All research sources
Sources & Citations

The Quiet Rewrite

62 primary sources 5 categories We publish the receipts
1

Federal layerFERC · DOE · NERC

DOE Secretary Wright invoked Section 403 of the DOE Organization Act on October 23, 2025, directing FERC to initiate rulemaking on standardized large-load interconnection; accompanied by 14 principles including joint co-located generation+load interconnection requests.

U.S. Department of Energy press release, October 23, 2025 View source

FERC opened corresponding rulemaking docket RM26-4-000 on October 28, 2025.

FERC docket RM26-4-000 View source

FERC committed to act on the Section 403 proposal by end of June 2026.

FERC Commission statements; widely reported by K&L Gates, Day Pitney, Baker Botts, Morgan Lewis client alerts View source

FERC December 18, 2025 order in Docket EL25-49-000 found PJM’s tariff “unjust and unreasonable” and ordered PJM to implement transparent rules for large loads co-located with generation resources.

FERC Order, Docket EL25-49-000, December 18, 2025 View source

DOE issued 202(c) emergency orders during Winter Storm Fern (Jan 24–26, 2026) directing PJM, Duke Energy, and ERCOT to keep diesel generators ready and dispatchable.

DOE press releases, January 24, 25, 26, 2026 View source

NERC Standards Committee accepted SAR for new Reliability Standard targeting computational load on March 18, 2026 (Project 2026-02 — Computational Load Alignment Phase 1).

NERC Project 2026-02; comment period through April 30, 2026 View source

NERC RSTC approved Large Loads Working Group whitepaper #2, “Assessment of Gaps in Existing Practices, Requirements, and Reliability Standards for Emerging Large Loads,” on March 12, 2026.

NERC RSTC agenda package, March 12, 2026 View source

NERC Reliability Standard FAC-002-4 (Facility Interconnection Studies) in force as the foundational standard for interconnection studies.

NERC Reliability Standards library View source
2

ISO / RTO layer

Seven markets

NOGRR 282 + NPRR 1308 filed November 14, 2025. Creates Large Electronic Load (LEL) class — ≥75 MW where ≥50% of demand is power-electronic.

ERCOT NOGRR 282, full redline filed Nov 14, 2025 View source

Full voltage ride-through curve, §2.14 Table A: continuous 0.9–1.1 pu; 2.0 s at 0.8–0.9 pu; 0.5 s at 0.5–0.8 pu; 0.25 s at 0.2–0.5 pu; 0.15 s below 0.2 pu. Per-unit measured at the Service Delivery Point (138 kV / 345 kV).

NOGRR 282 §2.14 Table A (Nov 14, 2025 redline) View source

Strict ride-through band effective January 1, 2028. Interim band before that date allows proportional reduction; strict band requires continued active power consumption.

NOGRR 282 §2.14 (effective dates) View source

ERCOT contracted McKinsey to support improvement of the Large Load Interconnection process; deliverables expected to feed next round of NOGRR filings.

ERCOT press release, December 12, 2025 View source

PJM Board Critical Issue Fast Path (CIFP) decision on large-load interconnection, finalized January 16, 2026.

PJM Board decisional letter, January 16, 2026 View source

Expedited Interconnection Track operational by August 2026. Connect-and-Manage framework subordinates large-load growth to curtailment ahead of pre-emergency Demand Response.

PJM Board letter (Jan 16, 2026), p. 4 and Summary Table p. 7 View source

Verbatim from PJM Board letter: “the incremental demand associated with such load growth would be subject to curtailment prior to the deployment of pre-emergency Demand Response.”

PJM Board letter, January 16, 2026, page 4 View source

Large Load Considerations Issue Paper published January 30, 2026; information session February 5, 2026.

CAISO Large Load initiative View source

CAISO does not study load interconnections — those are retail-tariff functions under the connecting utility (PG&E, SCE, SDG&E). CAISO is developing parallel technical requirements (ride-through, ramp, telemetry, dynamic modeling).

CAISO Large Load page, direct statement View source

4.5 GW of data center demand under study in 2025–2026 transmission planning cycle. CEC forecast: +1.8 GW by 2030, +4.9 GW by 2040.

CAISO Large Load page (citing California Energy Commission) View source

High Impact Large Load (HILL) Integration unanimously approved by FERC on January 14, 2026 (effective January 15, 2026).

SPP press release View source

CHILLS revisions refiled February 10, 2026, Docket ER26-1323-000; target effective date July 1, 2026. Maximum 7-year bridge term, non-firm service, lower priority than firm NITS.

SPP filing, Docket ER26-1323-000 View source

Price Adaptive Load (PAL), Schedule 16: non-firm service indexed to LMP. Customers pay LMP for withdrawals; receive no compensation when curtailing.

SPP Schedule 16 PAL Service tariff View source

Large Load framework triggers September 1, 2026. Defines Large Load as >50 MW total capacity at a single site, or +25 MW expansion of an existing >50 MW load.

MISO Large Load Working Group; Workshop presentation Jan 30, 2026 View source

Five reliability requirement categories: performance & ride-through behavior; flexibility limits; operational readiness (telemetry & metering); system stability impacts; security & resilience.

MISO LLWG documentation View source

48 large-load proposals totaling ~12 GW in queue as of December 31, 2025 (up from 6 projects in 2022). Current interconnection studies trigger at ≥10 MW at ≥115 kV or ≥80 MW <115 kV.

NYISO Load Interconnection Procedure View source

Reform timeline: Feb–May 2026 concepts; June–July 2026 straw proposal; August 2026 detailed proposal; December 2026 Board approval and FERC filing.

NYISO reform roadmap View source

New York PSC opened Case 26-E-0045 (“Energize NY Development”) on February 12, 2026, modernizing interconnection policy for load-intensive facilities under the Climate Leadership and Community Protection Act (CLCPA).

NY PSC Case 26-E-0045 View source

Next cluster interconnection request window: October 5 – November 19, 2026.

ISO-NE Cluster Interconnection Studies View source
3

State layerEight jurisdictions

Senate Bill 6 signed by Governor Abbott on June 20, 2025. Mandates remote-disconnect equipment and curtailment participation for new ≥75 MW loads after December 31, 2025.

Texas Senate Bill 6, 89th Legislature (capitol.texas.gov) View source

PURA § 37.0561 narrows ERCOT’s operational authority over co-located generation+load arrangements (≥50% serve-from-self threshold, non-exporting).

SB 6 text; client alerts from Baker Botts (July 2025) and Bracewell (July 2025) View source

PURA § 39.169 governs net-metering arrangements between large loads and co-located standalone generators.

SB 6 text; Perkins Coie SB 6 Implementation update View source

PUCT Project 58481 (Large-Load Interconnection Standards) — proposed 16 TAC § 25.194. PUCT staff voted to publish March 12, 2026; comment deadline April 17, 2026.

PUCT interchange filing 58481 View source

PUCT Projects 58479 (net-metering / co-location), 58480 (large-load forecasting, ≥10 MW threshold), 58482 (reliability + voluntary demand reduction), 58484 (transmission cost allocation / 4CP review).

PUCT interchange filings View source

SCC approved GS-5 data center rate class November 25, 2025 (Case PUR-2025-00058). Applies to new GS-5 contracts on or after January 1, 2027. Trigger: customer >25 MW with monthly load factor >75%.

Virginia State Corporation Commission, Case PUR-2025-00058 View source

85% minimum bill on contracted T&D demand; collateral obligations up to 60% of minimum charges; minimum 14-year contract regardless of buildout.

SCC Fact Sheet (Feb 2026) View source

AEP Ohio data center tariff adopted by PUCO July 9, 2025. 12-year framework (4-year ramp + 8-year fixed). Minimum monthly billing demand ≥85% of customer’s highest previously established monthly billing demand.

AEP Ohio data center tariff page View source

Amazon, Google, Meta, Microsoft, and the Ohio Manufacturers’ Association sought rehearing. PUCO denied. (OMA appealed to Ohio Supreme Court.)

PUCO orders View source

In February 2026 PUCO filing, AEP Ohio described the rule as “weeding out uncommitted data center load.”

AEP Ohio February 2026 PUCO filing View source

Ohio HB 706 (introduced March 2026) would extend the framework statewide.

Ohio General Assembly, 136th GA, HB 706 View source

SRP LCIP and E-67 commercial/industrial price plan (2025). Minimum billing = greater of actual demand or 80% of forecasted load.

SRP 2025 Ratebook, Price Plan E-67 View source

ACC Large Load Workshop April 16, 2026 (Docket E-00000A-25-0069). 59 SRP large-load customers totaling ~7 GW reported.

Arizona Corporation Commission View source

TVA review thresholds: >5 MW requires TVA review; >100 MW requires TVA board approval.

TVA contract approval framework View source

TVA board voted February 11, 2026 to add 150 MW to xAI’s Memphis allowance — roughly doubling it. Same decision cycle reversed previously planned closures of the Kingston (2027) and Cumberland (2028) coal plants.

TVA Board minutes, February 11, 2026 View source

Data centers represent ~18% of TVA industrial load in 2025; projected to double by 2030.

TVA CEO Don Moul public statements View source

Georgia PSC approved Georgia Power’s ~10 GW gas expansion (9,885 MW). Approximately $16 billion capital plan. Base rate freeze through 2028 (July 31, 2025 PSC order).

Georgia PSC data center fact sheet View source

Verbatim stipulation: “downward pressure of at least $8.50 per month to the typical residential customer using an average of 1,000 kWh per month for the years 2029, 2030 and 2031.”

Georgia Power data center fact sheet, verbatim View source

~6 GW data center pipeline in Duke Carolinas territory. Duke Energy Progress NC rate case filed October 2025; Duke Energy Carolinas NC rate case filed November 20, 2025.

Duke Energy regulatory filings; NCUC dockets View source

Clean Transition Tariff announced via MoU with Amazon, Google, Microsoft and Nucor (not yet filed as tariff).

Duke Energy press release View source

Oregon: amendment to omnibus enterprise-zone legislation (SB/HB 4084, 2026 session) temporarily excluded data centers from expanded 10-year tax exemption.

Oregon Legislature, 2026 session records View source

Washington ESSB 6231 (signed by Gov. Ferguson) repeals sales and use tax exemption on replacement and refurbished data center equipment, effective July 1, 2026.

Washington State Legislature, ESSB 6231 View source

Washington Clean Energy Transformation Act (CETA) 100% emissions-free electricity mandate by 2045 remains in force (RCW 19.405).

Washington Revised Code, RCW 19.405 View source
4

Hardware specificationsOCP · NVIDIA

OCP ORv3 HPR (High Power Rack) 5.5 kW PSU shelf — the design used in NVIDIA GB200 NVL72 and Blackwell-class racks — published input voltage window: 180 to 305 VAC.

Advanced Energy ORv3 HPR PSU datasheet View source

Earlier ORv3 3 kW PSU runs narrower 200–277 VAC input window. Neither variant brackets the NOGRR 282 ride-through floor.

Advanced Energy ORv3 3 kW PSU datasheet View source

NVIDIA contributed GB200 NVL72 designs to the Open Compute Project under the ORv3 HPR specification.

NVIDIA Developer Blog View source

OCP Open Rack V3 BBU Module Spec rev 1.4 — battery backup unit shelf providing limited rack-level ride-through mitigation (seconds-scale).

OCP standards library View source

Independent corroboration of the upstream-fix thesis (facility-layer voltage conditioning required, not rack-layer): arXiv 2510.03867, October 2025.

arXiv preprint 2510.03867 View source
5

Demand-wall numbersThe triggering data

ERCOT interconnection queue >233 GW of large-load requests; >70% from data centers (December 9, 2025 board update).

ERCOT board update / System Planning Update, December 9, 2025 View source

ERCOT all-time system peak: 85,931 MW, set on August 20, 2024.

ERCOT operational records View source

PJM 2026/2027 capacity auction: $7,271,197,971 (82.1%) increase in capacity-market revenue attributable to forecast data center load.

Monitoring Analytics (IMM), Analysis of the 2026/2027 RPM Base Residual Auction, Part A, October 1, 2025 View source

PJM 2026/27 BRA cleared at the FERC-approved cap of $329.17/MW-day across the entire footprint (a record at the time of clearing; subsequently exceeded by the 2027/28 BRA).

PJM Inside Lines press release; IMM analysis View source

PJM covers 67 million people across 13 states + DC.

PJM Board letter Jan 16, 2026; PJM press release Dec 17, 2025 View source

Duke Carolinas data center pipeline: ~6 GW. Data centers ~1% of peak demand today; ~10% by 2030.

Duke Energy filings; NC + SC rate case dockets View source

APS large-customer load commitments approaching 13.1 GW (against an actual 2025 system peak of ~8.6 GW; system peak forecast ~11.4 GW by 2031 and ~13 GW by 2038).

APS Integrated Resource Plan; ACC docket E-00000A-25-0069 View source
These are the primary sources behind our research. Have a better one, or spot an error? Tell us — we’ll correct it.