SAVRN. Engage SAVRN
Insights Regulation

The August 17 Deadline

How FERC's show-cause order rewrites the AI factory interconnection playbook — the one day that resets the rules for every co-located, behind-the-meter, and >50 MW AI campus in the country, and why the off-grid campus is the only architecture that reads the rewrite as tailwind.

An off-grid AI data center campus with its own on-site power generation and closed-loop liquid cooling, standing apart from distant grid transmission towers that trail off unconnected — SAVRN's islanded campus model.
An off-grid AI factory campus generates its own power and islands from the grid — the transmission service the August 17 rewrite reshapes is one it never takes.
🎙 The Conversation
The August 17 Deadline
A two-host discussion with Gia & Alexey · 4:23
0:00 4:23

On August 17, 2026, six grid operators file the answers that will govern how every large AI campus in the United States connects to the grid for the next decade. This is the Show Cause Response deadline set by the Federal Energy Regulatory Commission on June 18, 2026 — a single 60-day window in which PJM, MISO, SPP, CAISO, ISO-NE, and NYISO must either demonstrate that their existing tariffs are just and reasonable or propose the tariff changes that fix what FERC has already found deficient (JD Supra national preview, McGuireWoods client alert). Ninety days ago, in “The Quiet Rewrite,” we called this the convergent framework and the 24-month window. August 17 is the day that framework stops being a forecast and becomes a filing.

The stakes are not academic. FERC's own language frames the orders as national industrial policy: how the transmission system is “studied, planned, expanded and operated is critical to the United States winning the AI race and onshoring manufacturing” (McGuireWoods). Chairman Swett described the six-order structure as the way to “spearhead lasting reform much more expeditiously” than a nationwide rulemaking. Read that as: the Commission decided the interconnection queue is too slow to survive the AI capex cycle, and that a nationwide notice-and-comment rulemaking is too slow to fix it. So it opened six parallel Section 206 proceedings and put every organized market on a stopwatch.

This is a field report from inside those six dockets, written for the operator, the university host, and the capital partner trying to underwrite a 2027 or 2028 energization date. Every date, every threshold, every docket below is sourced. And every one of them cuts the same way: the tariff being rewritten is the tariff the SAVRN campus never touches.

The 60-day compression

From issuance to filing: the show-cause clock

Jun 18 6 orders issued Jul 9 Intervention +21d Jul 20 Info reports +30d Aug 3 Abeyance + NERC L3 reply +45d AUG 17 · +60d Show Cause Response justify, reform, or seek abeyance Sep 16 Replies open +90d
Source: FERC Section 206 show-cause orders, June 18, 2026; schedule per McGuireWoods and JD Supra. All six informational reports filed on schedule July 20.

01The one-day rewrite

On June 18, 2026, FERC issued six tailored Section 206 show-cause orders — one to each FERC-jurisdictional RTO/ISO — finding the tariffs of all six “deficient in how they handle large load interconnection” (JD Supra). Each order directs the grid operator to “justify how their existing tariffs provide for the interconnection of large and co-located loads to the electric grid or to propose revisions to their tariffs” (McGuireWoods).

Six identical copper archway gates in a bright white gallery, one glowing blue — a metaphor for six grid markets placed under simultaneous FERC review.
Six markets, one order stack: FERC opened a separate Section 206 docket for each RTO/ISO and put them all on the same 60-day clock.

The six dockets are open and numbered:

RTO / ISODocket
PJMEL26-67-000
SPPEL26-68-000
NYISOEL26-69-000
MISOEL26-70-000
CAISOEL26-71-000
ISO-NEEL26-72-000

Each order requires each RTO/ISO to demonstrate that it already uses, or proposes to adopt, reforms in five categories (McGuireWoods, Electron Economics):

  1. Faster, standardized application and study processes for large loads.
  2. Greater transparency on network-upgrade costs and cost recovery — to keep new-load costs from shifting onto other ratepayers.
  3. Rates and terms for large loads served by co-located generation.
  4. New transmission services for flexible large loads.
  5. Study processes for generation serving electrically proximate load.

Read those five together. Categories three, four, and five are all describing the same architecture from three different angles: generation and load that sit on the same site, connected first to each other and second — if at all — to the transmission system. FERC did not settle who pays for the AI grid on June 18. It made every organized market design its own answer to that question in 60 days.

02Why “informational” reports were the real preview

On July 20, all six grid operators filed the Informational Reports FERC ordered as a first step. Read together, they are what one national practice team called a “rare, coast-to-coast snapshot of the regulatory landscape for data centers, AI campuses, and other large loads” (JD Supra). They also previewed the split every developer should expect on August 17.

  • PJM (EL26-67): described stakeholder initiatives and accepted reforms aimed at ensuring resource adequacy for new large loads and increasing the pace of adding generating capacity. Centerpiece: the Critical Issue Fast Path for Reliability Backstop Procurement.
  • SPP (EL26-68): argued its existing stack — ERAS, Provisional Load, HILLs, HILLGA, CHILLS, PDA, CPP — “collectively addresses resource adequacy for new large loads” and that “no immediate tariff overhaul is required.” All 65 Load Responsible Entities satisfy Summer 2026 resource-adequacy requirements, with an East BAA reserve margin of 17.1% and roughly 5,752 MW of excess accredited capacity.
  • NYISO (EL26-69): acknowledged emerging risks from large load growth and an aging generation fleet.
  • MISO (EL26-70): acknowledged that the “concentrated, fast-moving nature of new large load demand requires new tools.”
  • CAISO (EL26-71): described its coordinated resource-planning framework and transmission-expansion efforts.
  • ISO-NE (EL26-72): outlined existing and potential proposals to ensure adequate generation for new large loads.

The market's read is that August 17 will be “the defining moment”: some operators will file concrete tariff revisions, others will defend existing frameworks, and others will seek abeyance to make a Section 205 filing later in the fall (JD Supra). PJM has already taken the third path.

Filed since this cycle began

On July 28, 2026, PJM moved to hold EL26-67 in abeyance for 90 days and to file its Section 205 response by early-to-mid November 2026 (PJM, Motion for Abeyance in EL26-67). The practical meaning is direct: the largest of the six markets will not put substantive tariff revisions on the table on August 17 — it will put a schedule on the table, and the real filing lands in November. What no one disputes is that the tariff you sign in 2027 will not be the tariff on the books today.

03The PJM template: the 50 MW line and the December 18 cutoff

The clearest read on what “reform” actually means on the ground comes from PJM, which has been under a parallel FERC show-cause order for eight months already.

On December 18, 2025, FERC issued a unanimous 5-0 order finding PJM's existing tariff “unjust and unreasonable” on the basis that it “lacked consistent rules for co-located load at generating facilities” (Electron Economics). The order, cited in FERC's docket as PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025), directed PJM to create three new transmission service options for co-located customers — firm contract demand, non-firm contract demand, and an Interim Network Integration Transmission Service — and to fix a set of behind-the-meter generation (BTMG) netting rules that FERC concluded were shifting costs onto standard ratepayers (White & Case).

Behind-the-meter · single-line

Where the 50 MW boundary bites: the co-located one-line

GRID SIDE BEHIND THE METER UTILITY GRID SUBSTATION XFMR M REVENUE METER · POI CO-LOCATED CONFIGURATION SITE BUSBAR G ON-SITE GENERATION gas · fuel cell · storage AI DATA-CENTER LOAD compute + cooling cumulative BTMG = 50 MW ≤ 50 MW self-supply may net against transmission charges > 50 MW billed as if the generator did not exist
A behind-the-meter (co-located) single-line. On-site generation and the data-center load share a busbar behind the revenue meter. Above 50 MW cumulative nameplate, that self-supply can no longer net against transmission charges — it is billed as if the generator were not there.

PJM filed compliance on January 20 and February 23, 2026 in Docket ER26-5181, and the numbers that came out of that filing now define the operator playbook across every market watching the August 17 rewrite (White & Case, POWER Magazine):

  • The 50 MW line. Any BTMG configuration above 50 MW loses the right to net its self-supply against transmission charges under the old rules. Retail BTMG is capped at a cumulative nameplate rating of 50 MW or less.
  • The December 18, 2025 grandfather cutoff. Facilities above 50 MW are eligible to be permanently grandfathered only if operating under a contractual arrangement in effect before December 18, 2025. PURPA Qualifying Facilities operational before that date are also exempt. Everything else, “regardless of development stage or existing term sheets, faces the new framework” (Electron Economics).
  • The emergency-generation exemption. On-site backup generation is excluded from the 50 MW cumulative nameplate calculation — so a campus can maintain large diesel or natural-gas backup arrays for reliability without tripping BTMG netting restrictions, provided those units do not provide energy for standard retail netting.
  • The “Necessary Studies” process. Generators serving co-located load are required to reduce their Capacity Interconnection Rights and bear all upgrade costs (POWER Magazine).
  • The timing. PJM's Point of Change in Ownership definition is being litigated by Vistra and Constellation, which filed protests on March 16, 2026 arguing that transmission owners can manipulate facility boundaries to block grandfathering eligibility. An April 2026 FERC action required further revisions. The full mechanism, PJM concedes, “likely won't be active until 2027” (POWER Magazine).

A 300 MW AI campus with a 400 MW on-site gas plant is a fundamentally different asset before and after that number. After, it is transmission-charged as if the generator did not exist — and “behind the meter” as a financing construct collapses into a real-estate arbitrage that FERC has now told PJM to close.

Every developer signing a term sheet in 2026 for delivery in 2028 is signing into the new framework, not the old one. The five other RTOs are watching PJM's compliance dockets the way underwriters watch a comparable transaction. On August 17, several of them will publish their own version of the same line.

04The queue reality: PJM Cycle 1 and 200 GW of ambition

Behind the tariff rewrite is the queue rewrite. On April 27, 2026, PJM closed the application window for Cycle 1 of its reformed interconnection process. On August 3, 2026, PJM announced that 715 new generation projects, totaling 201.5 GW of nameplate capacity, had qualified to be studied in Cycle 1 out of 811 initial proposals (PJM Inside Lines). The new approach is “first-ready, first-served,” and PJM used HyperQ — an AI tool built by Google's Tapestry — to screen application data.

PJM Cycle 1 · accepted for study

A load-following queue, not a decarbonization queue

25 50 75 100 Nameplate capacity (GW) Natural gas 99.8 GW 147 projects Storage 60.0 GW 314 projects Nuclear 17.3 GW 24 projects Solar 11.8 GW 117 projects Solar-storage 7.5 GW 37 projects Wind · Other · Hydro 5.1 GW
Source: PJM Inside Lines, Aug 3, 2026. Total: 715 projects, 201.5 GW. Nearly half the capacity is natural gas; nuclear alone (17.3 GW) is larger than solar.

Read the mix. Nearly half the queue's capacity is natural gas. A quarter is storage. Nuclear alone — 24 projects, 17.3 GW — is larger than solar. This is not a decarbonization queue. This is a load-following queue built to serve AI. And PJM has already told the market what it thinks will actually get built: since 2020, PJM has processed more than 300 GW of projects, of which about 100 GW reached signed interconnection agreements and only 51 GW is currently active. Cycle 1 study runs one-to-two years, with completion expected in 2028.

PJM expects electricity demand to increase by up to 70 GW by 2038, driven largely by data centers and other large-load customers, “outpacing the addition of new supply” (PJM Inside Lines). Utilities in the PJM footprint collectively forecast 55 GW of new large-load growth by 2030 and 100 GW by 2037 (White & Case). The queue reform is designed to close the gap. Every operator paying attention knows the arithmetic does not close.

05Batch Zero: ERCOT does the same thing, faster

Texas is not a FERC-jurisdictional RTO, so it is not one of the six show-cause dockets. It is running its own version of the rewrite on a parallel timeline. On June 18, 2026 — the same day FERC issued the six show-cause orders — the Public Utility Commission of Texas approved Planning Guide Revision Request 145 and Nodal Protocol Revision Request 1325, effective July 11, 2026 (Krishnan Rangachari, “The Data Center Reckoning”). PGRR 145 and NPRR 1325 replaced ERCOT's project-by-project Large Load Interconnection Study with “Batch Zero” — a single, system-wide study evaluating all qualifying large-load requests (75 MW and above) together.

438,000
MW of large-load interconnection requests in ERCOT's queue
~89%
of that queue is data centers or crypto-mining
75 MW
Batch Zero threshold — studied as one cohort
Mar 1 '27
binding agreements, backed by financial security

The scale explains the process. Evaluating 438,000 MW project-by-project was, as one analyst put it, a queue “too large to be evaluated project-by-project without collapsing under its own backlog.” The Batch Zero schedule runs from mid-July 2026 technical submissions, to an August 7, 2026 inclusion notice, to full study results with year-by-year 2028–2032 capacity allocations on January 29, 2027, to binding interconnection agreements on March 1, 2027 (Krishnan).

Under Texas's SB 6 (2025), large loads such as data centers must accept curtailment during grid emergencies as a condition of interconnecting at all — the statute sets a 75 MW demand threshold and lets ERCOT direct a large load to deploy on-site backup generation or curtail (SB 6, Sec. 37.0561). ERCOT operationalizes that mandate through load elections of its own: a load that declines firm dispatch obligations (a “PCLR” election) or does not pair with onsite generation (a “WLPUN” election) is capped at a lower firm-capacity level (Krishnan). “Curtailment isn't a matter of ongoing negotiation in ERCOT's model. It's a statutory precondition.”

Same rewrite. Different acronyms. Same conclusion: the grid-tied AI campus is now a longer, harder, more expensive path.

06The PJM capacity signal

PJM's Board is not waiting for August 17 to price the shortfall. On July 27, 2026, PJM's Board of Managers proposed a package aimed at both procuring more capacity and reallocating the cost and risk of new large loads (Krishnan).

PJM capacity price signal

The backstop ceiling sits 68% above the last cleared price

$329.17 Last cleared price 134,479 MW cleared $555 Backstop auction ceiling targets ~6.8 GW gap +68% per MW-day
Source: Krishnan Rangachari. PJM's own analysis attributes 45% of the $47.2 billion in capacity costs across its last three auctions to data-center demand. The backstop auction is expected Sept 30–Oct 21, 2026.

Structurally more important than the auction: PJM's Board will direct staff to exclude incremental new large loads, relative to the 2028/29 forecast, from the demand counted in future capacity auctions — unless the large load lines up its own capacity supply. In PJM's own words, “existing consumers should not bear higher capacity costs caused by new large loads that do not bring, or otherwise contract for, the new supply necessary to serve them” (Krishnan).

On June 30, 2026, PJM's Members Committee endorsed the backstop procurement package and rejected all eleven proposed “Connect and Manage” curtailment options — none reached the required two-thirds sector-weighted threshold. Stakeholders backed a “Large Load Registry” instead, under which PJM would track large loads by site and whether they bring their own supply, and hand the data to state regulators.

The signal to any AI campus developer in PJM is unambiguous. Bring your own generation, or price yourself into the backstop.

07The reliability overlay: NERC Level 3 and the August 3 gate

Sitting on top of the market-design fight is a reliability-standards fight the market is only starting to price. On May 4, 2026, following a Board of Trustees vote on April 16, the North American Electric Reliability Corporation issued a Level 3 Essential Action Alert titled Computational Load Modeling, Studies, Instrumentation, Commissioning, Operations, Protection, and Control (NERC, Renewable Energy World). The alert names seven Essential Actions for Transmission Planners, Planning Coordinators, Transmission Owners, Balancing Authorities, Reliability Coordinators, and Transmission Operators — from annual stability-margin studies in areas with computational load, to a formal commissioning process, to dynamic fault-recording instrumentation, to interpersonal-communication capability between operators and each large load.

Acknowledgment was due May 11, 2026. Formal responses were due by midnight Eastern on August 3, 2026 through the NERC Alert System (ERCOT LLWG briefing). NERC has stated its intent to file revised registration criteria and Reliability Standards for large loads on or before December 31, 2026 (NERC filing in RM26-4).

Two operator-facing implications matter. First, commissioning any large AI facility from 2026 forward will land inside a formal computational-load process that did not exist twelve months ago — TO-authored, TP/PC-studied, and dynamic-fault-recorder instrumented. Second, the underlying finding of NERC's March 2026 white paper is that existing NERC Reliability Standards, industry processes, and requirements are “inadequate for the reliable integration of emerging large loads, including computational loads, onto the BPS” (NERC Large Loads FAQ). Mandatory Reliability Standards updates are landing by year-end.

August 17 sets the market design. August 3 already set the reliability floor. Both point at the same architecture.

08What the six-order stack means for the operator

Read all of it together — Section 206 orders in EL26-67 through EL26-72, the December 18 PJM order, Cycle 1's 715 projects and 201.5 GW, ERCOT's Batch Zero and 438,000 MW of queued load, the July 27 PJM capacity package, and the NERC Level 3 alert — and the signal is coherent.

  • Every market is pricing new large load as a source of cost causation.
  • Every market is moving to require that large loads bring, or contract for, the supply that serves them.
  • Every market is compressing the interconnection study window while raising the technical bar to enter it.
  • Every market is codifying curtailment obligations — through tariff (PJM), statute (ERCOT SB 6), or reliability standard (NERC's coming December 31 filing).
  • Every market is doing this while the queue-to-signed-agreement ratio, on PJM's own data, is roughly 33%.

The grid-tied AI factory business case now runs through five gates that did not exist as codified filings 18 months ago. Each gate is a source of delay, cost, and cost-shift risk. Each is being priced into the underwriting of every 2027, 2028, and 2029 energization.

The five gates

What the grid-tied campus must clear — and what a SAVRN campus does instead

The gateGrid-tied AI campusSAVRN off-grid campus
Section 206 tariff
Aug 17
Files into a transmission-service tariff being rewritten in real time.Takes no transmission service to power compute. A landlord's problem, not a tenant's.
BTMG netting rule
50 MW / Dec 18
Above 50 MW, netted as if the generator did not exist.Does not net; does not draw. Carve-outs are not the design margin.
Interconnection cycle
Cycle 1 / Batch Zero
Waits in a one-to-two-year queue; ~33% reach signed agreements.Enters no queue. Generation and load are behind the same fence.
Reliability commissioning
NERC Level 3
New TO-authored computational-load process; standards by year-end.Compute behind a private, closed-loop system. A small, controllable BPS interface.
Capacity cost allocation
Backstop / Registry
Cost allocated to loads that don't bring their own supply.Brings its own supply as the entire premise.
Every gate reads differently from an off-grid starting point. The dockets, thresholds, and deadlines above are the grid-tied campus's five-front problem — and the SAVRN campus's five-part answer.

09The SAVRN answer

SAVRN is the operator of an off-grid sovereign AI infrastructure campus model — owned power generation, owned compute, closed-loop liquid cooling — deployed in 6 to 12 months versus the 24-to-48-month industry standard. The campus is designed to island from the grid on day one. The transmission service is not undersized; it is not part of the design.

A self-contained AI factory campus enclosed in a copper power ring and a blue closed-loop cooling ring, with the public grid and its transmission towers sitting separate and untouched outside the circle — SAVRN's islanded, energy-independent model.
Generation and load behind one fence: the campus brings its own supply, so it never draws the town's capacity to energize.

The industry timeline the July 20 informational reports described — Section 206 tariff filings August 17, protests through September, compliance orders through fall, “and eventually interconnection-study and financing consequences” (Electron Economics) — is a two-to-four-year path to a codified answer. SAVRN campuses are being energized inside that window.

The reason a SAVRN campus is fast is the same reason it is a good neighbor: we own the power. Because we generate on site, we skip the queue — and because we skip the queue by islanding from the grid, we never draw the town's capacity to do it.

The town's grid, its rates, and its queue position are untouched by our arrival. The tariff being rewritten is the tariff we never touch. On August 17, six grid operators file the answer to a question SAVRN campuses are architected not to ask.

10Frequently asked questions

What is the August 17, 2026 FERC deadline?+
It is the Show Cause Response deadline in FERC's six Section 206 proceedings. Each of the six RTOs/ISOs — PJM, MISO, SPP, CAISO, ISO-NE, and NYISO — must either demonstrate that its existing large-load and co-location tariff is just and reasonable, or propose the tariff changes that fix the deficiencies FERC identified on June 18, 2026.
Which grid operators received the FERC show-cause orders?+
All six FERC-jurisdictional RTOs/ISOs: PJM (EL26-67-000), SPP (EL26-68), NYISO (EL26-69), MISO (EL26-70), CAISO (EL26-71), and ISO-NE (EL26-72). Each received a tailored Section 206 order on June 18, 2026.
What is the 50 MW behind-the-meter generation line?+
Under PJM's December 18, 2025 co-located load order, any behind-the-meter generation (BTMG) configuration above 50 MW loses the right to net its self-supply against transmission charges under the old rules. Above 50 MW a campus is transmission-charged as if its on-site generator did not exist — unless it was grandfathered by a contract in effect before December 18, 2025.
What is the December 18, 2025 grandfather cutoff?+
Facilities above 50 MW can be permanently grandfathered only if they were operating under a contractual arrangement in effect before December 18, 2025. PURPA Qualifying Facilities operational before that date are also exempt. New arrangements face the new framework regardless of development stage or existing term sheets.
What is ERCOT's Batch Zero?+
Batch Zero is ERCOT's system-wide large-load interconnection study, created by PGRR 145 and NPRR 1325 (approved June 18, 2026, effective July 11, 2026). It replaces the project-by-project study with a single cohort study of all qualifying large-load requests of 75 MW and above, delivering results January 29, 2027 and requiring binding agreements by March 1, 2027.
How many projects are in PJM's reformed Cycle 1 queue?+
On August 3, 2026, PJM announced that 715 generation projects totaling 201.5 GW of nameplate capacity qualified for Cycle 1, out of 811 initial proposals. Nearly half the capacity is natural gas. Historically only about a third of projects that enter PJM's queue reach a signed interconnection agreement.
What is the NERC Level 3 alert on computational load?+
On May 4, 2026, NERC issued a Level 3 Essential Action Alert titled “Computational Load Modeling, Studies, Instrumentation, Commissioning, Operations, Protection, and Control.” It names seven essential actions for planners and operators, with formal responses due August 3, 2026 and mandatory Reliability Standards expected by December 31, 2026.
Does the August 17 deadline apply to off-grid AI campuses?+
No. The show-cause orders rewrite the transmission-service tariff and co-located-load rules for campuses that draw from the grid. An off-grid campus that generates its own power and islands from the grid takes no transmission service, enters no interconnection queue, and does not net a behind-the-meter generator against network charges — so the rewrite does not gate its schedule.
What are the five gates a grid-tied AI campus must clear?+
A Section 206 tariff (August 17), a BTMG netting rule (50 MW / December 18), a reformed interconnection cycle (PJM Cycle 1 / ERCOT Batch Zero), a reliability commissioning process (NERC Level 3), and a capacity cost-allocation regime (PJM backstop / Large Load Registry). Each is a source of delay, cost, and cost-shift risk priced into every 2027–2029 energization.
How does SAVRN energize a campus faster than the grid-tied path?+
SAVRN builds off-grid: owned power generation, owned compute, and closed-loop liquid cooling, deployed in 6 to 12 months versus the 24-to-48-month industry standard. Because generation and load sit behind the same fence, a SAVRN campus skips the interconnection queue and never draws the surrounding community's capacity to do it.

Sources

Standalone sources pageEvery source on one page — grouped, linked, citable
Every primary source behind this article — FERC dockets EL26-67 through EL26-72 and RM26-4-000, PJM Docket ER26-5181, the NERC Level 3 alert, PJM Cycle 1 results, and the ERCOT PGRR 145 / NPRR 1325 record — is listed below, with a direct link to each.
  • FERC Section 206 show-cause orders, June 18, 2026 — Dockets EL26-67-000 (PJM), EL26-68 (SPP), EL26-69 (NYISO), EL26-70 (MISO), EL26-71 (CAISO), EL26-72 (ISO-NE). McGuireWoods client alert
  • National preview of the July 20 informational reports and the August 17 Show Cause Response deadline. JD Supra
  • PJM Motion for Abeyance in Docket EL26-67, filed July 28, 2026; Section 205 response by early-to-mid November 2026. PJM
  • December 18, 2025 Co-Located Load Show Cause Order, PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025), Docket EL25-49-000; 50 MW BTMG threshold; grandfather cutoff; compliance filings ER26-5181. White & Case
  • Five reform categories and the cost-allocation question. Electron Economics
  • PJM Cycle 1 results, Aug 3, 2026 — 715 projects, 201.5 GW, “first-ready, first-served,” HyperQ. PJM Inside Lines
  • ERCOT Batch Zero, SB 6, and the PJM capacity package. Krishnan Rangachari, PMP, “The Data Center Reckoning” · Texas SB 6
  • NERC Level 3 Essential Action Alert on computational load, May 4, 2026; response deadline Aug 3, 2026. NERC · Renewable Energy World
  • NERC Accelerated Large Load Action Plan — revised standards on or before Dec 31, 2026. NERC filing in RM26-4 · Large Loads FAQ
  • FERC's June deadline to rewrite large-load grid rules; Necessary Studies process; timing. POWER Magazine