending required agreements from 10… Qualifying data center customers must sign 15-year agreements with We Energies and pay costs associated with serving their demand. They must fund and subscribe to portions of multiple new… |
approved | |||
We Energies (WEPCO) |
WI | 6630-TE-113 | tariff | 2026-04-24 | The Public Service Commission issued a preliminary decision on We Energies’ proposed Very Large Customer rate structure, finding that the proposed tariff did not sufficiently protect households and other businesses from increased utility bills and taking action to address those deficiencies. The decision is intended to ensure that data centers and the utilities serving them pay the full costs of the energy and infrastructure they require, rather than shifting those costs to… |
pending | |
Madison Gas and Electric |
WI | tariff | MGE filed an application with the Wisconsin Public Service Commission proposing a Very Large Customer rate for new electric customers with demand of 100 MW or greater. MGE also proposed a Bespoke Resources Tariff allowing very large customers to receive service from dedicated energy resources and… Data centers with demand of 100 MW or greater could be served under the proposed Very Large Customer rate, with customers responsible for incremental energy, transmission, market,… |
pending | |||
Evergy Kansas / Evergy’s Kansas utilities |
KS | tariff | The Kansas Corporation Commission approved a settlement establishing a large-load power service rate plan for new facilities over 75 MW. The plan provides up to five years for ramp-up, requires at least 12 years of service, sets a minimum monthly bill based on 80% of contract demand, requires… Data centers and other facilities over 75 MW must commit to long-term service and pay for at least 80% of contracted demand even when using less. They must also fund transmission upgrades… |
approved | |||
MidAmerican Energy Berkshire Hathaway Energy |
IA | other | MidAmerican Energy received state approval to invest $3.9 billion in nearly 2,100 megawatts of wind and solar generation. The utility said the investment would come at no net cost to consumers, supported partly by Inflation Reduction Act tax credits and other renewable-energy incentives. MidAmerican expects Iowa’s energy demand to double by the mid-2030s as data centers and artificial intelligence development expand. The anticipated growth will require substantial… |
approved | |||
AEP Ohio |
OH | tariff | 2025-07-11 | The Public Utilities Commission of Ohio adopted AEP Ohio’s 2024 Data Center Tariff settlement on 2025-07-09. AEP Ohio filed its compliance tariff on 2025-07-11, and the tariff became effective on 2025-07-23. New data centers and expansions seeking service from AEP Ohio must complete a mandatory PowerClerk application. Facilities or expansions of 25,000 kW or greater must pay a load-study fee… |
approved | ||
AEP Ohio American Electric Power (AEP) |
OH | tariff | 2026-02-12 | AEP Ohio updated the Public Utilities Commission of Ohio on the operation of its approved Data Center Tariff. The tariff requires progressively increasing financial and legal commitments, including binding contracts and collateral, to align infrastructure investments with data center loads and… Data centers and developers must provide accurate load estimates, obtain engineering studies, provide collateral, and sign binding electric-service agreements with financial commitments.… |
approved | ||
Indiana Michigan Power AEP |
IN | IURC Cause No. 46276 | special contract | 2025-07-30 | Indiana Michigan Power filed a special joint contract with Google. The proposed contract includes Google’s transfer of long-term accredited capacity from clean energy resources to I&M and a custom demand-response offering with specified curtailment limits and use of qualifying behind-the-meter… The proposed arrangement would allow a large data center customer to provide clean-generation capacity and demand response, helping I&M meet PJM requirements and alleviate grid congestion… |
pending | |
American Electric Power (AEP) |
OH | tariff | AEP reported that it had secured data center tariffs in Ohio, followed by large-load tariff solutions in Indiana, Kentucky, and West Virginia. AEP also reported active filings for similar tariffs in Michigan, Oklahoma, Texas, and Virginia, including minimum demand charges and obligations for… Data center customers in AEP service areas may be subject to dedicated data center or large-load tariffs, minimum demand charges, and binding take-or-pay obligations covering… |
pending | |||
Duke Energy |
NC | statement | Duke Energy announced that it will include take-or-pay provisions in agreements covering 2 GW of U.S. data centers across its service area. Customers with demand exceeding 100 MW would be required to pay for a minimum amount of electricity regardless of actual usage, subject to direct regulatory… Data center customers with signed agreements and identified land but without finalized power contracts would face minimum payment obligations once contracts are completed. Duke is also… |
pending | |||
Duke Energy |
NC | tariff | Duke Energy proposed a large load tariff in testimony submitted to the North Carolina Utilities Commission. The proposal would apply to customers with loads of at least 50 megawatts and require minimum bills based on 75% of maximum potential usage, with minimum contract terms of 10 or 15 years. Data centers would face long-term minimum payment obligations regardless of actual electricity use, reducing Duke Energy’s risk from building infrastructure for demand that does not… |
pending | |||
Commonwealth Edison Company (ComEd) Exelon Corporation |
IL | ICC Docket No. 22-0486; ICC Docket No. 24-0181 | rate case | 2024-03-13 | ComEd filed a revised Multi-Year Integrated Grid Plan and an adjusted rate plan to address deficiencies identified by the Illinois Commerce Commission. On December 19, 2024, the ICC approved the compliant refiled grid plan and multi-year rate plan with modifications, allowing recovery of prudent… ComEd identified more than 11 GW of potential data-center growth in its service territory, with demand expected to ramp over up to 10 years. The approved plans support grid-capacity and… |
approved | |
Commonwealth Edison (ComEd) |
IL | tariff | The Illinois Commerce Commission approved ComEd’s proposal to increase security deposits required from developers of large-load projects based on projected energy needs. Projects requesting 50, 200 megawatts will start with a $1 million deposit, increasing by $500,000 for each additional 100… Data center and other large-load developers will face higher security deposits intended to protect ComEd from costs if projects are canceled, moved, or under-utilized. The revised tariff… |
approved | |||
Ameren Missouri |
MO | tariff | Ameren is pursuing a Large Load Customer Tariff case before the Missouri Public Service Commission for customers requesting 100 MW or more. The proposal includes minimum 15-year service contracts, minimum energy purchases, financial assurances, termination notice requirements, exit fees, and… Data-center developers requesting 100 MW or more would need long-term commitments and financial assurances before Ameren makes generation and transmission investments. The proposed terms… |
pending | |||
Duke Energy Carolinas, LLC (DEC); Duke Energy Progress, LLC (DEP) Duke Energy Corporation |
NC | E-100, Sub 208 | other | 2025-10-10 | Duke Energy Carolinas, LLC and Duke Energy Progress, LLC filed technical conference presentation materials addressing large electric load additions, including economic development projects, contracting protections, pricing and cost recovery, and resource-planning implications. The materials… The utilities reported an economic development pipeline of 420 projects representing an estimated 46 GW, including third-party and end-user data center categories. Data center developers… |
pending | |
Santee Cooper |
SC | tariff | Santee Cooper enacted a new experimental electricity rate for large-load customers requiring 50 MW or more, including data centers. The rate is effective immediately, requires 15-year contracts, permits higher charges during periods of high demand, and requires customers to ramp up to full… Qualifying data centers must cover the costs associated with their electricity use and accept long-term contract and usage-ramp obligations. The rate is intended to prevent costs from… |
approved | |||
Santee Cooper |
SC | tariff | 2025-04 | Santee Cooper’s board unanimously approved a special, higher electricity rate for new customers requiring 50 megawatts or more, including data centers and new manufacturing facilities. The rate is intended to ensure these energy-intensive customers cover the cost of the generation they require and… New data centers requiring at least 50 MW will pay a higher electricity rate designed to allocate the cost of required generation to those large loads rather than regular consumers. Data… |
approved | ||
Georgia Power Southern Company |
GA | statement | Georgia Power stated that it signed a 3.2-gigawatt, 25-year electric-service contract with OpenAI for a site near Savannah, Georgia. Service is expected to begin in phases in 2028, with 1 gigawatt of flexible demand response. The contract provides a long-term power arrangement for a major data-center customer. Its flexible demand-response component is intended to support system reliability during periods of… |
pending | |||
Dominion Energy |
VA | tariff | 2025-11 | The Virginia SCC approved Dominion’s GS-5 “High Load” tariff for customers with at least 25 MW of demand. The tariff requires large customers to pay a greater share of generation, transmission, and distribution investments, with service under a 14-year contract and an optional four-year ramp-up… Data centers and other large-load customers would bear more of the costs and risks associated with projected electricity demand. During the ramp-up period, customers would pay minimum… |
approved | ||
Louisville Gas & Electric and Kentucky Utilities (LG&E/KU) PPL Corporation |
KY | other | LG&E/KU are seeking approval to spend nearly $3 billion on two 645-megawatt natural-gas plants and to extend the life of two coal plants, citing forecast demand from future data centers. They also proposed an extremely high load factor tariff requiring qualifying new data centers to pay for at… New data centers expecting to use at least 100 megawatts would be required to sign the proposed EHLF tariff. A 525-megawatt data center could face at least $1.4 billion in demand charges… |
contested | |||
East Kentucky Power Cooperative (EKPC) |
KY | tariff | 2025-10-30 | The Kentucky Public Service Commission approved EKPC’s request for a special tariff establishing rates and terms for prospective data centers. The tariff applies to data centers using at least 15 megawatts, requires PSC approval of each special data-center contract, removes the cap on application… Future data centers in EKPC’s service area must use at least 15 megawatts and satisfy the special tariff requirements. Their contracts require PSC approval before taking effect, and… |
approved | ||
Entergy Arkansas, LLC |
AR | 23-070-TF | tariff | Entergy Arkansas, LLC established or revised Rate Schedule No. 69, Large Power High Load Density Service (LPHLDS), for qualifying high-energy-use or high-load-factor customers, including cryptocurrency-mining or similar operations. The tariff requires qualifying customers to take interruptible… The tariff does not specifically mention data centers. Large, flexible, relocatable, or otherwise qualifying high-load customers may be required to use the LPHLDS tariff, accept… |
approved | ||
Entergy Louisiana |
LA | tariff | Entergy Louisiana uses an Additional Facilities Charge to recover infrastructure costs for large-load customers, including data centers. Data-center customers would be charged directly for applicable additional facilities and related infrastructure costs. |
pending | |||
Southwestern Electric Power Company (SWEPCO) AEP |
LA | statement | SWEPCO signed the White House Ratepayer Protection Pledge, stating that new large energy users should pay for the facilities and system upgrades they require. Under Louisiana Public Service Commission oversight, agreements require incoming large customers to pay for substations, transmission… Data-center developers and other large customers are expected to pay their electricity costs and the infrastructure required to serve them, rather than having existing SWEPCO customers… |
pending | |||
Duke Energy |
FL | tariff | Duke Energy petitioned the Florida Public Service Commission for a new large data center rate. The PSC voted 4-1 to deny consumer advocates’ motion to dismiss the petition, allowing it to proceed to an evidentiary hearing. The proposed large data center rate and related customer protections remain under review. The petition will proceed to an evidentiary hearing, so the rate has not been finalized. |
pending | |||
Public Service Company of Oklahoma |
OK | tariff | 2026-07-01 | PSO filed a large-load tariff with the Oklahoma Corporation Commission establishing separate terms and conditions for large-scale customers, including data centers and crypto-mining operations. The tariff requires commission approval. The tariff is intended to ensure data centers and other large-load customers pay rates reflecting the cost of serving them, helping prevent existing customers from subsidizing related… |
pending | ||
Public Service Company of Oklahoma (PSO) |
OK | tariff | The page describes a tariff and regulatory protections for large-load customers of 150 MW or more. These protections require customer-funded infrastructure and service costs, upfront financial guarantees, and long-term payment commitments intended to shield existing customers from financial risk. Data-center developers with loads of 150 MW or more may be required to provide financial safeguards and remain responsible for infrastructure and service costs even if usage declines or… |
approved | |||
Oklahoma Gas & Electric (OG&E) |
OK | tariff | 2026-06-17 | OG&E proposed a large-load tariff to the Oklahoma Corporation Commission for customers planning to use 75 megawatts or more. The proposal would require such customers to pay for estimated electricity usage, fund their own grid connections, and pay monthly fees that could support credits for other… New data centers and other large energy users would be separately classified and responsible for their estimated electricity usage and grid-connection costs, reducing the risk that… |
pending | ||
Southwestern Public Service Co. Xcel Energy |
NM | other | Southwestern Public Service Co. filed an application with New Mexico utility regulators seeking approval to build eight new energy resources, including natural gas plants, solar and wind farms, battery storage, and transmission upgrades. The utility said the projects are partly needed to serve… Data-center expansion is identified as a major driver of projected electricity-demand growth and the proposed resource additions. Environmental advocates argued that data centers should… |
contested | |||
Southwestern Public Service Company (SPS) Xcel Energy Inc. |
TX | special contract | 2026-01 | SPS entered into an Electric Service Agreement with Fermi America to provide up to 200 MW of electricity to Fermi’s Project Matador Campus. Service is scheduled to begin at 86 MW in January 2026 and gradually expand to 200 MW under the ESA and applicable tariffs. The agreement provides a dedicated, phased electricity supply for Fermi’s Project Matador Campus through SPS’s 115-kilovolt transmission system. It may also create an opportunity for SPS… |
pending | ||
Board of Public Utilities (BPU) |
KS | other | BPU said it is developing rate structures and cost-allocation requirements for large customers as three proposed data-center projects advance. Developers would be required to pay 100% of on-site infrastructure and substation costs, provide up to $140 million in parent-company-backed collateral,… Data-center developers would not receive special rates or utility subsidies and would bear their on-site infrastructure and associated costs. The first project to sign an agreement would… |
pending | |||
Evergy |
KS | other | Evergy initiated processes with the Kansas Corporation Commission and the Missouri Public Service Commission to establish pricing structures for large power users. The proposed structures are intended to recognize the benefits of adding large users to the shared grid and prevent existing customers… Evergy said electricity demand could nearly double if all potential new customers arrive in the Kansas City area. Regulators may establish safeguards to protect customers if a large data… |
pending | |||
Evergy |
MO | tariff | 2025-11-13 | The Missouri Public Service Commission approved Evergy’s large-load rate for users requiring at least 75 megawatts at peak times. The rate is intended to allocate transmission, generation, infrastructure, and grid-related costs to new large power users. Data centers and other large power users would pay rates higher than existing commercial and industrial customers. The safeguards are intended to prevent existing customers from bearing… |
contested | ||
Brazos Electric Power Cooperative, Inc. |
TX | tariff | 2025-11 | Brazos Electric published an Interconnection Guidebook describing requirements and procedures for entities establishing or significantly modifying connections to the ERCOT grid through its transmission system. It includes interconnection requirements for Large Load Customers with peak demand of at… Data center loads may be subject to surveys and steady-state, short-circuit, dynamic-stability, facilities, and potentially subsynchronous-oscillation studies before initial energization.… |
pending | ||
Dominion Energy |
VA | tariff | Dominion Energy proposed creating a new rate class for data-center customers consuming more than 25 MW with a monthly load factor above 75 percent. The proposal includes 14-year contracts, minimum demand charges for transmission, distribution, and generation infrastructure, and exit fees for… Many of the approximately 450 data centers in Dominion’s coverage zone could potentially be classified in the new rate class. Under the proposal, affected customers could be responsible… |
contested | |||
Dominion Energy Virginia Dominion Energy |
VA | IRP | 2024 | Dominion Energy Virginia filed its 2024 Integrated Resource Plan with the Virginia State Corporation Commission and the North Carolina Utilities Commission. The plan proposes an all-of-the-above generation and grid-investment strategy, while the Virginia SCC required least-cost and Virginia Clean… Dominion projects substantial electricity-demand growth primarily driven by data centers, including 8 GW of contracted data-center capacity through 2032 and additional demand under study.… |
contested | ||
Appalachian Power |
WV | special contract | Appalachian Power, Google, and West Virginia manufacturers reached a settlement concerning terms for large-load customers, including potential data centers. The settlement requires Public Service Commission approval and includes minimum site capacity, contract-term, and power-purchase commitments. Data centers locating in West Virginia would need to contract for at least 100 MW at an individual site, commit to an initial term of at least 12 years, and purchase at least 80% of their… |
pending | |||
Appalachian Power Company |
VA | rate case | 2026-05 | Appalachian Power filed an application with the Virginia State Corporation Commission seeking to raise rates, citing potential service to 36 large-load customers requiring significant infrastructure investment. The SCC separately approved new requirements for new large-load customers, including… Data-center developers connecting to Appalachian Power’s system may be required to sign 14-year contracts and pay minimum charges. Infrastructure costs may be assigned to large customers… |
pending | ||
Old Dominion Electric Cooperative (ODEC) |
VA | other | ODEC prepared and submitted a 2026 large load adjustment to PJM for the DOM Zone, covering data-center load forecasts over a 20-year period. The submission included projects with, or expected imminently to have, signed Construction Commitments, Electric Service Agreements, and other listed… Data-center projects with an Electric Service Obligation and Construction Commitment were classified as Firm and allowed to impact the Reliability Pricing Model; other projects were… |
pending | |||
Old Dominion Electric Cooperative (ODEC) |
VA | statement | ODEC CEO John Lee discussed the generation and transmission challenges and financial risks cooperatives may face when serving high-load members, including data centers. He also addressed the economic benefits data centers can bring to local communities. Data-center development may increase generation and transmission challenges and create financial risks for cooperatives serving high-load members. Data centers may also provide economic… |
pending | |||
PG&E |
CA | tariff | 2025-09 | PG&E’s proposed Rule 30 Tariff is pending California Public Utilities Commission approval. It would apply to new load additions greater than 10 MW interconnected at 50 kV, 230 kV, including hyperscale data centers. The tariff would establish tailored cost-recovery mechanisms, reliability standards, and service terms for large, transmission-connected, mission-critical facilities. It is intended to… |
pending | ||
City of Santa Clara dba Silicon Valley Power (SVP) |
CA | statement | 2021-03-22 | SVP submitted a public comment letter to the CAISO Board regarding the 2021, 2022 Transmission Plan. SVP requested immediate coordination with PG&E on transmission-capacity increases and mitigation projects in the South Bay due to rapid hyper-scale data-center load growth and expected reliability… SVP projected peak load growth from 592 MW in 2020 to 1,011 MW in 2025, primarily driven by hyper-scale data centers. SVP warned that South Bay transmission constraints could affect the… |
pending | ||
Silicon Valley Power |
CA | IRP | Silicon Valley Power’s draft Integrated Resource Plan forecasts that annual system load will nearly double by 2035, primarily due to data-center demand. The plan proposes additions including geothermal, wind, solar, storage, hydrogen, and biogas resources, as well as a planned 50 MW, four-hour… Data centers are SVP’s largest load, with an approximately 80% load factor, requiring clean and firm resources capable of serving demand in all hours. Existing and planned transmission… |
pending | |||
PacifiCorp |
OR | other | 2025-02 | The Oregon Public Utility Commission approved PacifiCorp’s proposal to impose penalties on large-load customers, including data centers, when actual energy use at new facilities does not align with forecast needs. The proposal includes a five percent buffer for missed forecasts. Data center operators may face penalties and higher costs when actual load falls materially below reserved or forecast load. The rules are intended to reduce unnecessary grid investment… |
approved | ||
Portland General Electric Company |
OR | UM 2377 | tariff | The OPUC approved PGE’s New Large Load Tariff in docket UM 2377. The tariff increases data center pricing by approximately 30% while lowering costs for other customers. Data center customers will face pricing approximately 30% higher under the approved large-customer tariff. |
approved | ||
Idaho Power Company |
ID | tariff | 2026-01-01 | Schedule 19, Large Power Service, establishes service terms and charges for customers with metered demand of at least 1,000 kW in three or more of the most recent 12 billing periods. It also permits an optional mutually agreed special contract for customers contracting for firm demand of 10,000 kW… Data-center developers with loads of 1,000 kW or more may be subject to Schedule 19 once the demand criterion is met, or may request service based on expected initial usage. Loads… |
approved | ||
Public Service Company of Colorado (Xcel Energy) Xcel Energy |
CO | tariff | 2026-04-02 | Xcel Energy proposed a special tariff for new large-load customers requiring at least 50 megawatts of generating capacity, including data centers. The Colorado Public Utilities Commission ordered Xcel to create the tariff and must approve it. New data centers would need to sign interconnection and energy service agreements, demonstrate site control, pay a $120,000 deposit plus load and transmission study costs, and enter… |
pending | ||
Public Service Company of Colorado Xcel Energy |
CO | IRP | 2025-11 | The Colorado Public Utilities Commission approved Xcel Energy’s electric resource plan in November 2025, limiting new generation in the plan to 6,000 MW, with a second pool of projects if needed. It required Xcel to use large-load negotiating principles for customers needing 50 MW or more,… Data center developers must provide financial commitments before Xcel includes their projects in its load forecast or commits to new generation and transmission. They must sign… |
approved | ||
Black Hills Energy |
WY | tariff | 2020-05 | The Wyoming Public Service Commission approved Black Hills Energy’s Large Power Contract Service Tariff. The tariff allows qualifying Wyoming retail customers with loads over 13 MW to use customer-owned, behind-the-meter dispatchable generation during periods of high demand while Black Hills… Data centers with loads over 13 MW can use onsite backup generation and obtain market-based and renewable energy resources at a firm price. The arrangement is intended to support… |
approved | ||
Tri-State Generation and Transmission Association |
CO | tariff | Tri-State filed a proposal with the Federal Energy Regulatory Commission for a high-impact load tariff (HILT) covering demands of 45 megawatts or more. The tariff is intended to ensure Tri-State can provide capacity to large-load developers while ensuring other cooperative members do not subsidize… If approved, the HILT tariff would establish a framework for connecting and serving data centers and other loads of at least 45 megawatts on Tri-State’s system. Tri-State also has a… |
pending | |||
Tri-State Generation and Transmission Association, Inc. |
CO | tariff | 2025-09 | Tri-State filed its High Impact Load Tariff (HILT) with FERC to establish an integrated process for adding large loads and allocating related generation, transmission, and distribution costs. FERC denied the filing in approximately October 2025 because provisions governing energy-sale terms… The proposed tariff would have applied to first-ready large loads exceeding 45 MW or forecasted to exceed 45 MW within four years, with requirements including site control, binding… |
denied | ||
Avista |
WA | statement | 2026-05 | Avista stated that it signed a Memorandum of Understanding with an unnamed data center developer interested in building within its Washington service territory. Negotiations are paused while Avista considers the need for broader coordinated planning; the MOU is not a final decision or commitment… The potential data center is not guaranteed service or approval. Avista will evaluate whether it can meet the project's energy needs, with the developer responsible for the evaluation… |
pending | ||
NorthWestern Energy |
MT | tariff | 2026-03-31 | NorthWestern Energy submitted an application to the Montana Public Service Commission requesting approval of a Large New Load Tariff. The proposed tariff would require data centers and other large new-load customers to pay the full costs of the infrastructure and electric service needed to support… Data centers would be responsible for the infrastructure and electric service costs they create. The proposed tariff includes minimum service commitments, minimum demand and energy billing… |
pending | ||
NorthWestern Energy |
MT | tariff | 2026 | Community, conservation, and Indigenous-led organizations filed a petition with the Montana Public Service Commission seeking intervention in NorthWestern Energy’s data-center tariff proceeding. The proceeding addresses rates, terms, and conditions for electricity service to data centers,… The petition seeks data-center tariff provisions addressing capacity and energy purchase obligations, penalties, collateral, minimum payments based on forecast demand, energy efficiency,… |
contested | ||
PJM Interconnection |
MD | complaint | 2026-05-07 | The Maryland Office of People’s Counsel filed a complaint at FERC challenging PJM’s hybrid regional transmission cost-allocation methodology. The complaint asks FERC to assign data center-driven transmission costs to the PJM zones where the data centers are located or charge those costs directly… Data center-driven transmission costs could be assigned to the zones hosting the data centers, such as Dominion Energy’s zone in Virginia, rather than broadly spread across PJM.… |
contested | ||
Delmarva Power and Light |
DE | tariff | 2025-12-19 | Delmarva Power proposed a tariff to the Delaware Public Service Commission for large-load electric customers using more than 25 megawatts. The proposal would require grid-impact studies, detailed energy-use projections, and 10-year financial guarantees from large energy users. The tariff would establish different rates and requirements for large users such as data centers in Delmarva’s Delaware territory. The Delaware Public Service Commission has paused major… |
pending | ||
Delmarva Power and Light Company |
DE | 25-0826 | tariff | 2025-08-28 | Commission staff and the Division of the Public Advocate petitioned for Delmarva Power to create a tariff for customers with monthly maximum demand of 25 megawatts or more. Delmarva Power proposed a large-demand service class, GS-LD, and an application process for customers with projected loads of… Large-load and data-center customers would be placed in a separate proposed service class and subject to an application process for projected loads of at least 50 megawatts. The proceeding… |
contested | |
PECO Energy Company |
PA | M-2025-3054271 | tariff | 2026-05-12 | The Pennsylvania Public Utility Commission adopted a model interconnection tariff for new Large Load Customers, including individual customers exceeding 50 MW or closely located customers with aggregate capacity of at least 100 MW. The tariff addresses interconnection studies, network-upgrade cost… Data center developers meeting the applicable thresholds may face three-to-five-year load-ramp periods, minimum five-year initial contract terms, responsibility for “but for”… |
approved | |
New Jersey electric public utilities (statewide data center tariff standards) |
NJ | tariff | New Jersey lawmakers passed a bill requiring the New Jersey Board of Public Utilities to establish tariff standards for data centers of at least 50 MW. The standards would allocate attributable costs to large data centers, require demand-response and efficiency programs, prioritize data-center… Existing and prospective data centers meeting the 50 MW threshold would face special tariffs and financial-guarantee requirements intended to protect other ratepayers from grid-connection… |
pending | |||
Monongahela Power; Potomac Edison Co. FirstEnergy |
WV | other | Monongahela Power and Potomac Edison Co. applied to the West Virginia Public Service Commission for permission to build the Maidsville Energy Center, including a 1,200-MW gas-fired power plant and three solar projects totaling 70 MW. Mon Power also seeks to impose a customer surcharge to fund… The project is primarily intended to serve potential data center load. If service agreements are executed and approved, data center owners would be responsible for their proportionate… |
contested | |||
Mon Power and Potomac Edison FirstEnergy |
WV | other | Mon Power and Potomac Edison are seeking approval to build the 1,200-megawatt Maidsville Energy Center, three solar projects, and an associated Generation Projects Surcharge. The initial surcharge is estimated to increase residential rates by $1.18 per month, or 0.9%. Projected load growth is substantially driven by prospective data-center demand, including an unnamed large-load customer projected to reach 1,012 MW from 2033 through the end of the… |
contested | |||
Mon Power and Potomac Edison FirstEnergy |
WV | other | Mon Power and Potomac Edison applied to construct a $2.48 billion, 1,200-megawatt combined-cycle natural gas plant at the Fort Martin site in Monongalia County, along with 70 megawatts of solar generation. The utilities say the project is needed to address an anticipated capacity shortfall… Opponents argued that the project could increase customer electric bills while primarily serving speculative future data centers. No specific data-center tariff, interconnection… |
contested | |||
Mon Power; Potomac Edison FirstEnergy |
WV | Case No. 26-0108-E-CN | other | Mon Power and Potomac Edison filed an application with the Public Service Commission of West Virginia to build a 1,200-megawatt natural-gas-fired power plant adjacent to the Fort Martin Power Station, along with three solar projects. The proposed $2.48 billion project is intended largely to meet… The proposed plant is intended to serve anticipated data-center demand, but existing customers could face an initial surcharge before the new demand is served. Opponents argue that data… |
contested | ||
Monongahela Power and Potomac Edison FirstEnergy |
WV | IRP | Monongahela Power and Potomac Edison asked the West Virginia Public Service Commission for permission to build a 1.2-GW gas-fired power plant in Maidsville, West Virginia. The proposed $2.5 billion project is included in the utilities’ integrated resource plan and is intended to support growing… If the proposal is accepted, FirstEnergy said it would seek additional generation in West Virginia to support data centers and could apply for a second, third, or fourth unit. FirstEnergy… |
pending | |||
Mon Power |
WV | other | Mon Power is asking the West Virginia Public Service Commission to approve a $2.4 billion natural gas-fired power plant near its Fort Martin Plant, with operations planned for 2031. It is also requesting a $1.18-per-month customer surcharge to help finance the plant. The plant is intended to serve electricity demand from data centers, and Mon Power says data-center developers would eventually pay through contracts. No data-center contracts have been… |
contested | |||
Public Service Electric and Gas (PSE&G) Public Service Enterprise Group (PSEG) |
NJ | statement | PSE&G said its pipeline of potential large-load customers, almost all data centers, increased 47% to 9.4 GW at the end of June from 6.4 GW three months earlier. The utility expects approximately 10% to 20% of interconnection inquiries to become actual customers and is discussing supplying data… Data-center developers face uncertainty because PSE&G expects only a minority of current interconnection inquiries to result in customers. Developers may also be evaluated for power… |
pending | |||
Consolidated Edison’s Rockland Electric; Exelon’s Atlantic City Electric; FirstEnergy’s Jersey Central Power & Light; Public Service Enterprise Group’s Public Service Electric and Gas Consolidated Edison; Exelon; FirstEnergy; Public Service Enterprise Group |
NJ | tariff | New Jersey legislation signed by Gov. Mikie Sherrill requires utilities to craft tariffs for data centers larger than 50 MW. The tariffs must address potential service costs, including requiring data center owners to guarantee payment for at least 85% of requested service for at least 10 years. Data center developers must meet minimum payment guarantees and may face requirements related to energy efficiency, new clean energy, energy storage, and colocated power supplies. They may… |
approved | |||
New Jersey electric public utilities (statewide large-load tariff legislation) |
NJ | other | New Jersey legislation would require public electric utilities to submit proposed tariffs to the New Jersey Board of Public Utilities for energy users consuming more than 100 megawatts monthly. The tariffs would begin one year after enactment, and the bill would incentivize data centers to capture… Data centers consuming more than 100 megawatts monthly would be subject to new tariffs intended to protect other ratepayers from data-center-driven electricity cost increases. They would… |
contested | |||
Wisconsin Electric Power Company (We Energies) |
WI | 6630-TE-113 | tariff | 2025-03 | We Energies proposed linked Very Large Customer and Bespoke Resources tariffs for very large data-center loads. The Wisconsin Public Service Commission approved the tariffs on 2026-04-24 with modifications, including lowering the eligibility threshold to 100 MW, extending the minimum term to 15… Data-center customers with loads of at least 100 MW must enroll in the Very Large Customer rate class and execute a binding Bespoke Resources agreement. Developers must fund 100% of… |
approved | |
MidAmerican Energy Company Berkshire Hathaway Energy Company |
IA | special contract | MidAmerican’s Load Commitment Agreement applies to new large loads, including data centers. It requires binding load-ramp schedules and a minimum monthly charge for 10 years regardless of actual usage, with signed customers funding incremental transmission and substation investments. Data center developers must commit to binding ramp schedules and pay minimum monthly charges for 10 years regardless of actual usage. They must also fund incremental transmission and… |
approved | |||
Indiana Michigan Power Company |
IN | Cause No. 46097 | tariff | 2025-02-19 | Indiana Michigan Power received commission approval to modify its existing Industrial Power Tariff for new or expanding large-load customers, including data centers. The tariff applies to loads exceeding specified capacity thresholds and includes long-term contract, minimum demand, exit-fee, and… Data center developers must commit to an initial contract term of at least 12 years and pay monthly demand charges for at least 80% of contracted capacity, even if actual usage is lower.… |
approved | |
Indiana Michigan Power (I&M) American Electric Power (AEP) |
IN | tariff | The Indiana Utility Regulatory Commission approved, with one change, a settlement agreement amending Indiana Michigan Power’s industrial power tariff for new or expanded facilities with contract capacity of at least 70 MW, or 150 MW aggregated across a company. The tariff requires large-load… Data centers meeting the capacity thresholds would receive a standard electric-service tariff and be responsible for grid-upgrade costs rather than passing those costs to existing… |
approved | |||
Consumers Energy |
MI | tariff | 2026-02-19 | The Michigan Public Service Commission denied Michigan Attorney General Dana Nessel’s request for a rehearing in a previous Consumers Energy case involving rate structures for data centers and other large-load customers. The approved tariff includes protections for residential customers associated with large new loads and requires data centers to pay more, helping reduce costs for other customers. |
denied | ||
Rochester Gas and Electric Corporation |
NY | Case No. 25-E-0379 | tariff | 2026-06-01 | Rochester Gas and Electric Corporation issued revisions to Service Classification No. 3 in compliance with the May 14, 2026 order in Case No. 25-E-0379. The revisions establish delivery charges effective June 1, 2026, including a $401.00 monthly customer charge and an energy delivery charge of… Customers with measured demand of at least 100 kW during any three of the previous 12 months may take service under Service Classification No. 3. Customers using or potentially using 300… |
approved | |
AEP Ohio |
OH | tariff | Regulators approved a new large-load tariff for AEP Ohio. Following approval, AEP Ohio reduced its large-load forecast by more than 50%, from 30 GW to 13 GW. The tariff appears to have reduced speculative requests in AEP Ohio’s large-load pipeline. Manufacturers in Ohio said data center demand remained inflated. |
approved | |||
New York Independent System Operator (NYISO) |
NY | other | New York Gov. Kathy Hochul signed an executive order pausing state environmental permits for new hyperscale data centers consuming 50 megawatts or more for up to one year. The pause will remain in effect while the New York Department of Public Service completes a Generic Environmental Impact… Projects awaiting approval from the New York State Department of Environmental Conservation as of July 14 may be impacted. Projects using only local permitting processes that do not… |
approved | |||
Duke Energy Carolinas, LLC (DEC) and Duke Energy Progress, LLC (DEP) |
NC | other | 2025-07-24 | DEC and DEP filed a response to the North Carolina Utilities Commission’s June 6, 2025 request regarding integration of large-load additions exceeding 100 MW. Duke described its large-load intake process, including transmission studies, potential agreements, customer financial and performance… Data centers and other large-load customers must engage Duke early, undergo transmission studies, and may need to provide refundable capital payments, satisfy minimum billing requirements,… |
pending | ||
Duke Energy Carolinas |
NC | tariff | 2026-07-15 | Duke Energy proposed a large-load tariff requiring customers requesting 50 megawatts or more to pay 75% of their demand charges in advance. The utility also agreed to participate in a fast-track regulatory process to develop rates for data centers and other large energy users. Data centers and other large electricity users could be subject to a separate rate structure and advance payment of 75% of demand charges. The threshold and final cost implications remain… |
contested | ||
Georgia Power Southern Co. |
GA | other | Georgia Power filed an update to its load forecast as part of its request for proposals certification proceedings. The update projected capacity needs aligned with 10 GW of requested capacity resources, including five gas combined-cycle units and 11 battery energy storage facilities. The filing reflects capacity planning for projected large-load growth, including data centers. Southern Co. reported contracts with large-load customers representing 7 GW through 2029,… |
pending | |||
Southern Company |
GA | statement | Southern Company stated that it uses minimum 15-year contracts for data centers, minimum bill provisions similar to take-or-pay structures, termination payments tied to incremental cost to serve, and significant collateral requirements. Multiple pieces of legislation have been proposed in the… Data-center developers seeking service from Southern Company may face minimum 15-year contracts, minimum bill obligations, termination payments, and significant collateral requirements.… |
pending | |||
Tennessee Valley Authority |
TN | tariff | 2026-02-18 | TVA proposed changes to wholesale and resale rate schedules and related policies, including removing data centers from manufacturing-service rate schedules and credits. It also proposed options for AI and data-center loads, such as a potential new large-load class, capacity commitment charges,… Data centers would no longer be eligible for manufacturing-service rate schedules or General/Small Manufacturing Credits under the proposal. New or expanding data centers could face… |
pending | ||
Public Service Company of Oklahoma (PSO) |
OK | tariff | PSO proposed a separate large-load electricity tariff for customers including data centers, cryptocurrency mining operations, artificial intelligence facilities, and installations requiring more than 75 megawatts. The proposal includes self-supply, partial-supply, and full-supply options,… Data centers would face separate service terms, including long-term commitments, base and usage charges, collateral requirements, exit fees, and restrictions on early termination.… |
pending | |||
Evergy Kansas |
KS | tariff | The Kansas Corporation Commission approved a settlement establishing a large-load power service rate plan for new facilities over 75 MW. The plan was agreed to by Evergy’s Kansas utilities, the Data Center Coalition, Sierra Club, NRDC, Google and other groups. Data centers and other large-load customers over 75 MW may have up to five years to ramp up, followed by a minimum 12-year service term. They must pay a minimum monthly bill based on 80%… |
approved | |||
Nebraska Public Power District |
NE | other | 2026-04-14 | NPPD supported and informed the design of LB 1261, which passed into law on April 14, 2026. The law requires data center customers to build and maintain the energy infrastructure needed to serve them, bear 100% of the financial burden for new energy generation, and sign long-term contracts with… Data center developers must bear the full cost of new energy-generation construction and associated infrastructure and enter into long-term contracts with the local public power district.… |
approved | ||
Lincoln Electric System |
NE | statement | The Google data center in Lincoln is reshaping Lincoln Electric System’s electric system, accounting for 11% of the utility’s retail revenue and driving hundreds of megawatts of new wind energy. The Google data center represents a substantial electric load for Lincoln Electric System and is contributing to additional wind-energy investment. The source does not state specific… |
pending | |||
CenterPoint Energy |
TX | statement | In a first-quarter earnings presentation, CenterPoint Energy stated that ERCOT had approved 3.2 GW of data-center load, with another 9 GW expected to be submitted for approval. The company expects 8 GW to be energized by 2029, followed by an additional 4.2 GW, and is conducting a refreshed load… CenterPoint reports 3.5 GW of data-center capacity already under construction in its Houston-area territory and expects 8 GW of data-center load to be energized by 2029. The utility said… |
pending | |||
ERCOT transmission/distribution utilities (statewide SB6 rulemaking) |
TX | other | 2026-03-12 | The Public Utility Commission of Texas voted to publish draft rule 16 TAC §25.194 to implement Texas SB 6 interconnection standards for new loads of 75 MW or greater. The proposed rule would impose interconnection fees, financial-security requirements, study fees, disclosure obligations, and… Data centers and other projects involving 75 MW or more would need to provide site-control and permitting information, energization and generation data, study fees, and financial security… |
pending | ||
AEP Texas AEP / American Electric Power |
TX | tariff | AEP Texas has a pending large-load tariff proposal addressing cost responsibility for new large loads. The utility has 36 GW of large loads that comply with Senate Bill 6 and are backed by letters of agreement. If adopted, the tariff would shift infrastructure costs associated with new large loads, including data centers, toward the customers driving those needs rather than existing customers.… |
pending | |||
Oncor Electric Delivery |
TX | Docket No. 59220 | other | 2026-01-09 | FGE Goodnight I, LLC and Crusoe Energy Systems LLC jointly applied for approval to net meter the 265.5 MW GOODNIT1 wind facility with the proposed 260 MW Crusoe Load Two data center. The PUCT approved the arrangement, requiring full data-center curtailment within 30 minutes during an ERCOT… Crusoe Load Two must fully disconnect during an ERCOT transmission emergency without financial compensation, and emergency curtailment is not capped by the capacity of the paired… |
approved | |
Electric Reliability Council of Texas (ERCOT) |
TX | other | 2026-08-03 | Texas Gov. Greg Abbott ordered the PUCT and ERCOT to audit all data center projects in the ERCOT interconnection queue before additional projects advance. ERCOT suspended the first scheduled deliverable of its Batch Zero large-load interconnection process and planned to seek a good-cause exception… The action could delay 49.8 GW of new data center electricity demand, with BNEF estimating potential project revenue at risk of just over $8 billion under a 60% AI-related capacity mix or… |
pending | ||
Electric Reliability Council of Texas (ERCOT) |
TX | other | 2026-08-03 | Texas Governor Greg Abbott directed the Public Utility Commission of Texas and ERCOT to conduct a comprehensive verification and audit of all data centers advancing through ERCOT’s interconnection process before additional projects may move forward. ERCOT stated that it would not issue project… Data centers advancing through ERCOT’s interconnection process may not move forward until they complete the verification and audit process. Batch Zero projects face postponed… |
pending | ||
ERCOT transmission/distribution utilities (statewide SB6 rulemaking) |
TX | Project No. 58317 | other | 2025-07-29 | Texas Senate Bill 6 directs the Public Utility Commission of Texas to establish new interconnection standards and cost-sharing requirements for ERCOT large-load customers, including customers with expected system demand exceeding 75 MW. It also requires rules addressing co-location with existing… Data-center developers and other large-load customers may face additional interconnection delays, study and cost-sharing requirements, site-control and financial-commitment obligations,… |
pending | |
ERCOT transmission/distribution utilities (statewide SB6 rulemaking) |
TX | Project 58480; Project 58481; Project 58479; Project 58482; Project 58484 | other | 2025-10-17 | The Public Utility Commission of Texas is developing rules and evaluating policies under Texas Senate Bill 6 concerning large-load forecasting, interconnection standards, net-metering arrangements, demand-management services, and transmission-cost allocation. The materials state that proposed… Data centers represent nearly 69% of the 189 GW of large-load requests tracked in the ERCOT queue. The proposed requirements could affect data-center interconnection, forecast… |
pending | |
ERCOT transmission/distribution utilities (statewide SB6 rulemaking) |
TX | other | 2026-03-12 | The Public Utility Commission of Texas voted to publish draft 16 TAC §25.194 implementing Senate Bill 6 interconnection standards for new loads of 75 MW or greater. The proposed rule would require interconnection fees, financial security, disclosures, study fees, upfront payment of direct… Data centers seeking at least 75 MW of new or expanded interconnection capacity would face a $50,000/MW non-refundable interconnection fee, $50,000/MW financial security, study fees,… |
pending | ||
Dominion Energy |
VA | tariff | Dominion Energy’s Virginia tariff requires data centers to provide $1.5 million per MW in collateral. Data center developers in Virginia may face substantially higher upfront collateral requirements than under the Texas SB6 proposals. |
pending | |||
Old Dominion Electric Cooperative (ODEC) |
VA | other | 2025-03 | PJM submitted a necessary studies agreement to study the grid effects of an LSP Digital Infrastructure project at or near LS Power’s Doswell power plant. ODEC protested, citing insufficient details about construction timing and when the data center would begin taking power from the grid. The proposed colocated campus could include up to five 60-MW, always-on data center buildings, with LS Power selling up to 300 MW under a five-year power purchase agreement. ODEC raised… |
contested | ||
Black Hills Energy (Cheyenne Light, Fuel & Power) Black Hills Corp. |
WY | other | Black Hills stated that the proposed 1.8-gigawatt data center project in Cheyenne continues to move forward. Its Wyoming electric utility subsidiary filed a Certificate of Public Convenience and Necessity for a supporting substation in January, executed a substation agreement with the large-load… The data center is expected to receive service under the Wyoming utility’s Large Power Contract Service Tariff through a dedicated substation. Service is expected to begin in early 2028,… |
pending | |||
Black Hills Corporation |
WY | tariff | Black Hills Corporation serves data center and blockchain customers in the Cheyenne, Wyoming area under approved tariffs using a market energy procurement model. Earnings from these customers are separated from retail customers for rate-making purposes, providing utility-like returns without… Data center developers and operators in the Cheyenne area may be served under the approved tariff and market energy procurement model. Existing customers, new customers, and expansions are… |
approved | |||
Grant PUD |
WA | statement | Grant PUD plans to impose load-growth limits on data centers and notify each data-center customer of the additional megawatts remaining before its assigned limit is reached. The limits are intended to address potential outage and voltage-instability risks as data-center loads grow rapidly. Data-center customers will face limits on additional load growth. Grant PUD may raise the limits after substation upgrades and increased transmission capacity allow the system to safely… |
pending | |||
Basin Electric Power Cooperative |
ND | tariff | NextEra Energy Resources and Basin Electric Power Cooperative are considering jointly developing a 1,450-MW combined-cycle gas-fired power plant in North Dakota to serve a potential data center complex. They applied to the Southwest Power Pool’s fast-track interconnection study process to evaluate… The proposed generation and transmission arrangements are intended to serve new, high-demand energy users such as data centers. Basin Electric said its program is intended to insulate… |
pending | |||
Maryland electric utilities (statewide large-load tariff docket) |
MD | other | The page concerns large-load customer regulations and tariffs interconnecting to the electric system serving Maryland. The provided material does not state what was proposed, filed, or decided. The provided material does not specify requirements, tariffs, interconnection procedures, cost allocation, delays, or other impacts on data-center developers or operators. |
pending | |||
Delmarva Power |
DE | tariff | Delmarva Power proposed a large-load tariff. Stakeholders agreed to raise the eligibility threshold from 25 MW to 50 MW and exclude existing customers, while the Joint Agencies urged more stringent requirements. Data-center and other large-load projects meeting the proposed 50 MW threshold could be subject to the tariff, while existing customers would be excluded. Additional requirements could… |
pending | |||
Delmarva Power |
DE | 25-0826 | tariff | The Delaware Public Service Commission opened docket 25-0826 to develop an interim large-load tariff for Delmarva Power customers using 25 MW or more, following a joint petition from PSC staff and the Division of the Public Advocate. The PSC also paused interconnection of new large-load facilities… Data centers and other large-load facilities using 25 MW or more face a pause on new interconnections in Delmarva territory until the tariff is established. The tariff is intended to… |
pending | ||
PPL, PECO, and FirstEnergy Pennsylvania electric distribution companies |
PA | M-2025-3054271 | tariff | 2026-05-13 | The Pennsylvania Public Utility Commission approved a model large-load tariff framework requiring single customers above 50 MW, or aggregated loads above 100 MW, to pay for grid infrastructure and interconnection upgrades caused by their projects. The framework also addresses deposits, collateral,… Data centers and other large-load customers would bear the grid infrastructure and interconnection costs they cause rather than shifting those costs to households and small businesses. The… |
approved | |
AEP |
OH | Case No. 24-508-EL-ATA | tariff | 2025-09 | The Public Utilities Commission of Ohio denied OMAEG’s request for reconsideration and upheld its order authorizing AEP to implement a data center tariff. The PUCO rejected arguments that AEP had not demonstrated a capacity constraint, that its self-imposed moratorium was unlawful, or that the… AEP is authorized to implement the data center tariff. OMAEG is considering whether to appeal the decision to the Supreme Court of Ohio. |
denied | |
Ohio Edison; The Cleveland Electric Illuminating Company; The Toledo Edison Company |
OH | tariff | 2026-06-12 | The three FirstEnergy utilities filed an application with the Public Utilities Commission of Ohio seeking approval of a new Data Center Tariff, Schedule DCT. The proposed tariff includes long-term contract requirements, collateral tied to new infrastructure costs, minimum monthly billing demand… Data-center customers would face additional contractual and financial protections intended to ensure they bear responsibility for infrastructure costs if a project does not materialize or… |
pending | ||
Alliant Energy |
IA | special contract | Alliant implemented a five-year base electric-rate freeze in Iowa supported by data center growth. Alliant is also working with Meta to match energy and capacity requirements with clean energy. Data center growth is identified as supporting rate stability in Iowa. Meta’s Wisconsin project is being coordinated with clean-energy matching for its energy and capacity requirements. |
pending | |||
Wisconsin Electric Power Company (WEPCO) |
WI | tariff | 2026-04-24 | The Public Service Commission of Wisconsin approved, subject to conditions, WEPCO’s proposed Very Large Customer and Bespoke Resources tariffs. The Commission extended the contract term to 15 years and required minimum billing demand charges based on forecasted or actual demand, whichever is higher. Data-center customers must sign 15-year Energy Service Agreements, including the ramp-up period, and may be responsible for non-recoverable preparation costs, certain generating-resource… |
approved | ||
Kentucky Power |
KY | tariff | The Kentucky PSC approved protections for large-load customers of 150 MW or more. These protections require upfront financial guarantees and long-term payment commitments, including when usage declines, to shield existing Kentucky Power customers from financial risk. Data center customers must provide financial guarantees and make long-term payment commitments so existing Kentucky Power customers are not responsible if a project changes, leaves, or… |
approved | |||
Dayton Power & Light (AES Ohio) |
OH | Case 25-0960-EL-ATA et al. | rate case | A settlement in a PUCO proceeding requires Dayton Power & Light to file a separate proposal governing the interaction between Standard Service Offer service and data centers. The interim stipulation adopts a data-center tariff under which a data center may take SSO service only if it certifies… The proposed framework would remove data-center load from the utility’s regular default service and establish a data-center-specific default-service class with hourly pricing and… |
pending | ||
AES Ohio |
OH | rate case | In AES Ohio’s pending rate case, PUCO staff recommended that AES Ohio receive a new data center tariff creating separate rate classes for data centers. Staff acknowledged that AES Ohio has not experienced the same level of data center activity as AEP Ohio but said the utility should “get ahead” of… Data centers in AES Ohio’s territory could be placed in separate rate classes under a new tariff. The recommendation would provide special rate treatment based on a potential future… |
pending | |||
East Kentucky Power Cooperative, Inc. (EKPC) |
KY | Case No. 2025-00140 | tariff | 2025-10-30 | The Kentucky Public Service Commission approved EKPC’s Data Center Power tariff. The tariff applies to loads of 15 megawatts or more, with enhanced requirements for projects exceeding 250 megawatts, including uncapped application fees, scaled collateral, and a PSC-approved special contract for… Data center developers must pay application and study-related costs, provide financial security, and obtain a project-specific PSC-approved special contract. The tariff is intended to… |
approved | |
Northern States Power Co., d/b/a Xcel Energy |
MN | E-002/M-25-289 | tariff | 2025-10-13 | Tract Capital Management, LP submitted comments to the Minnesota Public Utilities Commission on Xcel Energy’s proposed Large General Time of Day Service and Large Peak Controlled Time of Day Service tariffs for large-load customers. Tract recommended changes concerning incremental cost testing,… The proposed tariffs would establish terms for serving new large-load customers, including data centers. Tract stated that greater predictability and transparency are needed regarding… |
pending | |
Northern States Power Company, doing business as Xcel Energy |
MN | E002/M-25-___ | tariff | 2025-07-16 | Northern States Power Company filed a petition with the Minnesota Public Utilities Commission seeking approval of new Large General Time of Day Service and Large Peak Controlled Time of Day Service tariffs for new or existing nonresidential customers with new electric demand of at least 100 MW.… Data centers with new demand of at least 100 MW would generally be required to use one of the proposed tariffs, execute electric service and interconnection agreements, and obtain… |
pending | |
Northern States Power Company, d/b/a Xcel Energy |
MN | E-002/M-25-289; E-002/M-25-387 (HCTS) | tariff | 2025-07-16 | Xcel Energy filed a petition seeking approval of new Large General Time of Day Service and Large Peak Controlled Time of Day Service tariffs for very large customers, proposed as subclasses of the Demand class. The proposal includes a 100 MW eligibility threshold, 15-year default contract term,… Data centers and other customers meeting the proposed 100 MW threshold could receive service under the new tariffs and related electric service agreements. The Minnesota Office of the… |
contested | |
New York State Electric & Gas Corporation (NYSEG) |
NY | PSC Case 14-M-0094, et al. | statement | 2025-12-08 | A December 8, 2025 paper discusses the potential effects of the Cayuga Data Campus on energy prices in Lansing. It states that NYISO and NYSEG must complete reliability studies, with the campus responsible for required system-upgrade costs, and explains potential effects on delivery and supply… The Cayuga Data Campus would pay the system-upgrade costs required for reliable interconnection. Its large electricity consumption may spread fixed delivery costs across a larger base,… |
pending | |
National Grid |
NY | Case 26-E-0045 | tariff | 2026-06-15 | National Grid filed reply comments in the New York Public Service Commission’s Energize NY Development proceeding, supporting stronger forecasting discipline, financial commitments, and protections against non-materializing large loads while cautioning against one-size-fits-all mandates. The proceeding may establish requirements for data-center load forecasting, financial commitments, credit support, interconnection cost allocation, and service classifications. No final… |
pending | |
New York investor-owned utilities (statewide large-load interconnection reform) |
NY | other | 2026-02 | New York lawmakers proposed a three-year pause on approvals for new data centers above 20 MW. Governor Kathy Hochul directed the New York Public Service Commission to reform large-load interconnection rules, potentially addressing grid-upgrade costs, reliability, flexibility, on-site power, and… Data center developers above 20 MW could face a three-year approval moratorium if the bill passes. Developers may also be required to bear more interconnection costs, operate flexibly,… |
pending | ||
Duke Energy |
NC | tariff | Duke Energy filed a proposed “large load tariff” with the North Carolina Utilities Commission for data centers and other massive energy users. The proposal would require covered facilities to pay minimum monthly bills for at least 10 years and assume financial obligations supporting grid… Data centers would face long-term minimum-payment obligations and would be required to pay for infrastructure such as substations and transmission lines built to serve their electricity… |
contested | |||
Dominion Energy South Carolina |
SC | 2026-9-E | rate case | 2026-07-02 | PSC Order No. 2026-374 approved a large-load stipulation in Dominion Energy South Carolina’s general rate case. Dominion agreed to join and participate in generic Docket 2026-138-E, deferring issues involving new loads of 50 MW or more to that proceeding. Data-center and other large-load arrangements will be reviewed in the statewide generic proceeding rather than resolved immediately in Dominion’s rate case. Developers may face future… |
approved | |
Alabama Power |
AL | Docket 33709 | special contract | 2026-08-03 | The Alabama Public Service Commission is deciding how to review contracts between Alabama Power and large data centers. Energy Alabama filed initial comments supporting a published large-load tariff, enforceable minimum obligations, public disclosure of power buyers, and an affirmative Commission… Large data centers could be subject to a published large-load tariff and enforceable minimum obligations intended to keep risk with the data center rather than families and small… |
pending | |
Tennessee Valley Authority (TVA) |
TN | tariff | 2026-08-20 | TVA planned to present a new large-load or data-center rate class to its Board for consideration on August 20, 2026. No final tariff or special rate class had been adopted as of July 17, 2026. A dedicated large-load rate could establish different pricing and cost-allocation treatment for data-center customers. The final effect on data-center electricity costs remained… |
pending | ||
Entergy Louisiana Entergy Corporation |
LA | U-37882 | other | 2026-03-27 | Entergy Louisiana filed a proposal for more than 5,200 MW of generation across seven new gas combined-cycle plants, approximately 240 miles of 500kV transmission, battery storage, nuclear uprates, and up to 2,500 MW of Meta-funded renewables. The LPSC voted 4, 1 in April 2026 to fast-track the… The proposal would add more than 5,200 MW of generation and related infrastructure for Meta Phase 2 and the Hyperion campus. The public application does not disclose the associated… |
pending | |
Florida Power & Light (FPL) |
FL | PSC-2026-0022-S-EI | tariff | 2026-01 | The Florida Public Service Commission approved FPL’s Large Load Contract Service tariffs, LLCS-1 and LLCS-2, effective January 1, 2026. LLCS-1 applies to new or incremental loads of 50 MW or more with an 85% or higher load factor in designated zones, while LLCS-2 applies outside those zones. Data center developers in the LLCS-1 zones face a combined 3 GW cap, a $28.07 per kW per month incremental generation charge, a 20-year minimum term, a 70% minimum take-or-pay demand… |
approved | |
Florida Power & Light |
FL | 20250011-EI | tariff | 2026-01-01 | FPL’s Incremental Generation Charge was approved as part of a contested, non-unanimous settlement in its 2025 base-rate case. Rate schedules LLCS-1 and LLCS-2 apply to new or incremental load of 50 MW or more with a load factor of at least 85%. New or incremental large-load customers, including data centers, must pay incremental generation costs in addition to embedded cost-based rates. Transmission interconnection is handled… |
approved | |
Oklahoma Gas and Electric Co. (OG&E) |
OK | tariff | 2026-06 | OG&E submitted a proposed comprehensive large-load tariff to the Oklahoma Corporation Commission for high-energy users such as data centers. The proposal includes upfront infrastructure payments, customer protection charges, a proposed 15-year minimum service term, exit fees, financial security… Data centers and other large-load customers would be required to bear allocated electricity-service and infrastructure costs, provide collateral, pay minimum charges tied to reserved… |
pending | ||
Unified Government Board of Public Utilities (BPU) |
KS | other | 2025-05-29 | Developers of a proposed $12.6 billion data center business park pledged to fund utility upgrades, including two BPU substations. The planning commission voted 4-2 to recommend approval, while Kansas approved a 20-year state sales tax exemption for qualifying data centers. The project would require 600 megawatts of service, exceeding BPU’s stated 500-megawatt capability, and would require additional substations and power from the Southwest Power Pool. The… |
contested | ||
Nebraska Public Power District (NPPD) |
NE | rate case | 2026-04-21 | NPPD reported that it was evaluating a new large-load rate planned for a January 1, 2027 effective date to recover costs from new high-demand customers and protect existing customers. The rate was still under development and had not been board-approved. A future NPPD large-load rate could require new high-demand customers, including data centers, to bear costs associated with serving their load and help protect existing customers from… |
pending | ||
South Central Public Power District |
NE | tariff | 2025-01-01 | The District revised and made effective Large Power Schedule LP-3, Rate Schedules 60, 61, and 62 (Sub 8), for Large Power Service Over 7,500 Installed KVA. The tariff establishes energy, demand, transmission, distribution, billing-demand, minimum-charge, power-factor, and… Data centers requiring 7,500 kVA or more of installed transformer capacity may qualify for the tariff if located on or near the District’s qualifying facilities. Applicable costs include… |
approved | ||
Public Utility District No. 1 of Chelan County (Chelan PUD) |
WA | tariff | 2024-06-01 | Chelan PUD published tariff provisions for high-density and data-center-related loads. Rate 36 for data centers and similar loads became effective June 1, 2024, while Schedule 35 for high-density loads became effective February 1, 2024; commissioners also approved 3% electric rate increases… Data centers and similar computing loads up to 3 MW are directed to Schedule 35 or Rate 36, which include demand charges, energy charges, and an upfront capital charge. A power-sales… |
approved | ||
HILCO Electric Cooperative, Inc. |
TX | other | Infrakey DC Parks LLC and HILCO Electric Cooperative, Inc. signed a Memorandum of Understanding establishing a framework for 150 MW of dedicated nameplate power capacity for the Lacy Lakeview Data District in McLennan County, Texas. The parties intend to finalize definitive electric service… The MoU provides a planned pathway for retail electric service and wholesale transmission service for the Lacy Lakeview Data District, targeting commercial operation on 2027-03-15. Power… |
pending | |||
Dominion Energy Virginia Dominion Energy |
VA | PUR-2025-00058 | rate case | 2025-11 | In its November 2025 final order in Dominion’s biennial rate review, the Virginia State Corporation Commission created the GS-5 rate class for new customers with demand of at least 25 MW on a contiguous site and a load factor of at least 75%. The order requires long-term contracts, minimum demand… New qualifying AI data centers taking service after January 1, 2027 will face long-term minimum payment obligations, collateral requirements, and potential exit fees, shifting… |
approved | |
Virginia Electric and Power Company (Dominion Energy Virginia) Dominion Energy, Inc. |
VA | PUR-2026-00011 | other | 2026-02-02 | Virginia Electric and Power Company filed an application with the Virginia State Corporation Commission seeking approval of Large-Load Connection Queue Process Standards. The proposed standards create a formal four-stage process for evaluating and connecting large-load delivery-point requests,… Data-center developers and their electric distribution companies would need to submit delivery-point requests through Dominion Energy Virginia’s Delivery Point Exchange, provide specified… |
pending | |
Virginia Electric and Power Company (Dominion Energy; VEPCO) |
VA | Case No. PUR 2023-2023-00217 | IRP | 2024 | Dominion Energy’s 2024 Integrated Resource Plan establishes four resource portfolios through 2039 to meet projected demand, including extreme load growth from proposed data centers. The plan includes gas-fired generation, nuclear power, renewable energy, storage, and infrastructure investments,… Data-center demand is projected to increase energy demand by 5.5% annually and double overall demand by 2039; without data centers, peak demand would grow by 0.47% annually. Infrastructure… |
contested | |
Appalachian Power Company (APCo) |
VA | PUR-2026-00044 | tariff | 2025-03-24 | APCo filed proposed modifications to its Large Power Service tariff, Rate Schedule L.P.S., for new large-load additions of at least 150 MW on an aggregated basis or 100 MW at an individual site. The SCC approved the schedule on 2026-06-01, with modifications to collateral requirements and exit fees. Data center and other large-load developers using Schedule L.P.S. would face long-term contract commitments, advance notice requirements, minimum monthly billing demand, collateral… |
approved | |
Virginia investor-owned utilities (statewide SCC technical conference) |
VA | other | The Virginia State Corporation Commission scheduled a technical conference to evaluate the impacts of data centers and other large energy users. Potential regulatory changes include revised utility line-extension policies, direct assignment of transmission costs, and a tariff with minimum contract… Data-center developers may face revised line-extension rules, direct assignment of transmission costs, minimum contract terms, and collateral requirements. These measures are intended to… |
pending | |||
PJM Interconnection |
PJM | tariff | 2024-10 | PJM Interconnection filed proposed tariff revisions with the Federal Energy Regulatory Commission in October 2024. The revisions would require new large loads exceeding 100 MW, primarily data centers, to execute a Firm Capacity Service Agreement and post financial security before receiving a firm… Data centers exceeding 100 MW would generally need to post financial security of $15/kW, with the deposit subject to forfeiture if the project withdraws within 24 months of receiving a… |
contested | ||
Pacific Gas and Electric Company (PG&E) |
CA | Resolution E-5420 | special contract | 2025-10-30 | The California Public Utilities Commission adopted Resolution E-5420 approving two agreements between PG&E and STACK Infrastructure to interconnect and energize STACK’s 90 MW Silicon Valley data center. The Commission modified the refund process to provide annual refunds equal to 75% of… STACK must pay the actual costs of PG&E’s special facilities and transmission work as incurred, rather than making a one-time advance payment. STACK is ineligible for PG&E’s 50% discount… |
approved | |
Pacific Gas and Electric (PG&E) |
CA | Resolution E-5455; PG&E Advice Letter 7785-E | special contract | 2025-12-18 | PG&E asked the California Public Utilities Commission to approve an exceptional case agreement with Google LLC for a new 250 MW transmission-level retail load at 230 kV in San Jose. The CPUC delayed its vote on Advice Letter 7785-E, with the vote moved from August 13, 2026, to September 3, 2026. The agreement would provide service for a 250 MW Google data center load at 230 kV. Its ratepayer protections could become de facto large-load terms for later hyperscaler or data-center… |
pending | |
Portland General Electric (PGE) |
OR | tariff | 2026-05-07 | The Oregon Public Utility Commission approved PGE’s new large-load tariff framework. The tariff applies to new customers with loads exceeding 20 MW and requires customers creating the demand to bear the costs of serving their large loads, including necessary infrastructure. The tariff may increase power costs for new data-center facilities while providing greater certainty around grid access and infrastructure-development timelines. It may also encourage… |
approved | ||
Salt River Project (SRP); Arizona Public Service (APS); Tucson Electric Power (TEP) |
AZ | statement | 2026-04 | SRP, APS, and TEP stated that large-load data center customers will be responsible for their infrastructure and service costs. The Arizona Corporation Commission opened a docket and held a workshop to consider policies for large-load customers and protections for ratepayers. Data center developers must pay applicable infrastructure, minimum energy, forecasted demand, or full cost-of-service charges. SRP requires customers using more than 20 megawatts to pay… |
pending | ||
Cheyenne Light, Fuel & Power Company, doing business as Black Hills Energy Black Hills Corp. (NYSE: BKH) |
WY | tariff | Black Hills Energy serves qualifying Wyoming data center customers through its Large Power Contract Service tariff, which has been in place since 2016. The tariff was developed with an early data center customer to support growing industrial and data center load while protecting other customers… The tariff provides customized energy solutions for data center operations, including support for mission-critical electric reliability and sustainability objectives. It is intended to… |
approved | |||
Cheyenne Light, Fuel and Power Company, doing business as Wyoming Electric and Black Hills Energy Black Hills Corporation |
WY | special contract | 2026-04-22 | Wyoming Electric entered into a generation reservation agreement with a prospective customer seeking to construct a 1.8 GW data center under its Large Power Contract Service tariff. The agreement received refundable advances and was amended in July 2026 to increase those advances to $377 million… The agreement supports procurement of long-lead-time generation equipment for the prospective data center while definitive service and generation arrangements remain under negotiation. |
pending |
Interconnection queue
Large-load and data center cluster studies from state utility commissions and utility filings, and the data-center-flagged rows in the national generation and large-load queues. Source and resource breakdowns for the full 32,326-row queue are in the panel above.
Large-load and data center cluster studies
| Utility | State | Study | Requested MW | Filed | Status | Source |
|---|---|---|---|---|---|---|
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 1; announced load 3,500 MW and initial in-service date Q2 2031. Project name, type, city,… |
3,500 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 2; announced load 3,210 MW and initial in-service date Q2 2028. Project name, type, city,… |
3,210 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 3; announced load 3,000 MW and initial in-service date Q4 2027. Project name, type, city,… |
3,000 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 4; announced load 2,000 MW and initial in-service date Q2 2028. Project name, type, city,… |
2,000 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 5; announced load 2,000 MW and initial in-service date Q2 2028. Project name, type, city,… |
2,000 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 6; announced load 2,000 MW and initial in-service date Q2 2028. Project name, type, city,… |
2,000 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 7; announced load 1,600 MW and initial in-service date Q2 2030. Project name, type, city,… |
1,600 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 8; announced load 1,500 MW and initial in-service date Q4 2027. Project name, type, city,… |
1,500 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 9; announced load 1,463 MW and initial in-service date Q4 2027. Project name, type, city,… |
1,463 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 10; announced load 1,400 MW and initial in-service date Q2 2032. Project name, type, city,… |
1,400 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 11; announced load 1,400 MW and initial in-service date Q2 2028. Project name, type, city,… |
1,400 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 12; announced load 1,200 MW and initial in-service date Q2 2028. Project name, type, city,… |
1,200 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 13; announced load 1,200 MW and initial in-service date Q2 2028. Project name, type, city,… |
1,200 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 14; announced load 1,200 MW and initial in-service date Q4 2027. Project name, type, city,… |
1,200 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 15; announced load 1,200 MW and initial in-service date Q4 2027. Project name, type, city,… |
1,200 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 16; announced load 1,200 MW and initial in-service date Q4 2027. Project name, type, city,… |
1,200 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 17; announced load 1,200 MW and initial in-service date Q4 2027. Project name, type, city,… |
1,200 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 18; announced load 1,115 MW and initial in-service date Q2 2028. Project name, type, city,… |
1,115 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 19; announced load 1,020 MW and initial in-service date Q4 2027. Project name, type, city,… |
1,020 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 20; announced load 1,000 MW and initial in-service date Q2 2028. Project name, type, city,… |
1,000 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 21; announced load 910 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
910 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 22; announced load 910 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
910 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 23; announced load 910 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
910 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 24; announced load 860 MW and initial in-service date Q2 2029. Project name, type, city, county,… |
860 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 25; announced load 840 MW and initial in-service date Q2 2029. Project name, type, city, county,… |
840 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 26; announced load 750 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
750 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 27; announced load 725 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
725 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 28; announced load 725 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
725 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 29; announced load 651 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
651 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 30; announced load 648 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
648 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 31; announced load 648 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
648 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 32; announced load 600 MW and initial in-service date Q2 2028. Project name, type, city, county,… |
600 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 33; announced load 600 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
600 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 34; announced load 600 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
600 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 35; announced load 600 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
600 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 36; announced load 576 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
576 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 37; announced load 567 MW and initial in-service date Q2 2030. Project name, type, city, county,… |
567 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 38; announced load 550 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
550 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 39; announced load 550 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
550 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 40; announced load 550 MW and initial in-service date Q2 2030. Project name, type, city, county,… |
550 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 41; announced load 500 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
500 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 42; announced load 500 MW and initial in-service date Q2 2029. Project name, type, city, county,… |
500 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 43; announced load 500 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
500 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 44; announced load 500 MW and initial in-service date Q2 2030. Project name, type, city, county,… |
500 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 45; announced load 481 MW and initial in-service date Q2 2029. Project name, type, city, county,… |
481 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 46; announced load 480 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
480 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 47; announced load 455 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
455 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 48; announced load 455 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
455 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 49; announced load 455 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
455 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 50; announced load 455 MW and initial in-service date Q2 2029. Project name, type, city, county,… |
455 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 51; announced load 450 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
450 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 52; announced load 450 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
450 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 53; announced load 450 MW and initial in-service date Q2 2030. Project name, type, city, county,… |
450 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 54; announced load 432 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
432 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 55; announced load 420 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
420 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 56; announced load 405 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
405 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 57; announced load 365 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
365 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 58; announced load 365 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
365 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 59; announced load 360 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
360 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 60; announced load 360 MW and initial in-service date Q2 2029. Project name, type, city, county,… |
360 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 61; announced load 350 MW and initial in-service date Q2 2028. Project name, type, city, county,… |
350 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 62; announced load 350 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
350 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 63; announced load 325 MW and initial in-service date Q2 2028. Project name, type, city, county,… |
325 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 64; announced load 300 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
300 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 65; announced load 300 MW and initial in-service date Q2 2028. Project name, type, city, county,… |
300 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 66; announced load 264 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
264 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 67; announced load 252 MW and initial in-service date Q2 2028. Project name, type, city, county,… |
252 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 68; announced load 250 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
250 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 69; announced load 240 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
240 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 70; announced load 240 MW and initial in-service date Q2 2029. Project name, type, city, county,… |
240 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 71; announced load 230 MW and initial in-service date Q2 2029. Project name, type, city, county,… |
230 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 72; announced load 216 MW and initial in-service date Q2 2029. Project name, type, city, county,… |
216 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 73; announced load 216 MW and initial in-service date Q2 2029. Project name, type, city, county,… |
216 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 74; announced load 200 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
200 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 75; announced load 200 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
200 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 76; announced load 180 MW and initial in-service date Q2 2029. Project name, type, city, county,… |
180 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 77; announced load 180 MW and initial in-service date Q2 2028. Project name, type, city, county,… |
180 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 78; announced load 175 MW and initial in-service date Q2 2028. Project name, type, city, county,… |
175 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 79; announced load 144 MW and initial in-service date Q2 2029. Project name, type, city, county,… |
144 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 80; announced load 50 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
50 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 81; announced load 50 MW and initial in-service date Q2 2029. Project name, type, city, county,… |
50 | 2026-05-15 | pending | |
Georgia Power Company large load request |
GA | 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline Docket 55378; 56002 Redacted technical-review large-load pipeline entry 82; announced load 45 MW and initial in-service date Q4 2027. Project name, type, city, county,… |
45 | 2026-05-15 | pending | |
Arizona Public Service large load request |
AZ | ACC Data Center/Large Load Workshop Highlights Docket E-00000A-25-0069 ACC workshop materials report APS's estimated large-customer peak-demand load at approximately 13.1 GW in 2026; APS has developed a prospective… |
13,100 | 2026-04-20 | pending | |
Salt River Project large load request |
AZ | ACC Data Center/Large Load Workshop Highlights Docket E-00000A-25-0069 ACC workshop materials state that SRP serves 59 large-load customers with nearly 7,000 MW combined load and has a prospective data-center queue;… |
7,000 | 2026-04-20 | approved | |
Xcel Energy, Colorado other |
CO | Proposed Large Load Tariff Xcel submitted a proposed Colorado large-load tariff for new customers or significant expansions of 50 MW or more; it requires interconnection and… |
2026-04-02 | pending | ||
Dominion Energy Virginia large load request |
VA | Large-Load Connection Queue Process Standards Docket PUR-2026-00011 Dominion's aggregate large-load delivery-point queue was reported at about 70 GW, with approximately 45 GW under study and most requests tied to… |
70,000 | 2026-02-02 | pending | |
AEP Ohio cluster study |
OH | AEP Ohio Schedule DCT Load Study, Cluster 1 Docket 24-508-EL-ATA Aggregate formal-load-study cluster of new data-center projects totaling 5,454.5 MW. Individual customer names, MW values, and POIs were not… |
5,454.5 | 2025-11-07 | pending | |
AEP Ohio cluster study |
OH | AEP Ohio Schedule DCT Load Study, Cluster 2 Docket 24-508-EL-ATA Aggregate formal-load-study cluster of new data-center projects totaling 4,353.2 MW. Individual customer names, MW values, and POIs were not… |
4,353.2 | 2025-11-07 | pending | |
AEP Ohio cluster study |
OH | AEP Ohio Schedule DCT Load Study, Cluster 3 Docket 24-508-EL-ATA Aggregate formal-load-study cluster of new data-center projects totaling 3,215.0 MW. Individual customer names, MW values, and POIs were not… |
3,215.0 | 2025-11-07 | pending | |
Duke Energy Carolinas integrated resource plan appendix |
SC | Carolinas Resource Plan revision for large site projects Duke's revised forecast identifies 35 large site projects, including announced data centers, requiring 24.7 TWh/year by 2033. The public report does… |
approved | |||
ERCOT cluster study |
TX | Batch Zero Interconnection Study Process for Large Loads Docket PGRR145 ERCOT's Batch Zero process applies to large-load facilities of 75 MW or more. The public page gives process thresholds and deadlines but publishes… |
pending | |||
Xcel Energy special contract |
MN | Meta / Amber Kestral enterprise data-center filing Public reporting on an MPUC-related Xcel filing says the enterprise data-center project was expected to start at at least 10 MW and exceed 75 MW in… |
pending |
Data center flagged queue rows
| Project | ISO / utility | State | Developer | MW | Resource | Status |
|---|---|---|---|---|---|---|
Giga Texas Data Center Travis |
ERCOT | Giga Texas Energy, LLC | 133 | battery | IA signed | |
Bullock Gas Hill |
ERCOT | Bullock Data Center, LLC | 1,400 | gas | study | |
Liberty Thermal Energy Center Hill |
ERCOT | Liberty Data Center I, LLC | 1,400 | gas | study | |
IRON MOUNTAIN WIND ENERGY SAN BERNARDINO |
CAISO | CA | 149.4 | wind | withdrawn | |
IRON MOUNTAIN SOLAR 1 RIVERSIDE |
CAISO | CA | 49.5 | solar | withdrawn | |
IRON MOUNTAIN SOLAR 2 RIVERSIDE |
CAISO | CA | 49.5 | solar | withdrawn | |
WARD VALLEY SOLAR ENERGY 2 SAN BERNARDINO |
CAISO | CA | 250 | solar | withdrawn | |
MARTELLA SOLAR KINGS |
CAISO | CA | 20 | solar | withdrawn | |
North Country Data Center St. Lawrence |
NYISO | NY | North Country Data Center | 435 | other | active |
St Lawrence Data and Agricultural Center St. Lawrence |
NYISO | NY | ZeroC Data Centers, LLC | 200 | other | study |
SDC St. Lawrence St. Lawrence |
NYISO | NY | Sabey Data Center Properties, LLC | 120 | other | study |
Suffern Quarry Data Center Rockland |
NYISO | NY | Robert Delcalzo | 200 | other | withdrawn |
Hudson Valley Data Center Rockland |
NYISO | NY | Equity Suffern Developers, LLC | 50 | other | withdrawn |
Hudson Valley Data Center Rockland |
NYISO | NY | Robert Delcalzo | 50 | other | study |
New York State Artificial Intelligence Data Center St. Lawrence |
NYISO | NY | ZeroC Data Centers, LLC | 300 | other | withdrawn |
Olean Digital Data Center Cattaraugus |
NYISO | NY | Olean Digital LLC | 300 | other | withdrawn |
Greenidge 200 MW Data Center Project Yates |
NYISO | NY | Greenidge Generation, LLC | 200 | other | study |
New York State Artificial Intelligence Data Center St. Lawrence |
NYISO | NY | ZeroC Data Centers, LLC | 300 | other | study |
Wulf Compute Data Center II Niagara |
NYISO | NY | TeraWulf Brookings LLC | 250 | other | study |
1 Gig Data Center East Fishkill, NY Dutchess |
NYISO | NY | Donovan Drive Holdings LLC | 1,000 | other | study |
North East Data LLC Data Center Niagara |
NYISO | NY | North East Data LLC | 500 | other | study |
Brookhaven Data Center Suffolk |
NYISO | NY | Brookhaven Logistics Center, LLC | 300 | other | withdrawn |
Pontoon Bridge Road Data Center St Lawrence |
NYISO | NY | American Data Center Partners LLC | 250 | other | study |
Massena Development LLC Power Allocation St; Lawrence |
NYISO | NY | North Country Data Center LLC | 200 | other | study |
iPark 84 Data Center Interconnection Dutchess |
NYISO | NY | iPark East Fishkill LLC | 150 | other | study |
NYISO Load Interconnection Process - Data Center Inquiry Horseheads |
NYISO | NY | URI TALY | 150 | other | study |
Highwall Data Center Clearfield |
NYISO | PA | Highwall Energy, LLC | 400 | other | study |
Compass Rockland |
NYISO | NY | PPL Electric Utilities | 0 | other | withdrawn |
Cedar Lake Solar St. Lawrence |
NYISO | NY | Emeren US, LLC | 8.4 | hybrid | withdrawn |
Suffern Quarry Data Center Rockland |
NYISO | NY | Orange & Rockland | 0 | other | withdrawn |
Bethlehem Energy Center Uprate Albany |
NYISO | NY | GB II New York | 875 | gas | withdrawn |
Colora Tap Cecil |
PJM | MD | 465 | gas | other | |
Colora Tap Cecil |
PJM | MD | 465 | gas | other | |
Colora 34.5kV Cecil |
PJM | MD | 10 | solar | withdrawn | |
Hopewell-Surry 230kV Surry |
PJM | VA | 142.4 | solar | other | |
Dawson-South Justice 115kV Alamance |
PJM | NC | 60 | solar | other | |
Dawson-South Justice 115kV Alamance |
PJM | NC | 80 | solar | other | |
Dawson-South Justice 115kV Halifax |
PJM | NC | 20 | solar | withdrawn | |
Dawson-South Justice 115kV Halifax |
PJM | NC | 140 | solar | other | |
Colora 230 kV Cecil |
PJM | MD | 100.8 | battery | withdrawn | |
Colonial Trail 230 kV Surry |
PJM | VA | 160 | battery | withdrawn | |
Hopewell - Colonial Trail 230 kV Surry |
PJM | VA | 150 | hybrid | active | |
Colonial Trail - Surry 230 kV Surry |
PJM | VA | 80 | solar | withdrawn | |
New Halifax - Dawson 115 kV Halifax |
PJM | NC | 74.9 | hybrid | withdrawn | |
Dawson-South Justice 115kV Halifax |
PJM | NC | 140 | solar | withdrawn | |
Colora 230 kV Cecil |
PJM | MD | 100.8 | battery | withdrawn |
Public companies
Publicly traded issuers with material exposure to tracked projects or jurisdictions, with links to SEC EDGAR and the most recent disclosure on record.
| Ticker | Company | Exposure | EDGAR | Most recent disclosure |
|---|---|---|---|---|
| DLR | Digital Realty Trust | Multi-tenant Texas exposure via Dallas metro; commented favorably on Abbott initiative Aug 7, 2026 | Filings ↗ | 2026-08-07 · press: Digital Realty Welcomes Abbott Initiative 3 on record |
| APLD | Applied Digital | Texas-heavy HPC portfolio | Filings ↗ | 2026-07-29 · 10-K: Applied Digital fiscal 2026 annual report covering AI data center buildout and risk… 4 on record |
| IREN | Iris Energy (IREN) | Childress, TX facility | Filings ↗ | 2026-08-13 · 8-K: IREN delivers Horizon 1 50MW AI data center to Microsoft at Childress Texas 3 on record |
| RIOT | Riot Platforms | Rockdale + Corsicana + Navarro, TX | Filings ↗ | 2026-08-10 · 8-K: $9.1B AI lease at Rockdale + Q2 2026 results 5 on record |
| MARA | Marathon Digital | Texas presence via various JVs | Filings ↗ | 2026-08-06 · 10-Q: MARA second quarter 2026 report disclosing ERCOT Batch Zero and August 3 2026 Texas… 3 on record |
| CLSK | CleanSpark | Texas operations, filed explicit moratorium disclosure | Filings ↗ | 2026-08-06 · 10-Q: CleanSpark third quarter fiscal 2026 report disclosing August 3 2026 Abbott directive… 3 on record |
| BTDR | Bitdeer | Texas mining-to-HPC transition | Filings ↗ | 2026-08-10 · 6-K: Bitdeer reports unaudited second quarter 2026 results with AI cloud and HPC leasing update 3 on record |
| CORZ | Core Scientific | TX HPC exposure; recent AMD AI datacenter pact | Filings ↗ | 2026-08-14 · 8-K: Core Scientific reports update on merger with CoreWeave 4 on record |
| BE | Bloom Energy | On-site power partner | Filings ↗ | 2026-07-28 · 10-Q: Bloom Energy Q2 2026 Form 10-Q, quarterly report with data center fuel cell agreements 3 on record |
| AMZN | Amazon (AWS) | Texas 7.65 GW gas plant + Hobart lawsuit + Tucson cancellation | Filings ↗ | 2026-08-07 · news: Amazon confirmed as backer of 7.65 GW private gas power plant for Texas data centers 4 on record |
| MSFT | Microsoft | Stargate/Abilene + Wisconsin cancellations | Filings ↗ | 2026-07-29 · 10-K: Microsoft fiscal 2026 Form 10-K, annual report with cloud and AI infrastructure spending 3 on record |
| GOOGL | Alphabet/Google | Armstrong TX (BTM) + Pine Island MN (litigation) + Indiana cancellation | Filings ↗ | 2026-07-23 · 10-Q: Alphabet Q2 2026 Form 10-Q, quarterly report with technical infrastructure investment 4 on record |
| META | Meta Platforms | TX facility reported near Austin (unverified) | Filings ↗ | 2026-08-10 · news: Abbott data center agreement with Meta appears to have no impact on Northeast El Paso… 3 on record |
| ORCL | Oracle | Abandoned TX site March 2026; Wisconsin lawsuit; Shackelford Cty delay | Filings ↗ | 2026-08-17 · news: Oracle drops lawsuit challenging Wisconsin data center credit rules 3 on record |
| NVDA | NVIDIA | OpenAI datacenter lease disclosure (10-Q Aug 17) | Filings ↗ | 2026-08-17 · news: OpenAI to lease Ohio data center backed by NVIDIA guarantee 3 on record |
Filings and disclosures
SEC filings with delay or moratorium disclosure language, plus investor press releases and material news on record for watchlist issuers. Newest first.
| Ticker | Form | Date | Filing |
|---|---|---|---|
| ORCL | news | 2026-08-17 | Oracle drops lawsuit challenging Wisconsin data center credit rules Litigation over data center tariffs, Port Washington project |
| NVDA | news | 2026-08-17 | OpenAI to lease Ohio data center backed by NVIDIA guarantee NVIDIA lease and power payment guarantee for AI data center |
| FRMI | 10-Q | 2026-08-14 | Project Matador, Amarillo, Texas (private-grid AI data center and nuclear/gas power campus) Fermi disclosed that Texas's evolving regulatory environment for data centers, including SB6, NOGRR 282, and NPRR 1308, and Governor Abbott's August 3, 2026 directive for PUCT/ERCOT to audit data centers advancing… |
| CORZ | 8-K | 2026-08-14 | Core Scientific reports update on merger with CoreWeave CoreWeave acquisition of Core Scientific |
| IREN | 8-K | 2026-08-13 | IREN delivers Horizon 1 50MW AI data center to Microsoft at Childress Texas Texas AI data center delivery milestone |
| IREN | news | 2026-08-13 | IREN delivers Horizon 1 to Microsoft and achieves NVIDIA exemplar cloud status on GB300 NVL72 Texas AI cloud deployment milestone |
| CRWV | 10-Q | 2026-08-12 | CoreWeave data center delivery / delayed data center site amortization CoreWeave's Q2 2026 10-Q defines a 'delayed data center site amortization date' in its credit facility terms for data center sites that did not meet certain delivery requirements by a specified date, confirming… |
| RIOT | 10-Q | 2026-08-10 | Corsicana Facility and Rockdale Facility, Texas (ERCOT interconnection) Riot disclosed that on August 3, 2026 Texas Governor Abbott directed the PUCT and ERCOT to conduct a comprehensive audit of all data center projects advancing through ERCOT's interconnection process, which could delay… |
| RIOT | 8-K | 2026-08-10 | $9.1B AI lease at Rockdale + Q2 2026 results |
| RIOT | 8-K | 2026-08-10 | Riot second quarter 2026 results with Rockdale AI lease expansion and Corsicana 1 GW letter of intent Texas AI lease expansion and Corsicana LOI |
| BTDR | 6-K | 2026-08-10 | Bitdeer reports unaudited second quarter 2026 results with AI cloud and HPC leasing update Q2 results, AI cloud and HPC leasing, Rockdale Texas |
| META | news | 2026-08-10 | Abbott data center agreement with Meta appears to have no impact on Northeast El Paso project Texas standards and incentive exposure for El Paso campus |
| DLR | press | 2026-08-07 | Digital Realty Welcomes Abbott Initiative |
| DLR | press | 2026-08-07 | Digital Realty welcomes Governor Abbott initiative for responsible Texas data center investment Texas oversight, ERCOT, grid reliability commitment |
| AMZN | news | 2026-08-07 | Amazon confirmed as backer of 7.65 GW private gas power plant for Texas data centers Texas behind-the-meter gas power for AI data centers |
| CLSK | 10-Q | 2026-08-06 | Sandersville, Georgia HPC data center (Sandersville Lease) and Texas ERCOT interconnection sites CleanSpark disclosed the August 3, 2026 letter from Texas Governor Greg Abbott directing ERCOT and the PUCT to audit all data centers advancing through the ERCOT interconnection process before they can proceed, plus… |
| MARA | 10-Q | 2026-08-06 | MARA behind-the-meter data center sites (Texas) MARA's 10-Q references the ERCOT/CenterPoint 'Batch Zero' large-load interconnection review process affecting timing for its behind-the-meter data center power arrangements in Texas. |
| WULF | 10-Q | 2026-08-05 | Cayuga Site, Lansing, New York (HPC data center development) TeraWulf disclosed that in July 2026 New York Governor Kathy Hochul issued Executive Order No. 62, temporarily pausing certain discretionary permits and approvals for covered data center projects, directly implicating… |
| NI | 10-Q | 2026-08-05 | NIPSCO data center contracts with Google/Alphabet (ADS Contract) NiSource's 10-Q discloses material dependence on performance under its 'ADS Contract' data center agreement with Alphabet subsidiary ADS, warning that any decision by ADS or Alphabet to terminate or reduce committed… |
| BTDR | 6-K | 2026-08-05 | Bitdeer reports AI and HPC colocation lease at Tydal Norway AI/HPC colocation lease |
| CIFR | 10-Q | 2026-08-04 | Odessa Facility, Texas (Luminant Lease Agreement) and 700MW HPC hyperscaler pipeline across Texas/Ohio Cipher disclosed that operations require approval from Oncor, AEP, and/or ERCOT to energize each data center, and that deposits with Oncor and AEP for interconnection infrastructure are contingent on energizing sites… |
| WEC | 10-Q | 2026-08-04 | WEC Energy large-scale data center customer projects (Wisconsin) WEC Energy Group's 10-Q lists project termination, cancellation, or delay by data center and other large-scale customers as an explicit risk factor, alongside public opposition to data centers and failure to garner… |
| HUT | 10-Q | 2026-08-04 | Hut 8 site-level ERCOT interconnection exposure Hut 8's Q2 2026 10-Q incorporates by reference its annual report risk factor discussion regarding potential impacts from evolving data center regulatory and tax abatement scrutiny across its jurisdictions, without new… |
| ETR | 10-Q | 2026-07-31 | Meta Platforms data center project, Richland Parish, Louisiana (Entergy Louisiana electric service agreement) Entergy's 10-Q discloses that in June 2026 intervenors in a Louisiana Public Service Commission (LPSC) proceeding sought a subpoena of Meta Platforms to obtain information about its data center project's investment,… |
| D | 10-Q | 2026-07-31 | Loudoun County, Virginia data center cluster ('Data Center Alley') Dominion Energy's 10-Q specifically names Loudoun County, Virginia as a concentration risk for data center-driven demand growth, warning about the ability to obtain regulatory, environmental, and other permits to… |
| DLR | 10-Q | 2026-07-31 | Digital Realty Trust Q2 2026 Form 10-Q, quarterly report with data center portfolio and development Dallas metro and Texas development exposure |
| AMZN | 10-Q | 2026-07-31 | Amazon.com Q2 2026 Form 10-Q, quarterly report with elevated data center capital expenditures AWS data center buildout and capex |
| XEL | 10-Q | 2026-07-30 | Xcel Energy data center customer tariffs (multi-state) Xcel Energy's 10-Q discusses new data center-specific tariffs including minimum demand/revenue requirements and termination or exit fees, designed to ensure data center customers pay the incremental costs to serve… |
| META | 10-Q | 2026-07-30 | Meta Platforms Q2 2026 Form 10-Q, quarterly report with data center and AI capital expenditures Data center capex and El Paso venture context |
| APLD | 10-K | 2026-07-29 | Applied Digital HPC data center campuses (Texas/North Dakota development pipeline) Applied Digital's 10-K risk factors note that governmental authorities have historically imposed moratoria on data center development citing energy usage concerns, and that lessees may terminate leases if construction… |
| MSFT | 10-K | 2026-07-29 | Microsoft fiscal 2026 Form 10-K, annual report with cloud and AI infrastructure spending Data center capital commitments and lease disclosures |
| CORZ | 10-Q | 2026-07-28 | Core Scientific data center delivery to CoreWeave Core Scientific's 10-Q addresses ERCOT interconnection timing risk and community opposition to data center development as factors that could delay conversion of its Texas sites into HPC colocation capacity for… |
| BE | 10-Q | 2026-07-28 | New York hyperscale data center moratorium (statewide) Bloom Energy's 10-Q dedicates a section to 'Increasing Opposition to Data Center Development,' citing the July 2026 New York executive order creating a moratorium on new hyperscale data centers and temporarily pausing… |
| CMS | 10-Q | 2026-07-28 | CMS Electric Supply Plan / Michigan data center load growth CMS Energy's 10-Q flags risk that regulatory action could prohibit, delay, or impair implementation of its Electric Supply Plan, and that anticipated demand growth from data center expansion may not materialize as… |
| CORZ | 8-K | 2026-07-28 | Core Scientific and AMD announce infrastructure partnership for up to 2.5 GW including Texas Pecos and Hunt… Texas AMD AI data center leases |
| META | press | 2026-07-28 | Meta announces strategic venture with BlackRock to develop El Paso Texas data center Texas AI data center, 1 GW, over 10 billion dollar investment |
| GOOGL | 10-Q | 2026-07-23 | Alphabet Q2 2026 Form 10-Q, quarterly report with technical infrastructure investment Data center capex and buildout |
| CLSK | 8-K | 2026-07-14 | CleanSpark secures twenty year Sandersville Georgia data center lease and Texas 885 MW portfolio letter of… data center lease and Texas power portfolio LOI |
| CLSK | press | 2026-07-14 | CleanSpark secures twenty year lease with high investment grade global technology company for data center in… data center lease and Texas portfolio LOI |
| MARA | 8-K | 2026-07-09 | MARA reports Volt Texas acquisition of Texas site with 2,000 MW power capacity subject to ERCOT approval Texas data center site, ERCOT interconnection |
| ORCL | 10-K | 2026-06-22 | Oracle Cloud Infrastructure data center expansion pipeline Oracle's 10-K explicitly warns that government-imposed limits or moratoria on data center construction in a given market could hinder its ability to execute expansion plans, citing delays across design, engineering,… |
| HIVE | 10-K | 2026-06-02 | HIVE data center sites in Canada, Sweden, and Paraguay HIVE's 10-K warns that securing power interconnection agreements and permits for its data centers may be delayed, denied, or become cost-prohibitive due to regulatory processes, and that community opposition to siting… |
| GOOGL | news | 2026-05-26 | Court halts construction on Google Pine Island Minnesota data center Litigation, temporary restraining order over environmental review |
| IREN | 10-Q | 2026-05-08 | IREN Texas and British Columbia data center sites IREN's 10-Q flags 'large load interconnection' risk factors tied to ERCOT-region development, echoing the broader Texas regulatory scrutiny of data center interconnection queues affecting its Childress buildout. |
| CIFR | 10-Q | 2026-05-05 | Cipher Texas/Ohio 4.4GW pipeline sites Cipher's Q1 2026 10-Q reiterates 'large load interconnection' as a specific named risk category for its Texas and Ohio pipeline of 4.4GW across seven sites, noting substation and grid interconnection advancement as… |
| APLD | 8-K | 2026-05-05 | Applied Digital reports completion of financing tied to CoreWeave North Dakota data center lease AI data center lease financing |
| BTDR | 20-F | 2026-04-30 | Bitdeer US data center / ASIC hosting facilities Bitdeer's annual report references ERCOT interconnection exposure for its Texas hosting operations amid heightened regulatory scrutiny of large-load data center interconnection requests in the state. |
| MARA | 8-K | 2026-04-30 | MARA reports transaction with FTAI Infrastructure for 485 MW co-located data center power asset data center power asset transaction |
| BE | press | 2026-04-27 | Oracle, BorderPlex and Bloom Energy to power Project Jupiter with fuel cell technology On-site fuel cell power replacing gas turbines for Texas data center |
| APLD | 10-Q | 2026-04-08 | Applied Digital data center campuses (construction supply chain) Applied Digital disclosed that global supply logistics delays affecting power and cooling equipment for HPC/AI data centers have been, and may continue to be, impacted by tariffs, extending construction timelines. |
| GOOGL | news | 2026-04-07 | Google to use natural gas to power off grid data center in Armstrong County Texas Behind-the-meter gas power, Texas, Crusoe Goodnight campus |
| BITF | 10-K | 2026-03-31 | Panther Creek, Nesquehoning, Pennsylvania (PJM interconnection) and Magog, Quebec lease termination Bitfarms (now Keel Infrastructure) disclosed PJM's 2025 Regional Transmission Expansion Plan indicates transmission enhancements needed to serve new data center power demand could take more than five years, and… |
| GREE | 10-K | 2026-03-31 | Greenidge/Vulcan data center and power generation facilities (New York, Texas) Greenidge (now Vulcan Infrastructure & Power) references general data center construction and permitting delay risk in its 10-K following its corporate rebrand and pivot toward broader infrastructure/power generation… |
| BTBT | 10-K | 2026-03-27 | WhiteFiber subsidiary data centers (MTL-1, MTL-2, MTL-3 Montreal; North Carolina) Bit Digital's 10-K, discussing its WhiteFiber subsidiary, disclosed that development delays could arise from zoning and permitting requirements, and specifically from local community resistance or protests in response… |
| WYFI | 10-K | 2026-03-26 | WhiteFiber Montreal (MTL-1/2/3) and North Carolina data centers WhiteFiber's 10-K states its data center operations are currently limited to Montreal, Canada, with North Carolina coming online, and discloses that development activities face delays from zoning and permitting… |
| MSFT | news | 2026-03-24 | Microsoft to rent Abilene Texas data center dropped by OpenAI and Oracle Texas Stargate-adjacent lease, capacity reshuffle |
| ORCL | news | 2026-03-06 | Oracle and OpenAI end plans to expand flagship Abilene Texas data center Texas Stargate expansion abandoned |
| CORZ | 10-K | 2026-03-02 | Core Scientific HPC/AI data center conversions (Texas colocation sites); Texas Senate Bill 6 Core Scientific disclosed that Texas enacted Senate Bill 6 in June 2025, introducing significant new requirements for large-load electricity customers exceeding 75MW in ERCOT, including new obligations to contribute to… |
| CRWV | 10-K | 2026-03-02 | Third-party-provided data centers (widely reported to involve Core Scientific) CoreWeave's 10-K explicitly discloses delays announced in November 2025 regarding delivery of certain data centers to be provided by a third-party data center provider, warning that failure by third-party providers to… |
| WULF | 10-K | 2026-02-27 | Justified Data Campus (up to 480MW gross power availability) TeraWulf's 10-K describes construction of the Justified Data Campus HPC/AI data center, noting the buildout is subject to site planning and phased construction beginning in 2026 extending through 2027, dependent on… |
| VST | 10-K | 2026-02-27 | Vistra nuclear/gas generation serving data center large-load customers (ERCOT and PJM) Vistra's 10-K discusses risks tied to serving large-load data center customers, including project termination, cancellation, or delay risk, and the need for regulatory approval of new tariffs designed to allocate… |
| HUT | 10-K | 2026-02-25 | Hut 8 HPC data center sites (Texas/North America) Hut 8's 10-K risk factors cite tax abatement scrutiny and local moratoria as increasing constraints on new data center development in jurisdictions where the company operates. |
| NVDA | 10-K | 2026-02-25 | Customer/partner AI data center build-outs dependent on Nvidia hardware NVIDIA's 10-K warns that power or water shortages, land or permitting constraints, or regulations limiting energy, water, or land availability could impair customers' ability to expand data center capacity and consume… |
| CIFR | 10-K | 2026-02-24 | Cipher 5.3GW data center portfolio across 11 sites (Texas and Ohio) Cipher's 10-K states its ~5.3GW portfolio across 11 sites is at various stages of interconnection, with 700MW of HPC facilities under development across three sites for hyperscaler tenants, and warns that community… |
| CEG | 10-K | 2026-02-24 | Crane Clean Energy Center (Three Mile Island Unit 1 restart) for Microsoft PPA Constellation's 10-K discloses that under its agreement, Microsoft will purchase the output of the restarted Crane Clean Energy Center (formerly Three Mile Island Unit 1, retired in 2019) to power its data centers,… |
| NRG | 10-K | 2026-02-24 | PJM region data center large-load interconnection studies NRG's 10-K discloses that all 13 PJM-region governors signed a Statement of Principles urging PJM to address revenue certainty for new generation and allocate new resource costs to data centers, and that project delays… |
| AMT | 10-K | 2026-02-24 | American Tower data centers segment (ground-up builds and expansions) American Tower's 10-K states that local authorities and community residents periodically oppose data center construction, which can delay or prevent new builds, and that power constraints, delays, and unfavorable… |
| DLR | 10-K | 2026-02-13 | Digital Realty global data center development pipeline Digital Realty's 10-K risk factors cite zoning and permitting delays, including public or government opposition, as risks that could delay completion of its global data center development pipeline (769 MW of projects… |
| IRM | 10-K | 2026-02-12 | Iron Mountain Global Data Center Business Iron Mountain's 10-K discloses that its Global Data Center Business is susceptible to regional/local power costs, shortages, and outages, and that connectivity interruptions or terminations could adversely affect its… |
| EQIX | 10-K | 2026-02-11 | Equinix global colocation/interconnection data center portfolio Equinix's 10-K risk factors discuss supply chain and procurement disruptions leading to construction delays, plus zoning, permitting, and community/government opposition risk affecting new data center construction… |
| BE | 10-K | 2026-02-09 | FERC/DOE large load co-located generation rulemaking Bloom Energy's 10-K discusses that grid constraints and permitting delays are extending time-to-power for traditional data center facilities and expansions, and that local moratoria, protests, or siting restrictions on… |
| RIOT | 8-K | 2026-01-16 | Riot acquires Rockdale land and signs first data center lease with AMD in Texas Rockdale Texas AMD data center lease |
| RIOT | news | 2026-01-16 | Riot announces fee simple acquisition of land and first data center lease with AMD at the Rockdale site Rockdale Texas AMD lease detail |
| BE | news | 2026-01-08 | American Electric Power agrees to deploy up to 1 GW of Bloom Energy fuel cells Utility-scale on-site power for data centers bypassing grid queue |
| AMZN | news | 2025-12-16 | Hobart Indiana officials sued by residents over rezoning for Amazon data center Litigation over data center rezoning |
| AMZN | news | 2025-12-02 | Amazon pulls out of Project Blue data center campus in Tucson Arizona Data center cancellation over water and power concerns |
| CLSK | 10-K | 2025-11-25 | Sandersville, Georgia HPC data center campus CleanSpark's 10-K risk factors warn that if it fails to complete the Sandersville facility on time under the Sandersville Lease, the customer may terminate the agreement, seek damages, or pursue other remedies, and… |
| NVDA | 10-Q | 2025-11-19 | NVIDIA Q3 fiscal 2026 Form 10-Q, quarterly report noting no assurance of definitive OpenAI agreements SEC risk disclosure on OpenAI data center commitment |
| IREN | 8-K | 2025-11-03 | IREN secures approximately 9.7 billion dollar AI cloud contract with Microsoft at Childress Texas Texas AI cloud contract with Microsoft |
| GOOGL | news | 2025-09-22 | Google withdraws proposed data center in Franklin Township Indiana after opposition Data center cancellation after community pushback |
| NVDA | press | 2025-09-22 | OpenAI and NVIDIA announce strategic partnership to deploy 10 gigawatts of NVIDIA systems Up to 100 billion dollar OpenAI data center investment |
| APLD | 8-K | 2025-08-29 | Applied Digital finalizes additional 150MW CoreWeave lease at Polaris Forge 1 Ellendale campus 150MW AI/HPC lease, North Dakota |
| IREN | 10-K | 2025-08-28 | Childress, Texas facility (Horizon 1 direct-to-chip liquid cooling deployment) IREN disclosed that ERCOT issued a July 23, 2025 market notice requesting information on voltage ride-through capabilities for data center and crypto-mining loads of 75MW or greater, to determine reliable… |
| APLD | 8-K | 2025-06-02 | Applied Digital announces 250MW AI data center lease with CoreWeave at Ellendale North Dakota 250MW AI/HPC lease, North Dakota |
| MSFT | news | 2025-03-21 | Microsoft halts work on future phases of Wisconsin Mount Pleasant data center Data center project pause and design reevaluation |
| TLN | EX-99.1 | 2025-02-27 | Susquehanna nuclear plant co-located data center campus (Pennsylvania) Talen's earnings materials reference its data center campus adjacent to the Susquehanna nuclear generating station and the interconnection/regulatory review process for co-located large loads that FERC and PJM were… |
| CORZ | press | 2025-02-26 | Core Scientific and CoreWeave announce 1.2 billion dollar expansion at Denton Texas site Denton Texas HPC expansion |
| RIOT | 8-K | 2025-01-21 | Riot Platforms launches formal evaluation of AI and HPC uses for remaining 600 MW at Corsicana Texas Corsicana Texas AI/HPC evaluation |
Government releases
Official statements and regulatory notices from the Governor of Texas, ERCOT, the PUCT, and the Texas Legislature on the data center audit and large-load interconnection process. Newest first.
Methodology and scope
This watchlist tracks U.S. data center projects, operators, and jurisdictional actions that carry a documented public paper trail: securities filings, regulatory dockets, litigation, government statements, utility filings, and trade press. It is maintained as a neutral reference. Entries are recorded as observed; the tracker does not rank projects or advocate an outcome.
- Status reflects the most recent public signal for each entry. Where a project continues on schedule, that is recorded as plainly as a delay.
- Capacity is shown in megawatts where reported, and left blank where not disclosed.
- Local restrictions, utility dockets, lawsuits, and federal actions are drawn from primary filings and reputable outlets, each linked to its source.
- The ERCOT queue snapshot is extracted directly from the ERCOT GIS Report.
- Signals are collected on a recurring basis and reconciled into a single source of truth before publication.
Every citation on one page: Sources and citations. Companion policy map: SAVRN Data Center Moratorium Tracker. Capital side: North American Data Center Capital Atlas. Founder essay: The Queue Was the Fiction.
What is the Nationwide Data Center Delay Watchlist?
It is a continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Each entry links to its documented public source, and it is maintained as a neutral reference.
How is a project's status determined?
Status reflects the most recent public signal for each entry: halted, delayed, cancelled, pending review, litigation active, audit paused, under appeal, or withdrawn. Where a project continues on schedule, that is recorded as plainly as a delay.
How are delay days measured?
Delay days are measured against the original announced target where available, or against the first documented delay date.
How often is the watchlist updated?
Signals are collected on a recurring basis from SEC EDGAR and trade-press feeds and reconciled into the single source of truth before publication.
How is this different from the Data Center Moratorium Tracker?
The Moratorium Tracker maps state and local policy measures. This watchlist tracks named projects, operators, public-company exposure, and securities filings, with delay status and cause for each. The two are companion references.